    HOW TO CALCULATE THE

    COST OF TIME UNITSIN SOFTWARE INDUSTRY

    By; Alaa S. Al-Agamawi20 Oct. 2009

    cost standards for Egyptian software SME s companies

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    2/21

    Objectives (Why cost of units) Calculating the timely rate costs in Software companies

    represents an important corner stone in Any business improvement process for our companies.

    More cooperation between our members.

    Future task forces to talk about best practices. So we need to

    Having a well-thought-of methodology.

    Contributing together to apply this methodology in order tocome up with reliable results.

    Disseminating the results to all members.

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    3/21

    Approach Forming a task force that can come-up with a good estimate for the

    cost of person/hours, person/days and person/months for different

    software activities. Accepting some approximation in the beginning provided that there

    should be continuous future refinement.

    Forming a questionnaire that it is to be distributed to all members

    and even none-members. Gathering data in an anonymous way that preserves companies

    confidentiality.

    After this, we should make many awareness sessions to all stakeholders to evangelize our findings.

    Each of us can also use the findings in enhancing his companys ownperformance (participants or everybody).

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    4/21

    Agenda P&L Statement

    Why costing?

    Billable and non-billable hours

    Software Industry a time dependant industry

    The Editors desk

    Dairy Farms and Cheese Factories Days and hours in a typical month

    Net salary vs. Gross salary

    Indirect cost

    Software subsectors Whats next?

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    5/21

    P&L Statement Profit is the spirit of any

    business entity, without whichit can never grow and wouldeven be subjected to manyproblems.

    Cash flow is a killer.

    Keywords

    Revenue

    COGS

    Gross Profit

    Net Profit

    e a n ng pos ve cas owthat covers at least a periodof three months shouldalways be consideredamong the highest priorities.

    P&L statement, Cash Flowstatement will represent agood indicator for yourcompany financial health .

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    6/21

    Why Costing? When working in more than

    one project, how are you goingto tell about the profitability ofeach project?

    Projects that costs more than itearns means that ou are

    subsidizing a bad customer. Inother words, you are makinggood profit from a project,then losing that profit onanother project.

    Without costing, how are yougoing to calculate theadequate motivation forAchievements?

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    7/21

    Billable and none-billable hours You do not get money out of

    all of your staff/activities.Some gets money andothers dont.

    How are you going to pay or your accountant

    finance your marketingcampaigns

    Your top management, i.e.the human brain! 6% of body weight 20% consumption of resources

    (sugar & oxygen)Keywords

    Billable

    None-Billable

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    8/21

    Software Industry A time dependant industry

    In a typical mass-

    production commoditymanufacturer enterprise;

    90% of the cost is NOT

    time dependant. In a typical software

    company; things are

    reciprocal.

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    9/21

    The Editor Desk

    For journalists, financial

    auditors, lawyers, etc.,there is always a non-

    negotiable deadline (e.g.

    8pm to deliver articles). In software, we lack such

    editors desk.

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    10/21

    Dairy farms and Cheese factories

    Software service providers arelike a dairy farm, they pay forproduction cost even of there isno projects.

    Ready-made productsmanufacturers can en o an

    elongated period beforedisposing milk on the river.

    For the first group, Gapsbetween projects can exhaustall profits.

    Even in ready-made productcase, Different tasks and theirinternal dependability (AdamSmith) will result waste ofproduction time also.

    Keywords

    Gaps

    between

    Projects.

    Redoing

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    11/21

    How many days in a typical month,

    and how many hours?

    Professional working days per year

    Regular Gregorian Year 365

    minus actual

    Weekends 104 261

    National Holidays 13 248

    Annual Vacation 30 218

    Training and HR Development 20 198

    Assume 10% of the

    total available time

    Gaps between Projects 20 178

    Assume the industry

    standard 10%

    Number of billable days per month 15

    Number of working hours per month 89

    Assuming 6 hours per

    day (World record is

    6.75)

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    12/21

    Who pays for the OFF-HOURS ?

    In a monthly contract, the customers pays for

    the week-ends and national holidays(remember that in most cases you are the

    .

    In daily rate contracts, you pay for all off-

    days.

    In hourly rate contracts, you pay for all off-hours.

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    13/21

    Net Salary (take-home) and Gross

    Salary (what company pays)

    Direct labor cost:

    Take home salary

    Social Insurance

    Medical Insurance

    Net SalarySocial

    Insurance Payroll Tax TotalPercentageof Increase

    $750 $279 $0 $1,029 137%

    $1,000 $279 $0 $1,279 128%

    $1,500 $279 $100 $1,879 125%

    Payroll taxes

    , ,

    $2,500 $279 $300 $3,079 123%

    $3,000 $279 $400 $3,679 123%

    $3,500 $279 $500 $4,279 122%

    $4,000 $279 $600 $4,879 122%

    $4,500 $279 $700 $5,479 122%

    $5,000 $279 $800 $6,079 122%

    $5,500 $279 $900 $6,679 121%

    $6,000 $279 $1,000 $7,279 121%

    Do not forget

    Medical Insurance

    Bonuses

    Correction factors

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    14/21

    Indirect Cost

    Place

    Equipments

    depreciation.

    Technical

    Total Cost per Day Total Cost per Hour

    NetSalary

    DirectCost Min Max Min Average Max Min Average Max

    $750.0 $1,028.8 $1,543.2 $2,572.0 $104.0 $138.7 $173.4 $17.3 $23.1 $28.9

    $1,000.0 $1,278.8 $1,918.2 $3,197.0 $129.3 $172.4 $215.5 $21.6 $28.7 $35.9

    $1,500.0 $1,878.8 $2,818.2 $4,697.0 $190.0 $253.3 $316.7 $31.7 $42.2 $52.8

    At a glance

    Factor that isNOT LESS

    THAN 1.9 and

    up to 3.2

    Coaching.

    Supervision

    HRD

    Management

    $2,000.0 $2,478.8 $3,718.2 $6,197.0 $250.7 $334.2 $417.8 $41.8 $55.7 $69.6

    $2,500.0 $3,078.8 $4,618.2 $7,697.0 $311.3 $415.1 $518.9 $51.9 $69.2 $86.5

    $3,000.0 $3,678.8 $5,518.2 $9,197.0 $372.0 $496.0 $620.0 $62.0 $82.7 $103.3

    $3,500.0 $4,278.8 $6,418.2 $10,697.0 $432.7 $576.9 $721.1 $72.1 $96.2 $120.2

    $4,000.0 $4,878.8 $7,318.2 $12,197.0 $493.4 $657.8 $822.3 $82.2 $109.6 $137.0

    $4,500.0 $5,478.8 $8,218.2 $13,697.0 $554.0 $738.7 $923.4 $92.3 $123.1 $153.9

    $5,000.0 $6,078.8 $9,118.2 $15,197.0 $614.7 $819.6 $1,024.5 $102.5 $136.6 $170.8

    $5,500.0 $6,678.8 $10,018.2 $16,697.0 $675.4 $900.5 $1,125.6 $112.6 $150.1 $187.6

    $6,000.0 $7,278.8 $10,918.2 $18,197.0 $736.1 $981.4 $1,226.8 $122.7 $163.6 $204.5

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    15/21

    Software Subsectors

    Multi-Media

    Application Development Content Development

    System level programming

    Skilled personneldeployment services

    Technologies research and

    development

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    16/21

    Software Subsectors (continued)

    Market price for each

    subsector differs.Percentage of contribution

    for each skill level varies.

    50%

    20%

    20%

    10% Art work Designer

    Flash Developer

    Subject MatterExpert

    Project Manager

    Multi Media

    10%20%

    20%

    10%

    20%

    15%

    JuniorDeveloper/tester/support

    Developer

    SeniorDeveloper

    Team Leader

    Application

    Development

    5%10%

    30%15%

    20%

    10%10%

    JuniorDeveloper/tester/support

    Developer

    SeniorDeveloper

    Team Leader

    System Level

    Programming

    5%

    30%

    20%20%

    20%

    5%

    JuniorDeveloper/tester/support

    Developer

    SeniorDeveloper

    Team Leader

    Research &

    Development

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    17/21

    Multi-Media

    Average Project Participation

    Art work Designer 50% $52.02 $208.89 $8.67 $34.81

    Flash Developer 20% $25.86 $124.00 $4.31 $20.67

    Subject Matter Expert 20% $50.13 $204.90 $8.36 $34.15

    Project Manager 10% $37.20 $142.90 $6.20 $23.82

    Overall Project Average cost EGP165 EGP681 EGP28 EGP113

    EGP423 EGP70

    Just for the sake of Statistics

    Daily cost in US$ 5.600 $29.50 $121.55 $4.92 $20.26

    Daily Cost in Euro 8.008 20.63 85.00 3.44 14.17

    Monthly Cost in EGP $2,450.70 $10,097.00

    Monthly cost in US$ 5.600 $437.63 $1,803.04

    Monthly Cost in Euro 8.008 306.03 1,260.86

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    18/21

    Application DevelopmentAverage Project Participation

    Junior Developer/tester/support 10% $12.93 $62.00 $2.16 $10.33

    Developer 20% $50.13 $184.68 $8.36 $30.78

    Senior Developer 20% $74.40 $245.35 $12.40 $40.89

    Team Leader 10% $55.40 $153.01 $9.23 $25.50

    Designer 20% $147.21 $366.70 $24.54 $61.12

    Analyst 15% $128.61 $305.36 $21.44 $50.89

    Project Manager 5% $48.94 $101.79 $8.16 $16.96

    Overall Project Average cost 100% EGP518 EGP1,419 EGP86 EGP236

    EGP968 EGP161

    Just for the sake of Statistics

    Daily cost in US$ 5.600 $92.43 $253.37 $15.41 $42.23

    Daily Cost in Euro 8.008 64.64 177.19 10.77 29.53

    Monthly Cost in EGP $7,678.20 $21,047.00

    Monthly cost in US$ 5.600 $1,371.11 $3,758.39

    Monthly Cost in Euro 8.008 958.82 2,628.25

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    19/21

    System Level Programming

    Average Project Participation

    Junior Developer/tester/support 5% $6.47 $31.00 $1.08 $5.17

    Developer 10% $25.07 $92.34 $4.18 $15.39

    Senior Developer 30% $111.60 $368.03 $18.60 $61.34

    Team Leader 15% $83.11 $229.52 $13.85 $38.25

    Designer 20% $110.81 $366.70 $18.47 $61.12

    Analyst 10% $55.40 $203.58 $9.23 $33.93

    Project Manager 10% $61.47 $203.58 $10.25 $33.93

    v r r c v r g c ,

    EGP974 EGP162

    Just for the sake of Statistics

    Daily cost in US$ 5.600 $81.06 $266.92 $13.51 $44.49

    Daily Cost in Euro 8.008 56.68 186.66 9.45 31.11

    Monthly Cost in EGP $6,733.20 $22,172.00

    Monthly cost in US$ 5.600 $1,202.36 $3,959.29

    Monthly Cost in Euro 8.008 840.81 2,768.73

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    20/21

    Research and Development

    Average Project Participation

    Junior Developer/tester/support 0% $0.00 $0.00 $0.00 $0.00

    Developer 5% $12.53 $46.17 $2.09 $7.69

    Senior Developer 30% $111.60 $368.03 $18.60 $61.34

    Team Leader 20% $110.81 $306.03 $18.47 $51.00

    Designer 20% $110.81 $366.70 $18.47 $61.12

    Analyst / Subject Matter Expert 20% $110.81 $407.15 $18.47 $67.86

    Project Manager 5% $30.74 $101.79 $5.12 $16.96

    ,

    EGP1,042 EGP174

    Just for the sake of Statistics

    Daily cost in US$ 5.600 $87.02 $284.98 $14.50 $47.50

    Daily Cost in Euro 8.008 60.85 199.28 10.14 33.21

    Monthly Cost in EGP $7,228.20 $23,672.00

    Monthly cost in US$ 5.600 $1,290.75 $4,227.14

    Monthly Cost in Euro 8.008 902.62 2,956.04

  • 8/8/2019 How to Calculate Timely Rates in Software Industry

    21/21

    What is next? Contributing in the task force that is to work on

    Coming up with the final version of the questionnaire. Evangelizing the concept to all members and inviting

    them to participate.

    Collects the data and apply the statistical methods. Publishing the results.

    Thank you