hc precast system. _ 1.0-hcps-malaysian technology.… · open system and proprietary system is a...
TRANSCRIPT
. Open System And Proprietary System Is A Technology
. Important Precast elements requirements to complete a building is
“ Sequence Of Work ” & “ Comply To The Code ” and Precast building
elements should not involve many different manufactured components.
HC Precast System100% Malaysian Technology with 5 IP’s (Intellectual Property)
Customized & Flexibility to suit all Architectural Demands
. Industrialised Building System Is A System Not A Machine Or Component
Box system Load bearing wall Modular shear keys ( wet joint )
Important Elements Required To Complete A Building Is Sequence Of Work : 5 Steps & No Variation Order
Step 1 : Drawing Conversion 2D to 3D
Step 2 : Mould Fabrication
Step 3 : Production (advance casting)
Step 4 : Delivery (4 options)
Step 5 : Installation (numbering)
Decide by Client (Speed & Production)
HC Precast System
IBS Superstructure In Malaysia 3 in 1
. System Provider or Manufacturer should provide installer of the building precast elements
. Important Precast elements requirements to complete a building is “ Sequence Of Work ” & “ Comply To The Code.”
Original 2D To System 3D
Step 1.0 : - Drawing conversion 2D to 3D
- 1 Month
Original drawing
Step 1.1 : - M & E conversion original to system shop drawing
- 1 Month
System shop drawing - 1
Step 1.2 : - M & E shop drawing system - No hacking for M&E work
- Provided by HC Precast
1 - Light & Fan Point 2 - Power Point
System shop drawing - 2
3 - Switch Point 4 - Tel & MATV Point
Step 1.2 : - M & E shop drawing system - No hacking for M&E work
- Provided by HC Precast
System shop drawing - 3
Step 1.3 : - M & E shop drawing system - No hacking for M&E work
- Provided by HC Precast
5 - Sanitary & plumbing
Step 2.0 : - Mould Fabrication
- 1 Month
Received tiling work
- Designed by you - Coping one cast - Chequer plate ( Tiling )
- Half Slab- Door Frame one Cast- L shape Panel
Step 3 to 5 : Decide client ( speed & production )
- Production 7 to 9 units single storey per day / Capcity
- Quality control & Assurance
- Delivery
- 4 options ( Logistic )
- Installation
- Block by block & One time adjustment
- Numbering sequence
Step 3 to 5 : - Decide by client ( speed & production )
- Production 7 to 9 units single storey per day - Capacity
- Proper Storage Yards - Bay yard storage 7 days- G30 design mixed 14 hours hoist - Panel 18 hours hoist
Future development 13 acres
2,500 to 3,500 units( single storey / 1000 ft2 per year )
Existing production 8 acres
1,800 to 2,500 units( single storey / 1000 ft2 per year )
Step 3 to 5 : - Decide by client ( speed & production )
- Production 7 to 9 units single storey per day - Capacity
Decide by client
Rebound Hammer Test Panel Lifting Vertical Curing 7 days Proper Storage Yards
Every Truck Every 20 m3
Step 3 to 5 : - Production
- Quality Control & Assurance
Casting & Leveling Mould Dismantling
Step 3 to 5 : - Decide by client ( Delivery )
- Delivery ( 4 options / Logistic )
- Internal transport to block yard
Step 3 to 5 : - Decide by client ( Delivery )
- External transport to project - Internal transport to Block yard
- Proper Storage Yards - G30 design mixed 14 hours hoist - Panel 18 hours hoist - Bay yard storage 7 days
- External transport to project
Delivery ( 4 options / Logistic )
1. Bay Yard to Block Yard 2. Bay Yard to Site yard (project) – Advance Casting
3. Storage Yard (factory) to Block Yard – Advance Casting 4. Storage Yard (factory) to Site Yard (project) – Advance Casting
Step 3 to 5 : - Installation Block by Block
- One Time Adjustment
Blk - 1 Blk - 2
Blk - 3
Blk - 4
Blk - 5
- Installation block by block - One time adjustment ( 25 mm tolerant )
Step 3 to 5 : - Installation
- Numbering Sequence
IBS Superstructure In Malaysia 3 in
Load bearing wall, Modular shear keys ( wet joint ) & Box system
10 days completed with 6 workers
Superstructure - Frame, Wall & R.C Flat Roof
THANK YOU
ANY DESIGN
CAN BE BUILT
BY HC PRECAST SYSTEM