high radiation to materials project report · high radiation to materials project report iefc,...

38
HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility Reminder Installation progress report WANF and T1 dismantling Primary beam line Irradiation area Next steps Commissioning plans Summary S. Evrard EN/MEF EDMS No: 1126463 Thanks to: I. Efthymiopoulos, A. Pardons, M. Meddahi, C. Hessler, N. Conan, C.Theis, Y. Algoet Ph. Trilhe, C. Magnier, D. Grenier, B.Goddard, V. Kain

Upload: others

Post on 11-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

HIGH RADIATION TO MATERIALS PROJECT REPORT

IEFC, February 11, 2011

Outline

The HiRadMat facility – Reminder

Installation progress report

WANF and T1 dismantling

Primary beam line

Irradiation area

Next steps

Commissioning plans

Summary S. Evrard – EN/MEF

EDMS No: 1126463

Thanks to: I. Efthymiopoulos, A. Pardons, M. Meddahi, C. Hessler, N. Conan, C.Theis, Y. Algoet

Ph. Trilhe, C. Magnier, D. Grenier, B.Goddard, V. Kain

Page 2: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

The HiRadMat Facility – Reminder

S. Evrard -IEFC - Feb.11, 2011

2

Facility to study the impact of intense pulsed beams on materials Thermal management (heating)

material damage even below melting point

material vaporization (extreme conditions), cavitation

Radiation damage to materials – change of properties

Thermal shock - beam induced pressure waves

Important test bed for the design validation of LHC near-beam components before installation in the machine

Uses LHC-type beam protons @450 GeV from 1-288 bunches, 1.1 (nominal) to 1.7 (ultimate) x 1011 ppb

ions @177 GeV/n from 1-52 bunches, 7 x 107 – 3.6 x 109 ipb

Foreseen clients : LHC collimators, protection devices, machine components, material studies (bulk, superconductors), high-power targetry, irradiation tests of electronics Transnational Open Access within EUCARD to other teams

Goals

Page 3: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

The HiRadMat Facility – Reminder3 Location

SPS

TI 2

T9 target area / TNC

TT60

Beam

End of common part

with TI 2 transfer line

50 m

Beam

S. Evrard -IEFC - Feb.11, 2011

TT66 new line

Page 4: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

The HiRadMat Facility – Reminder4 Location

S. Evrard -IEFC - Feb.11, 2011

BA7

TCC6 B.846

TNC

TT61

Page 5: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Progress report – WANF & T1 dismantling5 T1 removal

September 2009January 2011

February 2011

S. Evrard -IEFC - Feb.11, 2011

Page 6: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Progress report – WANF & T1 dismantling6

Horn and support sent to waste storage (ISR)

Stripline treated in TT4 by ENDEL

WANF Horn removal

S. Evrard -IEFC - Feb.11, 2011

Page 7: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Progress report – WANF & T1 dismantling7

2 stages

~ remotely controlled

Moved to waste storage (ISR)

WANF collimator removal

S. Evrard -IEFC - Feb.11, 2011

Page 8: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Obsolete services dismantling in TNC & TCC68

Old lighting system (temporary one installed) Air ducts in TCC6 and TNC Piping works in TCC6 and TNC Cable trays in TJ7 and WANF Obsolete crane power line Fire detection in WANF Old vacuum DN250 pipe

Progress report – WANF & T1 dismantling

S. Evrard -IEFC - Feb.11, 2011

Page 9: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Waste disposal path9

Progress report – WANF & T1 dismantling

Summary of waste handled by RP-RW

TOTAL 89 transports 83 T. 270 m3

0

5

10

15

20

25

30

35

40

45

jan feb mar apr may jun jul aug sep oct nov dec jan fev

masse (t)

vol (m3)

WANFTT4

ISR

573

BA7

24-Jan-11 WANFen

attenteSupport acier,alu 932 2.232

24-Jan-11 WANF 4559080 gaines ventilation 1180 12.00027-Jan-11 WANF 4557234 Fer,inox,cables,dalle fp… 2212 7.5008-Feb-11 WANF 4563553 Cible t9 150 4.1488-Feb-11 WANF 4563553 Collimateur bloc acier 1700 0.252

S. Evrard -IEFC - Feb.11, 2011

Page 10: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation10

Progress report – Primary beam line

Beam

25 m

Experimental area

TI 2

TT60

TT66

S. Evrard -IEFC - Feb.11, 2011

Page 11: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation11

Progress report – Primary beam line

Beam

Experimental area

TI 2

TT60

TT66

TT60 upstream chicane:

• All magnets installed and aligned.

• Vacuum system installed and under

vacuum

S. Evrard -IEFC - Feb.11, 2011

Page 12: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation12

Progress report – Primary beam line

Experimental area

TT60

TT66

TI 2:

• Re-installation completed and under vacuum.

• Additional BPMs installed.

• TBSE installed.

S. Evrard -IEFC - Feb.11, 2011

Page 13: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation13

Progress report – Primary beam line

25 m

Experimental area

TT60

TT66

TT66 in TCC6:

Installation completed up to former T1

target position:

• Magnets/BI/vacuum system installed.

• Cables pulled and connected.

• Under vacuum.

S. Evrard -IEFC - Feb.11, 2011

Page 14: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation14

Progress report – Primary beam line

Beam

Experimental area

TI 2

TT60

TT66

TT66 in TJ7/TNC:

• Magnets and most BI installed.

• Aim to have this

part under vacuum

and the electrical

connections

completed at the

end of this

technical stop.

S. Evrard -IEFC - Feb.11, 2011

Page 15: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Beam line installation15

Progress report – Primary beam line

Beam

Experimental area

TI 2

TT60

TT66

TT66 in the passage way

between TCC6/TJ7:

• Could not yet be installed because space

is still needed for evacuation of radioactive

material from TNC and the dismantling of

the T9 target was delayed.

• Installation to be completed during the

next technical stop and accesses during

stable LHC physics beam operation.

S. Evrard -IEFC - Feb.11, 2011

Page 16: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Summary table16

Progress report – Primary beam line

Equipment Status Comments

Magnets 23/25

Vacuum pipes 75% installed 70% under vacuum

Electrical feeds 80 %

Cooling connections 80 %

Power converters 7/14 installed Last ones in March 11

Beam instrumentation & Control 70% in place

Machine interlocks depends mainly on the installed equipment

Survey 75%

Power converters for MBB and MBS magnets installed in BA6.

TT60 power converters upgraded for HiRadMat and commissioned.

4 power converters for QTL magnets installed in BA7.

Production of remaining power converters within schedule, but schedule very tight.S. Evrard -IEFC - Feb.11, 2011

Page 17: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

S. Evrard - IEFC Feb.11,2011

Infrastructure17

New crane final acceptance

Air duct installed underground

Painting of TNC

Civil engineering works

Doors refurbishment + access control tests

Progress report – Irradiation area

Page 18: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

18

Interface platform allows experiment assembly outside the irradiation area Access (time) limitations due to

LHC operation

Access limitations due to radiation

Surface lab: Experiment assembly on the

interface platform

Alignment “copy” of the installation at the

tunnel 0.1mm precision

Readout / movement tests

Will be lowered for final cabling and installation in the irradiation area

Design

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 19: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

19 Test stand manufacture

Progress report – Irradiation area

Design frozen : 3 test stands

Base plates, mobile plates and lifting devices manufactured

Successful repeatability tests of experimental area tables

Installation at the next technical stops (March, April)

S. Evrard -IEFC - Feb.11, 2011

Page 20: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

S. Evrard - IEFC Feb.11,2011

Operational RP issues20

Studies completed on:

Prompt dose rate in accessible areas

Residual dose rate in the experimental area

Activation (air & cooling circuits)

Detailed Fluka model of the facility

Several operational scenarios considered

Negligible dose rates in the accessible areas in bldg. 876 and surroundings

Top of the shaft sufficiently shielded even for the worse case scenario of HiRadMat operation

Progress report – Irradiation area

Worst case

scenario

Bldg. 876

Page 21: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

T9 to TED modification: our plan21

1. Preparatory works & T9 shielding opening2. Remove target & upstream collimator3. Remove downstream collimator blocks (4)4. Install new shielding5. Install TED (not possible right now: TED not ready) 6. Install new upstream collimator block

T9 target to become a TED dump:

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 22: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

22

January 2011: TBID dismounted Dose rate inside collimator volume

(1mx1mx1.2m) was measured (N. Conan):

Reminder: forbidden area if d> 100mSv/h

The 4 copper blocks:

Each block has a hot corner

Axis of bloc 2&3 is outside range of overhead crane

No remote handling foreseen (in 1993)

T9 to TED modification: a big challenge !

Débit de dose télétector 12.01.11

40cm à l’extérieur des blocs : 20mSv/h

5 cm à l’extérieur des blocs : 60mSv/h

430mSv/h 10-15 cm dans les blocs Cu:

1 Sv/h Max obtenu (distance non estimée)

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 23: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

23

Axis of bloc 2&3 is outside range of overhead crane

Take 1&2 / 3&4 together

Use custom-made lifting beam

No remote handling foreseen

Use existing threaded holes (4 per block)

Handling plates must be installed on copper blocks

Each block has a hot corner

Handling plates + extra shielding to protect personnel when fixing plates

Blocs will be placed inside container in sarcophagus downstream TNC (40cm iron)

T9 to TED modification: a big challenge !

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 24: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

24

Extensive tests on mock-up

(carried out 01&02/02/2011, extensive report on EDMS1119840)

T9 to TED modification: mock-up test

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 25: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

25

Presentation in ALARA L3 committee of 17/01 & 04/02/2011

Followed-up by “review in detail” in the following week (M. Tavlet, P. Bonnal, C. Theis)

Extensive documentation (procedure, DIMR, thorough risk analysis, ...) in EDMS for approval

T9 to TED modification: ALARA approval

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 26: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

26

roof block, target and collimator removed on 2/2/2011

T9 to TED modification: phase 1 & 2

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

Page 27: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

27

2 upper blocks removed on 7/2/2011

T9 to TED modification: phase 3

Progress report – Irradiation area

S. Evrard -IEFC - Feb.11, 2011

2 lower blocks should be removed today

Page 28: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

28

WANF dismantling 5 air ducts to be removed above T9

Primary beam line Complete beam line installation (passage way between TCC6/TJ7) during

technical stop in week 13.

Dry runs to check the overall beam equipment functionality (W14 & W20).

Commissioning of the facility with beam (weeks 20 and 21).

Ready for operation.

Irradiation area Complete T9 modification to TED (steps 4 to 6) in TS1/2011

Installation of 3 test stands and related services in TS1&2/2011

Install surface lab and control room

Commissioning of the facility with beam (summer 2011).

Next steps

S. Evrard -IEFC - Feb.11, 2011

Page 29: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Master schedule

DR#1 (w14)

DR#2 (w19-20)

29

Commissioning plans

S. Evrard -IEFC - Feb.11, 2011

Page 30: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

LHC 2011 Q1/Q230

Commissioning plans

HRM

Dry

Run

#1

End of HRM works

TS11-1

TS11-2 TS11-3HRM dry

run #2 +

Beam

Comm.

S. Evrard -IEFC - Feb.11, 2011

Page 31: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

LHC 2011 Q3/Q431

Commissioning plans

TS11-4 TS11-5

TS11-6

Exp

#1

Inst

.

Exp

#1

Test

Exp

#1

Test

Exp

#2

Inst

.

Exp

#2

Test

Exp

#2

Test

S. Evrard -IEFC - Feb.11, 2011

Page 32: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

32

We managed to squeeze the HiRadMat installation work foreseen initially in two shutdowns in only one year

Despite the disturbance caused by the “Copper block story” and thanks to the efforts and flexibility of many people the HiRadMat is well on track, with commissioning sometime in Summer’11 with first experiments hopefully later in Autumn’11

Within the project, old facilities: T1 & T9 targets, WANF have been dismantled which is a bonus for CERN

Lot of work is being put to fine tune the irradiation area and the associated infrastructure in view of the future users and the future experiments

We are quite pleased to receive 12 beam requests and we hope to be able to do some experiments in 2011. The decision to run the LHC the whole 2012 is welcome and allow us to establish a challenging schedule for 2012 as well

Doing experiments in HiRadMat would be very interesting, lots of physics questions to answer, but also very challenging

For further info – keep tuned to : http://cern.ch/hiradmat

Summary

S. Evrard -IEFC - Feb.11, 2011

Page 33: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Spares33

Page 34: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

Risk analysis34

:Questions to be addressed:

For each possible incident: what are the consequences?

How frequently each possible incident might occur?

Risk evaluation matrix

takes into account:

Probability of occurrence

Severity of consequences

Risk is the “product” of the probability times the severity

M. Gruwe - IEFC Workshop 2010

Progress report – Irradiation area

Page 35: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

M. Gruwe - IEFC Workshop 2010

Risk management35

Questions to be addressed:

What can we do to minimize the probability of an incident?

What can we do to minimize the consequences of an incident?

What can we do to minimize the risk?

What do we choose to do, and why ?

Content: Explanation of the technical and organizational choices

Purpose is to ensure

Adequacy of the system with the requirements

Traceability of the technical and organizational choices

Validity in time of these choices

Coherence (in time) between the system and the safety requirements

Progress report – Irradiation area

Page 36: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

The HiRadMat @ SPS

I. Efthymiopoulos - EDMSNo:1120918

36

HiRadMat beam time requests can be submitted via a form in our web page

http://cern.ch/HiRadMat

HiRadMat is included in the EUCARD/FP7 project as Transnational Access

http://eucard.web.cern.ch/EuCARD/activities/access/

Funds available to support EU users for the exploitation of the facility – within limits!

Application forms will be reviewed by a User Selection PanelMandate:

Evaluate the scientific merit of the proposed experiments

Discuss safety or other operational issues

Distribute yearly beam time and EU funds

12 applications received so far for 2011 !!!

Transnational Access

Page 37: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

OperationGeneral lines37

Guidelines 10 users/year

(up to) 10^15 protons/user

(up to) 100 high intensity pulses: 100x3.0E11 p/pulse

Several pilot pulses/user during setup

Pilot pulses (setup) can be done in an almost transparent way to present operations

High-intensity pulses will be done in dedicated HiRadMat cycles – no other physics for SPS

HiRadMat cycle parameters studied Impact on magnets/power supplies

Impact on physics schedule for SPS users

S. Evrard -IEFC - Feb.11, 2011

Page 38: HIGH RADIATION TO MATERIALS PROJECT REPORT · HIGH RADIATION TO MATERIALS PROJECT REPORT IEFC, February 11, 2011 Outline The HiRadMat facility –Reminder Installation progress report

User’s support38

Future users already interested in using HiRadMat Collimator phase 2 (prototyping work)

LHC beam dump entrance window robustness

Studies of protection devices and windows (TE-ABT)

Vacuum chamber coatings for electron cloud mitigation

R2E teams - irradiation facility – radiation damage

BLM developments

LARP Rotatable Collimator Robustness Test (SLAC)

Radiation tolerance tests (EN-STI)

ISOLDE – Target and Ion Source Development

Infrastructure needed for users Racks/space for electronics and readout in BA7

Lab space nearby

Office space

Training and access procedure

S. Evrard -IEFC - Feb.11, 2011