high radiation to materials project report · high radiation to materials project report iefc,...
TRANSCRIPT
HIGH RADIATION TO MATERIALS PROJECT REPORT
IEFC, February 11, 2011
Outline
The HiRadMat facility – Reminder
Installation progress report
WANF and T1 dismantling
Primary beam line
Irradiation area
Next steps
Commissioning plans
Summary S. Evrard – EN/MEF
EDMS No: 1126463
Thanks to: I. Efthymiopoulos, A. Pardons, M. Meddahi, C. Hessler, N. Conan, C.Theis, Y. Algoet
Ph. Trilhe, C. Magnier, D. Grenier, B.Goddard, V. Kain
The HiRadMat Facility – Reminder
S. Evrard -IEFC - Feb.11, 2011
2
Facility to study the impact of intense pulsed beams on materials Thermal management (heating)
material damage even below melting point
material vaporization (extreme conditions), cavitation
Radiation damage to materials – change of properties
Thermal shock - beam induced pressure waves
Important test bed for the design validation of LHC near-beam components before installation in the machine
Uses LHC-type beam protons @450 GeV from 1-288 bunches, 1.1 (nominal) to 1.7 (ultimate) x 1011 ppb
ions @177 GeV/n from 1-52 bunches, 7 x 107 – 3.6 x 109 ipb
Foreseen clients : LHC collimators, protection devices, machine components, material studies (bulk, superconductors), high-power targetry, irradiation tests of electronics Transnational Open Access within EUCARD to other teams
Goals
The HiRadMat Facility – Reminder3 Location
SPS
TI 2
T9 target area / TNC
TT60
Beam
End of common part
with TI 2 transfer line
50 m
Beam
S. Evrard -IEFC - Feb.11, 2011
TT66 new line
The HiRadMat Facility – Reminder4 Location
S. Evrard -IEFC - Feb.11, 2011
BA7
TCC6 B.846
TNC
TT61
Progress report – WANF & T1 dismantling5 T1 removal
September 2009January 2011
February 2011
S. Evrard -IEFC - Feb.11, 2011
Progress report – WANF & T1 dismantling6
Horn and support sent to waste storage (ISR)
Stripline treated in TT4 by ENDEL
WANF Horn removal
S. Evrard -IEFC - Feb.11, 2011
Progress report – WANF & T1 dismantling7
2 stages
~ remotely controlled
Moved to waste storage (ISR)
WANF collimator removal
S. Evrard -IEFC - Feb.11, 2011
Obsolete services dismantling in TNC & TCC68
Old lighting system (temporary one installed) Air ducts in TCC6 and TNC Piping works in TCC6 and TNC Cable trays in TJ7 and WANF Obsolete crane power line Fire detection in WANF Old vacuum DN250 pipe
Progress report – WANF & T1 dismantling
S. Evrard -IEFC - Feb.11, 2011
Waste disposal path9
Progress report – WANF & T1 dismantling
Summary of waste handled by RP-RW
TOTAL 89 transports 83 T. 270 m3
0
5
10
15
20
25
30
35
40
45
jan feb mar apr may jun jul aug sep oct nov dec jan fev
masse (t)
vol (m3)
WANFTT4
ISR
573
BA7
24-Jan-11 WANFen
attenteSupport acier,alu 932 2.232
24-Jan-11 WANF 4559080 gaines ventilation 1180 12.00027-Jan-11 WANF 4557234 Fer,inox,cables,dalle fp… 2212 7.5008-Feb-11 WANF 4563553 Cible t9 150 4.1488-Feb-11 WANF 4563553 Collimateur bloc acier 1700 0.252
S. Evrard -IEFC - Feb.11, 2011
Beam line installation10
Progress report – Primary beam line
Beam
25 m
Experimental area
TI 2
TT60
TT66
S. Evrard -IEFC - Feb.11, 2011
Beam line installation11
Progress report – Primary beam line
Beam
Experimental area
TI 2
TT60
TT66
TT60 upstream chicane:
• All magnets installed and aligned.
• Vacuum system installed and under
vacuum
S. Evrard -IEFC - Feb.11, 2011
Beam line installation12
Progress report – Primary beam line
Experimental area
TT60
TT66
TI 2:
• Re-installation completed and under vacuum.
• Additional BPMs installed.
• TBSE installed.
S. Evrard -IEFC - Feb.11, 2011
Beam line installation13
Progress report – Primary beam line
25 m
Experimental area
TT60
TT66
TT66 in TCC6:
Installation completed up to former T1
target position:
• Magnets/BI/vacuum system installed.
• Cables pulled and connected.
• Under vacuum.
S. Evrard -IEFC - Feb.11, 2011
Beam line installation14
Progress report – Primary beam line
Beam
Experimental area
TI 2
TT60
TT66
TT66 in TJ7/TNC:
• Magnets and most BI installed.
• Aim to have this
part under vacuum
and the electrical
connections
completed at the
end of this
technical stop.
S. Evrard -IEFC - Feb.11, 2011
Beam line installation15
Progress report – Primary beam line
Beam
Experimental area
TI 2
TT60
TT66
TT66 in the passage way
between TCC6/TJ7:
• Could not yet be installed because space
is still needed for evacuation of radioactive
material from TNC and the dismantling of
the T9 target was delayed.
• Installation to be completed during the
next technical stop and accesses during
stable LHC physics beam operation.
S. Evrard -IEFC - Feb.11, 2011
Summary table16
Progress report – Primary beam line
Equipment Status Comments
Magnets 23/25
Vacuum pipes 75% installed 70% under vacuum
Electrical feeds 80 %
Cooling connections 80 %
Power converters 7/14 installed Last ones in March 11
Beam instrumentation & Control 70% in place
Machine interlocks depends mainly on the installed equipment
Survey 75%
Power converters for MBB and MBS magnets installed in BA6.
TT60 power converters upgraded for HiRadMat and commissioned.
4 power converters for QTL magnets installed in BA7.
Production of remaining power converters within schedule, but schedule very tight.S. Evrard -IEFC - Feb.11, 2011
S. Evrard - IEFC Feb.11,2011
Infrastructure17
New crane final acceptance
Air duct installed underground
Painting of TNC
Civil engineering works
Doors refurbishment + access control tests
Progress report – Irradiation area
18
Interface platform allows experiment assembly outside the irradiation area Access (time) limitations due to
LHC operation
Access limitations due to radiation
Surface lab: Experiment assembly on the
interface platform
Alignment “copy” of the installation at the
tunnel 0.1mm precision
Readout / movement tests
Will be lowered for final cabling and installation in the irradiation area
Design
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
19 Test stand manufacture
Progress report – Irradiation area
Design frozen : 3 test stands
Base plates, mobile plates and lifting devices manufactured
Successful repeatability tests of experimental area tables
Installation at the next technical stops (March, April)
S. Evrard -IEFC - Feb.11, 2011
S. Evrard - IEFC Feb.11,2011
Operational RP issues20
Studies completed on:
Prompt dose rate in accessible areas
Residual dose rate in the experimental area
Activation (air & cooling circuits)
Detailed Fluka model of the facility
Several operational scenarios considered
Negligible dose rates in the accessible areas in bldg. 876 and surroundings
Top of the shaft sufficiently shielded even for the worse case scenario of HiRadMat operation
Progress report – Irradiation area
Worst case
scenario
Bldg. 876
T9 to TED modification: our plan21
1. Preparatory works & T9 shielding opening2. Remove target & upstream collimator3. Remove downstream collimator blocks (4)4. Install new shielding5. Install TED (not possible right now: TED not ready) 6. Install new upstream collimator block
T9 target to become a TED dump:
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
22
January 2011: TBID dismounted Dose rate inside collimator volume
(1mx1mx1.2m) was measured (N. Conan):
Reminder: forbidden area if d> 100mSv/h
The 4 copper blocks:
Each block has a hot corner
Axis of bloc 2&3 is outside range of overhead crane
No remote handling foreseen (in 1993)
T9 to TED modification: a big challenge !
Débit de dose télétector 12.01.11
40cm à l’extérieur des blocs : 20mSv/h
5 cm à l’extérieur des blocs : 60mSv/h
430mSv/h 10-15 cm dans les blocs Cu:
1 Sv/h Max obtenu (distance non estimée)
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
23
Axis of bloc 2&3 is outside range of overhead crane
Take 1&2 / 3&4 together
Use custom-made lifting beam
No remote handling foreseen
Use existing threaded holes (4 per block)
Handling plates must be installed on copper blocks
Each block has a hot corner
Handling plates + extra shielding to protect personnel when fixing plates
Blocs will be placed inside container in sarcophagus downstream TNC (40cm iron)
T9 to TED modification: a big challenge !
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
24
Extensive tests on mock-up
(carried out 01&02/02/2011, extensive report on EDMS1119840)
T9 to TED modification: mock-up test
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
25
Presentation in ALARA L3 committee of 17/01 & 04/02/2011
Followed-up by “review in detail” in the following week (M. Tavlet, P. Bonnal, C. Theis)
Extensive documentation (procedure, DIMR, thorough risk analysis, ...) in EDMS for approval
T9 to TED modification: ALARA approval
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
26
roof block, target and collimator removed on 2/2/2011
T9 to TED modification: phase 1 & 2
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
27
2 upper blocks removed on 7/2/2011
T9 to TED modification: phase 3
Progress report – Irradiation area
S. Evrard -IEFC - Feb.11, 2011
2 lower blocks should be removed today
28
WANF dismantling 5 air ducts to be removed above T9
Primary beam line Complete beam line installation (passage way between TCC6/TJ7) during
technical stop in week 13.
Dry runs to check the overall beam equipment functionality (W14 & W20).
Commissioning of the facility with beam (weeks 20 and 21).
Ready for operation.
Irradiation area Complete T9 modification to TED (steps 4 to 6) in TS1/2011
Installation of 3 test stands and related services in TS1&2/2011
Install surface lab and control room
Commissioning of the facility with beam (summer 2011).
Next steps
S. Evrard -IEFC - Feb.11, 2011
Master schedule
DR#1 (w14)
DR#2 (w19-20)
29
Commissioning plans
S. Evrard -IEFC - Feb.11, 2011
LHC 2011 Q1/Q230
Commissioning plans
HRM
Dry
Run
#1
End of HRM works
TS11-1
TS11-2 TS11-3HRM dry
run #2 +
Beam
Comm.
S. Evrard -IEFC - Feb.11, 2011
LHC 2011 Q3/Q431
Commissioning plans
TS11-4 TS11-5
TS11-6
Exp
#1
Inst
.
Exp
#1
Test
Exp
#1
Test
Exp
#2
Inst
.
Exp
#2
Test
Exp
#2
Test
S. Evrard -IEFC - Feb.11, 2011
32
We managed to squeeze the HiRadMat installation work foreseen initially in two shutdowns in only one year
Despite the disturbance caused by the “Copper block story” and thanks to the efforts and flexibility of many people the HiRadMat is well on track, with commissioning sometime in Summer’11 with first experiments hopefully later in Autumn’11
Within the project, old facilities: T1 & T9 targets, WANF have been dismantled which is a bonus for CERN
Lot of work is being put to fine tune the irradiation area and the associated infrastructure in view of the future users and the future experiments
We are quite pleased to receive 12 beam requests and we hope to be able to do some experiments in 2011. The decision to run the LHC the whole 2012 is welcome and allow us to establish a challenging schedule for 2012 as well
Doing experiments in HiRadMat would be very interesting, lots of physics questions to answer, but also very challenging
For further info – keep tuned to : http://cern.ch/hiradmat
Summary
S. Evrard -IEFC - Feb.11, 2011
Spares33
Risk analysis34
:Questions to be addressed:
For each possible incident: what are the consequences?
How frequently each possible incident might occur?
Risk evaluation matrix
takes into account:
Probability of occurrence
Severity of consequences
Risk is the “product” of the probability times the severity
M. Gruwe - IEFC Workshop 2010
Progress report – Irradiation area
M. Gruwe - IEFC Workshop 2010
Risk management35
Questions to be addressed:
What can we do to minimize the probability of an incident?
What can we do to minimize the consequences of an incident?
What can we do to minimize the risk?
What do we choose to do, and why ?
Content: Explanation of the technical and organizational choices
Purpose is to ensure
Adequacy of the system with the requirements
Traceability of the technical and organizational choices
Validity in time of these choices
Coherence (in time) between the system and the safety requirements
Progress report – Irradiation area
The HiRadMat @ SPS
I. Efthymiopoulos - EDMSNo:1120918
36
HiRadMat beam time requests can be submitted via a form in our web page
http://cern.ch/HiRadMat
HiRadMat is included in the EUCARD/FP7 project as Transnational Access
http://eucard.web.cern.ch/EuCARD/activities/access/
Funds available to support EU users for the exploitation of the facility – within limits!
Application forms will be reviewed by a User Selection PanelMandate:
Evaluate the scientific merit of the proposed experiments
Discuss safety or other operational issues
Distribute yearly beam time and EU funds
12 applications received so far for 2011 !!!
Transnational Access
OperationGeneral lines37
Guidelines 10 users/year
(up to) 10^15 protons/user
(up to) 100 high intensity pulses: 100x3.0E11 p/pulse
Several pilot pulses/user during setup
Pilot pulses (setup) can be done in an almost transparent way to present operations
High-intensity pulses will be done in dedicated HiRadMat cycles – no other physics for SPS
HiRadMat cycle parameters studied Impact on magnets/power supplies
Impact on physics schedule for SPS users
S. Evrard -IEFC - Feb.11, 2011
User’s support38
Future users already interested in using HiRadMat Collimator phase 2 (prototyping work)
LHC beam dump entrance window robustness
Studies of protection devices and windows (TE-ABT)
Vacuum chamber coatings for electron cloud mitigation
R2E teams - irradiation facility – radiation damage
BLM developments
LARP Rotatable Collimator Robustness Test (SLAC)
Radiation tolerance tests (EN-STI)
ISOLDE – Target and Ion Source Development
Infrastructure needed for users Racks/space for electronics and readout in BA7
Lab space nearby
Office space
Training and access procedure
S. Evrard -IEFC - Feb.11, 2011