HIGH SPEED RAIL TEST TRACK XIAN Facts Project Description High-speed railway track (up to 350km/h) with a total length of 500 km incl. bedding and ballastless track system "Slab Track System Züblin". Thereof 80km tunnels, 280km bridges, 140km earth structures. 1. Test Track Design and construction of all substructures (800m tunnel, 4.5km bridges, 4.5km cuts, embankments) incl. major foundation measures. Design and construction of track works as ballastless track system, incl. numerous turn- outs. 1 station. 2. Know-how Transfer of the Ballastless Track Technology - Transfer of specific know-how and utilisation riths for the "Züblin Type" Ballastless Track System - Technical documentation for the design - Training of the design institutes with regard to design and surveying - Checking and revision of the design - Training of the Chinese companies - Site supervision and quality management during construction - Technical support and quality management of the sleeper production 3. Production and delivery of special machinery Züblin developed and produced in total 16 machinery and equipment units in China City/Country Xi`an / China Client PG "Special Passenger Railway Line Zhengzhou-Xi'an", Zhengzhou Architect DEC/Parsons Brinckerhoff/Design Institut Contract Value € 69,60 Mio. Construction Period 10/2005 - 10/2007 (24 months) .

Upload: trinhphuc

Post on 05-Jul-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

HIGH SPEED RAIL TEST TRACK XIAN

Facts Project DescriptionHigh-speed railway track (up to 350km/h) with a total length of 500 km incl. bedding andballastless track system "Slab Track System Züblin". Thereof 80km tunnels, 280kmbridges, 140km earth structures.

1. Test TrackDesign and construction of all substructures (800m tunnel, 4.5km bridges, 4.5km cuts,embankments) incl. major foundation measures.Design and construction of track works as ballastless track system, incl. numerous turn-outs. 1 station.

2. Know-how Transfer of the Ballastless Track Technology- Transfer of specific know-how and utilisation riths for the "Züblin Type" Ballastless TrackSystem- Technical documentation for the design- Training of the design institutes with regard to design and surveying- Checking and revision of the design- Training of the Chinese companies- Site supervision and quality management during construction- Technical support and quality management of the sleeper production

3. Production and delivery of special machineryZüblin developed and produced in total 16 machinery and equipment units in China

City/Country

Xi`an / China

Client

PG "Special Passenger Railway LineZhengzhou-Xi'an", Zhengzhou

Architect

DEC/Parsons Brinckerhoff/Design Institut

Contract Value

€ 69,60 Mio.

Construction Period

10/2005 - 10/2007 (24 months)

.