Hopewell Elementary SchoolProject Update 09.13.2018
project updates
• budget
• LEED v4
• construction
• looking ahead
[picture]
design process general to specific
updateproject budget
LEED v4
• Tracking 50 points (LEED Silver)
Construction
Update
Photo A1
• Retaining walls for Media Center
Photo A2
• Plumbing stub up for Lower Level Classroom Wing
Photo B1
• Building pad for Gym
Photo C1
• Footings in Area C Classroom Wing
Photo D1
• Retaining wall forms below Administration
Line Creek ParkwayRoad
Master Schedule
Key Dates
– Start Structural Steel
– BOE Jobsite Tour
– Complete StructuralSteel
– All Roofs Dried-In
– All Areas Complete
• 09/24/18
• 12/13/18
• 12/13/18
• 03/11/19
• 08/02/19