November 19, 2016

Hollywood Park

Construction Update

Meeting

Page 2: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

PROJECT TEAM

Page 3: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Introduction and Welcome

Michelle Ballard, VP, Community & Citizenship,

Turner-Hunt JV

Infrastructure Update

Juresha Alemayehu, Senior Project Engineer,

Turner

Casino Demo

Elston Ridgle, Safety Manager,

Turner-Hunt JV

Stadium Update

Dave Masel, General Superintendent – Field Operations,

Turner-Hunt JV

Hollywood Park Development

Gerard McCallum, Project Manager,

Wilson Meany

Page 4: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

INFRASTRUCTURE

Page 5: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 6: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Building Demolition

100% Complete

Page 7: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Site Demo & Crushing

80% Complete

Page 8: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Street Widening & Hardscape

95% Complete

Page 9: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Environmental Remediation: 178 Acres

Grading: 27 Acres

Page 10: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Storm Drain Relocation

99% Complete

Page 11: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Offsite Sewer Improvements

100% Complete

Page 12: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

GRADING AREA AROUND STADIUM

BOWL

Page 13: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

GRADING AREA AROUND STADIUM

BOWL

Page 14: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Anticipated Work

Page 15: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

ANTICIPATED WORK

Onsite

• Infrastructure will continue to remediate unsuitable soil and demo Northern 60 acre parking lot

Prairie

• Ground Cover being planted and irrigation systems undergoing final testing.

• Minor clean-up work will continue to the end of November.

Century

• No Anticipated Work at this time.

Page 16: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Prairie Ave

Landscaping along Prairie

Ave. is nearly complete.

Ground Cover is being

planted and irrigation

systems are undergoing

final testing. Anticipated

completion in early

December 2016.

Page 17: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Paving & Striping on Prairie

Prairie Ave. paving and striping is complete. All

traffic signals are operational including pedestrian

crossing indicators. Minor pickup work remains and

is scheduled for completion by the end of November

2016

Page 18: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Century Blvd

No Anticipated Work at This Time

Page 19: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Casino and Pavilion Demo

Page 20: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Casino and Pavilion Demo

• Casino demo is

nearly complete

aside from

basement.

• Pavilion Soft Demo

is complete (removal

of non structural

items)

• Pavilion Hard Demo

to begin week of

11/28.

Page 21: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Gutting of Pavilion

Casino and Pavilion Demo

Page 22: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium Update

Page 23: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium Update

• Mass Grading

• Nightly Dust Control

• Mobilizing trailer complex

• Engaging local workforce – Ramping up in January

• THJV and the community

Page 24: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Mass Grading

Page 25: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Dust Control

• There are currently 13 pieces of Dust Control Equipment

working

• Water Trucks run continuously from 7:00am to 5:30pm

• The quantity of water that is placed averages 1,300,000

gallons/day

Kiewit Infrastructure West is the subcontractor currently

working on the site. If you or your neighbors have

additional concerns please contact one of the following

Kiewit Managers immediately:

Allison Reinicke (310) 846-2402

Ron Robison (310) 846-8402

Page 26: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Scrapers

Page 27: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Mobilizing Trailer Complex

Page 28: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Engaging Local Workforce

Information and Resource Fair

Date: Thursday, December 1, 2016

Time: 9:00 am to 2:00 p.m.

Location: Rogers Park (Gymnasium & Auditorium), 400

West Beach Avenue, Inglewood, California, 90301

Page 29: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

SUMMARY/OVERVIEW

Page 30: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Plan Overview

Page 31: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 32: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 33: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 34: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 35: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 36: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 37: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 38: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany
Page 39: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium –Southeast View

Page 40: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium –Lake Park View

Page 41: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium –Champions Plaza

Page 42: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Stadium – Entrance

Page 43: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Q & A

Page 44: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

To receive construction

updates or for questions

email

[email protected] call

424-750-3598

Page 45: Hollywood Park Construction Update Meetinglastadiumathp.com/wp-content/uploads/2017/04/Area-Community-M… · Hollywood Park Development Gerard McCallum, Project Manager, Wilson Meany

Dust Control

• There are currently 13 pieces of Dust Control Equipment

working

• Water Trucks run continuously from 7:00am to 5:30pm

• The quantity of water that is placed averages 1,300,000

gallons/day

Kiewit Infrastructure West is the subcontractor currently

working on the site. If you or your neighbors have

additional concerns please contact one of the following

Kiewit Managers immediately:

Allison Reinicke (310) 846-2402

Ron Robison (310) 846-8402