how much time should you allow for your windows 10 …...windows 10 migration timing (months) •...

1
Part of the Seamless Migration to Windows 10 Series How Much Time Should You Allow for Your Windows 10 Migration? 4 STAGES OF MIGRATION Depending on the size of your organization, you should allow approximately 5-11 months for your transition to Windows 10. This infographic shows how that timing breaks down across the four stages of the migration process. • Identify all applications environment Identify all devices Determine user groups Review Active Directory group policies of strategic initiatives overseen by survey respondents were deemed outright failures. 28% Initiation • Execute deployment schedule Image the devices Execution Each stage involves distinct processes and tasks that must be accomplished regardless of the size of the migration. The amount of time you should set aside for each stage, however, varies depending on the size and complexity of the organization and the number of end devices to be migrated. 1 Month 1 Month 2 Months 3 Months 1 Month 1 Month 2 Months 3 Months Small Medium Large Enterprise 2 Months 2 Months 2 Months 4 Months • Build deployment solution • Update Active Directory group policies • Test application compatibility • Procure replacement devices • Collect device drivers Preparation • Build base image • Define detailed schedule • Host user open house* • Start executing OCM solution • Set up imaging depot* * (If applicable) 1 Month 1 Month 1 Month 1 Month • Validate 100% deployment of Windows 10 • Ensure automated update (if applicable) Close-out Sources: Copyright 2018 HMB, Inc. All rights reserved Trademarks and registered trademarks are property of their respective owners. ¹ Success Rates Rise, Transforming the high cost of low performance (PMI’s Pulse of the Profession® - 2017) https://www.pmi.org/-/media/pmi/documents/public/pdf/learning/thought-leadership/pulse/pulse-of-the-profession-2017.pdf LEarn More Download our business brief, Timing Considerations for Your Windows 10 Migration, or contact us directly for more information on how to ensure a seamless migration. 614.221.6831 | [email protected] | hmbnet.com hmbnet.com/easywindows10 windows 10 migration timing (months) Determine Windows 10 deployment solution Determine Organizational Change Management (OCM) solution Provide one-on-one user support Address any/all Issues • Long-term imaging solutions and recommendations • Application standardization results • System maintenance instruction For purposes of our discussion, we will define organization size as follows:

Upload: others

Post on 11-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: How Much Time Should You Allow for Your Windows 10 …...windows 10 migration timing (months) • Determine Windows 10 deployment solution • Determine Organizational Change Management

Part of the Seamless Migration to Windows 10 Series

How Much Time Should You Allow for Your Windows 10 Migration?

4 STAGES OF MIGRATION

Depending on the size of your organization, you should allow approximately 5-11 months for your transition to Windows 10. This infographic shows how that timing breaks down across the four stages of the migration process.

• Identify all applications environment • Identify all devices • Determine user groups • Review Active Directory group policies

of strategic initiatives overseen by survey respondents were

deemed outright failures.

28%

Initiation

• Execute deployment schedule • Image the devices

Execution

Each stage involves distinct processes and tasks that must be accomplished regardless of the size of the migration. The amount

of time you should set aside for each stage, however, varies depending on the size and complexity of the organization

and the number of end devices to be migrated.

1 Month 1 Month 2 Months 3 Months

1 Month 1 Month 2 Months 3 Months

Small Medium Large Enterprise

2 Months 2 Months 2 Months 4 Months

• Build deployment solution • Update Active Directory group policies • Test application compatibility • Procure replacement devices• Collect device drivers

Preparation• Build base image • Define detailed schedule • Host user open house*• Start executing OCM solution• Set up imaging depot** (If applicable)

1 Month 1 Month 1 Month 1 Month

• Validate 100% deployment of Windows 10 • Ensure automated update (if applicable)

Close-out

Sources:

Copyright 2018 HMB, Inc. All rights reservedTrademarks and registered trademarks are property of their respective owners.

¹ Success Rates Rise, Transforming the high cost of low performance (PMI’s Pulse of the Profession® - 2017)https://www.pmi.org/-/media/pmi/documents/public/pdf/learning/thought-leadership/pulse/pulse-of-the-profession-2017.pdf

LEarn MoreDownload our business brief, Timing Considerations for Your Windows 10 Migration, or contact us directly for more information on how to ensure a seamless migration.

614.221.6831 | [email protected] | hmbnet.com

hmbnet.com/easywindows10

windows 10 migration timing (months)

• Determine Windows 10 deployment solution• Determine Organizational Change Management (OCM) solution

• Provide one-on-one user support • Address any/all Issues

• Long-term imaging solutions and recommendations• Application standardization results• System maintenance instruction