Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
Hook-Up Procedure for Site Erection
for
OSX Ship Yard Cranes (Eletric Part)
Rev. Date 2012.11.05
Kumoh
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
2 of 7 pages
Out-Line
This procedure is a guidance of erection works for the cranes designed and built by KUMOH which will be supplied to OSX.
All equipments in cranes have been so precisely designed and manufactured that care must be taken to maintain their original condition even after transportation.
“Qualified SPECIALIST” is the person has got used to installing products, loading, starting on, managing, and cleaning and in good repair. Qualified someone needs to have full attention to contents included all the warning and processing to cleaning and in good repair.
• According to established safety process, someone needs to have educated or qualified about a circuit and ground connection, tag of equipment.
• According to established safety process, you need to have educated or qualified about managing protective gear and using.
• Need to have educated first-aid treatment.
Qualified expert
Out-Line
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
3 of 7 pages
Contents Out-Line ....................................................................................................................................................... 2
Contents ...................................................................................................................................................... 3
1. General Matters ...................................................................................................................................... 4 1.1. Working area must be fenced off, and tools are also needed to be well organized. ..................... 4 1.2. All managers must be informed of work details in advance. .......................................................... 4 1.3. Assembly work should be done by skilled and qualified persons. ................................................. 4 1.4. Check if all power supply is shut down before commencing any work. ......................................... 4 1.5. Make sure of no persons staying under moving oad and at its vicinity. ......................................... 4
2. Site Erection Flow .................................................................................................................................. 5 2.1. Flow Chart for Site Erection ........................................................................................................... 5 2.2. Explanation for Site Erection .......................................................................................................... 6 2.2.1. Erection each Equipments for cranes ......................................................................................... 6 2.2.2. Cable pulling Equipments to the others ...................................................................................... 6 2.2.3. Reconnection the pulled cables .................................................................................................. 7
3. Attachment (Typical Installing Drawing) .............................................................................................. 7
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
4 of 7 pages
1. General Matters This Procedure covers Site Erection for OSX Ship Yard Cranes.
Site Erection must be cause followings ;
1.1. Working area must be fenced off, and tools are also needed to be well organized.
1.2. All managers must be informed of work details in advance.
1.3. Assembly work should be done by skilled and qualified persons.
1.4. Check if all power supply is shut down before commencing any work.
1.5. Make sure of no persons staying under moving oad and at its vicinity.
If this procedure is NOT contained adequacy, sufficient part or having any question, please contact our engineer(s) to ;
Kumoh heavy Industrial Co., Ltd / Design Team TEL: +82-55-521-5700 FAX: +82-55-521-4700 E-Mail: [email protected]
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
5 of 7 pages
2. Site Erection Flow
2.1. Flow Chart for Site Erection
Confirm Erection
Preparing for Site Erection
Erection each Equipments for crane
NOChecking by Supervisor
YES
Cable pulling Equipments to the others
NOChecking by Supervisor
YES
Reconnection the pulled cables
NOChecking by Supervisor
YES
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
6 of 7 pages
2.2. Explanation for Site Erection
2.2.1. Erection each Equipments for cranes
Erection each electrical Equipments as “Electrical Equipment Arrangement” which drawing No. is as following table ;
No. Item Number Q’ty Drawing No. Remarks1 OSX-CN-10-SPC-00001 1 Set UPA01-150.01-EI-DF-KUM-0102-15 2 OSX-CN-10-SPC-00002 4 Set UPA01-150.01-EI-DF-KUM-0202-15 3 OSX-CN-10-SPC-00015A 2 Set UPA01-150.01-EI-DF-KUM-15A02-15 4 OSX-CN-10-SPC-00015C 2 Set UPA01-150.01-EI-DF-KUM-15C02-15 5 OSX-CN-10-SPC-00016 1 Set UPA01-150.01-EI-DF-KUM-1602-15 6 OSX-CN-10-SPC-00017 1 Set UPA01-150.01-EI-DF-KUM-1702-14 7 OSX-CN-10-SPC-00018 4 Set UPA01-150.01-EI-DF-KUM-1802-14 8 OSX-CN-10-SPC-00020 1 Set UPA01-150.01-EI-DF-KUM-2002-14 9 OSX-CN-20-SPC-00010 1 Set UPA01-150.03-EI-DF-KUM-1002-14 10 OSX-CN-20-SPC-00012 1 Set UPA01-150.03-EI-DF-KUM-2002-15 11 OSX-CN-20-SPC-00013 1 Set UPA01-150.03-EI-DF-KUM-1302-14 12 OSX-CN-20-SPC-00017-1 8 Set UPA01-150.03-EI-DF-KUM-1702-14 13 OSX-CN-20-SPC-00019-1 4 Set UPA01-150.03-EI-DF-KUM-1902-15 14 OSX-CN-20-SPC-00024 1 Set UPA01-150.05-EI-DF-KUM-2402-14 15 OSX-CN-40-SPC-00012 1 Set UPA01-150.07-EI-DF-KUM-1202-14
And Refer 3. Attachment (Typical Installing Drawing)
2.2.2. Cable pulling Equipments to the others
After erection electrical equipments then, cable pulling must be done by “Interconnection wiring diagram” which conform wiring tag, numbering, location and etc. Its drawing No. for each cranes as following table ;
No. Item Number Q’ty Drawing No. Remarks1 OSX-CN-10-SPC-00001 1 Set UPA01-150.01-EI-DH-KUM-0103-00~ 2 OSX-CN-10-SPC-00002 4 Set UPA01-150.01-EI-DH-KUM-0303-00~ 3 OSX-CN-10-SPC-00015A 2 Set UPA01-150.01-EI-DH-KUM-15A03-00~ 4 OSX-CN-10-SPC-00015C 2 Set UPA01-150.01-EI-DH-KUM-15C03-00~ 5 OSX-CN-10-SPC-00016 1 Set UPA01-150.01-EI-DH-KUM-1603-00~ 6 OSX-CN-10-SPC-00017 1 Set UPA01-150.01-EI-DH-KUM-1703-00~ 7 OSX-CN-10-SPC-00018 4 Set UPA01-150.01-EI-DH-KUM-1803-00~ 8 OSX-CN-10-SPC-00020 1 Set UPA01-150.01-EI-DH-KUM-2003-00~ 9 OSX-CN-20-SPC-00010 1 Set UPA01-150.03-EI-DH-KUM-1003-00~ 10 OSX-CN-20-SPC-00012 1 Set UPA01-150.03-EI-DH-KUM-2003-00~ 11 OSX-CN-20-SPC-00013 1 Set UPA01-150.03-EI-DH-KUM-1303-00~ 12 OSX-CN-20-SPC-00017-1 8 Set UPA01-150.03-EI-DH-KUM-1703-00~ 13 OSX-CN-20-SPC-00019-1 4 Set UPA01-150.03-EI-DH-KUM-1903-00~ 14 OSX-CN-20-SPC-00024 1 Set UPA01-150.05-EI-DH-KUM-2403-00~ 15 OSX-CN-40-SPC-00012 1 Set UPA01-150.07-EI-DH-KUM-1203-00~
Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes
7 of 7 pages
2.2.3. Reconnection the pulled cables
Reconnect already installed equipments. As “Interconnection wiring diagram” which is drawing for Interconnection.
3. Attachment (Typical Installing Drawing)