honeoye falls-lima central school district€¦ · •parking lot work and concrete sidewalks will...

34
Honeoye Falls - Lima Central School District 2016 Additions and Alterations Phase 2 Project Update March 2020

Upload: others

Post on 22-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Project Update

March 2020

Page 2: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

2016 Additions and Alterations Phase 2

Referendum Value $29,986,084

Incidental Budget $ 4,632,681

Construction Contingency $ 1,564,311

Contracts Awarded $22,848,873

State Contract $ 940,219

Page 3: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Construction Contingency Budget Update

•Construction Contingency Budget $1,564,311

•Additional Co-Op Purchases $ 187,098

•Additional Credit $ 63,092

•Approved Change Orders $1,098,108

•Remaining Construction Contingency $ 342,197

•Construction Project is 76% Complete

•Contingency Budget is 78% spent

•Contract allowance approved totals $0

•Project Team is following approximately $267,739 in pending issues.

Page 4: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Manor Intermediate

• Rooms 303 and 305 have been

completed and turned over to the

District.

• Construction in the Music Room has

begun.

Transportation Building

• Concrete for the Mezzanine has

been poured.

• Overhead plumbing, ductwork and

electrical conduit are ongoing.

• Masonry block work is ongoing.

Senior High School

• The Display Cases have been installed in the

Lobby.

• Wall tile and floor tile have been installed in

the Kitchen and Cafeteria.

• Ceiling grid is installed throughout the

Cafeteria and Kitchen and ceiling tile is being

dropped.

• The Cougar Mural has been installed in the

stairwell adjacent to the Cafeteria.

• Demolition has begun in the Robotics Lab.

• Demo of B&G has begun.

Page 5: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

2016 Additions and Alterations Phase 2

Project Status/Schedule Update

Lima Intermediate

• The Main Office has undergone

demolition, framing has begun and

MEP rough-ins are ongoing.

• Rooms 107, 108, 109 and 110 have

been abated and new flooring is going

in.

Middle School

• The building has been switched over to the

new Day Automation platform.

Page 6: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

2016 Additions and Alterations Phase 2

What to expect in the upcoming Month

Manor Intermediate

• Heavy demo will continue in the

Music Room.

Senior High School

• The Cafeteria will be turned over to the

District.

• Construction will continue in the Kitchen

Area.

• The Faculty Lounge will be completed

and turned over to the District.

• Construction in the Robotics Lab will

continue.

• Parking lot work and concrete sidewalks

will continue.

Lima Elementary

• Construction in the Main Office will

continue.

Transportation Building

• Masonry work, drywall, floor leveling

and MEP rough-ins will all continue.

Page 7: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Honeoye Falls-Lima Central School District

2016 Additions and Alterations Phase 2

Progress Photos

Page 8: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Mezzanine – Transportation Center

Page 9: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Mezzanine – Transportation Center

Page 10: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Office Space – Transportation Center

Page 11: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Temporary Wall in Manor Cafeteria

Page 12: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Music Room - Manor

Page 13: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Music Room - Manor

Page 14: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Cafeteria – High School

Page 15: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Cafeteria – High School

Page 16: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Cafeteria – High School Kitchen

Page 17: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Flexible Learning Lab – High School

Page 18: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Flexible Learning Lab – High School

Page 19: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Robotics Lab – High School

Page 20: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Main Entrance Lobby – High School

Page 21: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Main Entrance Lobby – High School

Page 22: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Main Entrance Lobby – High School

Page 23: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

B&G Building Demolition

Page 24: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

B&G Building Demolition

Page 25: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

B&G Building Demolition

Page 26: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Concrete Sidewalks – High School

Page 27: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Concrete Sidewalks – High School

Page 28: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

New Main Office – Lima

Page 29: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Room 107 – Lima

Page 30: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Room 108 – Lima

Page 31: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Room 109 – Lima

Page 32: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Room 110 – Lima

Page 33: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Cougar Mural – High School

Page 34: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation

Honeoye Falls-Lima Central School

District

Questions?