hollywood park construction update...
TRANSCRIPT
November 19, 2016
Hollywood Park
Construction Update
Meeting
PROJECT TEAM
Introduction and Welcome
Michelle Ballard, VP, Community & Citizenship,
Turner-Hunt JV
Infrastructure Update
Juresha Alemayehu, Senior Project Engineer,
Turner
Casino Demo
Elston Ridgle, Safety Manager,
Turner-Hunt JV
Stadium Update
Dave Masel, General Superintendent – Field Operations,
Turner-Hunt JV
Hollywood Park Development
Gerard McCallum, Project Manager,
Wilson Meany
INFRASTRUCTURE
Building Demolition
100% Complete
Site Demo & Crushing
80% Complete
Street Widening & Hardscape
95% Complete
Environmental Remediation: 178 Acres
Grading: 27 Acres
Storm Drain Relocation
99% Complete
Offsite Sewer Improvements
100% Complete
GRADING AREA AROUND STADIUM
BOWL
GRADING AREA AROUND STADIUM
BOWL
Anticipated Work
ANTICIPATED WORK
Onsite
• Infrastructure will continue to remediate unsuitable soil and demo Northern 60 acre parking lot
Prairie
• Ground Cover being planted and irrigation systems undergoing final testing.
• Minor clean-up work will continue to the end of November.
Century
• No Anticipated Work at this time.
Prairie Ave
Landscaping along Prairie
Ave. is nearly complete.
Ground Cover is being
planted and irrigation
systems are undergoing
final testing. Anticipated
completion in early
December 2016.
Paving & Striping on Prairie
Prairie Ave. paving and striping is complete. All
traffic signals are operational including pedestrian
crossing indicators. Minor pickup work remains and
is scheduled for completion by the end of November
2016
Century Blvd
No Anticipated Work at This Time
Casino and Pavilion Demo
Casino and Pavilion Demo
• Casino demo is
nearly complete
aside from
basement.
• Pavilion Soft Demo
is complete (removal
of non structural
items)
• Pavilion Hard Demo
to begin week of
11/28.
Gutting of Pavilion
Casino and Pavilion Demo
Stadium Update
Stadium Update
• Mass Grading
• Nightly Dust Control
• Mobilizing trailer complex
• Engaging local workforce – Ramping up in January
• THJV and the community
Mass Grading
Dust Control
• There are currently 13 pieces of Dust Control Equipment
working
• Water Trucks run continuously from 7:00am to 5:30pm
• The quantity of water that is placed averages 1,300,000
gallons/day
Kiewit Infrastructure West is the subcontractor currently
working on the site. If you or your neighbors have
additional concerns please contact one of the following
Kiewit Managers immediately:
Allison Reinicke (310) 846-2402
Ron Robison (310) 846-8402
Scrapers
Mobilizing Trailer Complex
Engaging Local Workforce
Information and Resource Fair
Date: Thursday, December 1, 2016
Time: 9:00 am to 2:00 p.m.
Location: Rogers Park (Gymnasium & Auditorium), 400
West Beach Avenue, Inglewood, California, 90301
SUMMARY/OVERVIEW
Plan Overview
Stadium –Southeast View
Stadium –Lake Park View
Stadium –Champions Plaza
Stadium – Entrance
Q & A
Dust Control
• There are currently 13 pieces of Dust Control Equipment
working
• Water Trucks run continuously from 7:00am to 5:30pm
• The quantity of water that is placed averages 1,300,000
gallons/day
Kiewit Infrastructure West is the subcontractor currently
working on the site. If you or your neighbors have
additional concerns please contact one of the following
Kiewit Managers immediately:
Allison Reinicke (310) 846-2402
Ron Robison (310) 846-8402