September 2015

Hanover Square Ticket Hall Update

C412-XRL-Z1-XBU-CR084_1-50001

Timing of works • CSJV work 24hrs Monday to

Friday; and 07:00 to 18:00 on Saturdays

Duration of work • End September: grouting of

head brackets commences • Early October: slab

construction at L-5 begins • Early October: lining walls of

L-4 complete • Early November: excavation

of L -5 complete

What to expect • Removal of excavated

material from site by road • Break out and removal of

temporary slabs and piles • Delivery of concrete for slab

pours • Delivery of steel

reinforcement • General site activity

What we will do • Monitor dust, noise and

vibration to keep it within permitted levels

• Use wire cutting techniques for removing the temporary piles to minimise noise and vibration

• Traffic marshalls on site to help with traffic flow and vehicle access into and out of the site.

Eastern Ticket Hall Excavation to level -5 is well underway. The first stage, which involved excavating clay and removing the temporary running tunnel and crossover tunnel, has now been completed. Excavation will now continue to remove clay between bearing piles so they can be cut, and the temporary slab within the North West shaft will be removed. These works are expected to be completed by the first week of November. Slab construction at level -5 is expected to begin in early October and the lining of walls at level -4, which is currently underway, will be complete in early October.

Platform Tunnels Civil works to construct the track bed and platform is now largely complete and the focus in this area has moved towards Platform Edge Screen (PES) installation. Works to install head brackets and side brackets are underway and grouting of the head brackets commences End September.

Platform

Track bed

Page 2: Hanover square ticket_hall_update_sept_15_v2

About Crossrail

Crossrail is Europe’s largest construction project, delivering a new railway for London and the South East.

When the service opens, Crossrail trains will travel from Reading and Heathrow in the west to Shenfield and Abbey Wood in the east via new twin tunnels under central London. It will link Heathrow Airport, the West End, the City of London and Canary Wharf.

Bond Street Community Liaison Panel Crossrail runs a community liaison panel for each central London station to keep local community representatives informed of progress and plans. If you would like further information please contact [email protected]