How to talk like a local:
“May-ner”
“Burn-it”
“Gwad-loop”
“Man-Shack”
Overview
Importance of Pavement Smoothness Current State of Smoothness
Specifications Keys to Achieving Pavement Smoothness
Requirements1. Construction Practices2. Monitoring Your Work
Overview
Importance of Pavement Smoothness Current State of Smoothness
Specifications Keys to Achieving Pavement Smoothness
Requirements1. Construction Practices2. Monitoring Your Work
Importance of Pavement Smoothness
Contractor Perspective1. Reflects the quality of your work (and the
industry?)2. $$$ (Incentives/Disincentives/Corrective
Work)
Current Smoothness Specifications
Merritt et al. 2015
Merritt et al. 2015
Current Smoothness Specifications
Current Smoothness Specifications
Summary of IRI-based specification thresholds for concrete pavement
Merritt et al. 2015
Incentive Upper Limit
Full Pay Lower Limit
Full Pay Upper Limit
Disincentive Lower Limit
Disincentive Upper Limit
Threshold for
Correction
MRI & IRI
(22 states)
min 39.9 40.0 54.0 54.1 67.5 60.0 max 70.0 71.0 93.0 93.1 140.0 150.0 avg. 56.2 56.5 71.7 72.5 95.3 96.9
HRI (CO only) 57.9 58.0 67.0 67.1 85.0 85.0
Current Smoothness Specifications
Range of Incentives/Disincentives
Merritt et al. 2015
Pay Adjustment Basis Maximum Incentive
Maximum Disincentive
$ per lot (0.1 mi) 9 states
min $200 -$250 max $1,600 -$1,750 avg. $879 -$900
$ per lot (SY) 2 states
min $1.40 -$1.12 max $1.40 -$1.40 avg. $1.40 -$1.26
$ per lot (1.0 mi) 1 state
$7,350 -$7,350
$ per lot (0.01 mi) 1 state
$50 -$500
$ per lot (500 ft.) 1 state
$250 -$250
Extended Pay Adjustment $ per lot (0.1 mi)
13 states (NJ excluded)
min $200 -$250 max $1,600 -$1,750 avg. $825 -$831
Percent Contract Price 7 states
min 102% 90% max 108% 50% avg. 105% 75%
Concrete Pavement(3 states)
Min -$10
Max -$250
Average -$173
Localized Roughness
Overview
Importance of Pavement Smoothness Current State of Smoothness
Specifications Keys to Achieving Pavement Smoothness
Requirements1. Construction Practices2. Monitoring Your Work
Keys to Pavement Smoothness
1. Construction Practices
The “Sweet Spot”
Mixture Factors
Paving Factors
Human Factors
Stolen from: Gary Fick
Keys to Pavement Smoothness
1. Construction Practices
Stolen from: Gary Fick
The “Sweet Spot”
Mixture Factors
Paving Factors
Human Factors
Keys to Pavement Smoothness
1. Construction Practices
Stolen from: Gary Fick
The “Sweet Spot”?
Mixture Factors
Paving Factors
Human Factors
Keys to Pavement Smoothness
1. Construction Practices: Mixture FactorsCombined gradation
Reduced paste content Improved workability Durability
Between batch uniformity Consistent combined gradation
and water contentUniform delivery of concrete
Minimizing paver stops
Tarantula Curve
Keys to Pavement Smoothness
1. Construction Practices: Paving FactorsTrack lineStringline/Stringless modelPaver setup
Draft/Lead Sensitivities Vibrator frequency Vibrator height Float pan
Concrete headFinishing, Curing and texturing
Keys to Pavement Smoothness
1. Construction Practices: Paving FactorsProfile – trimmed or stabilized base placed
with grade controlStability – non-yielding and non-pumpingWidth – full width of track supported
Keys to Pavement Smoothness
1. Construction Practices: Paving FactorsDoes hand finishing improve pavement
smoothness?
Distance (ft)
Real-TimeHardened
IRI (
in/m
i)
Keys to Pavement Smoothness
1. Construction Practices: Human FactorsEveryone on the project contributes to
smoothness Training Experience Communication Empowerment
Keys to Pavement Smoothness
2. Monitoring Your Work Check your work (hardened profiles) DAILY.
Lightweight Inertial Profiler
Keys to Pavement Smoothness
2. Monitoring Your Work Check your work (hardened profiles) DAILY.
Tractor-Based ProfilerWalking Profilers
Keys to Pavement Smoothness
2. Monitoring Your Work Use Real-Time profilers to check your work
as you pave.
Real-Time Smoothness Technology
GOMACO GSI Ames RTP
Keys to Pavement Smoothness
2. Monitoring Your Work Use Real-Time profilers to check your work
as you pave.
Real-Time Smoothness Technology
GOMACO GSI Ames RTP
Keys to Pavement Smoothness
2. Monitoring Your Work Note effects of construction operations on
smoothness numbers (real-time and/or hardened). Mixture changes Paver operation (paver setup, paver stops, etc.) Crew changes Other factors (weather, etc.)
Be wary of the warp (and curl) Time of day for profile data collection can
significantly impact IRI values.
Keys to Pavement Smoothness
2. Monitoring Your Work Use ProVAL to analyze profile data.
Identify effects of paving processes on smoothness.
Identify systematic “patterns” of roughness caused by paving operations.
Pinpoint corrective action
www.RoadProfile.com
Keys to Pavement Smoothness
2. Monitoring Your WorkUse ProVAL to identify “patterns” of
roughness caused by paving operations.What happening at 10.5’-11’?
15’ Joint Spacing
??
Real-Time Profiles
Keys to Pavement Smoothness
2. Monitoring Your WorkUse ProVAL to identify “patterns” of
roughness caused by paving operations.What happening at 10.5’-11’?
15’ Joint Spacing??Hardened Profiles
Keys to Pavement Smoothness
2. Monitoring Your WorkRoughness spikes every 300-400 ft on right
side. What is it?
Distance (ft)
IRI (
in/m
i)
RTP-LeftRTP-Right
Keys to Pavement Smoothness
2. Monitoring Your WorkRoughness spikes every 300-400 ft on right
side. Is it in the hardened profile as well?
Distance (ft)
IRI (
in/m
i)
Real-TimeHardened
Keys to Pavement Smoothness
2. Monitoring Your WorkUse ProVAL to pinpoint corrective action.Grinding Simulation – will grinding help?
Distance (ft)
IRI (
in/m
i)
Keys to Pavement Smoothness
2. Monitoring Your WorkUse ProVAL to pinpoint corrective action.Grinding Simulation – will grinding help?
Distance (ft)
IRI (
in/m
i)
Before GrindingAfter Grinding
Yes Yes
No
Keys to Pavement Smoothness
2. Monitoring Your Work
IRI (
in/m
i)
Distance (ft)
Elev
atio
n (in
)
Roughness
vs.
Profile
Dip
Keys to Pavement Smoothness
How to Reduce Must-Grinds and Increase Profits:1. Good Construction Practices – finding the
“sweet spot”.2. Monitoring Your Work – using tools such as
Real-Time Smoothness and ProVAL.