Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
March 2020
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•Additional Co-Op Purchases $ 187,098
•Additional Credit $ 63,092
•Approved Change Orders $1,098,108
•Remaining Construction Contingency $ 342,197
•Construction Project is 76% Complete
•Contingency Budget is 78% spent
•Contract allowance approved totals $0
•Project Team is following approximately $267,739 in pending issues.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Rooms 303 and 305 have been
completed and turned over to the
District.
• Construction in the Music Room has
begun.
Transportation Building
• Concrete for the Mezzanine has
been poured.
• Overhead plumbing, ductwork and
electrical conduit are ongoing.
• Masonry block work is ongoing.
Senior High School
• The Display Cases have been installed in the
Lobby.
• Wall tile and floor tile have been installed in
the Kitchen and Cafeteria.
• Ceiling grid is installed throughout the
Cafeteria and Kitchen and ceiling tile is being
dropped.
• The Cougar Mural has been installed in the
stairwell adjacent to the Cafeteria.
• Demolition has begun in the Robotics Lab.
• Demo of B&G has begun.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Lima Intermediate
• The Main Office has undergone
demolition, framing has begun and
MEP rough-ins are ongoing.
• Rooms 107, 108, 109 and 110 have
been abated and new flooring is going
in.
Middle School
• The building has been switched over to the
new Day Automation platform.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Heavy demo will continue in the
Music Room.
Senior High School
• The Cafeteria will be turned over to the
District.
• Construction will continue in the Kitchen
Area.
• The Faculty Lounge will be completed
and turned over to the District.
• Construction in the Robotics Lab will
continue.
• Parking lot work and concrete sidewalks
will continue.
Lima Elementary
• Construction in the Main Office will
continue.
Transportation Building
• Masonry work, drywall, floor leveling
and MEP rough-ins will all continue.
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
New Mezzanine – Transportation Center
New Mezzanine – Transportation Center
Office Space – Transportation Center
Temporary Wall in Manor Cafeteria
New Music Room - Manor
New Music Room - Manor
Cafeteria – High School
Cafeteria – High School
Cafeteria – High School Kitchen
Flexible Learning Lab – High School
Flexible Learning Lab – High School
Robotics Lab – High School
Main Entrance Lobby – High School
Main Entrance Lobby – High School
Main Entrance Lobby – High School
B&G Building Demolition
B&G Building Demolition
B&G Building Demolition
New Concrete Sidewalks – High School
New Concrete Sidewalks – High School
New Main Office – Lima
Room 107 – Lima
Room 108 – Lima
Room 109 – Lima
Room 110 – Lima
Cougar Mural – High School