1 71 I 5.4.7 - IT
Infrastructure at the
State Data Center and
Disaster Recovery
Center - Indicative
Hardware Bill of
Material
600 VA UPS with 60 Min backup No specifications has been provided for this product. We would like to suggest
minimum specifications as under in order to provide clarity to all bidders:- "600
VA Line Interactive UPS with 60 min. backup on single PC load & min. battery
capacity of 336 VA"Please refer to the
Corrigendum for the
specifications of 600 VA UPS
2 104 I 5.5 - Scope of Services -
Post-Implementation
Phase / Operate and
Maintain Phase
(Volume I)
SI shall provide the Operations
and Maintenance Services for a
period of <<5>> years following
the deployment and “Go-Live” of
the complete solution in the
Haryana Police.
As the project period is for 5 years, we suggest that batteries being a
consumable item, at least one mandatory replacement of batteries during the 5
year period may be defined, in order to ensure proper battery backup.SI is required to meet the
Service Levels as defined for
the project. Hence SI shall
provide with as many
replacements required to
keep them running and
finally at the end of the
project the hardware handed
over to the department
should be in good
accepetable conditions.
Please refer RFP for more
details
3 187 Backup period should be atleast 2
Hr with minimum 3000 VAH for
3KVA
The VAH specified may be insufficient to provide 2 hours backup, and may
kindly be enhanced to atleast 7200 VAH.
4 187 Isolation Transformer It is recommended to specify that an inbuilt galvanic isolation transformer at
UPS input may be provided in the UPS System to provide protection from
surges & spikes prevalent in input power supply especially at rural areas.
6 187 The proposed DG set should be
able to support the Police Unit
equipments along with AC, in
absence of primary power source.
We request that DG set requirement of min. 5 KVA be considered to support
3KVA UPS, since the current for battery charging for 2 hrs. has also to be taken
into account.
7 187 Engine Type - Multi Cylinder We suggest that kindly consider Single / multi Cylinder in lieu of Multi Cylinder
for such small rating of DG Set.
Haryana CCTNS RFP: Pre-Bid Queries and Responses
I
3. Technical
Specifications of SNMP
based UPS System -
Annexure V (Volume -
1)
Please refer to the
Corrigendum for the
updated specifications of
SNMP based UPS
I
4. Technical
Specifications of 2KVA
Generator Set -
Annexure V (Volume -
1)
Please refer to the
Corrigendum
8 132 III 9 (B) (i) Layer 2 switch Should have Layer 2/L3 Stackable switch9 132 III 9 (B) (ii) 24 No 10/100 ports Should Support 24 No 10/100/1000 PoE Plus ports
10 132 III 9 (B) (iii) 2 Nos. 10/100/1000 Should Support 2 Nos. of dedicated 1000 Base X11 133
III 9 (B) (iv) Nonblocking architectureShould have support to enable dedicated 64Gbps Stacking and 2* 10G ports by
seemless addition of hardware resources
12 133
III 9 (B)(v) 8 Gbps switching fabric and 6
Mpps forwarding rate
Must Have Nonblocking architecture or Pls. increase the Switching Fabric to 32
Gbps switching fabric and 6.5 Mpps forwarding rate
13 133
III 9 (B)(vi) Support IGMP Snooping with
Broadcast Control IGMP v3.
Should have minimum 160 Gbps switching fabric and 65.5 Mpps forwarding
rate
14 133III 9 (B)
(vii) Support for minimum 8000
MAC addresses.Should Support IGMP Snooping with Broadcast Control IGMP v3.
15 133III 9 (B)
(viii) Ethernet, Fast Ethernet
supportShould Support for minimum 20000 MAC addresses.
16 133III 9 (B)
(ix) Spanning tree/Rapid Spanning
Tree supportShould Support Ethernet, Fast Ethernet support
17 133III 9 (B) (x) Per VLAN Spanning Tree Should Support Spanning tree/Rapid Spanning Tree support
18 133III 9 (B)
(xi) Support for dynamic VLAN
RegistrationShould Support Per VLAN Spanning Tree
19 133III 9 (B)
(xii) Dynamic Trunking Protocol or
equivalent.Should Support for IEEE 802.1Q tagging
20 133III 9 (B)
(xiii) VLAN Trunking Protocol or
equivalentShould support Link Aggragtion Control Protocol
21 133
III 9 (B)
(xiv) Traffic classification should
be based on user-definable
application types: TOS, DSCP, Port
based, Mac address, IP address,
TCP/UDP port number
22 133III 9 (B)
(xv) Multicast filtering per port
should be supportedMulticast filtering per port should be supported
23 133III 9 (B) (xvi) Support SNMP upto ver.3 Should Support SNMP upto ver.3
24 133 III 9 (B) (xvii) Prioritization support Should have Prioritization support25 133 III 9 (B) (xviii) Minimum 250 vlans Should support Minimum 500 vlans26 133 III 9 (B) (xix) SNMP and Telnet support Must have SNMP and Telnet support27 133
III 9 (B)(xx) Web-based and CLI
management Should Support both Web-based and CLI management
Please refer to the
Corrigendum for the
updated specifications of
Switch
28 133III 9 (B) (xxi) Four RMON groups (1,2,3&9) Should have Four RMON groups (1,2,3&9)
29 133III 9 (B)
(xxiii) L3 Features : Static routes &
RIPPls. add this Point Out of Band Management Ethernet RJ45 Port
30 NAPls. add L3 Features : Static routes, RIPv1 & v2 and RIPng. IP v6 Should be
supportable both on Hardware as well as Software
31 NAPls. add the following features Security : Time based L2/L3/L4 Access Control
Lists, 802.1x and AAA Radius support
32 133III 9 (B)
(xxiv) Mounting: 19” Rack
mountableMounting: 19” Rack mountable
33 133
III 9 (B)(xxv) Source power supply: 230 V
AC Single phase 50Hz
Should support Source power supply: 230 V AC Single phase 50Hz to internal
hot swappable PSU. Support for Internal RPSU.
34Should have Enviornment and Cooling : 0 to 45 degree Celcius. Hotswapanble
Fan tray for continious operation
35 Please provide extension for four weeks for submission of the bid. This is
required to understand the complexities involved in the programPlease refer to the
Corrigendum
36
32 II
Section 3.6 Failure to
agree with the Terms
and Conditions of the
RFP
Failure of the successful bidder to
agree with the Terms &
Conditions of the RFP shall
constitute sufficient grounds for
the annulment of the award, in
which event Haryana Police
may award the contract to the
next best value bidder as per
Haryana State Government Policy
or call for new proposals from the
interested bidders or invoke the
PBG of the most
responsive bidder as per section
2.8 of this volume.
We understand that state is referring about EMD rather than PBG because PBG
would not have been submitted by the successful bidder.
Please refer to the
corrigendum
37
33 II Section 4.1
A PBG of 10% of value of the
contract would be furnished by
the bidder in the form of a Bank
Guarantee as per the attached
format in Annexure
Please reduce PBG to 5% of total value or equivalent to 35% of project value
(amount payable in Implementation phase) as all the payment milestones apear
after the serivces or infrastructure is deliverd. Also, allow PBG issued by Bank of
America.
Please refer section 4.1,
Vol.II of this RFP
Please refer to the
Corrigendum for the
updated specifications of
Switch
38
33 II Section 4.2
In the event of the Bidder's failure
to submit the Bonds, Guarantees
and Documents and supply the
solution / equipment as per
schedule specified in this RFP,
Haryana Police may at its
discretion withhold any payment
until the completion of the
contract. Haryana Police may also
deduct from the Bidder as agreed,
liquidated damages to the sum of
0.5% of the contract price of the
delayed/undelivered services (as
detailed in Volume I of this RFP)
for every week of delay or part of
a week, subject to the maximum
value of the Liquidated Damages
being not more than 10% of the
value of delayed services. This
right to claim any liquidated
damages shall be without
prejudice to other rights and
LD should be applicable for the delay directly attributable to the vendor.
Further LD should be the sole and exclusive remedy.
Please refer section 4.2,
Vol.II of this RFP
39
82 IIF. Undertaking On
Patent Rights
1. I/We as System Integrator (SI)
do hereby undertake that none of
the deliverables being provided by
us is infringing on any patent or
intellectual and industrial property
rights as
per the applicable laws of relevant
jurisdictions having requisite
competence.
2. I/We also confirm that there
shall be no infringement of any
patent or intellectual and
industrial property rights as per
the applicable laws of relevant
jurisdictions having
requisite competence, in respect
of the equipments, systems or any
part thereof to be supplied by us.
We shall indemnify Haryana Police
against all cost/claims/legal
claims/liabilities arising from third
party claim in this regard at any
We request to consider restricting the provisions to the IPs existings and
registered in India. The format should be linked with relevant scetion of MSA of
the RFP. The IP infringement should have exclusion like: (a) Client's use of the
Deliverable other than in accordance with the Agreement ; (b) modification of
the Deliverable other than by or on behalf of Accenture; (c) the Client's failure
to use corrections or enhancements that have been made available by
Accenture; (d) the Client's use of the Deliverable in combination with any
product or information not owned or developed by Accenture, except to the
extent contemplated in the Agreement; (e) the Client’s distribution, marketing
or use of the Deliverables, for the benefit of third parties; (f) information,
software, direction, specification or materials provided by the Client or any
third party; or (g) any wilful, wrongful or negligent act or omission of the Client
in its use of the Deliverable.
The proposed Undertaking is
as per the guidelines of
NCRB. Hence, No Change
40
30 IIISection 2.20, Audit,
Access and Reporting
The System Integrator shall allow
access to the CLIENT or its
nominated agencies to all
information which is in the
possession or control of the
System Integrator and which
relates to the provision of the
Services as set out in the Audit,
Access and Reporting Schedule
and which is
reasonably required by the CLIENT
to comply with the terms of the
Audit, Access and Reporting
Schedule set out as Schedule IV of
this Agreement.
We request to consider modification and include the provision that any such
audit should be subject to the following conditions: 1. Reasonable prior written
notice of the audit (not less than 3 weeks); 2. Confidentiality obligations on the
Client and auditor; 3. Audit is not carried out by the SI's competitor; and 4.
Scope of audit is restricted to assess compliance of obligations under the
Contract
Please refer section 2.20,
Vol. III of this RFP
41
III
We request to consider adding a liability cap section in the RFP as under: "The
sole liability of SI (whether in contract, indemnity, tort, negligence, strict liability
in tort, by statute or otherwise) for any claim in any manner related to this
Agreement, including the work, deliverables or services covered by this
Agreement, shall be the payment of direct damages and damages due by SI
under this Agreement shall in no event in the aggregate exceed the yearly fees.
In no event shall either party be liable for any consequential, incidental,
indirect, special or punitive damage, loss or expenses (including but not limited
to business interruption, lost business, lost profits, or lost savings) even if it has
been advised of their possible existence. Each Party has a duty to mitigate the
damages and any amounts payable under an indemnity or any claim that would
otherwise be recoverable from the other Party pursuant to this Agreement by
taking appropriate and commercially reasonable actions to reduce or limit the
amount of such damages or amounts".
Please refer to the
Corrigendum
42
28 ISection 5.2.1, CCTNS
Functional Modules
FSL module: DNA databank with
cross matching facility will be a
part of it.
This functionality has little in common with other requirements. Please confirm
that DNA databank is not part of the project. Also, please explain what
functionality really needs to be developed.
Please refer Annexure VI,
Vol. I of this RFP for further
details
43
30 ISection 5.2.1, CCTNS
Functional Modules
Knowledge Management Module Please share volume of documents that will be part of this module. Also, what
are the formats that needs to be supported.
Please refer Annexure VI,
Vol. I of this RFP for further
details44
30 ISection 5.2.1, CCTNS
Functional Modules
Geographic Information System Is GIS implemented in the state already? Will same GIS software will continue to
be used after CAS implementation? We understand that the scope here is
interface with existing GIS system.
GIS is not implemented in
the State
45
30 ISection 5.2.1, CCTNS
Functional Modules
Global Positioning System Please confirm that state will own and operate GPS hardware/ services. CAS
application will provide required interface to the system.Please refer to the
Corrigendum
46
42 I Section 5.3
Implement (This shall only begin
after CAS (State) has been
received from NCRB, MHA) – T1
What is the dependency of time cycle T with T1? Can T and T1 time cycles run in
parallel? SI is required to meet the
project timelines as defined
in the RFP. Please refer RFP
for more details
47
60 I Section 5.4.3.5
The selected System Integrator
would create a testing &
development environment for the
CCTNS integrated solution to be
implemented in Haryana. This
would be maintained by the
vendor and transferred to the
Department at the end of the
contract at no additional cost.
Are the required hardware and software resources part of indicative BOM
shared or this needs to be considered as additional requirement. We suggest
that this requirements be captured in BOM as separate line item and specified
as part of RFP.
Yes, these are part of SI
scope. Hence, bidders are
free to include this a
separate line item
appropriately. Please refer
RFP for more details
48
61 I Section 5.4.3.7
SI shall implement all the
suggestions/ changes proposed by
Haryana Police without
considering it as part of the
Change Control till the completion
of one year of Handholding
support by SI.
Please drop this statement. All changes to application must go through change
control as best practice and to maintain traceability till the end.
Please refer section 5.4.3.7,
Vol.I of this RFP
49
62 I Section 5.4.3.7
The SI shall prepare the required
test data and get it vetted by
SPMC/ State Mission Team/SPMU
or a Third Party Agency.
Test data needs to be provided by Haryana police. This approach will make sure
that the data set is near real life and will provide better results for system
improvements.Please refer to section
5.4.3.7, Vol.I of this RFP
50
65 I Section 5.4.5
SI may propose to use the existing
SWAN connectivity or implement
VPN over broadband
Please confirm that Haryana Police will arrange for payment of broadband
charges. Also, please confirm that broadband connections will be taken in the
name of Haryana police.
Please refer Section 7, Form
2, Pg 65, Vol.II of this RFP
51
76 I Section 5.4.8
Haryana Police may, at its will,
verify the test results provided by
SI.
Haryana police is expected to provide sign off. This statement needs to be
removed.Please refer to section 5.4.8,
Vol.I of this RFP
52
77 I Section 5.4.8
Data digitization exercise shall
involve data entry of manual
records, in both English and Hindi
language
Data digitization exercise shall involve data entry of manual records in the
language it is written - in order to maintain data quality. Please confirm. Data to be digitized available
in whichever language
(Hindi/ English) will be
digitized in both Hindi and
English. Please refer RFP for
more details
53
78 I Section 5.4.8
30% records of each Police Station
under his jurisdiction
Please have a look at this matrix. District DSP will need to verify a very large
number of records and this will not be viable. Else, please confirm that DSP
office will have required number of resources to carry out this exercise.Please refer section 5.4.8,
Vol.I of this RFP
54
88 I Section 5.4.10
SI shall conduct at least three
Change Management Workshops
(minimum of one day) in the State
Police Headquarters and at least
two Change Management
Workshops (minimum of one-day)
at all the Districts (at the District
Headquarters) covering at least 3
officers/constables (SHO,
SI/ASI/HC, and Station Writer)
from each police station in the
district and one such workshop
(minimum of one-day) at HPA/
Madhuban every month for
participants of long term training
courses and also one workshop in
each RTC/ PTC (minimum of one-
day)
The requirement results into 62 change management workshops. Please
confirm if this understanding is true? Does SI have option of conducting web
based sessions for shorter duration than full day program which may not
happen effectively due to logistical reasons?
Please refer section 5.4.10,
Vol.I of this RFP
55
91 I Section 5.4.10
However, it is advised to bidders
to consider variations (increase/
decrease) up to 20% in the
number and the same shall not be
considered for any kind of
associated additional cost.
The table suggests total personnel to be trained at approximate 38000.
Considering +20% growth, the number will go up to 45000+. Please confirm
that Haryana police is looking at such large number to be trained for at least 25
hours in one year. Please refer section 5.4.10,
Vol.I of this RFP
56
93 I Section 5.4.10
The main challenges to be
addressed effectively by the SI are
the geographically dispersed
trainee base, wide variability in
education and computer
proficiency and minimal
availability of time.
We recommend that training for all personnel covered under group 4 to group
9 be done by internal trainers. Another option is that this groups can be trained
during handholding period by technical personal assigned at the site. Please
consider change in approach for this requirement.Please refer section 5.4.10,
Vol.I of this RFP
57
94 I Section 5.4.10
System Administrator training for
approximately 1000 police
officials: a few members of the
police staff with high aptitude
would be trained to act as system
administrators and
troubleshooters for CCTNS.
This seems to be too high number. Please validate. System admin is a specific
skill and needs a pre-requisite. The total number could be around 100 at the
most.
Please refer section 5.4.10,
Vol.I of this RFP
58
94 I Section 5.4.10
SI shall provide detailed training
material providing step-by-step
approach in soft and hard copies
to all police stations and offices
for reference.
Is this in addition to providing training material to all participants? It is
suggested that training material is available in soft copy format and manuals
can be printed on need basis to save paper. Please confirm. Please refer section 5.4.10,
Vol.I of this RFP
59
96 I Section 5.4.10
SI would be responsible for
providing certificate to the trained
participants for being Trainers
after conducting their
examination.
It is recommended that Haryana police provide the certificate as it will help
personnel records of participants. An online certificate can be generated at the
end of the test and can be printed by participant himself. Please confirm.Please refer to the section
5.4.10, Vol.I of this RFP
60
97 I Section 5.4.10
Class Room trainings shall be
provided on the subjects such as
Major Acts, Police Rules, Local and
Special Laws, Police functioning
and duties, etc, which are
fundamentals to CCTNS project.
Please check this requirement. SI vendors are not subject matter expert in
police rules. This training needs to be taken out from track 1. Or confirm that
track 1 training will be conducted by Haryana police.Track 1 training will be
conducted by Haryana
Police. Please refer RFP for
more details
61
98 I Section 5.4.11
The deployed qualified trained
person should support the office
from 7 AM in the morning till 11
PM in the night on all weekdays
and may remain off from duty on
Sundays.
We recommend only day time support, which will be sufficient considering
onsite presence of the person. Please consider the change.
Please refer to section
5.4.11, Vol.I of this RFP
62 During handholding period, the police stations are going to work live on CCTNS
application and a trained person is allocated to help them resolve the issue.
Please clarify the requirement of training during this period.
63 Also, it will not be possible to arrange for quality training infrastructure at police
station level. Please consider this requirement and drop this requirement.
64
99 I Section 5.4.11
It is important to mention that the
requests for amendments during
Handholding support, i.e. for one
year post Go-Live of complete
system in the State shall not be
eligible for any type of Change
requests by SI.
Please confirm that changes requested will be related to existing functionality
only and no new requirements. Also, please confirm that all changes will go
through change control process.
Please refer section 5.4.11,
Vol.I of this RFP
99 I Section 5.4.11
The SI will bear the cost of
providing the training, supply of
course material, any consumables,
IT infrastructure required for
training etc. while Haryana Police
will provide the training premises.
Please refer section 5.4.11,
Vol.I of this RFP
65
101 I Section 5.4.13
The system
developed/customized by SI shall
be reviewed and verified by
SPMC/ SPMU against the
Functional Requirements signed-
off between Haryana Police and
SI. Any gaps, identified as a severe
or critical in nature, shall be
addressed by SI immediately prior
to Pilot and Go-live of the system.
We understand that this review will happen during SRS preparation phase.
Please confirm.
Please refer to section
5.4.13, Vol.I of this RFP
66
103 I Section 5.4.14
The successful bidder shall insure
the entire hardware infrastructure
deployed at all locations for the
entire duration of the contract
against theft, vandalism, and fire
and lightening. In case of any
such event,
Please specify which hardware needs to be covered under insurance. Hardware
like desktops, digital pens etc. will be handled by Haryana police and need to be
excluded from insurance. SI can take insurance of servers deployed at SDC and
DR site. Please confirm.Please refer to the
Corrigendum
67
105 I Section 5.5
SI shall deploy personnel having
degree/ diploma of at least B.Sc.
(IT), BCA, BTech, or equivalent
Please remove this restrictions as handholding support needs to be given in
vernacular language in rural areas. Please refer section 5.5, Vol.I
of this RFP
68
106 I Section 5.5
If during contract period, any
equipment has a hardware failure
on four or more occasions in a
period of less than three months,
it shall be replaced by equivalent
or higher-level new equipment by
the SI at no cost to Haryana Police.
However, if the new equipment
supplied is priced lower than the
price at which the original item
was supplied, the differential cost
should be refunded to Haryana
Police.
Please remove this clause. Price of computer equipment drop when new
models are introduced. SI can not be penalized for change in market dynamics.
Please refer section 5.5, Vol.I
of this RFP
69
106 I Section 5.5
In case any hard disk drive of any
server, SAN, or client machine is
replaced during warranty / AMC
the unserviceable HDD will be
property of Haryana Police and
will not be returned to
SI.
Please remove this requirement, as it does not meet standard warranty
arrangement of any OEM.
Please refer to the
Corrigendum
70
106 I Section 5.5
Warranty should not become
void, if Haryana Police buys, any
other supplemental hardware
from a third party and installs it
within these machines under
intimation to the SI.
Please remove this requirement, as it does not meet standard warranty
arrangement of any OEM.
Please refer section 5.5, Vol.I
of this RFP
71
108 I Section 5.5
Establish 16X6 Help Desk facilities
for reporting issues/ problems
with the software, hardware and
other infrastructure
Please confirm that SI can work with OEM to provide a comprehensive helpdesk
support and need not establish a dedicated helpdesk support only for this
project.Please refer to section 5.5,
Vol.I of this RFP
72
113 I Section 6.2
SI shall put together a team of
domain experts with a minimum
of 10 years of experience in the
Police Department who will work
on this project on a full time basis
during the entire duration of the
project.
Staffing details do not mention this requirement. Please mention clearly what is
expected here. What sourcing model is expected for SI?
Please refer to the
Corrigendum
73
117 I Section 6.3
Third Party Acceptance Testing
Certificate
Please confirm that Haryana police will own responsibility of getting certificate
from third party after successful completion of all tests. This is because the third
party, appointed as neutral party will be answerable only to Haryana police.Please refer section 5.4.13,
Vol.I of this RFP
74
130 I Annexure 2
All the trainees within each of the
training program should pass the
training exam with more than 80%
or more marks conducted after
their training
Please modify this SLA. SI does not have nay control on police personnel. Else,
Haryana police need to make it mandatory for police personnel to take the test
again within next two working days. Please refer to the Annexure
2, Vol.I of this RFP
75
133 I Annexure 2
All the trainees should pass the
online training exam with more
than 80% marks
Please remove this metric as this will be not be a fair measurement. Instead the
metric for on-time training sessions or favorable training feedback can be taken
as fair metrics.
Please refer to the Annexure
2, Vol.I of this RFP
76
139 I Annexure 2
RPO (zero data loss in case of
failure of Primary DC) should be
zero minutes
Recovery point objectives can approach zero value. Please set reasonable limit
of performance.Please refer to the
Corrigendum
77
143 I Annexure 2
Availability of the critical client site
infrastructure components at all
the implementation sites shall be
at least 99%
Please specify components at all sites that must be up 99%. We assume that
this is true for networking components only and not for desktops, printers etc..
The system is designed to run in offline mode.Please refer Annexure 2,
Vol.I of this RFP
78
148 I Annexure 2
Availability of the network and all
related components at all the
implementation sites shall be at
least 99%
SI will be using WAN available within state. How the metric will be measured as
it will not be under control of SI? Please refer Annexure 2,
Vol.I of this RFP
79
66 II Section 7
Annual Charges for 512 Kbps
bandwidth at each location
No. of locations are shown as 270. Are this locations fixed? What happens at
police stations where WAN connectivity already exists.No. of locations are
indicative and provided for
seeking unit price of each
component. However
payments would be made on
actual quantity procured,
supplied and commissioned
as part of this project. Please
refer RFP for more details
80
68 II Section 7
Cost of digitization of data (data
entry of the Master data and
minimum historical transactional
data entry)
Please clarify what are this costing about. Unit of service is shown as 2 persons
for 3 months (6). This costs can be given per record. Please refer section 7, Vol.II
of this RFP
81
68 II Section 7
Cost of scanning of existing files
for the Integrated Workflow and
Document Management System
Please clarify what are this costing about. Unit of service is shown as 1 persons
for 6 months. This costs can be given per record. Please refer section 7, Vol.II
of this RFP
82
69 II Section 7
Change Management Trainings Change management workshop size wil depend on Group it is addressing to.
For example, for senior officers, number of attendees can be much less. For
junior officers, the number can be higher. Do you want belended rate per
workshop?
Please refer section 7, Vol.II
of this RFP
83
69 II Section 7
Trainings on the Application
modules
Is this the rate for role based training? Again, the training is different for
different groups. How SI is expected to show pricing?Please refer section 7, Vol.II
of this RFP
8470 II Section 7
Electricity charges This services are not part of scope. Please remove this line item. Please refer to the
corrigendum85
70 II Section 7Physical Security This services are not part of scope. Please remove this line item. Please refer to the
corrigendum86
86 IIAnnexure-Other
Formats : J
Undertaking on Functional
Requirement Specifications
RFP defines complete process for collecting and verifying the functional
requirements. There is no need for separate undertaking. Please consider
removing this undertaking.
Please refer to the Annexure -
Other Formats:J, Vol.II of this
RFP
87
87 IIAnnexure-Other
Formats : K
Undertaking on Offline
Functionality
RFP defines complete process for collecting and verifying the functional
requirements. There is no need for separate undertaking. Please consider
removing this undertaking.
Please refer to the Annexure -
Other Formats:K, Vol.II of
this RFP
88
88 IIAnnexure-Other
Formats : L
Undertaking on Provision for
Required Storage Capacity
This undertaking can be given meaningfully after all requirements are studied.
Please consider waiving submission of this undertaking at this stage.Please refer to the Annexure -
Other Formats:L, Vol.II of this
RFP
89
94 IIAnnexure-Other
Formats : R
I/We understand that the
certification expenses will be
borne by SI, and also the
responsibility to ensure successful
certification lies with the System
Integrator.
This cost element is not part of commercial format. Haryana police already have
an option to utilize SPMC/ SPMU services for AT. If Haryana police wants to
appoint third party, then the expense provision will have to be made by
Haryana Police.
Please refer to the Annexure -
Other Formats:R, Vol.II of
this RFP
90
95 IIAnnexure-Other
Formats : S
We undertake to design
team/organization structure at
Haryana Police to manage the
system
Please confirm that role of SI will be to provide recommendations on proposed
team size and roles.Please refer to the Annexure -
Other Formats:S, Vol.II of this
RFP
91
96 IIAnnexure-Other
Formats : T
Undertaking on Continuous
Improvement
This undertaking does not convey what is expected of SIPlease refer to the Annexure -
Other Formats:T, Vol.II of
this RFP
92
98 IIAnnexure-Other
Formats : V
Onsite team of Software
Development Agency operating
out of Haryana Police premises
will be provided only with seating
space. Any other requirements
such as desktops, software will be
System Integrator’s responsibility.
Please confirm that this is for the project implementation phase. Further, we
recommend that SI be allowed to use infrastructure available as police HQ, as
infrastructure suply is part of the project. This will ensure that there are no time
lags in implementation for SI as well as Haryana police.Please refer to the Annexure -
Other Formats:V, Vol.II of
this RFP
93
99 IIAnnexure-Other
Formats : W
I/We as System Integrator do
hereby acknowledge that we
understand that the request for
changes to contract clauses and
any other terms and conditions in
the RFP, submitted in our
proposal as per the RFP are just
suggestions for change.
Please consider removing this undertaking.
Please refer to the Annexure -
Other Formats:W, Vol.II of
this RFP
94
52 I PKI Security and Encryption
As we understand that security should be an integral part of the infrastructure
and therefore to ensure integrity and confidentiality, the data collected (both
online and offline) at the police location should be digitally signed and
encrypted before it is sent from one location to other / central data center.
Appliance based FIPS certified Hardware Security module shall help in security
of the signing key, key management and multifactor authentication to access
the key and
most significantly it will enhance the performance of the complete system by
offloading the complete cryptography. All data interchanged among various
police offices and between the users of an application interface, Core
application, Police agencies and CCTNS databases should be digitally signed and
encrypted using the PKI infrastructure. Hardware Security Module should be
used to provide a higher level of security. The PKI public and private keys will be
stored inside the hardware module thus making it inaccessible, tamper proof
and highly secure.
Please refer to the
Corrigendum
95
110 III
Enterprise
Management and
Monitoring Solution
(EMS)
As part of implementing the
monitoring tool for this project, SI
is required to procure full use CAL
licenses of the existing EMS with
Haryana State for this project
from the OEM. SI shall be
responsible for configuring and
integrating the Haryana Police
sites on the existing EMS. SI shall
be required to provide all the
necessary hardware/ software to
meet the below mentioned
indicative requirements from
EMS.
Please provide details of existing EMS running at Haryana SDC for which
licenses needs to be procured by OEM in order to cater to monitoring needs of
this project. Haryana SDC shall have CA
Spectrum , CA eHealth ,CA
Service Desk ,CA Wily
APM,CA Host based Access
Control ,CA Database
Performance ,CA Server
Monitoring software.
Additional licenses as
defined in the RFP of CA EMS
should be provided from
OEM to meet RFP
requirements. Please refer
RFP for more details
96
110 III
Enterprise
Management and
Monitoring Solution
(EMS)
As per best practice EMS servers should be set up at DC site for monitoring DR
Network devices & servers from DC .Please confirm whether you need EMS
servers at DR site as well? EMS Servers will be hosted at
SDC site only and should be
able to monitor DR network
devices & DR servers
pertaining to CCTNS project
from DC site. Please refer RfP
for more details97
110 III
Enterprise
Management and
Monitoring Solution
(EMS)
Please clarify if EMS servers running at SDC can be used wherever applicable for
monitoring CCTNS EMS components?Bidder can make use of EMS
servers at SDC & provide
necessary supporting servers
as required to meet EMS
requirements mentioned in
RFP. For more details, please
refer Annexure V, Vol.I of
this RFP
A. Minimum Technical
Specifications Requirement at
State Data Center & Disaster
Recovery Site
98
52 I
How many users should be considered for the Single Sign On solution
Entire Police force would be
the internal users of the
system. However concurrent
users would be aprrox. 2500
at present
99
52 I
It is part of the security best practice and strongly recommended to have a
defense in depth security strategy and have a security layer outside the CCTNS
application which provides centralized, policy-based Web access management
and Web single sign-on.
Specifically the following points should be part of the overarching security
requirements which has been asked in the rfp:
• Authentication management – Answering, who are you? Managing the
different users (privilege or otherwise at various authentication levels as
desired)
• Authorization management – Answering what applications and data are you
authorized to access?
• Audit – Answering what have you done? What is going on my Web
application? Who has access to what?
• Session management – Providing single sign-on (SSO), single sign-off & session
timeouts
Please refer Corrigendum for
more details
(b) Single Sign On
The Solution should enable single-
sign-on so that any user once
authenticated and authorized by
system is not required to be re-
authorized for completing any of
the services in the same session.
For employees of the Haryana
Police, the browser based
application accessed on the
intranet, through single-sign-on
mechanism, will provide access to
all the core services (based on
their roles and responsibilities),
Help module, Basic and advanced
Reporting etc. Similarly, for
external users (Citizens,
Hotels, Cyber Cafes, Hospitals,
Jails, Transport Department etc),
based on their profile and
registration, the system shall
enable single-sign on facility to
apply for various services, make
payments, submit queries
/complaints and check status of
their applications.
100
52 I(f) Security
Security design should provide for
a well-designed identity
management system, security of
physical and digital assets, data
and network security, backup and
recovery and disaster recovery
system.
The RFP clearly asks for a well designed identity management as a business
requirements, however, since the technical requirements are not mentioned
and can be interpreted in different ways by different SI’s; can the below
mentioned standard definition for Identity Management taken from Wikipedia
be taken as the basis for technical compliance?
(http://en.wikipedia.org/wiki/Identity_management_systems). It is
recommended that if DIT has a different view on Identity management
requirement than the same be brought out as part of the response to this query
so that all SI’s have the same understanding as what is to be delivered.
An identity management system refers to an information system, or to a set of
technologies that can be used to support the management of identities.
An identity management system:
1. Establishes the identity
a. Links a name (or number) with the subject or object;
b. Re-establishes the identity (i.e. links a new or additional name, or number,
with the subject or object);
2. Describes the identity:
a. Optionally assigns one or more attributes applicable to the particular subject
or object to the identity;
Please refer to the
Corrigendum
101
72 I
Data Digitization &
Data Migration: The SI
shall perform the data
digitization &
migration from
manual and/or the
existing systems to the
new system.
Integrated Investigation Form (1
to 7),Village Crime Notebook (Part
III, III A, V), Village Crime
Notebook Part II
Kindly clarify the number of pages in earch form. This would be necessary to
calulate exact number of Documents to be scanned.
Please refer to the
Corrigendum
102
103 I Licenses
The software proposed should be
from an OEM with presence in
India (and easy availability of
skilled resources for the product
in India).
Does the OEM need to have office in Haryana State? Else how to measure
availabilty of Skilled resources in India?
Please refer section 5.5, Vol.I
of this RFP
103
108 I
Scope of Services
during Operate and
Maintain Phase: The
service will be
provided in the local
language of the
Haryana Police.
Hindi & EnglishKindly clarify the if our assumption is correct. Further, Training in English &
Hindi is envisaged by us.
Services mentioned here are
part of Handholding Services
to provide Centralized
Helpdesk and support for
end user. Please refer RFP
for more details.
104
334 I
Existing Legacy
System: Registration:
Common Integrated
Police Application,
Crime Criminal
Information System.
Investigation:
Fingerprint Analysis &
Criminal Tracing
System, Portrait
Building System.
Prosecution: Court
Process Management
System (CPMS), Case
Investigation System
(CIS). Verification:
Passport Management
System, Service
Verification System.
Delivery Channel:
Web Portal, Inventory
management / Control
The data needs to be migrated to
new modules of CCTNS.
Kindly elaborate the amount of exiting Data need
to be migrated from the legacy System.
Please provide location the where all the legacy
System are installed. Ie. Number of Installation.
And whether in case of distributed databases is
the collation of data from distributed location is
part of the bidder?
Data Digitization and Data
Migration exercise is to be
carried out from respective
office locations. Yes in case
of distributed databases, the
responsibility of collating
data from distributed
location lies with SI. Please
refer RFP for more details.
105
36 I
Weeding out of
Records: SI would be
required to configure
the CCTNS system, to
enforce, Haryana
Police
specific requirements
for weeding out of
records.
Weeding out of Records would be
done by Authorised users
Please explain the procedure for Weeding out of
Records.
Different retention period is
prescribed under Law for
each piece of data. Some
data is to be retained
permanently and rest have
to be destoyed/ weeded out
after a period of pre-defined
time. The system should be
able to implement that.
Please refer RFP for more
details
106
46 I
Project Planning and
Management:
Procure, Commission
and maintain
Project Management,
Configuration
Management and
Issue Tracker Tools at
State Police HQ
The SI shall install the project
management software at Haryana
Police’s premises right at the
beginning of the project
Kindly confirm if web based Project montoring tools is required.Please refer to section 5.4.1,
Vol.I of this RFP
107
171 I 4. Database
Should the database have native, active-active clustering with objectives of
scalability and availability of 24x7, meaning a single database supported by
multiple instances thus providing true high availability from an application's
standpoint. Should the database provide horizontal scalability in such a manner
that a new database node can be added (or removed) dynamically, as and when
required in future, without disturbing the normal functioning of production
system such as without shutdown. Should it be online and supported! by native
database clustering components
Please refer to the RFP for
more details
108
171 I 4. Database
Should the database be capable of handling the data growth over a period of
time without adversely impacting the application throughput, thereby justifying
the concepts of information lifecycle management by classifying data into
active, less-active and archival data. Should the database solution allow such
data to be stored onto different partitions on different types of storage media
thereby cutting down storage costs as well as increasing the overall application
performance. Should the database support option of different partitioning
schemes within the database (Range, List, Hash & combinations) to split large
volumes of data into separate pieces or partitions, which can be managed
independently.
Please refer to the RFP for
more details
109
171 I 4. Database
Do you need a centralized audit data store to ensure non-tampering of audit
information thus securing audit data. If yes, would you like to use it for detailed
insight (who did what, to which data and when)? Centralized server for Audit
data reduces the cost and complexity of compliance and helps detect suspicious
activity by automating the collection and consolidation of audit data. It provides
a secure and highly scalable audit warehouse, enabling centralized reporting,
analysis, and threat detection on audit data. It will help in transparently
collection and consolidation of audit data, providing valuable insight into who
did what to which data when – including privileged users who have direct
access to the database
Please refer to the RFP for
more details
110
171 I 4. Database
Is the solution expected to provide transparent encryption for both the data
residing under the database as well as data travelling over the network without
imposing any additional storage overhead and preventing any internal security
issues ? Should the database support tablespace encryption so that entire
application tables can be transparently encrypted and data blocks transparently
decrypted as they are accessed by the database.
Please refer to the RFP for
more details
111
171 I 4. Database Should the solution be capable of eliminating the risk of breaching sensitive
information when copying production data into non-production environments
for the purposes of application development, testing or data analysis.
Please refer to the RFP for
more details
112
171 I 4. Database
Is the DR site expected to remain ideal until a disaster actually takes place? Or
will it be better if the solution can actually use the DR site for readonly /
reporting purpose thereby resulting into better utilization of the DR investment.
Should it provide capabilities to use DR environment to offload production
query load and have built-in DR solution to replicate the changes happening in
the database across multiple DR Sites with an option to run real-time reports
from DR Sites without stopping the recovery mechanism.
Please refer to the RFP for
more details
113
171 I 4. DatabaseShould the solution provide a set of business processes, and a supporting
infrastructure, for the creation, maintenance, and use of digital identities in
online spaces.
Is the solution expected to provide single-sign-on authentication to the clients
Please refer to the RFP for
more details
114
171 I 4. DatabaseShould the database be able to compress structured data and unstructured
data such as documents, images, and multimedia in OLTP mode, and query
execution should be faster on compressed data. Should it be able to provide
different compression ratios on OLTP ,datawarehousing and archival data.
Please refer to the RFP for
more details
115
171 I 4. Database
Should the architecture provide a comprehensive solution for database
administrators (DBAs) and application developers to automate the process of
promoting planned schema changes from development to production. It also
helps enterprises easily identify the impact of application upgrades on
customizations and can pinpoint and remediate unplanned schema changes
that are often the cause of application downtime.
Please refer to the RFP for
more details
116
171 I 4. Database
Should the solution restrict DBAs and Privilege users (Super DBAs) to update
application data from backend? Rather than just avoid, its better to define
policies and restrict DBAs and other super users to access the application data
from backend to enforce consistency. Should it provide option for preventive
controls on privileged user access to application data and provide multi-factor
authentication based controls and policies taking account of IP addresses ,
application context etc.
Please refer to the RFP for
more details
117
179 I8. Storage and Backup
Solution
Host interface:
4 host ports per controller, Fibre
Channel (FC),4 Gbps per port
Host Interface:
4 host ports per controller, Fibre Channel (FC),4 Gbps per port and 2 1Gbps GbE
and 2* 10Gbit ports.
Today all leading OEMs provide FC and Ethernet ports for unified functionality
to address SAN and NAS functionality. This will allow Haryana police to utilize
both FC & Ethernet in their environment and save cost and reduce TCO of the
project.
Please refer to the
Corrigendum
118
179 I8. Storage and Backup
Solution
Drive interface:
4 drive ports per controller—Fibre
Channel (FC) Switched or FC
Arbitrated Loop (FC-AL) standard
per controller, 4 Gbps per port
Drive interface:
4 drive ports/ SAS Links per controller—Fibre Channel (FC) Switched @ 4Gpbs
or SAS Link @ 6Gpbs per controller
We would like to bring to notice of Haryana Police that SAS is the next
generation technology available from all leading vendors like EMC, HP, IBM and
Hitachi. This will allow latest product are quoted by all Vendors.
Please refer to the
Corrigendum
119
179 I8. Storage and Backup
Solution
SAN support:
Box should be compatible of SAN
environment
SAN support:
Box should be compatible of SAN and NAS environment.
Today all leading OEM provide unified storage which deliver SAN and NAS
functionality out of the same box. This helps customers to avail “File Sharing”
and Block service from the same box and save cost on NAS header later.
Request you to include this functionality too in the Specs.
Please refer to the
Corrigendum
120
180 I8. Storage and Backup
Solution
Storage subsystem shall support
146GB, 300GB 15K RPM disks and
400GB or
higher 10 K RPM Fiber channel
drives & 750GB, 1TB SATA or
higher SATA /
equivalent drives in the same
device array
Storage subsystem shall support 146GB, 300GB, 600 15K RPM disks and 400GB
or higher 10 K RPM Fiber channel/SAS drives & 750GB, 1TB SATA or higher
SATA / equivalent drives in the same device array
This will allow SAS disks passed arrays to participate in the tender.Please refer to the
Corrigendum
121
180 I8. Storage and Backup
Solution
The storage system should be
scalable from 30 …. to …. TB of
raw capacity
using 40% on Fiber Channel drives
and 60% on SATA / equivalent
drives using
the same configuration as Quoted
in this tender”. The Storage
should have atleast 2ports of 4
Gbps Frontend ports and 2 no’s of
back end ports of 4Gbps”The
storage array must have the
capability to do array based
remote replication using FCIP or IP
technology. per SPC-2 benchmark
The storage system should be scalable from 30 …. to …. TB of raw capacity using
40% on Fiber Channel drives and 60% on SATA / equivalent drives using the
same configuration as Quoted in this tender”. ”The storage array must have the
capability to do array based remote replication using
FCIP or IP technology.
We request you to remove the frontend and backend ports from this specs as
this has been covered earlier points.
Please refer to the
Corrigendum
122
72 I5.4.8 Data Digitization
& Data Migration
What would be the size and form of the data for migration and digitizationCIPA application at each
Police Station comprise of
approx. 30-40 MB data,
which is required to be
migrated in addition to the
other applications such as
HRMS, CRO/RW, CCIS, etc.).
Please refer RFP for more
details
123
171 I 4. Database
Databases mentioned are vendor specific. Request you to make it neutral to
give equal opportunity to all Database OEMs. The two technology stacks
have been prescribed by
NCRB. Hence No Change.
Please refer RFP for more
details
124
122 IAnnexure 1: CAS
(State) Solution Stack
The Annexure 1 mentions 2 options for the SI to choose as the Technology
stack. This kinds of limits proposing other available solutions and does
promotes a vendor lockin. Suggestion: To open for SI to propose other available
technologies in the area of BPM, Web Server, Application server etc. This would
benefit Haryana State with better choice of technology adoption, which in turn
could have both technical and commercial benefits.
The two technology stacks
have been prescribed by
NCRB. Hence No Change.
Please refer RFP for more
details
125
122 IAnnexure 1: CAS
(State) Solution Stack In the CAS (State) Solution, a very important aspect for any solution would be
the scalability that it offers for the a mission mode project such as CCTNS.
Suggestion: We would request Haryana Police to allow SI to decide on the
technology components considering such important Non Functional
requirements like Scalability.
Solution is required to meet
the scalability requirements
of the department. However
components mentioned in
the stack cannot be altered
as they have been prescribed
by NCRB . Please refer RFP
for more details
126
122 IAnnexure 1: CAS
(State) Solution Stack
In the CAS (State) Solution options, need more details on the Security related
requirements. Would the solution not require a Intrusion Prevention system?
As part of the SDC scheme,
Intrusion Prevention System
is being provided by Haryana
SDC. Hence no new IPS is
required specifically for
CCTNS. Please refer RFP for
more details
127
122 IAnnexure 1: CAS
(State) Solution Stack
For both Solution Stack 1 and Stack2, where ever a product has not been
proposed, and instead a custom code approach has been proposed, can the SI
propose a product. For e.g, for Rule Engine, Search etc, Custom code approach
is proposed. We would request Haryana Police to allow SI the option to decide
technologies in such open areas.
Please refer Annexure I, Vol.I
of this RFP
128
124 IAnnexure 1: CAS
(State) Offline Solution
The Synchoronization Solution is proposed as Custom Built. Will SI be making
this solution, or would this be provided? Also, request more details on
Synchronization related requirements.
Synchronization Solution will
be provided by NCRB. Please
refer RFP for more details
129
26 I5.2.1 CCTNS
Functional Modules
A list of customised functional modules is provided. This is a important list and
we would request that these core additional requirements should also be the
factor to drive the technology selection by the SI considering both Functional
and Non Functional priorities for Haryana Police.
The two technology stacks
have been prescribed by
NCRB. Hence No Change.
Please refer RFP for more
details
130
162 I Annexure V
This section refers details on Indicative Technical Specifications. In this context
it states that Haryana Police already has comprehensive Enterprise
Management Solution, but then at the same time elaborate set of requirement
have been stated for the EMS and NMS Solution. Is Haryana Police open to a
alternate EMS/NMS solution, considering the compliance requirements that are
state specific? This is with the assumption that the existing Monitoring solution
may not comply to elaborate requirements as stated in the RFP. Plus please
provide the details on the existing Monitoring solution.
Please refer Annexure V,
Vol.I of this RFP
131
162 I Annexure V
This section also states elaborate set of requirements for RDBMS, and ETL
technolgies, but then in Annexure 1 on Page 122, the RFP limits the choice of
technologies. How is SI required to look at these requirements in terms of
compliance? Can SI propose the technology most compliant based on Points in
Annexure V?
Please refer Annexure V,
Vol.I of this RFP
132
162 I Annexure V
On the similar lines, there are details provided on Web Server and Application
Server on Page 170, but as Part of Annexture 1, products have already been
proposed in the two technologies. Can the SI propose an alternative that is
most compliant for Haryana Police?
Please refer Annexure V,
Vol.I of this RFP
133
181 I Backup SoftwareThe proposed backup solution shall be offered with 4 Nos. UNIX based licenses,
26 Nos. Windows based licenses and the rest 20 Nos. LINUX based licenses for
both SAN based backup and the LAN based backup. Proposed backup solution
shall be offered with Online SAN backup agent on all database servers with LAN
based open file backup agent on rest of the other servers
Please refer to the
Corrigendum
134
21 II
2.6, Technical
Evaluation Scoring
Matrix, (A) Past
Experience
For SI Experience
Max 5 Citations showcasing
experience as system integrator
for turnkey projects in India in the
last 5 years for a project value of
more than 25 Crores each,
involving at least 50+ locations
and 1000+ users and value of
Bidder’s scope of work along with
Reference details of the Client
It is requested to change the requirement of 5 Citations to 3 citations, OR the
value of the project may be relaxed to 15 CroresPlease refer to the
Corrigendum
135
22 II
2.6, Technical
Evaluation Scoring
Matrix, (A) Past
Experience
For Police Domain
Max 5 Citations showcasing
experience of successful
deployments of software
application in Police domain in the
last 5 years Following parameters
will be examined for evaluation:
It is requested to change the requirement of 5 Citations to 3 citationsPlease refer section 2.6, Vol.
II of this RFP
136
175 I
Annexure V: Indicative
Technical
Specifications
Blade Chassis Specification: Two
hot-plug, redundant 1Gbps
Ethernet module with minimum
10 ports (cumulative), which
enable connectivity to Ethernet
via switch. Switch should be
(Internal/external) having Layer 3
functionality - routing, filtering,
traffic queuing etc
Two hot-plug, redundant 1Gbps Ethernet module with minimum 20 ports
(cumulative), which enable connectivity to Ethernet via switch. Switch should be
(Internal/external) having Layer 2 functionality
Please refer to the
Corrigendum
137
176 I
Annexure V: Indicative
Technical
Specifications
Blade Servers (Web, Portal,
Application, Directory, etc…):2
Quad core @ 2.0 GHz or above
with 4 MB shared L2 cache, 1066
MHz / 2000 MT/s FSB
2 Quad core @ 2.13 GHz or above with 4 MB shared L2 cache, 1066 MHz /
2000MT/s FSB
Please refer to the
Corrigendum
138
176 I
Annexure V: Indicative
Technical
Specifications
Blade Servers (Web, Portal,
Application, Directory, etc…): Min
32 GB FBD RAM with min 8 Nos.
free slots for future expandability.
Min 32 GB DDR3 RAM with min 8 Nos. free slots for future expandability.Please refer to the
Corrigendum
139
177 I
Annexure V: Indicative
Technical
Specifications
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…):2 Quad core @
2.0 GHz or above with 4 MB
shared L2 cache, 1066 MHz / 2000
MT/s FSB
2 Processor populated, Each CPU should have 6 processing cores or higher, 12
MB cache of higher, TDP of CPU should be 95W or lower, 32-bit & 64-bit OS
compatible, SPEC Rating of Throughput (60% of SPECint_rate_base2006 + 40%
of SPECfp_rate_base2006 scores) should be minimum 295 or higher with SPEC
documentary datasheets of the respective OEMs.
Please refer to the
Corrigendum
140
177 I
Annexure V: Indicative
Technical
Specifications
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…): Min 16 GB FBD
RAM with min 8 Nos. free slots for
future expandability.
2 x 8 GB DDR3 1333 MHz memory equally distributed among the populated
CPUs
Please refer to the
Corrigendum
141
178 I
Annexure V: Indicative
Technical
Specifications
Database Server:Minimum 4x
Quad core processor with 2.1GHz
or above with 1066Mhz FSB /
2000 MT /s expandable to 4
physical processor with min 4 MB
L3 cache per
processor
Minimum 4x Quad core processor with 1.86 GHz or above with 1066Mhz FSB /
2000 MT /s expandable to 4 physical processor with min 4 MB L3 cache per
processor
Please refer to the
Corrigendum
142
176 I
Annexure V: Indicative
Technical
Specifications
Blade Servers (Web, Portal,
Application, Directory, etc…):
“Min 32 GB FBD RAM with min 8
Nos. free slots for future
expandability”
All latest generation Intel processor support DDR3 Memory. (Pl change FBD
with DDR3 memory).
Please refer to the
Corrigendum
143
177 I
Annexure V: Indicative
Technical
Specifications
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…) :“Min 16 GB FBD
RAM with min 8 Nos. free slots for
future expandability”
All latest generation Intel processor support DDR3 Memory. (Pl change FBD
with DDR3 memory).
Please refer to the
Corrigendum
144
179 I
Annexure V: Indicative
Technical
Specifications
Storage Area Network Pl specify required storage capacity. Please refer to the
Corrigendum
145
182 I
Annexure V: Indicative
Technical
Specifications
Backup Software: The proposed
backup solution shall be offered
with 4 Nos. UNIX based licenses,
26 Nos. Windows based licenses
and the rest 20 Nos. LINUX based
licenses for both SAN based
backup and the LAN based backup
Suggest to removed & amend the same as
Bidder must quote the Online SAN based backup functionality on all proposed
database servers with LAN based backup on rest of the application/web/portal
servers
Please refer to the
Corrigendum
146
174 I
Annexure V: Indicative
Technical
Specifications
Server Load Balancing Mechanism -
NT Algorithm / Private Algorithm /
Customizable Algorithm /
Response Time
NT Algorithm/Private Algorithm/Customizable Algorithm mechanisms are
particular to one vendor and would restrict participation from other vendors. Its
requested to remove this clause
Please refer to the
Corrigendum
147
174 I
Annexure V: Indicative
Technical
Specifications
Segmentation / Virtualization
support along with resource
allocation
It is strongly recommended that resource allocation alongwith dedicated access
control on per segment / virtual partition basiss should be asked as the same
would ensure that maximum weigtage is given to business critical applications
for maximum perfromance and also would ensure complete isolation amongst
multiple applications being run on same server load balancer
Please refer to the
Corrigendum
148
Please clarify if you require the router to support following features for saving &
optimizing WAN bandwidth and for faster performance of application traffic
over WAN ?
Please refer to the
Corrigendum
149
1. Acceleration of all TCP based applications and supporting multiple optimized
TCP connections - minimum optimized 200 TCP connections and minimum
bandwdth of 4 Mbps.
Please refer to the
Corrigendum
150
2. Should compress TCP traffic using LZ compression.Please refer to the
Corrigendum151
3. Should support retransmission of lost data in case of any packet-loss.Please refer to the
Corrigendum152 4. Should have memory based caching / data duplication technique to reduce
traffic across WAN. Please refer to the
Corrigendum
183 I
Annexure V: Indicative
Technical
Specifications
c) Router Features:
153
It is highly recommended that scalability should be asked to 48 Ports minimum
which can take care of the future requirements including port-
trunking/aggregation requirement as well. Also, it is recommended that all
ports should support 8 Gbps speed on FC in future by just replacing the SFPs
only on the same switch.
Please refer to the
Corrigendum
154
Since ISL trunking for 8 Ports has already been asked therefore it is requested
to remove the requirement for 10 Gbps FC ports and also 10 Gbps FC ports are
non industry standard.
Please refer to the
Corrigendum
155
178 I
Should have inbuilt diagnostics
features like Power On Self Test,
FC Trace route,
FC Ping etc
In addition to the asked diagnostic features , kindly specify if you require the
SAN switch to have the ability to create multiple hardware-based isolated Fabric
instances within the same physical SAN switch for complete isolation on per
application/department basis ? Please refer to the
Corrigendum
156
179 I
Should have dual Fans and Hot
plug power supplies switching and
service modules.
Please clarify if you require redundant hot pluggable power supplies for the
SAN Switch?
Please refer to the
Corrigendum
157
184 I
Annexure V: Indicative
Technical
Specifications
The switch should support Layer 2 Trace route.Please refer to the
Corrigendum
158
184 I
Annexure V: Indicative
Technical
Specifications
The Switch should support Auto-QoSPlease refer to the
Corrigendum
159
184 I
Annexure V: Indicative
Technical
Specifications
The Switch support for configuration rollbackPlease refer to the
Corrigendum
160
184 I
Annexure V: Indicative
Technical
Specifications
The switch support for DHCP serverPlease refer to the
Corrigendum
161
184 I
Annexure V: Indicative
Technical
Specifications
The switch should support a pair of a Layer 2 interfaces (switchports or port
channels) configured to act as a backup to another Layer 2 interface. Please refer to the
Corrigendum
162
184 I
Annexure V: Indicative
Technical
Specifications
The switch should support strict priority QueuingPlease refer to the
Corrigendum
Annexure V: Indicative
Technical
Specifications
178 I
Annexure V: Indicative
Technical
Specifications
Minimum 16 Active ports (each
with minimum port speed 4 GB)
within same switch upgradeable
to 32 ports with minimum 2 Nos.
of additional 10 Gbps FC ports
163
184 I
Annexure V: Indicative
Technical
Specifications
The switch should support Four Egress Queues Per PortPlease refer to the
Corrigendum
164
184 I
Annexure V: Indicative
Technical
Specifications
IP SLA Responder or equivalentPlease refer to the
Corrigendum
165
184 I
Annexure V: Indicative
Technical
Specifications
ManagementPlease refer to the
Corrigendum
166
184 I
Annexure V: Indicative
Technical
Specifications
The Switch should be able to discover the neighboring device of the same
vendor giving the details about the platform, IP Address, Link connected
through etc, thus helping in troubleshooting connectivity problems
Please refer to the
Corrigendum
167
19 II Section 2.4, Notes 5.a
For items such as Site Preparation,
data digitization/ migration,
Capacity Building (Training
Personnel) and Handholding the
bidder may sub-contract the
work…
The sub contractor must be ISO
9001 in IT services. (ISO 27001)
certification wherever relevant)
The ISO 27001 certification has been included for sub-contractor. It should also
be included for lead bidder – SI to be selected.
Please refer to the
Corrgiendum
168
19 II Section 2.4, Notes 5.d
The sub contractor must have
completed 5 projects for
Government / PSU including one
project preferably with the State
Police Department involving
implementation at Police Stations
and Higher Offices.
It should be mandatory condition for the lead bidder to have completed 5
projects with any State Police Department involving implementation at Police
Stations and Higher Offices.
Please refer section 2.4,
Notes 5.d, Vol.II of this RFP
169
18 II Section 2.4 (vii)
The bidder must have been
assessed and must possess a valid
certification for CMMi Level 5 as
on the date of contract signing
and the certificate should be valid
for at-least a period of one year
from the date of submission of the
bid…
Pl allow certification for CMMi Level-3 or above as all processes for undertaking
development and maintenance of a project are well defined & standardized at
CMMI Level-3 itself. Further SI for State is just to implement the CAS application
developed by SDA. Even while selection of SDA for developing common
application CAS (Centre) and CAS (State) for entire country, was selected with
(CMMi L-4) as pre-qualification criterion.
In view of the above Pl allow certification for CMMi Level-3.
Please refer section 2.4 (vii),
Vol.II of this RFP
170
17 II Section-2.4 Pre-Qualification Criteria
Considering various activities to be performed under this project, it is suggested
to include the following factors for Pre-Qualification:
• CMMI V1.2 Level-3
• ISO 9001 for System Integration services – since about 60-70% of the project
cost could be towards Hardware (Storage, Servers, Security, Networking, FMS
etc.)
• Security certification – ISO 27001, ISO 20000
• IT Services certifications – at-least 5 ITIL certified professionals on the rolls of
bidder.
• ISO 9001 for Software Development
• Annual turnover at-least 10 times of envisaged project cost – say Rs 500 Cr for
Rs 50 Cr project.
• Regular staff of about 1000 on rolls
Please refer section 2.4,
Vol.II of this RFP
171
21 I Section 4
The SDA will provide Services for
CAS (State) for a period of three
(3) years followed by two optional
one-year periods from the date of
successful completion of the CAS
(State) Certification.
The decision on the two optional
one-year periods will be taken in
entirety by NCRB. During the
contract period, the SDA shall
offer the following services:
i. Application maintenance and
management Services for CAS
(Center) and CAS (state).
ii. Technical Program
Management of Implementation
of CAS (State) for all 35 States/UTs
throughout the duration of the
engagement with NCRB/MHA.
Provision of bug fixes, minor
changes, error resolutions and
Is SI required to provide maintenance services for CAS (State) for 4th and 5th
year in case SDA is not given maintenance services for 4th & 5th year?
Will the source code for CAS (State) with complete documentation be provided
to SI for various maintenance services?
Please refer section 4. Vol.I
of this RFP. Source code for
CAS (State) will be provided
by NCRB. However complete
ownership/ IPR will lie with
the State Government and
the strategic control of the
same will be with NCRB,
MHA, Government of India.
172
30 I Section-5.2.1
SI will be required to customize
the CAS (State) as received from
NCRB and shall also be
responsible for developing/
deploying other additional
Modules meeting the functional
requirements mentioned in the
Functional Requirement
Specifications attached as
Annexure to this document and
other integration requirements. Will the source code for CAS (State) with complete documentation be provided
to SI for various customization and adding additional modules?
Please refer to the response
of previous query
173
56 I Section-5.4.3.3
The selected System Integrator
will be responsible for the solution
development and customization
of end-to-end CAS (State)
application software including
additional functionalities,
integration with CAS Center and
external agencies on the basis of
the FRS, SyRS, SRS and solution
design.
174
57 I Section-5.4.3.3.g
The bidder will be solely
responsible for arranging any
software tools (apart from the
tools and software being provided
by the Centre) required during the
development / customization /
testing / commissioning /
maintaining of the CAS at his own
cost and State Government in no
case will be responsible for
arranging any such software /
tools. If any such software/
hardware/ middleware/ etc. is
being provided and the cost of the
same has been provided in
Commercial Bid, the same shall be
highlighted with reasons. Haryana
Police reserves the right to permit
its usage.
Pls provide the list and details of the tools and software that shall be provided
by the Centre.
Please refer to the response
of previous query
Will the source code for CAS (State) with complete documentation be provided
to SI for various customization and adding additional modules?
Please refer to the response
of previous query
175
77 IData Digitization: Digitization of
historical criminal data.
Pl provide a sample filled-in case file, Village Crime Notebook etc from where
legacy data is to be digitized. This is required to get idea on extent of data
digitization efforts.
Will the CAS (State) to be provided by the Centre would have the module for
digitization of legacy data?
It is suggested for interested
bidders to visit the nearest
Police Station in the state of
Haryana on prior one day
notice to the project nodal
officer for more details on
the same. Please refer RFP
for more details
176
240 I Section 20
Geographic Information System
(GIS)
Will the digitized base maps with attributes (cartographic data) be provided to
SI which can be used for building further capturing incidents, analysis, reporting
etc?Please refer Corrigendum
177
64 I Section-5.4.4.xiii & xiv.
Executive Chair: Executive Chair
for All manager High back Chairs
with nylon revolving base…
Visitor Chair: Visitor chair for High
back Chairs with Fixed base, ABS
seat and back…
The quantity required of these types of chairs may Pl be provided. This has not
been included in the BOM given on Vol-I. Pg-71.1 Executive Chair and 2
Visitor Chairs per Police
Station. Please refer
Annexure XIII, Vol.I of this
RFP
178
5 II Clause 1.2 a
All the above 4 envelopes along
with the cover letter, as specified
in
Annexure Other Formats - Error!
Reference source not found….
Broken Link. Kindly update this link.
Please refer to corrigendum
179
17 II Clause 2.4
Consortiums are not allowed Request to allow consortium to bid in a crucial project like this, as it would bring
diverse capabilities of multiple partners.Pleaser refer section 2.4,
Vol.II of this RFP
180
17 II Clause 2.4
All the prequalification criteria
have to be met by the bidder on
its own.
Pre-qualification criteria of respective consortium partner, responsible for that
particular component/tasts should be allowed.Pleaser refer section 2.4,
Vol.II of this RFP
181
21 II Clause 2.6 (A1)
Max 5 Citations showcasing
experience as system integrator
for turnkey projects in India in the
last 5 years for a project value of
more than 25 Crores each,
involving at least 50+ locations
and 1000+ users and the
following:
• IT infrastructure procurement,
deployment, and commissioning
• Software development and
implementation
• Network deployment and
commissioning (LAN/WAN)
• Site Preparation
• Technical Support including
Operations and maintenance
• Maintenance of SLAs
Request your to amend the clause as 25+ locations having 500+ users, and any
three (3) of the following:
• IT infrastructure procurement, deployment, and commissioning
• Software development and implementation
• Network deployment and commissioning (LAN/WAN)
• Site Preparation
• Technical Support including Operations and maintenance
Please refer Corrigedum
182
60 IIIImplementation SLA
(Capacity Building)
All the trainees within each of the
training program should pass the
training exam with more than 80%
or more marks conducted after
their training
This is very subjective. SI can only impart best of the training. Level of learning
entirely depends on an individual. This clause should be removed.
Please refer Annexure II,
Vol.I of this RFp
183
I Technical Specification
Should provision for LUN masking,
fiber zoning and SAN security (as
disk based encryption.
Please remove disk based encryption. As it would be specific to certain vendors
Please refer to the
Corrigendum
184
52 I
Web and DB servers should be
Scaleup as well as Scale out
if the servers have to be qouted with 4 and 8 processors respectively instead of
2 and 4 processors as mentioned in the specs on page 175, Vol. 1Please refer to the
Corrigendum
185
139 I
RPO (zero data loss in case of
failure of Primary DC) should be
zero Minutes
You have asked for online data replication in the Storage section and in the
RDBMS section there is mention of Zero data loss. Pl define if all data at DC site
needs to be covered under this clause.
Please refer to the
Corrigendum
186176 I
Minimum 2 external USB
connections functionality
Request you to change it to 1 Please refer to the
Corrigendum
187
176 I
Two hot-plug, redundant 1Gbps
Ethernet module with minimum
10 ports (cumulative), which
enable connectivity to Ethernet
via switch. Switch should be
(Internal/external) having Layer 3
functionality - routing, filtering,
traffic queuing
This Clause is Specific to OEM, request you to change to Two redundant 1Gbps
Ethernet modules with minimum 8 ports (cumulative) having L2/L3
functionality.
Please refer to the
Corrigendum
188
176 I
Two hot-plugs, redundant 4 Gbps
Fiber Channel for connectivity to
the external Fiber channel Switch
and ultimately to the storage
device.
Number of uplinks ports help define the bandwidth, thus it must be mentioned.
Please refer to the
Corrigendum
189
176 I
Hot Swap redundant power
supplies to be provided / Hot
Swappable and redundant Cooling
Unit
Request you to kindly change “hot Swap” to Hot Plug
Please refer to the
Corrigendum
190
176 I
Processor should be latest
series/generation for the server
model being quoted
We Request you to You can define the Processor Name and series to ensure
equivalent quote.Please refer to the
Corrigendum
191
176 I
Min 32 GB FBD RAM with min 8
Nos. free slots for future
expandability.
Please allow the latest DDR3 RDIMM memory technology to be qouted.Please refer to the
Corrigendum
192
176 I
• 2 X 146GB HDD or more hot
swappable system disk with
mirroring using integrated RAID
0,1 on internal disks, or min.16 GB
compact flash card to be
provided. It should be possible to
hot swap the drives without
shutting down the server.
please allow - hot plug drives with mirroring using RAID 0,1 on internal disk, 500
GB.
Please delete - It should be possible to hot swap the drives without shutting
down the server.Please refer to the
Corrigendum
193
177 I
• Minimum 4x Quad core
processor with 2.1GHz or above
with 1066Mhz FSB / 2000 MT /s
expandable to 4 physical
processor with min 4 MB L3 cache
per processor
You can define the Processor Name and series to ensure equivalent quote.
Minimum 4x Hex core Intel xeon 7500 series processor with 2.0 GHz or above
expandable to 4 physical processor with min 4 MB L3 cache per processor Please refer to the
Corrigendum
194
177 I
• Disk bays: Support for min 8
small form factor hot plug SAS /
SCSI hard drives in disk drive
carriers that slides out from front
This is OEM specfic clause and limits competition. Please remove the clause
"that slides out from front" so that more than one OEM can qoute.Please refer to the
Corrigendum
195
26 I Section 5.2.1, CCTNS
Functional Modules
CCTNS Functional Modules We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
196
27 I Section 5.2.1, CCTNS
Functional Modules
Call for Service Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
197
28 I Section 5.2.1, CCTNS
Functional Modules
Registration Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
198
27 I Section 5.2.1, CCTNS
Functional Modules
Investigation Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
199
27 I Section 5.2.1, CCTNS
Functional Modules
Prosecution Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
200
27 I Section 5.2.1, CCTNS
Functional Modules
Configuration Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
201
27 I Section 5.2.1, CCTNS
Functional Modules
Citizen Interface/ Portal Module We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
202
29 I Section 5.2.1, CCTNS
Functional Modules
HRMS Module Please mention in detail the list of modules required in HRMSPlease refer to the Annexure
VI, Vol.I of this RFP
203
30 I
Section 5.2.1, CCTNS
Functional Modules
Business Intelligence System Please mention the list of modules will require BI and quantify the number of
reports, dashboards required approximatelyBI would be essentially used
on the Crime and Criminal
database. More details will
be shared with the selected
SI
204
30 ISection 5.2.1, CCTNS
Functional ModulesKnowledge Management Module
Is there sponsorship for knowledge management in CCTNS after we implement
the system? What are the plans to maintain the knowledge in the system after
it is being deplyed. Will CCTNS have dedicated knowledge managers or will it be
a part of everyone in the system? What are the platforms on which the
intranet, temp KM portal and other current portals are built on? Which all
technologies will the integration of KM portal be required?
This is part of SI's
responsibilities. Please refer
RFP for more details
205
30 I Section 5.2.1, CCTNS
Functional Modules
Learning Management Module Total number of units will be part of the LMS. Please mention the termsThis query is not clear and
hence cannot be answered
206
29 I
Section 5.2.1, CCTNS
Functional Modules
Police Email and Messaging
Service Module
Please mention the existing Mailing system of CCTNSPresently Haryana Police is
using mailing system
provided by NIC. Please refer
RFP for more details
207
29 I Section 5.2.1, CCTNS
Functional Modules
Please provide more details on
the functionality expected.
We request for some more details on the functionality expected here to
baseline our scope for RFP responsePlease refer to the Annexure
VI, Vol.I of this RFP
208 HCL requires more specific details on the current CCTNS website in terms of the
following:
a)Overall functionalities of the existing portal
b)No. of static pages
c)No. of webparts and their functionalities
d) No. of reports hosted
e)Hit statistics
f) Any integration with any Internal, External or 3rd party applications if any. If
yes provide the details in detail
As such there is no CCTNS
specific website in Haryana.
Further, SI will be required to
develop afresh new website
for Haryana Police, therefore
it is not clear why is the said
information required. Please
refer RFP for more details
209 What are the different types of documents that are uploaded in the system?
Presently there are no
documents which can be
uploaded in the CIPA system.
However proposed CCTNS
system should allow
uploading of all type of case
related documents/ video-
audio clips/ pictures/ etc.
Please refer RFP for more
details
210 Please mention CCTNS has any plans for the secondary Production
environment(DR Setup)?Secondary production
environment is not required
at DR site. Please refer to the
RFP for more details
211 Please provide figure on the number of training hours required both user and
admin level?
Please refer section 5.4.10,
Vol.I of this RFP212 What will be peak load and peak hours for CCTNS portal?
This cannot be defined as of
now. Please refer to the RFP
for more details
213 What is the expected database growth in 5 years?
The expected database
growth every year would be
around 500 GB to 1 TB
214 Please categorize different types of users with its roles? Please refer section 5.4.10,
Vol.I of this RFP215 Other than as .xls, pdf, .doc, html, jpeg, wmv, .msg files, office format
documents, what will be other format of documents which need to be
supported by CCTNS application
These are only indicative
formats, however more
details would be known
once CAS (State) will get
developed at Central level.
Please refer RFP for more
details
216 Please share the number of reports which needs to be created? Functionality of
each reports.
Please refer Annexure VI,
Vol.I of this RFP217 What would be the total number of concurrent users?
Entire Police force would be
the internal users of the
system. However concurrent
users would be aprrox. 2500
at present
218 What is the authentication/Authorization mechanism envisaged in the new
system? AD authentication etcAuthentication mechanism
has been envisaged through
integrated Identity Access
Management. Please refer to
the corrigendum
219 1.What are the Directory Services and the Mailing solution.
2. What is the Authentication Mechanism that is being currently used at your
organisation and what is your choice for the Authentication Mechanism for the
new system.
Currently there are no
directory services in place in
Haryana Police. NIC mailing
solution is being used by the
department. For
Authentication mechanism,
please refer to the
corrigendum
220 Does CCTNS have preference for anyThis query is not clear and
hence cannot be answered
221 Are Retention and Archiving policies for the image / documents required
Different retention period is
prescribed under Law for
each piece of data. Some
data is to be retained
permanently and rest have
to be destoyed/ weeded out
after a period of pre-defined
time. The system should be
able to implement that.
Please refer RFP for more
details
222 Please elaborate on the type of retention periods for the data in the proposed
system Please refer to the response
of previous query
223 What is database size which needs to be migrated from the existing
portal/different files/folders? CIPA application at each
Police Station comprise of
approx. 30-40 MB data,
which is required to be
migrated in addition to the
other applications such as
HRMS, CRO/RW, CCIS, etc.).
Please refer RFP for more
details
224 Is there any data which need to be migrated with some due-diligence, if yes
then please share the format of data from different sourcesPlease refer to the section
5.4.8, Vol.I of this RFP
225 Does the proposed system requires 24/7 availability?Please refer to the Anneuxre
II, Vol.I of this RFP
226 What is the platform technology and data base of each application? Provide the
details of existing applications.
Please refer Annexure VIII,
Vol. I of this RFP227 Please provide the high level architecture of the existing application (for each
application) 3.Is this an "as-is" migration/development or would there be
enhancements to the functionalities?
Please refer section 5.2, Vol.I
of this RFP
228 Please find out customer's order of preference in terms of rolling out these
applications.
Please refer section 5.1.1,
Vol.I of this RFP
229 Please list all the 3rd party components used in the existing application Please refer Annexure VIII,
Vol. I of this RFP230 What are the types of documentation available for the existing application e.g.
functional test cases, functional specifications, design specifications, user
manual etc?Since all the existing
applications are planned to
be phased out, there is no
requirement for the
availbility of their
documentation. Please refer
to the RFP for more details
231 What are the release timelines if any? To reduce the release time, can we use
packaged products that are built as extension to the core platform?This query is not clear and
hence cannot be answered
232 Clarify on the hardware available in case if application is going to be hosted in
NIC location(Routers, Switches, RacKs, Storage etc.. )?Please refer to section 5.2.2,
Vol.I of this RFP
233 who will be responsible for the connectivity between DC and DR? Please refer to section 5.4.6,
Vol.I of this RFP234 If HTTPS protocol is required than additional digital certificate for SSL is also
required to be procured, Please confirm ? Any additional digital
certificate for SSL are not
being envisaged at this stage
235 Clarify who will be responsible for antivirus software / firewalls in DC and DR. Please refer section 5.4.7,
Vol. I of this RFP236
31 IDeployment
architecture
It is recommended that SI will opt
for Service Oriented Architecture
(SOA) for implementing CCTNS
application modules
SOA/XML is a vulnerable protocol and it involve publishing the web services. IPS
cannot handle targeted XML crafted attacks. Security is required to be
provisioned for SOA/XML.
Suggestion: It is suggested that XML gateways needs to be provisioned for
protecting the SOA/XML server /Application infrastructure.
Please refer section 5.2.2,
Vol.I of this RFP
237
20 I
Development of
CCTNS Core
Application Software
(CAS)
In order to achieve the key CCTNS
goal of facilitating the availability
of real time information across
police stations and between police
stations and higher offices, CAS
would be built as a web
application.
CCTNS application would be purely a web based application. Such applications
are vulnerable to various content level threats like SQL injection, web
defacement, Cross site scripting, Session hijack etc. To defend against such
attacks it is required that Web application firewall should be provisioned.
Suggestion: It is suggested to provision web application firewall along with
Server load balancer to provide adequate security against web threats.
Please refer to the
corrigendum for Server Load
Balancer specifications
238 There is no mention of security and network component for the DR. Kindly
clarify the requirement of SLB, LLB and IPS at DR.This is not required at DR
Site as part of this project
239
132 IIIMaster Service
Agreement
Router Port Requirements:
(iii) Packet Forwarding Speed-
Minimum 60 Kbps
The packet forwarding speed is measured in packet per second or pps.
We request you to correct it to 60kpps
Please refer to the
corrigendum
240
132 IIIMaster Service
Agreement
Software features:
(vi) Flash min 128 MB
Flash requirements differ from one manufacturer to other. We request you to
add "For the bidder who’s router does not match the Flash memory
requirement, should ensure to provide adequate memory to accommodate all
OS features required at present or in future."
Please refer to the Annexure
V, Vol. I of this RFP
241
107 IIIMaster Service
Agreement
C. Indicative Hardware
Requirements
16-Port Switch 130 nos.
The specs for 16-port switch has not been given in the RFP.
Are the specs for 16-port switch and 24-port switch same?
Please refer to the
Corrigendum
242
107 IIIMaster Service
Agreement
B. Switch:
(xxiii) L3 Features : Static routes &
RIP
The layer-3 routing functionalities are not required on the switches and hence
we suggest to remove it.
Please refer to the
Corrigendum
243
125 IIIMaster Service
Agreement
Database Server:-
OS support: Microsoft® Windows
Server 2003 / 2008, Enterprise
Edition / Red Hat® Enterprise
Linux 5 & 4 AP / SUSE® Linux
Enterprise Server 9 / Solaris for
x86
OS Support: Microsoft® Windows Server® 2008 R2, Microsoft® Windows
Server® 2003 R2, Novell SUSE Linux Enterprise Server, Red Hat Enterprise Linux,
Citrix® XenServer™, VMware Infrastructure
Please refer to the
Corrigendum
244
125 IIIMaster Service
Agreement
Database Server:-:-
RAID controller with RAID 0/1/5
with 256 MB cache
RAID controller with RAID 0/1/5 with 512 MB battery backed write cachePlease refer to the
Corrigendum
245
125 IIIMaster Service
Agreement
Database Server:-
HDD hot pluggable: 4 x 146 GB
2.5” 10 K RPM HDD or more
HDD hot pluggable: 4 x 146 GB 15K RPM HDD or morePlease refer to the
Corrigendum
246
126 IIIMaster Service
Agreement
Database Server:-
2 x 4 Gbps Fiber Channel Ports 2 x 8G FC Ports
Please refer to the
Corrigendum
247
105 I
SI shall obtain the five year
product warranty and five year
onsite free service warranty from
OEM on all licensed software,
computer hardware and
peripherals, networking
equipments
and other equipment for
providing warranty support to
Haryana Police.
PLease confirm if OEM would be responsible for Premium/Priority Support for
providing updates , patches , security updates , bug fixes , indemnification for
the entire period of contract for all the locations for the above products as
required in the tender through the web downloads.
Please refer section 5.5, Vol.I
of this RFP
248
107 I
Updates/Upgrades/New
releases/New
versions/Patches/Bug fixes: The
SI shall provide from time to time
the Updates/Upgrades/New
releases/New
versions/Patches/Bug fixes of the
software, operating systems, etc.
as required. The SI should provide
free
Updates/Upgrades/New
releases/New
versions/Patches/Bug fixes of the
software and tools to Haryana
Police as and when released by
OEM.
PLease confirm if OEM would be responsible for Premium/Priority Support for
providing updates , patches , security updates , bug fixes , indemnification for
the entire period of contract for all the locations for the above products as
required in the tender through the web downloads.
Please refer section 5.5, Vol.I
of this RFP
249
255 ISupport management of virtual
classrooms (e.g. WebEx, AT&T
Connect) courses and classes Please confirm if Virtual Classrooms are required.
Please refer section 5.4.10,
Vol.I of this RFP
250
177 I
Minimum 4x Quad core processor
with 2.1GHz or above with
1066Mhz FSB /
2000 MT /s expandable to 4
physical processor with min 4 MB
L3 cache per
processor
Please confirm if minimum 2x Quad core processor are required which should
be expandable to 4 physical processors.
Please refer to the
Corrigendum
251
196 I
Should support industry wide
operating systems.
Please confirm if the requirement is to have a portal that interoperates with
multiple industry wide Operating Systems.
This is to be in compliance
with atleast the two
Technology Stacks
mentinoed in the RFP. Please
refer RFP for more details
252
232 I
Should support industry wide
web servers.
Please confirm if the requirement is tohave a portal that interoperates with
multiple industry wide Web Servers.
This is to be in compliance
with atleast the two
Technology Stacks
mentinoed in the RFP. Please
refer RFP for more details
253
232 I
Should support industry wide
database management systems.
Please confirm if the requirement is tohave a portal that interoperates with
multiple industry wide Database Management Systems.
This is to be in compliance
with atleast the two
Technology Stacks
mentinoed in the RFP. Please
refer RFP for more details
254
232 I
Data Modeller Environment:
Universe builder: System should
have a tool to model, design and
build the middleware between the
database and the end user,
developing the proper key
indicators and dimensions in
order to analyse the information a
generate reports.
Kindly change it to: System should have atool to design and build the multi-
dimension model between the database and the end user, developing the
proper key indicators and dimensions in order toanalyse the information a
generate reports.
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
255
233 I
System should be able to build
reports through a web-based
multiplatform IDE tool which
allows interacting with the
software’s content and
applications. To log in, one must
only need a browser and site
address or URL. Then, the server
simply validates the user ID and
Password.
Kindly change it to: System should be able to build web-based which allows
interacting with the software’s content and applications. To log in, one must
only need a browser and site addressor URL. Then, the server simply validates
the user ID and Password.
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
256
232 I
System should gather information
from multiple data sources into
one report without central data
warehouse.
Kindly Change it to:System should be ableto gather information from multiple
data sources into one report with or without central data warehouse.
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
257
221 I
System should have a drill-down
action that allows performing
analysis of tasks by exploring the
data from high-level view
(aggregate data) to low-level view
(detailed/transactional data),
moving through the different
dimensions within the universe.
Kindly change it to: System should have adrill-down action that allows
performing analysis of tasks by exploring the data from high-level view
(aggregate data) to low-level view (detailed/transactional data), moving
through the different dimensionswithin the multi-dimensional model
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
258
255 I
System should allow different
types of document formats
(Crystal Reports, Web Intelligence,
Excel, PDF, etc). System should
provide a number of ways to
incorporate structured or
unstructured external data. If data
comes from excel or PDF
document, it can be store in the
repository. System should have an
architecture that allows the user
to merge corporate data with
external data and display via one
report or chart. System should
also allow storing external data in
a spreadsheet, which can be used
in Web Intelligence and Crystal
Report Documents.
Kindly change it to: System should allow different types of document formats
(Excel, PDF, word, notepad etc). System should provide a number of ways to
incorporate structured or unstructured external data. If data comes from excel
or PDF document, it can be store in the repository. System should have an
architecture that allows the user to merge corporate data with external data
and display via one report or chart. System should also allow storing external
data in aspreadsheet, which can be used by proposed reporting tools
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
259
177 I
System should be able to
evaluate the regularity of a user in
terms of using email service by
calculating average time between
two consecutive logins and
number of mails read/ written/
replied between the respective
consecutive logins. System should
categorise users based on their
frequency of using email service
as Regular, Irregular and Rare
User
These functionalities pertains to the Enterprise Management tool. Kindly
movethem to the functional requirenments required under the EMS tool.
Please refer to the Annexure
VI, Vol.I of this RFP
260
172 I
The database should be highly
available with every processing
node providing full view of data.
This means, in case of failure of
one server, each remaining server
in the cluster should provide full
access to all data at any point in
time.
Kindly Change to : The database should behighly available and in case of failure
of one server, the other server in the cluster should provide full access to all
data.
Please refer to the Annexure
V, Vol.I of this RFP
261
17 II Request you to relook at this clause and allow consortium in case a government
owned company with prior experience required is front ending.
Please refer section 2.4,
Vol.II of this RFP
262
17 II As this is an opportunity where deployment CAS (central) is to be done and
does not involve much coding, the criterion should be relaxed to ensure wider
participation and CMMi 3 Company companies should be allowed.
Please refer section 2.4,
Vol.II of this RFP
263
179 I Section 8
Cache :The storage array shall be
configured with at least 8 GB
cache scalable to min 16 GB
mirrored across two storage
controllers for disk I/O operations.
Change Requested :The storage array shall be configured with at least 8 GB
cache scalable to min 16 GB mirrored/protected across two storage controllers
for disk I/O operations. Reason : Different vendors use different technologies
to protect the data in the cache. One of the way is mirroring. Other
technologies of protecting data are NVRAM log mirroring. Hence, instead of
only mentioning mirroring as the protection technology, request to allow
different protection methodologies to participate
The specifications mentioned
are in line with the guidelines
of NCRB, hence cannot be
changed
Consortiums are not allowed The
bidder must have been assessed
and must possess a valid
certification for CMMi Level 5 as
on the date of contract signing
and the certificate should be valid
for atleast a period of one year
from the date of submission of the
264
180 I Section 8
SAN Specifications : Storage
subsystem shall support 146GB,
300GB 15K RPM disks and 400GB
or higher 10 K RPM Fiber channel
drives & 750GB, 1TB SATA or
higher SATA / equivalent drives in
the same device array
change Requested :Storage subsystem shall support 300GB 15K RPM disks and
400GB or higher 15 K RPM Fiber channel drives & 750GB, 1TB SATA or higher
SATA / equivalent drives in the same device array Reason : 146GB FC drives and
10K RPM drives are obselete now and are not available with all the disk
vendors. Hence request to remove the support of 146GB FC drives and change
10K RPM drives to 15K RPM drives
Please refer to the
corrigendum
265
180 I Section 8 Replication to the DR Site As per the requirements, 2 storage boxes are required, one per Primary and DR
site. But the storage replication license has not been asked in the tender.
Request to specify the requirement of storage based replication license for the
entire maximum supported capacity of the storage array
SI is required to propose
over and above the Bill of
Material specified in RFP for
successful implementation of
the project.
266
139 I Section 8Location of Primary and the DR
site
The tender specifies that the RPO has to be zero. Please spcify the location of
primary and the DR site. The storage based replication can deliver zero RPO
only when the two sites are not more than 100 kms apart. If the distance
between the two sites are more than 100 kms, then zero RPO cannot be
achieved through storage based replication.
Alternate method is to go with host based replication, but that will cause a lot
of CPU and memory overhead on the production servers and is not a robust
solution. Hence it is advisable to go with storage based replication. Request to
mention the location of the primary and the DR site and if the distance between
the 2 sites is more than 100 kms, then request to change the RPO value to be
greater than zero
Please refer to the
corrigendum
267
180 I Section 8 NAS functionality
The storage be configured with SAN as well as NAS protocols so that the NAS
functionality can also be used when required. The NAS can be provisioned
natively or through external appliance. If an external appliance is required, the
NAS appliance should be configured in high availability mode with automatic
failover capability.
Please refer to the
corrigendum
268
180 I Section 8 Snapshots
The storage shall have the ability to create instant, online and consistent point-
in-time images of the data including databases so that these images can be
used as online backups for instant restores. The system should be able to keep
at least 14 (twice a day) copies of these images per LUN/volume online for at
least one week on the storage for restores, if required, without affecting the
performance of the system.
If the storage uses a a Copy-On-Write method to create Snapshot copies that
affects the performance of the storage then atleast double the usable capacity
stated above needs to be supplied to prevent any performance impact on the
production storage.
The system should have the ability to create these images and restore these
images in seconds regardless of the data size. Any software required to take
such online, application consistent images including that for databases should
form part of the offered solution.
Please refer to the
corrigendum
269
180 I Section 8 Clones
The storage shall also provide functionality of creation of copy of volumes/LUNs
(clones), ideally without requiring any space. This is for use in development
environment, for running reports and for DR drills. The storage should be
configured with adequate capacity with high capacity FC drives to create
minimum of 3 clones (in addition to the primary capacity requirement). The
clones should be able to mountable to the host for I/O access simultaneously.
Please refer to the
corrigendum
270
180 I Section 8 Compliance Ready
The storage should offer functionality (inband or through an appliance) for
100% tamperproof and legally presentable data as required for legal, financial
and compliance data.
The data shall be stored in a manner such that even the system administrator
should not be allowed to change or delete the data or the filesystem.
Any additional hardware or software that is required for the same shall be
supplied in NSPOF mode for full system supported capacity.
Please refer to the
corrigendum
271
17 II
2.4 Pre-Qualification
Criteria/9. The Bidder
shall satisfy all of the
criteria below/iv.
The Bidder must have a proven
track record of providing a
successful ‘Turnkey
Solution’ for at least five (5) IT-
projects1 in last 5 years as on 31st
March 2010. At
least one of the 5 quoted projects
should be an integrated turnkey
project of a value of not less than
Rs. 10 Crores or above in India
including setting up and
configuring the hardware
(Servers, Desktop, Network
Clients) and implementing
software solution including
Operating Systems, Infrastructure
Management Software, RDBMS,
establishment of LAN / WAN
including Firewalls, IPS, PKI, etc.
and providing life cycle support.
Bidder must provide as a
Request you to moderate as below:
• for at least Three (3) IT-projects1 in last 5 years as on 31st March 2010
• At least one of the 3 quoted projects should be an integrated turnkey project
of a value of not less than Rs. 10 Crores or above in India.
Rational:
3 projects gives sufficient experience to a vender to do your projects. Also this
will broader base participation of various credible vender.
Please refer section 2.4,
Vol.II of this RFP
272
18 II
2.4 Pre-Qualification
Criteria/9. The Bidder
shall satisfy all of the
criteria below/iv.
The Bidder must have a proven
track record of implementing at
least two (2) e-
Governance projects2 summing
up to a value of << Rs. 10 Crores
or above in
last 2 years as on 31st March
2010. Bidder must provide as a
supporting
documentary proof in form of
work orders confirming year and
Area of activity,
value of services to be delivered
for each of the two projects,
Completion2 /
Partial Completion Certificate
from Client confirming year and
value of Bidder’s
scope of work, scope of work
completed by the Bidder and its
value along with
Reference details of the Client
Request you to moderate as below:
The Bidder must have a proven track record of implementing at least two (2) e-
Governance projects or any Govt. project summing up to a value of << Rs. 10
Crores or above in
Last 5 years as on 31st March 2010..
Rational: 2 year is very shprt period. Most of the RFP are asking experience in
last 5 years as you have also asked in Sr no 2. So keeping symmetry and again
getting wider participation. Please make it 2 years as 5 years as of31st March
2011.
Please refer section 2.4,
Vol.II of this RFP
273
21 II
2.6 Technical
Evaluation Scoring
Matrix/A1/System
Integration
Max 5 Citations showcasing
experience as system integrator
for turnkey
projects in India in the last 5 years
for a project value of more than
25 Crores
each, involving at least 50+
locations and 1000+ users and the
following:
Max. Score : 20
Request you to moderate as below:
Max 3 Citations showcasing experience as system integrator for turnkey
projects in India in the last 5 years for a project value of more than 25 Crores
Each, involving at least 50+ locations and 1000+ users. Partial sign off of the
large project with similar complexity should also be treated equally and should
be given equal marks.
Max score : 12
Balance mark should be adjusted to technical score.
Rational: 3 projects gives sufficient experience to a vender to do your projects.
Also this will broader base participation of various credible vender.
. More weight age should be given to technical solution than the references.
This will bring the entire participant at one platform. This will stop the
participant to score more by providing more references and compromise
technical solution. This will lead the Govt. to pay extra money to the vender not
for solution but for references.
Please refer Corrigendum
274
21 II
2.6 Technical
Evaluation Scoring
Matrix/A2/Application
development/
deployment in Police
domain
Max 5 Citations showcasing
experience of successful
deployments of
software application in Police
domain in the last 5 years
Following parameters will be
examined for evaluation:
project
project (Completed / on-going)
Request you to moderate as below:
Max 2 Citations showcasing experience of successful deployments of
Software application in Police domain in the last 5 years.
Rational:
This is because there can only few company’s who have worked in police
domain and they also have very limited engagement. So it is suggested to make
it 2 client citation instead of 5
Please refer section 2.6, Vol.
II of this RFP
275
22 II
2.6 Technical
Evaluation Scoring
Matrix/A3/Application
development/
deployment in Police
domain
Max 5 Citations showcasing
experience in Provisioning of Data
Centre
services (establishment / lease)
with Minimum value 3 Crores
from Data
Centre component involving at
least Site Preparation, Creation of
physical
environment, Procurement,
deployment and commissioning of
IT
Infrastructure, establishing data
security, technical support etc. in
last 5 years. Following parameters
will be examined for evaluation:
• Stage of commissioning of the
Data Centre (Completed / on-
going)
Bidder must provide as a
supporting documentary proof in
form of work
Request for Moderate :
Max 2 Citations showcasing experience in Provisioning of Data Centre services
(establishment / lease) with Minimum value 3 Crores from Data Centre
component involving at least Site Preparation, Creation of physical
environment, Procurement, deployment and commissioning of IT
infrastructure, establishing data security, technical support etc. in last 5 years.
For defining the value of Rs 3cr. Self declaration certificate from authorized
signatory should also be considered in case exact value of the datacenter in not
given in the purchase order but it is part of the project.
Rational: 3 projects give sufficient experience to a vender to do your projects.
Also this will give wider participation of various credible vender.
Please refer section 2.6, Vol.
II of this RFP
276
34 II
Payment terms
/A/Implementation
Phase
1. M1: Advance against
submission of Bank Guarantee 5%
2. M2: Pre – Go Live Readiness1 of
the Pilot Districts 5%
3. M3: Go-Live2 of the Pilot
Districts 5%
4. M4: Pre – Go Live Readiness1
for Phase II 5%
5. M6: Successful integration with
external agencies with successful
transfer of the data for three
months in succession 5%
6. M5: Go-Live2 of the Phase II
10%
M1: Advance against submission of Bank Guarantee 10%
2. M2: Pre – Go Live Readiness1 of the Pilot Districts 10%
3. M3: Go-Live2 of the Pilot Districts 15%
4. M4: Pre – Go Live Readiness1 for Phase II 15%
5. M6: Successful integration with external agencies with
successful transfer of the data for three months in succession
15%
6. M5: Go-Live2 of the Phase II 10%
Please refer section 4.3,
Vol.II of this RFP
277
34 IIOperations and
Maintenance Phase
Ten half-yearly installments over
Five years from the “Go-Live”
date, each installment being a
maximum of 6.5% of total
contract value depending upon
the quarterly performance level
assessed
on the basis of SLAs defined in this
RFP
Ten half-yearly installments over Five years from the “Go-Live” date, each
installment being a maximum of 2.5% of total contract value depending upon
the quarterly performance level assessed on the basis of SLAs defined in this
RFP
Please refer section 4.3,
Vol.II of this RFP
278
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Quantity- 1nos
Server load balancers are critical components and hence should be deployed in
HA mode to ensure max. uptimes. Hence, it is suggested that Server load
balancers- 2nos should be deployed at SDC for CCTNS application in HA mode.
Also, DR will require the server load balancer for DC/DR failover. Hence the
quantities of serve load balancer is suggested to be revised to 4 nos
Suggestion: Quantity -4 nos , 2 nos for DC and 2 nos for DR
Please refer to the
corrigendum
279
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
10/100/1000Mbps Ethernet Ports
– minimum 2 ports upgradeable
to 4 ports
Server load balancers should have adequate number of interfaces for
deployment flexibility and also considering that server load balancer will be
segmented and deployed at multiple firewall DMZ
Suggestion: Minimum 6 x 10/100/1000Mbps Ethernet Ports and 2 Fiber Gigabit
ports.
Please refer to the
corrigendum
280
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Minimum of 2 Gbps throughput For scalability it is suggested that the Server load Balancer should support
future upgrade to 4Gbps throughput handling capacity.
Suggestion: Minimum 2Gbps throughput and should be upgradeable to 4Gbps
Please refer to the
corrigendum
281
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Memory: Minimum 1 GB 1 Gb memory is not adequate to cater to 4 Gbps of traffic considering that
server load balancer would do content acceleration, caching, compression etc.
Minimum 2 GB memory is required to handle 4-5 million concurrent
connections seen at 3-4 Gbps traffic
Suggestion: Minimum memory :2 GB upgradeable to 4 GB
Please refer to the
corrigendum
282
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Minimum of 4000 SSL connections
scalable to 7500 SSL connections
For scalability it is suggested that the Server load Balancer should support
future upgrade to 10000 SSL connection per sec
Suggestion: Minimum of 4000 SSL connections scalable to 10000 SSL
connection per sec
Please refer to the
corrigendum
283
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
There is no mention of simultaneous/concurrent sessions handling capacity of
the server load balancer. It is suggested that the server load balancer should
have capacity to handle minimum 5 million concurrent session.
Suggestion: Server load balancer should support minimum 5 Million concurrent
sessions.
Please refer to the
corrigendum
284
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Load Balancing Applications Please clarify for deployment flexibility and scalability Global server load
balancing should be supported in same device? The server load balancer is
suggested to have inbuilt global load balancing feature for future disaster
recovery integration with SDC
Suggestion: Inbuilt Global load balancing supporting DNS, http, RTSP
redirection, route injection, Global triangulation mechanism
Please refer to the
corrigendum
285
I
Annexure V: Indicative
Technical
Specifications, 5.
Server Load Balancer
Segmentation / Virtualization
support along with resource
allocation
Please clarify for deployment flexibility and scalability Server load balancer
should support multiple segment?
Suggestion: Should support up to 6 Gigabit segmentsPlease refer to the
corrigendum
286
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Quantity There is no mention of quantities for Link load balancer. Please clarify
Suggestion: Link load balancer will be required at both DC and DR. It is
suggested that LLB quantity should be 4 nos Please refer to the
corrigendum
287
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Minimum 2 x 10/100/1000Mbps
Ethernet Ports & scalable to 4
ports
Link load balancers should have adequate number of interfaces for deployment
flexibility
Suggestion: Link Load Balancer should have 6 x 10/100/1000 Mbps copper
ports and 2 GBIC slots
Please refer to the
corrigendum
288
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Minimum memory 1 GB Link load balancers should have adequate memory to handle the growth in
terms of number of users/ throughput
Suggestion: Link Load Balancer should have minimum 2GB RAM Please refer to the
corrigendum
289
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
There is no mention of simultaneous/concurrent sessions handling capacity of
the link load balancer. It is suggested that the link load balancer should have
capacity to handle minimum 2 million concurrent session.
Suggestion: Link Load Balancer support for 2M Concurrent sessionPlease refer to the
corrigendum
290
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Minimum of 2 Gbps throughput Please clarify that 2 Gbps throughput is required on link load balancer. As per
SDC architecture, devices should be capable to handle the growth in terms of
number of users/ throughput. The link load balancer should provide enough
scalability to support the increase load of data center with existing device to
protect the investment.
Suggestion: Link Load Balancer should provide minimum 200 Mbps throughput
and should have a provision to be upgraded to 4 Gbps L7 throughput without
changing the hardware.
Please refer to the
corrigendum
291
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Minimum of 1 Gbps SSL
throughput
Please clarify SSL throughput is required on Link load Balancer. Server load
balancer is used for SSL acceleration and it has been asked in Server load
Balancer specifications. Link load balancer is used for ISP load balancing and
deployed on perimeter of network.
Suggestion: It is suggested this requirement need to be deleted
Please refer to the
corrigendum
292
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Minimum of 4000 SSL connections
scalable to 7500 SSL connections
Please clarify SSL Connection is required on Link load Balancer. Server load
balancer is used for SSL acceleration and it has been asked in Server load
Balancer specifications. Link load balancer is used for ISP load balancing and
deployed on perimeter of network.
Suggestion: It is suggested this requirement need to be deleted Please refer to the
corrigendum
293
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Supports Active-Active and Active-
Standby Redundancy
Please clarify Active-Active support is required on Link load Balancer. Link load
balancer is used for ISP load balancing and deployed on perimeter of network. It
works in routed mode with active/backup redundancy. whereas Server load
balancer works in active-active or active-backup.
Suggestion: It is suggested this requirement need to be deleted
Please refer to the
corrigendum
294
I
Annexure V: Indicative
Technical
Specifications, 5. Link
Load Balancer
Segmentation / Virtualization
support along with resource
allocation
Please clarify Segmentation/Virtualization support is required on Link load
Balancer. Server load balancer is used for to connect multiple segments and it
has been asked in Server load Balancer specifications. Link load balancer is used
for ISP load balancing and deployed on perimeter of network.
Suggestion: It is suggested this requirement need to be deleted
Please refer to the
corrigendum
295
II
Prequalification
Criteria Clause No. 2.4
(Point No. 2)
Consortium are not allowed.
The Bidder can be an individual organization or a consortium of
companies/firms/ corporations. In case of a consortium, the number of
consortium partner should be limited 3 (three) including the Lead bidder. “Lead
Partner” shall necessarily be the Systems Integrator (SI) and shall be responsible
for implementing the whole project as per the Scope of Work
Please refer section 2.4,
Vol.II of this RFP
296
II
Prequalification
Criteria Clause No. 2.4
(Point No. 9 iv)
The Bidder must have a proven
track record of providing a
successful ‘Turnkey Solution’ for
at least five (5) IT-projects n last 5
years as on 31st March 2010. At
least one of the 5 quoted projects
should be an integrated turnkey
project of a value of not less than
Rs. 10 Crores or above in India
including setting up and
configuring the hardware
(Servers, Desktop, Network
Clients) and Implementing s/w
solution including Operating
Systems, Infrastructure
Management Software, RDBMS,
establishment of LAN / WAN
including Firewalls, IPS, PKI, etc.
and providing life cycle support.
Bidder must provide as a
supporting documentary proof in
form of work orders confirming
The Bidder (Lead Partner in case of consortium) must have a proven track
record of providing a successful ‘Turnkey Solution’ for at least five (5) IT
–Projects. At least one of the 5 quoted projects should be an integrated turnkey
project of a value of 6 Crores or above in India or Globally including setting up
and configuring the hardware (Servers, Desktop, Network Clients) and
implementing Software Solution including Operating Systems, IMS, RDBMS,
establishment of LAN/WAN including Firewalls, IPS, PKI, etc and providing life
cycle support.
Please refer section 2.4,
Vol.II of this RFP
297
II
Prequalification
Criteria Clause No. 2.4
(Point No. 9 v)
The Bidder must have a proven
track record of implementing at
least two (2) e-Governance
projects summing upto a value of
<< Rs. 10 Crores or above in last 2
years as on 31st March 2010.
Bidder must provide as a
supporting documentary proof in
form of work orders confirming
year and Area of activity, value of
services to be delivered for each
of the two projects, Completion /
Partial Completion Certificate
from Client confirming year and
value of Bidder’s scope of work,
scope of work completed by the
Bidder and its value along with
Reference details of the Client
The Bidder (Lead Partner in case of consortium) must have a proven track
record of implementing at least two (2) e-Governance projects summing to a
value of 3 Crores or above
Please refer section 2.4,
Vol.II of this RFP
298
Prequalification
Criteria Clause No. 2.4
(Point No. 9 vii)
The bidder must have been
assessed and must possess a valid
certification for CMMi Level 5 as
on the date of contract signing
and the certificate should be valid
for atleast a period of one year
from the date of submission of the
bid.
The bidder (application software partner in case of consortium) must have a
valid SEI CMMi level 3 or above certification at the time of submission of the
bid.
Please refer section 2.4,
Vol.II of this RFP
299
72 I Clause No 5.4.8
Data Digitization and data
migration
Can the data migration be done off site
Data Digitization and Data
Migration exercise is to be
carried out from respective
office locations. In case of
distributed databases, the
responsibility of collating
data from distributed
location lies with SI. Please
refer RFP for more details.
300
234 I Clause No. 19
Command & dispatch We understand that a few cities of Haryana already have CADS in place. Is the SI
also going to integrate these cities with the new system or the CAD already
implemented will be replaced.
Please refer to section 5,
Vol.I of this RFP
301
240 I Clause No.20
GIS What is the scale of the map to be prepared. Please give the extent / areas of
the cities for which the map is to be prepared. Who will supply the satellite
images for the map preparation.Please refer Corrigendum
302250 I Clause No.21, S.No.2
GPS- The GPS should be able to
help track......
Please specify, how is this envisaged to be carried out.Please refer Corrigendum
303
250 I Clause No.21, S.No.4
GPS – The GPS should be able to
quickly transmit via satellite …...
Please specify, how is this envisaged to be carried out.
Please refer Corrigendum
304
18 II Clause No. 2.4/9/vii
The bidder must be assessed and
must possess a valid CMMi L5
Certificate
Moderate to CMMi L3Please refer section 2.4,
Vol.II of this RFP
305
27 I
5.2.1
Investigation Module
Audio/ Visual Tools for taking
witness statements - CCTV
Cameras/DVR at Interview Rooms
for each Police Station
Quality Evidence Bags for
collection of evidences
Supply of CCTV Cameras/DVR are in the scope of SI ?
Only Quality Evidence bags need to supply or with required tools?
Supply of CCTV Cameras/
DVR and the Quality
Evidence bags are not in the
scope of SI under this RFP
306
28 I
5.2.1
Third Eye Module
SMS Gateway Whether Haryana Police is having any SMS gateway right now or its part of SI
scope? Bidders are required to
provide commercial quote
for providing SMS gateway
with the Commercial Bid.
However, this will not be
used for commercial
evaluation.
307 Data Migration - at what level - SI/SDA/Both?This query is not clear and
hence cannot be answered
308
Section 5.3 Table (S #
10, 16, 25)
Based on schedule provided we understand that Data Migration of History Data
should happen first, then Active data for Pilot states (in Phase I) and then Active
data for all the states (in Phase II) happen next - using the same data migration
package? Is it correct?
Entire Data digitization and
Data Migration exercise is
required to be successfully
completed before Pilot Go-
Live. Please refer RFP for
more details
309
Lateral Scope
Please confirm the below Data Migration scope:
Sources: Data from CIPA, CMS , CCIS , FACTS , PBS , CIS , PMS , DCR , GIS , ALS ,
CIMS , As Is HRMS
Targets: CCTNS , To be HRMS
Out of Scope sources: CPMS , SVS , Web Portal , BMS , IMCS , CFMS , Return
Writer , CRO , Talash , MCSS , CIA , ADSIS , LIMS , TCS , MVCS , MHA , GoI
Please refer section 5.4.8,
Vol.I of this RFP
310
"Scope of Data
Migration" vs "E.
Existing Legacy
Systems
In Scope of Data Migration, it is mentioned that:
"Police Units also captures data relating to crime and criminals in RW and CRO
software deployed with Haryana Police. SI would be responsible for developing
data migration utility and migrating
data of approximately 3000 cases from existing system to the new system."
In E. Existing Legacy Systems, For RW and CRO it is mentioned that:
"Data from this application would not be migrated or digitized and would be
replaced by “Periodic Crime and Law and Order Reports and Review Dashboard
Service” module of CCTNS."
Please clear the data migration scope related to RW & CRO.
Please refer the
Corrigendum
311
Longitudinal ScopePlease confirm the below data migration process scope:
Requirements Analysis, Design (Data Modeling by Application Team),
Development, Unit Testing, Integration System Testing, Regression Testing, UAT
support, Implementation, Warranty, Knowledge Transition.
Please refer section 5.4.8,
Vol.I of this RFP
312
Section 5.4.8 first
paragraph
What does "closing or migration of open transactions" mean? Can you please
elaborate migration scope here?
Closing of the open
transactions: Department
shall provide the necessary
inputs to SI for SI to close the
open transactions and
further successfully
migrating the data of closed
transaction. Please refer to
the RFP for more details
313
Section 5.4.8 second
paragraph
"SI shall be preceded by an appropriate data migration need assessment
including data quality assessment." Are you expecting rigorous data cleansing or
basic data cleansing?
Please refer section 5.4.8,
Vol.I of this RFP
314 Additional Guidelines
for Data Migration.
Point 5
Does customer prefer to use Data Quality tools for Data Cleansing?Please refer section 5.4.8,
Vol.I of this RFP
315
Scope related
Our understanding is Data Migration Utility will be implemented for historical
data (of CAS-Central) first, then in 2 police stations (of CAS-State) in Phase I and
then remaining 37 police stations (of CAS-State) in next phases. Please confirm.Please refer section 5.4.8,
Vol.I of this RFP
316 What is the data migration window to be considered?
Bidder to plan in such a way
that entire data migration
and data digitization exercise
is successfully completed
before Pilot Go-Live without
impacting the daily business
operations of Police. Please
refer RFP for more details
317 What is the data size of the source to be migrated for both Active and
Archive/History data? CIPA application at each
Police Station comprise of
approx. 30-40 MB data,
which is required to be
migrated in addition to the
other applications such as
HRMS, CRO/RW, CCIS, etc.).
Please refer RFP for more
details
318 Are there any business critical deadlines for completing the migration? Please refer section 6, Vol.I
of this RFP319 Please mention the number of schemas present in the Source and the Target
databases.
Please refer section 5.4.8,
Vol.I of this RFP320 Do we have any inputs regarding the transaction volumes in the application?
CIPA application at each
Police Station comprise of
approx. 30-40 MB data,
which is required to be
migrated in addition to the
other applications such as
HRMS, CRO/RW, CCIS, etc.).
Please refer RFP for more
details
321
45 I Section 5.4
Procurement, Deployment and
Commissioning of IT infra-
structure at the Data Center and
Disaster Recovery Center
including the necessary hardware,
software and other networking
components Data migration and
Digitization of Historical Data
Where would the DC and DR be located?Please refer section 5.4.7,
Vol. I of this RFP
322
109 I Section 5.5
SI shall provide user support in
case of technical difficulties in use
of the software, answering
procedural questions, providing
recovery and backup information,
and any other requirement that
may be incidental/ancillary to the
complete usage of the application.
Backup life cycle has not been mentioned. Is there any predefined Backup
policy available?
It is in the scope of SI for
defining the backup policy.
Please refer RFP for more
details.
323
SLA
Time duration for each level of Incident ticket has not been mentioned.This query is not clear and
hence cannot be answered
324
Section 5.4.1
The SI would setup an online
repository on PMIS /
Configuration Management Tool
for providing centralized access to
all project documents including
manuals and other materials. The
online repository would be
maintained by the SI throughout
the engagement period. The SI
should ensure that the repository
is built on appropriate security
features such as role- and
necessity based access to
documents.
Is this repository different from the one which is mentioned in page 22Please refer section 4, Vol. I
of this RFP
325
33 II Section 4.2 Liquidated Damages
Request that Liquidated Damages shall be levied only for delays that are solely
and entirely attributable to Bidder and maximum value of liquidated Damages
shall not exceed 5% of the value of delayed/ undelivered services.Please refer section 4.2,
Vol.II of this RFP
326
72 II Section 8 (A) Non-Disclosure Agreement
Request to insert further standard exclusions to Confidential Information as
follows:
(d) Is obtained from another source without restriction; or
(e) Is required to be provided under any law, or process of law duly executed.
Please refer Annexure -Other
Formats (A), Non-Disclosure
Agreement, Vol.II of this RFP
327
79 II Section 8 (D) Earnest Money Deposit
The standard bank clause is missing in the EMD Format. Request to insert the
following provision towards the end of the format:
Notwithstanding anything contained hereinabove:
a) Our liability under this Bank Guarantee shall not exceed and is restricted to
Rs._______________ (Rupees _______________________________ only)
b) This Guarantee shall remain in force up to and including _________
(including claim period of three months)
c) Unless the demand/claim under this guarantee is served upon us in writing
before _________ all the rights of Government under this guarantee shall stand
automatically forfeited and we shall be relieved and discharged from all
liabilities mentioned hereinabove.
Please refer Annexure -
Other Formats (D), Earnest
Money Deposit, Vol.II of this
RFP
328
15 III Section 2.7.4 Final Testing and certification
Request to insert a provision for deemed acceptance of deliverables as follows:
Notwithstanding the foregoing sentence, a deliverable shall be treated as
accepted by Client if the Client (a) fails to provide the list of non conformities
within two (2) weeks of delivery, (b) fails to notify the acceptance of the
deliverables in terms of this clause within the period of two (2) weeks from
delivery, or (c) starts using the deliverable in a live production environment
(other than as part of agreed review and acceptance testing procedure, such as
UAT).
Please refer section 2.7.4,
Vol.III of this RFP
329
23 III Section 2.15.3 (a) Tax
Request that System integrator shall not be liable for payment of service tax
and value added taxes and such taxes shall be borne at actuals by Client.Please refer section 2.15.3
(a), Vol.III of this RFP
330
24 III Section 2.16.1 (a) (i) Material Breach
Request to provide upto thirty (30) days notice to System integrator for curing
Material Breach.Please refer section 2.16.1
(a) (i), Vol.III of this RFP
33124 III Section 2.17.1 Indemnification
Request to make this provision mutually applicable. Please refer section 2.17.1,
Vol.III of this RFP
332
30 III Section 2.19 (e) Confidentiality
Request to insert a further exclusion to Confidential information as follows:
• Information which is in the possession of, or was known to, the receiving
party prior to its receipt, without an obligation to maintain confidentiality.
Further, the confidentiality obligations of receiving party herein shall survive the
termination of this Agreement for a period of two (2) years.
Please refer section 2.19 (e),
Vol.III of this RFP
333
30 III Section 2.20 Audit, Access and Reporting
Request that such access for audit shall be allowed upon reasonable advance
written notice to System Integrator and upon compliance with the security and
confidentiality requirements of System integrator, while accessing the
premises/ facilities of System Integrator.
Please refer section 2.20,
Vol.III of this RFP
334
31 III Section 2.21.3 Bespoke Development
Request to modify the provision as follows:
The IPR rights for any bespoke development done specifically and exclusively
for Client by System Integrator during the implementation of the project,
subject to System Integrator’s pre-existing work and Third party IPR, will lie with
CLIENT.
Please refer section 2.21.3,
Vol.III of this RFP
33533 III Section 2.22.1 Personnel non-solicitation
Request to provide a time limit for such restriction. Eg. 2 years from termination
of the Agreement.
Please refer section 2.21.1,
Vol.III of this RFP336
33 III Section 2.22.4 Assignment
Request that neither party shall assign the Agreement to a third party without
the prior written consent of the other party.Please refer section 2.21.4,
Vol.III of this RFP
337
36 III Section 2.23 (b) Dispute Resolution
Request that unresolved dispute shall be referred for arbitration to a Board of
Arbitration. This Board will be constituted prior to the commencement of the
arbitration and will comprise of two arbitrators and an umpire. System
Integrator and the Client will each nominate an arbitrator to the Board and
these arbitrators will appoint the umpire. Such Arbitration shall be governed by
the provisions of the Arbitration and Conciliation Act 1996.
Please refer section 2.23(b),
Vol.III of this RFP
338
57 III Section 4.2 (d) Availability
Request that the time lost due to any of the following reasons shall be taken
into account while calculating the availability/ uptime requirement: (a) Time lost
due to power or environmental failures; (b) Time taken to recover the system
because of power or environmental failures; (c) Time lost due to damage or
malfunction in the system or any units thereof due to causes attributable to
Client such as attachment of additional devices, making alteration to the
system, maintenance of the system, etc. without System Integrator’s consent
and/ or failure to maintain the site as required by the System Integrator; (d)
Time taken for scheduled maintenance/ troubleshooting either for preventive
purposes or improvement in function or other purposes; (e) Time taken for
reconfiguration or other planned downtime situations; (f) Scheduled shutdowns
as required by Client; (System Integrator may also request Client for a
shutdown for maintenance purpose, which request will not be denied
unreasonably by Client); (g) Time taken for booting the system (h) Time lost due
to unavailability of links.
Please refer section 4.2 (d),
Vol.III of this RFP
339
86 III Section 4.9Violations and Associated
Penalties
Request that the maximum/ overall cumulative penalty levied under this
Agreement shall not exceed 1% of the Contract Value.Please refer section 4.9,
Vol.III of this RFP
340
III Additional Clause
The following provision is not appearing in the RFP document and is integral to
the Agreement. Request to insert the following provision into the RFP:
Limitation of Liability
Neither party shall be liable to the other for any special, indirect, incidental,
consequential (including loss of profit or revenue), exemplary or punitive
damages whether in contract, tort or other theories of law, even if such party
has been advised of the possibility of such damages.
The total cumulative liability of either party arising from or relating to this
Agreement shall not exceed the total amount paid to System Integrator by the
Client under that applicable work that gives rise to such liability (as of the date
the liability arose).
Please refer Corrigendum
341
68/1
38/1
39/1
72
I Section 5.4.7
Page # 68 - Haryana Police may
consider a data loss of maximum
(0.5) half hour in case of natural
disaster.
Page # 172 -It should provide
automated disaster recovery
solution to maintain transaction
consistency, providing an option
of zero data loss where required
Page # 138 - RTO shall be less than
or equal to six (6) hours.
Page #139 - RPO (zero data loss in
case of failure of Primary DC)
should be zero minutes
Please clarify on RTO and RPO requirements as different values are mentioned
in RFP.
Please refer Corrigendum
342
349 I
The proposed State Data Centre
shall also have a mirror Disaster
Recovery Site to host all set of
applications deployed as such at
the Haryana State Data Centre.
Does this mean 1:1 SDC :DRS? Kindly clarify.
Please refer to the
corrigendum
343
107/
128I
Page # 107 - Business hours in
Haryana Police will be from 0700
hours to 2300 hours from (Mon-
Sat)
Page # 128 - The business hours
are 8:30AM to 4:30PM on all
working days (Mon-Sat)
Please clarify on business hours.
Please refer to the
corrigendum
344
120 I
Annexure I
CAS (State) Solution - Stack 1
Can SI suggest changes/modifications to technology stack specified in RFP for
successful implementation?
Components mentioned in
the Technology Stack have to
be complied with, however
technical specifications of
the components can be over
an above what is mentioned
in the Indicative Technical
Specifications. Please refer
the RFP for more details
345
211 I
System should be able to record
the following details of the
person, as proposed by the
Planning Commission,
Government of India :
- Finger Prints
- IRIS
- Facial Maps
Does SI need to procure biometric solution to meet this requirement and
include in proposed BoM?It is clarified that the system
should have functionality of
capturing personal
particulars of an individual
including biometrics based
on the standards defined by
Planning Commission, GoI. SI
is not require to procure any
specific tools/ solution for
this requirement
346
53 I
Section 5.4.2.3
The solution shall support
advanced user authentication
mechanisms including Digital
Certificates and biometric
authentication.
How many users are in scope for digital certificates provisioning and biometric
authentication?
Biometric authentication has
not been envisioned in this
project. However, bidders
are required to quote the
prices for Digital Certificates
for 500 users. Haryana Police
may decide to go ahead
implementating Digital
Certificates for other aspects
of the project in near future
347
77 I
Section 5.4.8
Data digitization exercise shall
involve data entry of manual
records, in both English and Hindi
language
SI understands that whatever data available in whichever language(Hindi or
English) will be digitized accordingly i.e. data available in Hindi will be digitized
only in Hindi. Please confirm.
Data to be digitized available
in whichever language
(Hindi/ English) will be
digitized in both Hindi and
English. Please refer RFP for
more details
348
23 I Section 4
The SDA shall build CAS (State)
with interfaces in English and
Hindi; and also build CAS (State) in
such a way that it can be
configured for interfaces in other
local languages at the State level
by the State SIs. It is the
responsibility of the SI to
customize CAS (State) for
development of local language
interfaces.
SI understands that scope of this RFP includes Hindi and English as languages.
Please confirm if there is any other local language support needed, if yes, then
which is that language?
Please refer Section 5.2.3,
Key Configuration
Requirements, Vol.I of this
RFP
349
211 I
Should support Real-time exact
and relaxed matches of
fingerprints from the master
database using live scan
fingerprints or the latest prints
collected from the scene of crime.
Please clarify as whether matching based on IRIS and Facial maps is also
required or not, in addition to fingerprints as per RFP. Proposed application to be
customized/ developed
should support all
biometrics. Please refer RFP
for more details
350
25
Section 5.1.1
Pilot rollout
Does SI need to procure entire centralized infrastructure as part of pilot/phase1
implementation? Please refer "Successful
Implementation/ Go_live"
under Glossary of Terms for
this RFP
351
15
Section 3.3
External Departments of the State
such as Jails, Courts, Passport
Office, Transport Department and
Hospitals etc.
Please provide exhaustive list of external departments to be interfaced and
integrated in scope of this RFP.The exhaustive list shall be
shared with the selected
bidder
352
15
Section 3.3
Non-Government/Private sector
organizations
Please elaborate on these organizations The exhaustive list shall be
shared with the selected
bidder353
33
Section 5.2.2
All the proposed applications
would be able to function in an
offline mode and on availability of
connectivity, data would
automatically replicate with the
central repository in State Data
Centre.
To meet offline(local) needs, SI would include required infrastructure as part of
proposed BoM, as its not explicitly mentioned in indicative BoM Please refer Annexure I, Vol.
I of this RFP for Offline
Solution details. However
bidder is free to propose the
required infrastructure to
successfully implement the
project
354
206
Pt.38
System should allow the user to
capture Finger Print and Retina
Scan for accused in FIR
Finger prints and Retina to be captured for accused only or all other people too
involved e.g. - witnesses, suspects etc. Please clarify.Please refer Annexure VI, 3.
38, Vol. I of this RFP
355
212 Pt.59
System should allow the user to
record and print witness
statements
Does SI need to procure H/W to record statements as specified in RFP? If yes,
then whether it includes audio/video/both. Please clarify.Hardware to record the
statements as specified in
RFP shall be provided by
State. Please refer RFP for
more details
356
212 Pt.61
System should provide for an alert
to the user in cases where
accused identity is not known, but
1. Similar case has been
registered, where accused identity
is found to be near description
2. Similar case is registered with
same modus operandi
3. An arrest has been made in
another case with similar accused
description
Please clarify as based on what all parameters this alert mechanism need to be
built.
More details will be shared
with the selected SI.
357
15
I
Section 3.4
The Core application Software
(CAS) is expected to be ready by
<July 2011>.
Is July 2011 the certification date on which SDA will handover the certified
CAS(State) to States? Please confirm.This is an indicative date
provided by NCRB
358
74/341 I HRMS
Page # 74 - SI would be required
to migrate this data into the new
developed HRMS module.
Page #- 341- The SI should
upgrade the existing system with
the functionality suggested by the
Haryana Police and integrate with
CCTNS CAS.
Does SI need to develop new HRMS module or upgrade the existing module? If
SI needs to upgrade the existing module, then CAS (State) Solution - Stack 1
need to accommodate existing HRMS module technology requirements.
Can SI propose its own HRMS module?
Please refer to the
Corrigendum
359
341 IBudget Management
System
State Government has their own
Budget Monitoring System,
department would be using the
same application.
If SI needs to upgrade the existing module, then CAS (State) Solution - Stack 1
need to accommodate existing Budget Management module technology
requirements.
Please refer Annexure VI,
Vol.I of this RFP
360
342 ICentralised File
Monitoring System
System Integrator should
integrate this module on the basis
on the requirements suggested by
Haryana Police.
If SI needs to upgrade the existing module, then CAS (State) Solution - Stack 1
need to accommodate existing CFMS technology requirements. Please refer Annexure VI,
Vol.I of this RFP
361 Total number of Users
Entire Police force would be
the internal users of the
system. However concurrent
users would be aprrox. 2500
at present. Please refer RFP
for more details
362 Total number of Concurrent GIS Users.Please refer to the response
of previous query
363 List of various types of GIS users
All the Police officers directly
involved in Crime
Investigation & Crime
Preventation. Please refer
RFP for more details
364 Please provide the details of GIS data present. Please refer Corrigendum365 Is there a document or workflow diagrams that you can share with us for better
understanding & clarity?Please refer Corrigendum
366 Base map, Road Network map and Demographic and other related maps will be
provided by ClientPlease refer Corrigendum
367 Are there any GIS Software and System currently been used.Please refer Corrigendum
368 What is the Current Database been used in CAS(state) Please refer Corrigendum369
249 IAnnexure VII/ Section
20/143
Raster Image Support: The GIS
should use raster images such as
scanned paper maps, satellite
images, photographs and logos to
provide detailed content layers for
the maps.
Raster Images will be provided by client.
Please refer Corrigendum
370
245 IAnnexure VII/ Section
20/143
Data Creation & Editing: The GIS
should provide many CAD data
creation and editing tools as well
as the ability to edit one’s tabular
data such as values and names.
This means one doesn’t have to
switch between applications. The
GIS should allow making all
changes for maps and data in one
application thus saving time and
effort.
Is it be Desktop or Web Based Editing?
Please refer Corrigendum
371
241 I
Section 20, S.No.79
The GIS should have a data server
architecture that provides one
with access to all common
geospatial forms, most computer-
aided design formats, and even
simple forms such as text
documents. The data server
architecture should make it
possible to integrate both visually
and for interrogation a broad
range of mostly disparate forms,
thus bringing to one view all the
data needed to make sound
business decisions.
Is it support for common geospatial data formats(.shp,mdb,pgdb, etc)
Please refer Corrigendum
372
242 I
Section 20, S.No.87
The GIS should provide powerful
linear referencing and analysis
capabilities (including routing and
dynamic segmentation web
services) and the ability to build a
Web application that writes data
to accepted standard spatial
server applications.
What kind of data will be written. Is it analysis data or data editing will be done.
Please refer Corrigendum
373
242 I
Section 20, S.No,95
The GIS should be able to perform
continuous active monitoring of
high-risk and convicted sex
offenders
Please explain what kind of monitoring is required.
Please refer Corrigendum
374
242 I
Section 20, S.No,98
Field Mobility – Providing a
platform for data and information
exchange into and out of the field
What hardware devices are(would be) used to access the data exchange
services. Provide the example of data needs to be sent to the data servicePlease refer Corrigendum
375
243 I
Section 20, S.No.102
Journey to Incident Mapping: The
GIS should be able to use crime
mapping software to analyse data
based on average and maximum
distances travelled by serial
offenders to commit crimes and
routes taken after a crime through
the linking of recovered property.
What kind of crime mapping software's are being used currently? Are they web
based or desktop based applications.
Please refer Corrigendum
376
244 I
Section 20, S.No.112
The GIS should provide a full set of
image display, enhancement, and
manipulation tools entirely
integrated with other related and
relevant products.
Are there any image processing software's being used currently? Do they have
all the image processing algorithms?
Please refer Corrigendum
377
244 I
Section 20, S.No.114
The GIS should provide the ability
to generate accurate cadastral
maps in the timely manner. It
should let one perform parcel
geometry operations and interact
parcel map or neighborhood. The
GIS should have tools to simplify
with the GIS database while
viewing the the subdivision of
process, as well as other tools, to
enhance the rapid capture and
correction and integration of data.
The GIS should be designed to
work in a database environment
and provide tools that let one
interactively search or make
queries on maps to produce
information from the database.
What kind of editing is required(Any specific data set)? Does this needs a
approval process for multiuser editing
Please refer Corrigendum
378
249 I
Section 20, S.No.151
Universal Translator: The GIS
should be able to translate
bidirectional between it and other
mapping environments.
What is bidirectional translations?
Please refer Corrigendum
379
I
What are the existing GIS software, data image analysis products being used? Is
there any ESRI product is being used? If any how many licenses are in use.Please refer Corrigendum
380
IAny software being used for GIS data editing.
Please refer Corrigendum
381I
What would be the total estimated user base for the system?Please refer Corrigendum
382I
What would be the estimated user base for the data editing?Please refer Corrigendum
383
I
Are Haryana Police looking for only services from us or end to end solutions like
s/w supply, h/w supply as well as services? Please refer Corrigendum
384I
If the s/w supply is in scope, then how many licenses are required.Please refer Corrigendum
385
242 I
Pt.87
The GIS should provide powerful
linear referencing and
analysiscapabilities (including
routing and dynamic
segmentation web services) and
the ability to build a Web
application that writes data to
accepted standard spatial server
applications.
The GIS should provide powerful
linear referencing and analysis
capabilities (including routing and
dynamic segmentation web
services) and the ability to build a
Web application that writes data
to accepted standard spatial
server applications.
Pl explain/ elaborate the kind of tools that require to be developed and
expected outputs
Please refer Corrigendum
386
242 I
Pt.88
The GIS should be able to identify
risk factors including
businesses,buildings, or other
locations that draw crime
Pl explain/ elaborate the requirement
Please refer Corrigendum
387
242 I
Pt.89
The GIS should be able to rapidly
reconfigure beats and reallocate
resources after analysing crime
trends over time.
Our understanding of this requirement is that the GIS application need to
provide decision support to reconfigure beats and reallocate resources after
analysing crime trends over time. Pl confirm Please refer Corrigendum
388
242 I
Pt.90
The GIS should be able to develop
plans for special crime abatement
teams to address regional or
seasonal hot spot locations.
Our understanding of this requirement is that the GIS application need to
provide decision support to develop plans for special crime abatement
Please refer Corrigendum
389
I
Pt.93
The GIS should be able to provide
investigative leads by aggregating
data from multiple sources
Our understanding of this requirement is that the GIS application needs to
provide decision support towards investigative leads. Pl confirmPlease refer Corrigendum
390
242 I
Pt.97
Determine optimal locations for
deploying resources.
Our understanding of this requirement is that the GIS application needs to
provide decision support to determine optimal locations for deploying
resources
Please refer Corrigendum
391
245 I
Pt.117
The GIS should have terrain
analysis and visualization features.
It should have the ability to display
multiple geographic data types
simultaneously without
translation; It should be able to
ingest terrain, feature, and image
data to support a variety of terrain
analysis applications. It should
also include components to
generate three dimensional
Analysis: The GIS should be able to
analyse demographics and
psychographics.
It would not be advisable to have these functionalities on a web environment as
it will call for greater bandwidth. These functionalities can be provided as
desktop (thigh client functionalities). Pl confirm if this is ok. Also pl provide
number of clients where there functionalities are required
Please refer Corrigendum
392
247 I
Pt.130
Suspect and lead generation: The
GIS should analyse traffic patterns
and boundaries.
Pl explain/ elaborate the kind of analysis and expected outputs
Please refer Corrigendum
393
244 I
Pt.113
The GIS should have a
system/method to allow national,
regional, and military mapping
agencies to build enhanced
cartographiccapabilities and high
levels of GIS mapping automation
to produce their map series
products.
Is there a requirement of map production tool. If yes, how many such stations
will be required.
Please refer Corrigendum
394
144 I
Pt.114
The GIS should provide the ability
to generate accurate cadastral
maps in the timely manner. It
should let one perform parcel
geometry operations and interact
parcel map or neighborhood. The
GIS should have tools to simplify
with the GIS database while vi
operations and interact with the
GIS database while viewing the
parcel map or neighbourhood.
The GIS should have tools to
simplify the subdivision of
process, as well as other tools, to
enhance the rapid capture and
correction and integration of data.
The GIS should let one
interactively search or make
queries on maps to produce
information from the database.
Are cadastral mapping tools required? As we understand, these tools are
typically required in GIS data production in Land Records and related
applications. Pl explain.
Please refer Corrigendum
395
244 I
Pt.119
The GIS should provide the key
geospatial tools and technology to
help professionals in
municipalities, airports, seaports,
departments of transportation
(DOTs), rail companies, waterway
agencies, and pipeline operations
to enable efficient analysis of the
transportation infrastructure.
These analysis capabilities should
allow one to track information
about networks and perform
specialized analyses to help make
better decisions about public
safety, maintenance priorities,
and linear network model that
will support both Linear
Referencing System (LRS) and
vehicle routing applications.
Pl clarify, if the system will be open to users other than Haryana police, such as
municipalities, airports etc. Pl clarify the kind of functionalities to be provided to
such agencies.
Please refer Corrigendum
396
246 I
Pt.126
Complex Analysis Tools, Easy to
Use: Through a simple software
user interface, the GIS should be
able to automatically generate a
tool that allows one to easily
analyse retail trade areas, cellular
service areas, and voter
registration districts or risk
analysis reports. There should be
a feature in the GIS to easily divide
up areas under examination using
a street, a utility service line, or
any line at all.
Pl explain/ elaborate the kind of tools that require to be developed and
expected outputs
Please refer Corrigendum
397
246 I
Pt.127
Map Creation and Editing: The GIS
should include robust map
creation and analysis tools,
including the ability to auto trace
over complex regions or creates
any parcel region including a
diamond shape (or any
parallelogram). Users should also
be able to use the GIS to rotate
map objects, copy, and move or
nudge" them using the arrow
keys. "Snap-to" nodes should
automatically follow common
boundaries or geographical
features during data creation. "
This level of editing functionalities cannot be provided in a web environment.
We suggest putting desktop software (thick clients) at locations where these
functionalities will be required. Pl provide the number of locations where these
functionalities need to be provided.
Please refer Corrigendum
398
247 I
Pt.131
Intuitive Management of
Networks or Infrastructures: The
GIS should evaluate
geographically-based assets such
as cell towers, fibre-optic cable or
water, sewer and telephone
services.
Pl explain the kind of analysis that need to be done?
Please refer Corrigendum
399
247 I
Pt.133
Analysis: The GIS should be able to
analyse demographics and
psychographics.
Pl explain/ elaborate the kind of analysis that need to be done?
Please refer Corrigendum
400
250 I
Pt.4
The GPS should be able to quickly
transmit via satellite the
fingerprints, license numbers and
images of wanted individuals
GPS cannot be used to transmit data. The GPS based device also house a GPRS
modem for the transmission of data. Pl confirm
Please refer Corrigendum
401
250 I
Pt.5
The GPS should have the feature
of placing GPS bracelets on
paroled criminals to monitor their
movements.
Pl provide total number of bracelets to be supplied
Please refer Corrigendum
402
250 I
Pt.6
It should be possible to equip
vehicles with GPS along with other
equipments as bait in law
enforcement operations. The GPS
should be installable in the
construction machinery and even
computers to aid in sting
operations
Pl explain/ elaborate the requirement
Please refer Corrigendum
403
I
Google Maps: When viewing
vehicles' current location or
historical activity, the GPS should
allow choosing between four high-
quality map views: Standard,
Satellite, Hybrid and Terrain.
Does the client intend to use Google maps as a backdrop to view the tracking
information
Please refer Corrigendum
404
33 IIPerformance Bank
Guarantee
Can TCS submit a PBG from Schedule Bank also or only Nationalized Bank as
mentioned in RFP
4056 II
Earnest Money
Deposit
Can TCS submit a EMD from Schedule Bank also or only Nationalized Bank as
mentioned in RFP406
11 IIPrices and Price
information
Contract should be tax exclusive. Otherwise changes in tax rate or structure
should be borne by the customer.Please refer section 1.2 (iv),
Vol.II of this RFP
40723 III
Invoicing and
Settlement
Interest @ 1% pa. needs to be paid by customer if payment is delayed by more
than 30 daysPlease refer section 2.15.2,
Vol.III of this RFP
408
65 II Pricing SummaryWhen is blended person month cost for 300 person months will get paid? Please refer section 4.3,
Vol.II of this RFP
409
CASWhat all components (out of 27 mentioned in the scope) are being covered by
the CAS systemPlease refer section 3.6, Vol.I
of this RFP
410
CAS (Centre) 21-07-2011
The delay of availability of the centre application will affect the overall
application and SDLC ? Will we be able to see the HLD / SRS for customization?What ever will be released
by NCRB for selected SI, it
shall be shared
411Haryana SWAN
What is the availability of Bandwidth at the end user i.e. P S / Police chowki
level.
Please refer Annexure XII,
Vol.I of this RFP
Bank Guarantee for EMD/
Performance Bank
Guarantee, shall only be
acceptable if issued from
Indian Nationalised Bank
only
412
PS / P Chowki
What is the degree of IT preparedness of police stations and police chowki’s in
the state?Please refer Annexure VIIIA,
VIIIB, Vol.I of this RFP
413Enhanced Tools for Crime
Registration, Investigation, Crime
Prevention, Law & Order
Maintenance and other functions
like Traffic Management,
Emergency Response, Human
Resource Management, Store
Management, Finance
Management etc mentioned in
the various sections in 5.2.1 etc.
Please clarify
Configuration, Customization, and Extension (New Modules) Of CAS (State) and
Integration with CAS (Center) & External Agencies as per para 5.4.3 What is
present status of these components? These systems and components are the
systems in it, the parts of the CAS application or need for development as a
fresh application for each sub modules or just an interface has to be
developed?Please refer Overall Blue
Print on page 32, Vol.I of this
RFP
414Information security
There is requirement of clarification on Information security solution.Please refer Corrigendum
415Customization CAS (Centre) & CAS
(State)
What is the degree of customization? Has the requirement of customization
worked out? Request for more clarification for CAS (State) customization.Please refer Annexure VI,
Vol.I of this RFP
416 Time line of implementation and
support period
More time is required for SRS etc, implementation and support is required? Please refer section 5.3, Vol.I
of this RFP418
123 IIIBlade Chassis Specification: -
6U to 12U Rack-mountable
Request you to change to 10U Rack Mountable Chassis or less Please refer to the
corrigendum419
123 III
Blade Chassis Specification: -
Dual network connectivity for
each blade server for redundancy
should be provided. Backplane
should be completely passive
device. If it is active, dual
backplane should be provided for
redundancy
2 network controllers on each blade server should be present for redundancy of
the controllers. Additionally each controller shall have dual ports. Backplane
should be completely passive device. If it is active, dual backplane should be
provided for redundancy. Backplane throughput should be at least 5 TB/s or
more.Please refer to the
corrigendum
420
123 III
Blade Chassis Specification: -
Should accommodate Intel, AMD,
RISC / EPIC Processor based Blade
Servers for future applications
Should support Intel / AMD / RISC / EPIC processor blades for future
applications. Additionally the blades must have SPEC benchmarks.Please refer to the
corrigendum
421
124 III
Blade Chassis Specification: -
Two hot-plug, redundant 1Gbps
Ethernet module with minimum
10 ports (cumulative), which
enable connectivity to Ethernet
via switch. Switch should be
(Internal/external) having Layer 3
functionality - routing, filtering,
traffic queuing etc
2 x 1G Ethernet Switch to support the fully populated chassis with the above
mentioned blade network connectivity. Additionally the switches shall have at
least 10 uplink ports per switch and features like IP address filtering, Link
aggregation, Port mirroring. Note: Routing is a feature of the Core L3 switch
which anyway is going to be external and hence there is no justification for
additional investment.
Please refer to the
corrigendum
422
124 III
Blade Chassis Specification: -
Two hot-plugs, redundant 4 Gbps
Fiber Channel for connectivity to
the external Fiber channel Switch
and ultimately to the storage
device.
Two hot-plugs, redundant 8 Gbps Fiber Channel for connectivity to the external
Fiber channel Switch and ultimately to the storage device.
Please refer to the
corrigendum
423
124 III
Blade Chassis Specification: -
Support heterogeneous
environment: AMD, Xeon and
RISC/EPIC CPU blades must be in
same chassis with scope to run
Win2003/2008 Server, Red Hat
Linux 64 Bit UNIX, Suse Linux / 64
Bit UNIX / Solaris x86
Request to change to "Should support Intel / AMD / RISC / EPIC processor
blades. The Intel / AMD blade server must support Microsoft® Windows
Server® 2008 R2, Microsoft® Windows Server® 2003 R2, Novell SUSE Linux
Enterprise Server, Red Hat Enterprise Linux, Citrix® XenServer™, VMware
Infrastructure & Oracle® Enterprise Linux. The RISC / EPIC blade server must
support Microsoft® Windows Server® 2008 R2, Oracle® Solaris, IBM AIX, HP-UX"
Please refer to the
corrigendum
424
124 III
Blade Servers (Web, Portal,
Application, Directory, etc…):-
2 Quad core @ 2.0 GHz or above
with 4 MB shared L2 cache, 1066
MHz / 2000 MT/s FSB
2 Processor populated, Each CPU should have 6 processing cores or higher, 12
MB cache of higher, TDP of CPU should be 95W or lower, 32-bit & 64-bit OS
compatible, SPEC Rating of Throughput (60% of SPECint_rate_base2006 + 40%
of SPECfp_rate_base2006 scores) should be minimum 295 or higher with SPEC
documentary datasheets of the respective OEMs.
Please refer to the
corrigendum
425
125 III
Blade Servers (Web, Portal,
Application, Directory, etc…):-
Min 32 GB FBD RAM with min 8
Nos. free slots for future
expandability.
4 x 8 GB DDR3 1333 MHz memory equally distributed among the populated
CPUs
Please refer to the
corrigendum
426
125 III
Blade Servers (Web, Portal,
Application, Directory, etc…):-
The Blade should have redundant
4 Gbps Fiber Channel HBA (only
for database server)
The Blade should have redundant 8G FC Controller with dual ports on each
controller (only for database server)
Please refer to the
corrigendum
427
125 III
Blade Servers (Web, Portal,
Application, Directory, etc…):-
2 X (1000BASE-T) Tx Gigabit LAN
ports with TCP / IP offload engine
support / dedicated chipset for
network I/O on blade server
2 x 1G Ethernet Controller with dual ports on each controller for redundancy on
each blade server
Please refer to the
corrigendum
428
125 III
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…):-
2 Quad core @ 2.0 GHz or above
with 4 MB shared L2 cache, 1066
MHz / 2000 MT/s FSB
2 Processor populated, Each CPU should have 6 processing cores or higher, 12
MB cache of higher, TDP of CPU should be 95W or lower, 32-bit & 64-bit OS
compatible, SPEC Rating of Throughput (60% of SPECint_rate_base2006 + 40%
of SPECfp_rate_base2006 scores) should be minimum 295 or higher with SPEC
documentary datasheets of the respective OEMs.
Please refer to the
corrigendum
429
125 III
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…):-
Min 16 GB FBD RAM with min 8
Nos. free slots for future
expandability.
2 x 8 GB DDR3 1333 MHz memory equally distributed among the populated
CPUs
Please refer to the
corrigendum
430
125 III
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…):-
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…)The Blade should
have redundant 4 Gbps Fiber
Channel HBA
The Blade should have redundant 8G FC Controller with dual ports on each
controller
Please refer to the
corrigendum
431
125 III
Blade Servers for Infrastructure
Services (EMS, Backup, DNS,
Antivirus, etc…):-
2 X (1000BASE-T) Tx Gigabit LAN
ports with TCP / IP offload engine
support / dedicated chipset for
network I/O on blade server
2 x 1G Ethernet Controller with dual ports on each controller for redundancy on
each blade server
Please refer to the
corrigendum
432
125 III
Database Server:-
Minimum 4x Quad core processor
with 2.1GHz or above with
1066Mhz FSB / 2000 MT /s
expandable to 4 physical
processor with min 4 MB L3 cache
per processor
4 Processor populated, Each CPU should have 6 processing cores or higher, 12
MB cache of higher, TDP of CPU should be 95W or lower, 32-bit & 64-bit OS
compatible, SPEC Rating of Throughput (60% of SPECint_rate_base2006 + 40%
of SPECfp_rate_base2006 scores) should be minimum 470 or higher with SPEC
documentary datasheets of the respective OEMs.
Please refer to the
corrigendum
433
125 III
Database Server:-
OS support: Microsoft® Windows
Server 2003 / 2008, Enterprise
Edition / Red Hat® Enterprise
Linux 5 & 4 AP / SUSE® Linux
Enterprise Server 9 / Solaris for
x86
OS Support: Microsoft® Windows Server® 2008 R2, Microsoft® Windows
Server® 2003 R2, Novell SUSE Linux Enterprise Server, Red Hat Enterprise Linux,
Citrix® XenServer™, VMware InfrastructurePlease refer to the
corrigendum
434
125 III
Database Server:-:-
RAID controller with RAID 0/1/5
with 256 MB cache
RAID controller with RAID 0/1/5 with 512 MB battery backed write cachePlease refer to the
corrigendum
435
125 III
Database Server:-
HDD hot pluggable: 4 x 146 GB
2.5” 10 K RPM HDD or more
HDD hot pluggable: 4 x 146 GB 15K RPM HDD or more
Please refer to the
corrigendum
436
126 III
Database Server:-
Disk bays: Support for min 8 small
form factor hot plug SAS / SCSI
hard drives in disk drive carriers
that slides out from front
Disk bays: Support for min 8 hot plug SAS hard drives in disk drive carriers that
slides out from front
Please refer to the
corrigendum
437
126 IIIDatabase Server:-
2 x 4 Gbps Fiber Channel Ports
2 x 8G FC PortsPlease refer to the
corrigendum
438 All Products/ services rendered hereunder shall be deemed accepted, if
Customer does not provide a written notice of any rejection/confirmation of
acceptance or when Customer uses the Product/deliverable in its business,
whichever occurs earlier. In the event of any rejected product/service, Wipro
shall be given a 30 day period to correct the same.
Please refer section 2.7.4,
Vol.III of this RFP
439
63 I Pt. VII
Providing and installing Split type
AC, 2 Tonnage capacity of an ISO
certified company with associated
wiring/ fittings and voltage
stabilizer
Please confirm if any redundancy is required for the split ACs
Please refer section 5.4.4,
Vol.I of this RFP
440
Pt.V
Lighting fixtures in the room, 4 in
nos. each with 2X36W CFL
(Compact Fluorescent Light)
Mirror Optics reflector, anti-glare
ceiling/recessed mounted light
fixtures with CFL in approved
design
Please let us know, how much lumens do we have to maintain per site
Please refer section 5.4.4,
Vol.I of this RFP
441
Pt.II
Flooring of the room with 2 ft. X 2
ft. homogenous vitrified ISO
certified company tiles in
approved shade (anti-skid)
including 100 mm high skirting,
Please confirm the specifications for the ceiling as well
Please refer section 5.4.4, Pt.
(iii), Vol.I of this RFP
44270 I
2KVA Generator Set Please provide load details to be put on DG set. Also a single 2TR AC can not be
run on 2 KVA DG Set.Please refer Corrigendum
44371
600 VA UPS with 60 Min backup Please give the detailed specs for the samePlease refer Corrigendum
44471
KVM Switches Please give the detailed specs for the same Please refer to the
corrigendum445
45
LAN pls confirm the number of data and voice points per seatThis shall depend on the LAN
design finalized by selected
SI. However at present a LAN
of 6 seats is envisaged per
room.
446
123 I Annexure I
Identity Management – Microsoft
Active Directory
In stack 2, it is mentioned that we need to use Sun LDAP as well as MS AD for
directory. It is our understanding that MS AD is a directory service and not an
Identity Management solution. Is Haryana Police indicating that we should
consider IDAM solution offerings from Microsoft? Microsoft’s IDAM offering
includes ForeFront Identity Manager, ADFS, ADRMS.
Please refer to the
Corrigendum
447
90 I Capacity Building Plan
Police Staff under each rank as per
total sanctioned staff strength as
on 1.1.2010
What is the maximum number of users that the system will have? Can we
consider the staff strength mentioned here approx 57000 as the max limit. Entire Police force would be
the internal users of the
system. However concurrent
users would be aprrox. 2500
at present. Please refer RFP
for more details
448
87 I Communication Strategy
SI should ensure that the
communication messages are
consistent, continuous and easy to
understand and as far as possible
in vernacular medium using all
available channels
Can we build the access control and user management solution to use English
Language only – this includes the admin and self service screens.
Please refer section 5.4.10,
Vol.I of this RFP
449 From a DR perspective off the total modules proposed in CAS please classify
them according to their criticality level as high / medium / low.
450 For each criticality level please define the recovery objectives
451 RTO and RPO
452
67 I Section 5.4.7
The Disaster Recovery services for
Haryana State Data Centre are
envisaged to be provided by State.
Please provide more details as to where the site will hosted, will it the same
common DR site for the SDC or separate Please refer section 5.4.7,
Vol. I of this RFP
453
73 I Section 5.4.8
2. Carry out the migration of
legacy electronic data by using
data migration utility
From a DR perspective we assume that once the data is migrated from legacy
system to the new systems, we do not have to factor for the DR for these legacy
applications / data. Please confirm
Please refer Annexure XI,
Vol.I of this RFP
454138 I
Infrastructure Availability Kindly explain the bases on arrive on these RPO and RTO values Please refer to the
corrigendum
32 I Section 5.2.2
Deployment architecture
All the modules proposed
would act as one single
CCTNS application suite.
Therefore it is irrelevant to
classify their criticality.
Please refer RFP for more
details
455 Please refer to the
corrigendum456 Please refer to the
corrigendum457 RPO (zero data loss in case of
failure of Primary DC) should be
zero minutes
Please refer to the
corrigendum
458
250 I Sr.No.2
The GPS should be able to help
track and recover stolen cars.
Rather than giving chase, such a
stolen vehicle should be tracked
by law enforcement officials over
a long distance so that
apprehension of the thief can be
made once the car reaches its
destination.
It is not clear whether the GPS is for police cars or other general public vehicles
.will you need GPS to track the police cars if they are stolen or towed away.
Please refer Corrigendum
459
251 I Sr.No.6
It should be possible to equip
vehicles with GPS along with other
equipments as bait in law
enforcement operations. The GPS
should be installable in the
construction machinery and even
computers to aid in sting
operations.
Where do you expect to put the device? Inside computers or construction
equipment? How long do you want to keep the GPs device in these
equipments?
Please refer Corrigendum
460
252 S.No.21-29
The GPS should support
GPRS/SMS communication
How strong does the GPS bracelet needs to be. As it will run out of a battery,
how long should the battery last? SI is not required to provide
GPS bracelets as part of this
RFP. Please refer RFP for
more details
461
252 S.No.27
The GPS should have a Geo-fence
alarm, and should be able to setup
geo-fence areas in case of lost.
Do you need unique GEO Fencing for each bracelet, do you need to
change/update the geo-fencing info from a remote location. What do you mean
by " setup geo-fence area in case of lost"Please refer Corrigendum
462
252 S.No.26
If the wrist tracker exists in the
GPS, then it should be able to
report the position under ordered-
frequency and work in interval-
based saving power mode
What is the minimum interval for which you need to track the criminal
Please refer Corrigendum
RTO shall be less than or equal to
six (6) hours.
how will these SLA be measured
463
250
General How many Vehicle & Criminal to be tracked?This query is not clear and
hence cannot be answered
464
252 S.No.20
Instant Messaging: The GPS
should have the feature to send
information— such as addresses,
work orders, driving
directions—quickly and easily
from the web to the driver's cell
phone. The driver should also be
able to reply to that message from
the GPS.
Communication /Work Orders can be sent to the display unit in vehicle. Why
send it to Mobile phone of person as it may be switched off.
Please refer Corrigendum
465
251 S.No.6
Landmarks: The GPS should be
able to see vehicle positions with
reference to Landmarks as it is
useful for knowing where vehicles
are (or have been) in relation to
locations, such as police stations,
criminal and/or unauthorized
areas.
Will HP give us the landmarks to be shown in the map.
Please refer Corrigendum
466
250 S.No.4
The GPS should be able to quickly
transmit via satellite the
fingerprints, license numbers and
images of wanted individuals.
Do you need two way communication for sending and receiving Biometric data
and other information? Would you need data capture ( including biometric) in
the vehicle and sending it to server or do you need only information from
server to be send to vehicle GPS display.Please refer Corrigendum
467
210 S.No.29 & 55
System should allow the user to
enter/ capture the unique
identification details of the
convicts like IRIS, Fingerprints and
Facial patterns & System should
be able to record the following
details of the person,
as proposed by the Planning
Commission, Government of India
:
- Finger Prints
- IRIS
- Facial Maps (Facial Recognition
System)
Please confirm any one or all biometric Data IRIS, Fingerprint, Facial Patterns to
be captured.
The CCTNS application
should support capturing of
all biometric data. Please
refer RFP for more details
468
210 S.No.29
System should allow the user to
enter/ capture the unique
identification details of the
convicts like IRIS, Fingerprints and
Facial patterns
Do you need 270 devices to capture bimetric data
As part of this RFP Finger
print readers are only
required. However in near
future department may
decide to go ahead and plan
for capturing other
biometrics, therefore the
application should have
provision for implementing
such a plan. Please refer RFP
for more details
469
211 S.No.50
Should support Real-time exact
and relaxed matches of
fingerprints from the master
database using live scan
fingerprints or the latest prints
collected from the scene of crime.
What is the max size of master database? Approx how many finger print would
be their in master database? Master database of
fingerprints would be with
Finger Print Bureau. AFIS
project is a separate project
with Haryana Police. CAS
(State) comes with the
functionality of carrying the
fingerprints captured at
Police Station and send the
same to AFIS. AFIS in turn
would result with relaxed
and exact match.
470
27 I
Barcode/ RFID tags to be used to
track seized property
Do the bidder need to setup Barcode/ RFID solution at each police station? If
yes pls let us know the if you need barcode or RFID and Qty of tags required in
270 police stations
Barcode/ RFID concept is not
part of the scope. However
system should be able to
integrate the same in near
future
471
I
5.4.6 Network
Connectivity for PS
and Higher Offices)
Police Stations will be either on
SWAN or VPN over Broadband
with 512Kbps bandwidth
Comparing 512 Kbps Bandwidth availability in VPN over Broadband for shared
customers with SWAN would be much lesser. Broadband connection utilizes
best effort delivery of IP traffic whereas application traffic in Police Stations
would requires min bandwidth rather than competing with shared bandwidth
access over broadband being used by other customers of same Service
Provider. Keeping this in view either we would be requiring more bandwidth for
VPN over broadband connectivity using shared access or going for premium
Customer VPN connectivity over Broadband with dedicated 512 Kbps (if
available)
Minimum bandwidth has
been mentioned.
472
I
5.4.6 Network
Connectivity for PS
and Higher Offices)
However at some of the Police
Stations, Haryana Police may
use25 the existing SWAN
connectivity, and finally
connecting the Police Stations
(both VPN over broadband and
SWAN) to the State Data Centre
where CCTNS solution will be
hosted
Is link redundancy required in WAN to achieve high availability at Police
Stations?
Link redundacy is required
only at SDC. However
internet connectivity of 2
Mbps would be required at
SDC.
473
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please confirm if Department will provide area of interest boundary for
procurement of required inputs such as SOI top sheets, satellite images and
maps from respective Govt./Authorized agencyPlease refer Corrigendum
474
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please confirm or advise on the land base map prepared will prepared using
high resolution satellite image with spatial resolution of 0.5m or better as best
available. Also mention the vintage of satellite image. Please refer Corrigendum
475
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please confirm if client will procure required satellite images and provide to the
SI for GIS mapping and layer creation
Please refer Corrigendum
476
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please mention numbers of GIS data layers required like roads, streets,
buildings/parcel boundaries, landmarks etc as may be extracted from the image
processing.Please refer Corrigendum
477
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please ocnfirm if any software/application/infrastructure is available with
department and can be made available for this project.
Please refer Corrigendum
478
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please confirm. If GIS data developed under this project is of restricted nature
for the specific use of Police department only and developed using High
resolution image, we expect client will provide necessary authorization for the
same.Please refer Corrigendum
479
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please confirm and provide available data details. It is assumed that
data/details/ drawings/layouts maps as may be available with client will be
provided for necessary use and integration with the system developed under
this project. Please mention the format like hardcopy or softcopies and file
format for such available data.
Please refer Corrigendum
480
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Data of crime history will be made available to consultants for analyses purpose
and necessary use in the system. Please mention the format of such data
available with the department. Please confirm and provide available data
details.Please refer Corrigendum
481
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
We assume integration of geospatial browsers, such as Microsoft’s Virtual Earth
and Google Maps s for only viewing purpose and no data extraction which
require licensing and legal usage under copyright act as may be specified.Please
confirmPlease refer Corrigendum
482
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
We assume HW requirement will be taken care by client under separate budget
head. Scope of current project is to suggest or advise on the same. Please
confirmPlease refer Corrigendum
483
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Dispatchers should be able to
view an incident being created
prior to the incident being
entered into the system
Client will provide necessary access and guidance for law Enforcement records
of the department to use and integrate with the system. Please confirm
Please refer Corrigendum
484
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Change-Over-Time Mapping: The
GIS should be able to accurately
assess the affect of crime
reduction efforts and recognize
areas of satellite images after
certain periodic time frame as
mutually agreed
Change-Over-Time Mapping: client will provide provision of data review and
necessary procurement of satellite images after certain periodic time frame as
mutually agreed. Please confirm
Please refer Corrigendum
485
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
The GIS should have a
system/method to allow national,
regional, and military mapping
agencies to build enhanced
cartographic
We assume department facilitate necessary interaction and authorization with
national, regional, and military mapping agencies to build enhanced
cartographic capabilities considering sensitive nature of the task and wherever
required advise on necessary amendment to meet the system requirements
and objectives. Please confirm
Please refer Corrigendum
486
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Please provide the details of cadastral
Please refer Corrigendum
487
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
Maps available like the format whether digital or hardcopy and confirm same
can be made available to use and integrate with the system and GIS layer.
Please refer Corrigendum
The GIS should provide the ability
to generate accurate cadastral
488
240-
250I
Annexure VII:
Functional
Requirement
Speciifiicatiions -20.
Geographic
Information System
It should let one perform parcel
geometry operations and interact
with the GIS database while
viewing the parcel map or
neighbourhood.
We assume data related to terrain analysis and visualization features, will be
available with client and system should provide the facility to view the data as
GIS layer.Please refer Corrigendum
489
23 I
Data Migration of CAS (State)
related data from the legacy
systems and / or manual records
to CAS
Kindly help us in providing the details of legacy application if possible which may
help to design the overall migration strategy for smoother transition Please refer section 5.4.8,
Vol.I of this RFP
490
68 I
State will provide the premises for
hosting the solution in State Data
Centre as well as the Disaster
Recovery Centre (DRC)
Kindly share the status of SDC readiness, whether SDC will be ready by that time
& what would be the DR location
Please refer Corrigendum
491
220 ISection 9, Email &
messaging Services what is current mailing solution department is using as of now & how many
users are there
Presently Haryana Police is
using mailing system
provided by NIC
492
I Section 20, GIS/SDI
Are we using any GIS application/system if yes please specify the details of
existing GIS setup No, there are no such
existing application/ system
493
23 ISection 4, Helpdesk
Support
1. Please provide the estimated call volume per month ( or per quarter)
2. Please specify the helpdesk location
Call Volumes cannot be
decided. This would be
based on the quality of
handholding support
provided by SI at each
location. Helpdesk location
would be shared with
selected SI. Please refer RFP
for more details
494
77 ISection 5.4.8, Data
Digitization1. Please provide the expected duration and Time line for the entire Data
Migration and Digitization activity
2. Please provide the volume of number of fields/pages to be digitized
3. Will the Infrastructure for Digitization be provided by the Purchaser
Bidder to plan in such a way
that entire data migration
and data digitization exercise
is successfully completed
before Pilot Go-Live. Please
refer RFP for more details
495
89 ISection 5.4.10, People
Management Strategy 1. Will the Space/Venue, projector, other infrastructure etc for Training be
provided by the Supplier? Please clarify
Please refer section 5.4.11,
Vol.I of this RFP
496
104 I
Section 5.5, Scope of
Services - Post-
Implementation Phase
/ Operate and
Maintain Phase1. What is the minimum manpower for O&M support expected at DC and DR
Site
Min. 1 qualified and trained
person each for DC and DR
Site
497
133 III
Desktop-
a)Graphics Controller-Intel
Graphics Media Accelerator 4500
integrated graphics
b) Expansion Slot-3 full-height PCI,
1 full-height PCI Express x1, 2 full-
height PCI Express x16
a) GRAPHICS WILL BE INTEGRATED PART OF PROCESSOR. GMA 4500 IS FOR 4
SERIES CHIPSETS ONLY
b) 1 PCI, 2PCI X1 AND 1 PCI X16
Please refer Corrigendum
498
129 III Backup Software
Backup Software-
a) The proposed backup Solution
supports the capability to write
multiple data streams to a single
tape device or multiple tape
devices in parallel from multiple
clients to leverage the throughput
of the Drives using Multiplexing
technology.
b) The proposed backup solution
support de-multiplexing of data
cartridge to another set of
cartridge for selective set of data
for faster restores operation to
client/servers
a) Backup software should have the capability to write multiple streams to
multiple drives
(Points mentioned in RFP are of old technology.)
Please refer Corrigendum
499
129 III Tape Library
All points are as per compliance
Points to be incorporated
• MTBF: 250,000 Hours
• MSBF: 2,000,000 Cycles
• Minimum LTO5 Drives: 4 Half height Drive
• Drives Expandable Upto 16 HH Drive
• Minimum Slots for Tape Cartridge : 40
• Slots Expandable Upto: 150 or above
Better Technology and SLA & future expandability.
Please refer Corrigendum
500
22 II
Max 5 Citations showcasing
experience of successful
deployments of software
application in Police domain in the
last 5 years
Following parameters will be
examined for evaluation:
• Relevance to the current
project
• Stage of completion of the
project (Completed / on-going)
Bidder must provide as a
supporting documentary proof
in form of work orders
confirming year and Area of
activity, value of services to be
delivered for each of the two
projects, Completion / Partial
Completion Certificate from Client
confirming year and value of
Bidder’s scope of work, scope
of work completed by the
Request you to change the criteria as:
Max 5 Citations showcasing experience of successful deployments of
software application in Police/Central Government /State Government/PSU
domain in the last 5 years
Please refer section 2.6, Vol.
II of this RFP
501
32 II Section 3.6
Failure of the successful bidder to
agree with the Terms &
Conditions of the RFP shall
constitute sufficient grounds for
the annulment of the award, in
which event Haryana Police may
award the contract to the next
best value bidder
Failure of the successful bidder to agree with the Terms & Conditions subject to
suggested changes & Decencies of the RFP shall constitute sufficient grounds
for the annulment of the award, in which event Haryana Police may award the
contract to the next best value bidderPlease refer section 3.6, Vol.I
of this RFP
502
14 III Section 2.4
In the event that any of the
Conditions Precedent of the
System Integrator have not been
fulfilled within 15 days of signing
of this Agreement and the same
have not been waived fully or
partially by Client or its nominated
agencies, this Agreement shall
cease to exist;
In the event that any of the Conditions Precedent of the System Integrator have
not been fulfilled within 45 days of signing of this Agreement and the same
have not been waived fully or partially by Client or its nominated agencies, this
Agreement shall cease to exist;
Please refer section 2.4,
Vol.III of this RFP
503
24 III Section 2.15.3
In the event of any increase or
decrease of the rate of taxes due
to any statutory notification/s
during the Term of the Agreement
the consequential effect shall be
to the account of the System
Integrator.
Wipro Request Change in this clause:-In the event of any increase or decrease
of the rate of taxes due to any statutory notification/s during the Term of the
Agreement the consequential effect shall be to the account of the CLIENT.
Please refer section 2.15.3,
Vol.III of this RFP
504
25 III Section 2.15.4
If the System Integrator is not able
to deliver the services as per the
SLAs defined in Volume 1 of RFP
which translates into Material
Breach, then the CLIENT may
serve a 7 days written notice for
curing this Material Breach. In
case the Material Breach
continues, after the expiry of such
notice period, the CLIENT will have
the option to terminate this
Agreement. Further, the CLIENT
may after affording a reasonable
opportunity to the System
Integrator to explain the
circumstances leading
to such a delay.
If the System Integrator is not able to deliver the services as per the SLAs
defined in Volume 1 of RFP which translates into Material Breach, then the
CLIENT may serve a 30 days written notice for curing this Material Breach. In
case the Material Breach continues, after the expiry of such notice period, the
CLIENT will have the option to terminate this Agreement. Further, the CLIENT
may after affording a reasonable opportunity to the System Integrator to
explain the circumstances leading to such a delay. CLIENT will also reimburse SI
with the hardware/Software Licenses delivered and Services rendered till that
Day.
Please refer section 2.15.4,
Vol.III of this RFp
505
30 III Section 2.16.2 (d)
The System Integrator shall
ensure that all its employees,
agents and subcontractors
execute individual non disclosure
agreements, which have been
duly approved by the CLIENT with
respect to this Project.
The SI should ensure having back to back NDA signed with all its employees and
Sub contractor involved in this project and may produce at any given point of
time to CLIENT
Please refer section 2.16.2.
(d), Vol.III of this RFP
50630 III Section 2.20
As per RFP Audit, Access and reporting is limited to this project only Please refer section 2.20,
Vol.III of this RFP
507
32 III Section 2.22.2 ©
The System Integrator shall also
be responsible to train certain
employees of CLIENT, or its
nominated agencies with regard
to the Services being provided by
the System Integrator as and
when required by the CLIENT
Wipro request for absolute numbers instead of certain
Please refer section 2.22.2,
Vol.III of this RFp
508
33 III Section 2.22.3
System Integrator shall not
subcontract any work related to
the data recovery centre, data
centre, security, etc. other Core
activities to be performed under
this Agreement without CLIENT’s
prior written consent.
However the System Integrator
shall provide the list of all the
other services planned to be sub
contracted with the Technical
proposal. It is clarified that the
System Integrator shall be the
principal employer for all claims
arising from the liabilities
statutory or otherwise,
concerning the sub-contractors.
The System Integrator undertakes
to indemnify the CLIENT or its
nominated agencies from any
claims on the grounds stated
Wipro request change in this clause:-System Integrator may subcontract any
work related to the data recovery centre, data centre,security, etc. subject to
NDA and for all practical purposes SI would be solely responsible for service and
Delivery as per the SLA and Scope of work.SI may inform Client for all these
engagement.
However the System Integrator shall provide the list of all the other services
planned to be sub contracted with the Technical proposal. It is clarified that the
System Integrator shall be the principal employer for all claims arising from the
liabilities statutory or otherwise, concerning the sub-contractors. The System
Integrator undertakes to indemnify the CLIENT or its nominated agencies from
any claims on the grounds stated hereinabove.
Please refer section 2.22.3,
Vol.III of this RFP
509
36 III Section 2.23 (b)
As per RFP Request deletion of this one sided clause and Wipro request insertion of the
below clause:- If the dispute cannot be settled by mutual discussions within
the thirty (30) day period, either party may refer the matter to a panel of three
arbitrators. Each party shall choose one arbitrator, both of whom shall elect the
third arbitrator who shall be the presiding arbitrator. The arbitration
proceedings shall be held under the provisions of the Arbitration and
Conciliation Act, 1996 or any of its subsequent amendments. The arbitration
proceedings shall be in English and the venue of arbitration shall be Chandigarh,
India.
Please refer section 2.23(b),
Vol.III of this RFP
510
47 III Section 3.3.5 ©
To the extent that any Transfer
Regulation does not apply to any
employee of the System
Integrator, department, or its
Replacement System Integrator
may make an offer of
employment or contract for
services to such employee of the
System Integrator and the System
Integrator shall not enforce or
impose any contractual provision
that would prevent any such
employee from being hired by the
SPMU or any Replacement System
Integrator.
Request Deletion of this Clause
Please refer section 3.3.5,
Vol.III of this RFP
511
54 IIISection 3.6, Payment
Schedule
Implementation Phase 35%
Operation & Main Phase 65%
(Equated over 5 year on a half
yearly basis means 6.5% of O&M
per Half year)
Knowing the Capex and the Investment involved Wipro request change of the
clause is as Under:- A) Implementation Phase 65% B) O&M Phase 35%--
-It should be on quarterly basis 1.75% per qtr till 20 qtr Please refer section 3.6,
Vol.III of this RFP
512
55 IIISection 3.6, Payment
Schedule
All payments to the System
Integrator shall be made upon
submission of invoices along with
relevant sign-offs from Haryana
Police.
It is too wide and open ,Request you to clarify the specific Sign-off from Haryana
PolicePlease refer section 3.6,
Vol.III of this RFP
513
55 IIISection 3.6, Payment
Schedule
Pre –Go live readiness CLIENT hereby agrees to make the site ready as per the agreed specifications,
within the agreed timelines. CLIENT agrees that Wipro shall not be in any
manner be liable for any delay arising out of CLIENT's failure to make the site
ready within the stipulated period, including but not limited to levy of liquidated
damages for any delay in performance of Services under the terms of this
Contract. Further any idle time resulted due to non available of site or
infrastructure or data, Customer shall make payment to Wipro for the same.
Please refer section 3.6,
Vol.III of this RFP
514
55 IIISection 3.6, Payment
Schedule
The payment against the
hardware will be made on the
basis of the actual quantity of the
items procured. CLIENT will have
the right for reduction / addition
in the quantity proposed. Any
payments will be done on the
basis of the unit rates quoted by
the bidder in the Commercial bid.
The payment against the hardware will be made on the basis of the actual
quantity supplied and Installed .
Please refer to the
Corrigendum
515
56 IIISection 3.6, Payment
Schedule
Any fluctuation in prices due to
inflation, tax regulations, will be
borne by the bidder and not be
passed on to CLIENT
Any change in tax structure or Statutory amendment subsequent to submission
resulted into any change in taxes ,duties shall be borne by CLIENTPlease refer section 3.6,
Vol.III of this RFP
516
66 III
Penalties applicable for each of
the high severity violations are
0.1% of respective payment-
period payment to the SI.
Penalties applicable for each of the high severity violations are 0.1% of
respective payment-period payment to the SI.and subject to Maximum of 1% of
ContractPlease refer section 4, Vol.III
of this RFP
517
66 III
Penalties applicable for each of
the medium severity violations are
0.05% of respective payment-
period payment to the SI.
Penalties applicable for each of the medium severity violations are 0.05% of
respective payment-period payment to the SI.subject to Maximum of 1% of
ContractPlease refer section 4, Vol.III
of this RFP
518
87 III
It is to be noted that if the overall
penalty applicable for any of the
review period during the currency
of the contract exceeds 25% or if
the overall penalty applicable for
any of the successive half year
periods during the currency of the
contract is above 15%; then the
Haryana Police shall have the right
to terminate the contract.
Bidder request relook of this clause and maximum penalty for all the reasons
should be capped to 10%
Please refer section 4, Vol.III
of this RFP
519To be
Included(approval)
Government of Haryana to provide all relevant approvals before the start of the
contract & charges if any should not be levied on to Supplier. Please refer RFP
520
To be Included(Change
request)
Either party may request a change order (“Change Order”) in the event of
actual or anticipated change(s) to the agreed scope, Services, Deliverables,
schedule, or any other aspect of the Statement of Work. Bidder will prepare a
Change Order reflecting the proposed changes, including the impact on the
Deliverables, schedule, and fee. Absent a signed Change Order, Bidder shall not
be bound to perform any additional services. The parties agree to negotiate in
good faith all Change Order proposals. The parties further agree that Bidder
may undertake and accomplish tasks of a de minimis nature necessary to
perform its obligations under any Statement of Work at no additional cost and
without requiring the execution of a Change Order.
Please refer RFP
521
To be Included(Pre
existing IP)
Each party owns, and will continue to own all rights, title and interests in and to
any inventions however embodied, know how, works in any media, software,
information, trade secrets, materials, property or proprietary interest that it
owned prior to this Agreement, or that it created or acquired independently of
its obligations pursuant to this Agreement (collectively, “Preexisting Works”).
All rights in Preexisting Works not expressly transferred or licensed herein are
reserved to the owner.
Please refer RFP
522
To be Included(mutual
indemnification)
each party (the “Indemnifying Party”) shall defend, indemnify, and save
harmless the other party (the “Indemnified Party”) and its officers and
directors, employees, agents, and representatives from and against any losses,
damages, costs, attorneys’ fees, penalties, fees, liabilities, or expenses
(collectively, “Losses”) associated with any third party claim against the
Indemnified Party connected with (i) death, or (ii) injury to persons or property,
in each case resulting from the acts or omissions of the Indemnifying Party, its
employees, agents or contractors.
Please refer RFP
523 Please refer RFP 524 Please refer RFP
To be
Included(infringement
Wipro/SP shall have not obligation with respect to any infringement claims to
the extent that the infringement claim arises or results from (1) Inclusion in a
525
To be Included(LoL)
Wipro shall not be liable for any indirect, punitive, consequential or incidental
loss, damage, claims, liabilities, charges, costs, expense or injury, including,
without limitation, loss of use, data, revenue, profits, business interruption, and
loss of income or profits, that may arise out of or result from this Agreement,
irrespective of whether it had an advance notice of the possibility of any such
damages. Subject to the above and notwithstanding anything to the contrary
elsewhere contained herein, the maximum aggregate liability of Wipro for all
claims under or in relation to this Agreement, shall be, regardless of the form of
claim(s), the consideration actually received by Wipro under this Agreement.
Please refer RFP
526 Wipro’s failure to perform its contractual responsibilities, to perform the
services, or to meet agreed service levels shall be excused if and to the extent
Wipro’s non-performance is caused by Customer’s omission to act, delay,
wrongful action, failure to provide inputs, or failure to perform its obligations
under this Agreement.
Please refer RFP