HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500 Ac – 40 TMC Phase-I – 1,98,000 Ac. – 14 TMC Total Lift – 203 M Lifts on Main Canal (Phase- I – 7 Nos. TENDERS FINALISED TENDERS TO BE CALLED PACKAGE DETAILS ARE IN NEXT PAGE (+266.5 m) PATH IKONDA RESE RVOIR (+469.608 m) (+454 m) 0.00 KM 9.20 KM 56.75 KM 68.00 KM 80.12 KM 88.89 KM 97.49 KM 175.93 KM K RISHNAGIRI RESERV OIR (+290 m) (+289.17 m) (+316 m) (+311.18 m) (+340 m) (+338.82 m) (+370 m) (+368.79 m) (+400 m) (+398.96 m) (+430) (+429.29 m) (+440.95 m) FRL +885’ (269.75 m) MDDL +834’ (254.20 m) KM 216.30 JE E DI P AL L Y R ESER VOIR K U RN O OL DI ST R CI T 216.3 km 144.00 km 874.4 ft. 951.5 ft 1036.8 ft 948.8 ft 1115.5 ft 1020.98 ft 1213.9 ft 1111.67 ft 1312 ft 1210 ft 1410 ft 1309 ft 1489 ft 1408.5 ft 1447 ft 1540.8 ft RESERVOIR SRISAILAM Phase-I 9.20 KM 56.75 KM 68.00 KM 80.12 KM 88.89 KM 97.49 KM 175.93 KM 0 .0 0 K M L i ft 1 L i f t 2 L if t 3 L i f t 4 L i ft 5 L i ft 6 L i ft 7 L i ft 8 RESERVOIR 70.65 KM PATHIKONDA RESERVOIR R ES ER VO I R J E ED IP A LL Y ANANTAPUR DISTRICT PE RU R BR A N C H CA NAL ( 1 6 K M) ] 108.57 km SRISAILAM KRISHNAGIRI RESERVOIR PKG 23, C2 Approach channel (-3.42 km) PKG 24, C2 PKG 25, C2 PKG 26, C2 PKG 27,C2 PKG 29, C2 PKG 30, C-2 PKG 31, C2 PKG 32, C2 PKG 33, C2 PKG 28,C2 PKG 34, C2 PKG 35, C2 P K G 3 6 , C 2 20 km 40 km 64 km 77 km 100 km 114 km 134 km 155 km 176 km 210 km PHASE-I Capacity 0.898 TMC Capaci ty 1.55 TMC Cap.0.153 TMC

Upload: adrian-daniels

Post on 02-Jan-2016

248 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES)SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1

ULTIMATE STAGE

Utilisation – Ayacut 6,02,500 Ac

– 40 TMC

Phase-I – 1,98,000 Ac.

– 14 TMC

Total Lift – 203 M

Lifts on Main Canal (Phase-I – 7 Nos.

TENDERS FINALISED

TENDERS TO BE CALLED

PACKAGE DETAILS ARE IN NEXT PAGE

(+266.5 m)

PATH

IKO

ND

A

RES

ERV

OIR

(+469.608 m)

(+454 m)

0.00 KM

9.20 KM

56.75 KM

68.00 KM

80.12 KM

88.89 KM

97.49 KM

175.93 KM

KR

ISH

NA

GIR

I

RES

ERV

OIR

(+290 m)

(+289.17 m)

(+316 m)

(+311.18 m)

(+340 m)

(+338.82 m)

(+370 m)

(+368.79 m)

(+400 m)

(+398.96 m)

(+430)

(+429.29 m)

(+440.95 m)

FRL +885’ (269.75 m)

MDDL +834’ (254.20 m)

KM 216.30

JEE

DIP

AL

LY

RE

SER

VO

IR

KU

RN

OO

L D

IST

RC

IT

216.

3 km

144.

00 k

m

874.4 ft.

951.5 ft

1036.8 ft

948.8 ft

1115.5 ft

1020.98 ft

1213.9 ft

1111.67 ft

1312 ft

1210 ft

1410 ft

1309 ft

1489 ft

1408.5 ft

1447 ft

1540.8 ft

RESERVOIRSRISAILAM

Phase-I

9.20

KM

56.7

5 K

M

68.0

0 K

M

80.1

2 K

M

88.8

9 K

M

97.4

9 K

M

175.

93 K

M

0 .00

KM

Lif

t 1

Lif

t 2

Lif

t 3

Lif

t 4

Lif

t 5

Lif

t 6

Lif

t 7

Lif

t 8

RESERVOIR70.65 KM

PA

TH

IKO

ND

A

RE

SE

RV

OIR

RE

SE

RV

OIR

JEE

DIP

AL

LY

AN

AN

TA

PUR

DIS

TR

ICT

PER

UR

BR

AN

CH

CA

NA

L (16 K

M)]10

8.57

km

SRISAILAMKRISHNAGIRI

RESERVOIR

PKG 23, C2

Approach channel (-3.42 km)

PK

G 2

4, C

2

PK

G 2

5, C

2

PK

G 2

6, C

2

PK

G 2

7,C

2

PK

G 2

9, C

2

PK

G 3

0, C

-2

PK

G 3

1, C

2

PK

G 3

2, C

2

PK

G 3

3, C

2

PK

G 2

8,C

2

PK

G 3

4, C

2P

KG

35,

C2

PK

G 3

6, C

2

20 km 40 km 64 km77 km

100 km

114

km

134

km

155

km

176

km

210

km

PHASE-I

Capacity 0.898 TMC

Capacity 1.55

TMC

Cap.0.153 TMC

Page 2: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

H.N.S.S PROJECT – PHASE – I

1 PROJECT PROFILE : Lifting of 14 TMC water from foreshore of Srisailam Reservoir, Excavation of Main canal, distributaries formation of Balancing Reservoirs etd.

Length of canal : 216 Kms

No. of balancing Reservoirs : 3 No.Drinking water : 10 Lakh PeopleNo. of lifts : 7 Nos.

2 Administrative Sanction : G.O.Ms.No. 731, Dt: 24-7-05, for Rs. 1305 Crores

3 No. of EPC Packages : 14 (+1 No. of lifts packages under approval at Government)

4 Agreement value of packages (14 Nos.)

: Rs. 918.171 Crs.

5 Budget Provision :

Rs. 253.00 Crs.

6 Expenditure of the project

2004-05 : Rs. 41.23 Crs. (Mob Adv. Only)

2005-06 : Rs. 142.25 Crs.

Cum. Exp. : Rs. 183.48 Crs.

7 Utilisation : 14 TMC

8 Ayacut New : 1,98,000 acres

Page 3: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

9 Land Acquisition

Required : 10255.76 acres

Acquired : 301 acres

Balance to be acquired : 8369.27 acres

10

Power Required : 146 MW / 195711 HPs

LIFT DETAILS :

a) Lift-I

Lift Height : 48.50 m

No. of Pumps : 4 Nos.

Total pumps capacity : 32000 HP

b) Lift-II

Lift Height : 28 m

No. of Pumps : 4 Nos.

Total pumps capacity : 18476 HP

c) Lift-III

Lift Height : 31.5 m

No. of Pumps : 4 Nos.

Total pumps capacity : 20784 HP

d) Lift-IV

Lift Height : 33.50 m

No. of Pumps : 4 Nos.

Total pumps capacity : 22104 HP

H.N.S.S PROJECT – PHASE – I

Page 4: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

e) Lift-V

Lift Height : 31.5 m

No. of Pumps : 4 Nos.

Total pumps capacity : 20784 HP

f) Lift-VI

Lift Height : 31 m

No. of Pumps : 4 Nos.

Total pumps capacity : 19924 HP

g) Lift-VII

Lift Height : 27 m

No. of Pumps : 4 Nos.

Total pumps capacity : 17360 HP

h) Lift-VIII

Lift Height : 31 m

No. of Pumps : 4 Nos.

Total pumps capacity : 17024 HP

11

Mobilisation Advance paid/package wise

Paid Recovered

2004-05 : Rs.41.23 Crs. ---

2005-06 : Rs. 20.96 Crs. Rs. 12.06 Crs.

Total : Rs. 62.19 Crs. Rs. 12.06 Crs.

12 Target Date : 3/2007

H.N.S.S PROJECT – PHASE – I

Page 5: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

PKG No.

DescriptionAgt. Value & Date

Agt. PeriodName of the contractor

23

Investigation Preparation of H.Ps Designs, Drawings and excavation of HNSS main canal from Km (-) 3.420 to 20.00 including CM&CD Works and distributory system to feed an ayacut of 4200 Acres Khariff I.D.

Rs, 47.00 Cr.

25-02-05

24 months

M/s Back bone Projects, Ahmedabad.

24 - do – Km 20.00 to 42.00 – 2300 Acres

Rs, 57.78 Cr.

25-02-05

24 months

M/sSushee Hitech Construction, Hyderabad

25 - do – Km 42.00 to 64.00 – 1900 Acres

Rs, 56.50 Cr.

26-02-05

24 months

M/s Avantika Sai Venkata (J.V.), Nellore

26

Investigation Preparation of H.Ps Designs, Drawings and excavation of HNSS main canal from Km (-) 64.000 to 77.00 including CM&CD Works and distributory system to feed an ayacut of 5100 Acres Khariff I.D.

Rs. 55.87 Crs.

07-03-05

24 months

M/s ALS-KVR, Dowlaiswaram

27 - do – Km 77.00 to 100.00 – 5100 Acres

Rs. 55.35 Crs.

25-02-05

24 months

M/s Sushee Hitech Constructin, Hyderabad.

28 - do – Km 100.00 to 114.00 – 29200 Acres

Rs. 82.89 Crs.

28-02-05

24 months

M/s G. Venkata Reddy & Co, Hyderabad.

29Investigation Preparation of H.Ps Designs, Drawings and formation of Pathikunda Reservoir including distributory system to feed an ayacut of 32200 Acres Khariff I.D.

Rs. 68.69 Croes

10-03-05

24 months

M/s RM Mohit & Bhoorathanam, Sec’bad

30 - do – Km 114.00 to 134.00

Rs. 39.08 Croes

23-02-05

24 months

M/s Engg Projects (I) Ltd, Hyd.

HANDRI NIVA SUJALA SRAVANTHI PROJECT

Page 6: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

PKG No.

DescriptionAgt. Value & Date

Agt. PeriodName of the contractor

31Investigation Preparation of H.Ps Designs, Drawings and formation of Pathikunda Reservoir including distributory system to feed an ayacut of 32200 Acres Khariff I.D. Km 134.00 to 135.00

Rs. 65.62Croes

27-02-05

24 months

M/s RMN – GVR, Hyd

32 - do – Km 155.00 to 176.00

Rs. 77.04 Crs.

23-02-05

24 months

M/s Back bone Projects, Hyd

33 - do – Km 176.00 to 192.00 – 20900 Acres

Rs. 58.32 Crs.

23-02-05

24 months

M/s Engg Projects (I) Ltd

34 - do – Km 192.00 to 210.00 – 17300 Acres

Rs. 62.825 Crs.

10-03-05

24 months

M/s Reddy Veeranna, Bangalore

35Investigation Preparation of H.Ps Designs, Drawings and formation of Jidipalli Reservoir & main canal from Km 210.00 to 216.00 including CM&CD Works.

Rs. 97.89 Crs..

16-03-05

24 months

M/s RMN – GVR, Hyd

36 - do – Peruru Branch canal Km 0.00 to Km 6.00 – 80600 Acres

Rs. 93.296 Crs.

10-05-05

24 months

M/s Om – Ray (J.V), New Delhi

TOTAL Rs. 918.171 Crs.

HANDRI NIVA SUJALA SRAVANTHI PROJECT

Page 7: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.23 / Cat – II

i. Excavation of main canal from Km (-)

3.420 to Km.20.000 including CM&CD

works.

ii. Distributory system to feed an ayacut of

4200 acres Kharif ID.

HANDRI NIVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : Back Bone

Project Ltd., Ahmedabad.

Agreement Amount : Rs. 47.00 Crs.

Agreement Date : 25-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007

Investigation : Total length of 23.42 Kms is completed.

Machinery : Deployed 14 Nos (Proclain 3, Driller 1, Tipper 8,

Dozer 1, Vibro Max 1)

Expenditure : Rs. 20.16 Crs. (incl. Mob. Adv. Rs. 4.70 Crs.) against

Rs. 47.00 Crs.

2004-05 : Rs. 2.35 Crs. (Mob. Adv.)

2005-06 : Rs. 17.81 Crs. (Inc. Mob. Adv. Rs. 2.35 Crs.)

Land acquisition : Required - 209 Ha; Requisitioned – 209 Ha;

Acquired – Nil;

Page 8: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.24 / Cat – II

i. Excavation of main canal from Km

20.00 to Km.42.00 including CM & CD

Works.

ii. Distributory system to feed an ayacut

of 2300 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : Sushee

Hitech Com. (P) Ltd.,

Agreement Amount : Rs. 57.78

Crs.

Agreement Date : 25-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007

Investigation : Total length of 22.00 Kms is completed.

Expenditure : Rs. 10.65 Crs. (Inc. Mob. Adv. Rs. 2.89 Crs.) against

Rs. 57.78 Crs.2

2004-05 : Rs. 2.89 Crs. (Mob. Adv.)

2005-06 : Rs. 7.76 Crs.

Land Acquisition : Required – 242 Ha; Requisitioned – 324 ac;

Acquired – Nil;

Page 9: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.25 / Cat – II

i. Excavation of main canal from Km 42.00 to Km.64.00 including CM & CD Works.

ii. Distributory system to feed an ayacut of 1900 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor: M/S Sri Avantika –Saivenkata (J.V)

Agreement Amount : Rs. 56.50 Crs.

Agreement Date : 7-3-2005

Period of Completion : 24 Months

Target date of completion : 3/2007

Investigation : Total length of 22.00 Kms is completed.

No. of Machinery : Deployed 68 Nos (Proclain 8, Tippers 50,

Vibromax 2, Dozers 2, Compressor 2, Water

Tankers 3

Expenditure : Rs. 19.09 Crs (incl. Mob. Adv. Rs 2.83 Crs.)

against Rs. 56.50 Crs

2004-05 : Rs. 2.83 Crs. (Mob. Adv.)

2005-06 : Rs. 16.26 Crs.

Land Acquisition : Required – 245 Ha; Requisitioned - 245 Ha ;

Bottle Necks : Work could not be taken up in full swing because

of standing crops

Page 10: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.26 / Cat – II

i. Excavation of main canal from Km 64.00 to

Km.77.00 including CM & CD Works.

ii. Distributory system to feed an ayacut of

5100 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECTName of the Contractor : M/s ALS-KVR

Agreement Amount : Rs. 55.88 Crs.

Agreement Date : 7-3-2005

Period of Completion : 24 Months

Target date of Completion : 3/2007

Investigation : Total Length of 13.00 Km is completed

Qty. of earth work done: 2.7 Lakh cum

Execution : Length 3.6 Km completed against 13.00 KM

Expenditure : Rs. 13.64 Crs. paid (Incl. Mob. Adv. Rs. 2.79 Crs.)

against Rs. 55.88 Crs

2004-05 : Rs. 2.79 Crs. (Mob. Adv.)

2005-06 : Rs. 10.85 Crs.

Land Acquisition : Required – 381 Ha. Requisitioned – 381 Ha. Acquired

– Nil;

Bottle Necks : Work could not be taken up in full swing because of

standing crops

Page 11: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.27 / Cat – II

i. Excavation of main canal from Km

77.00 to Km.100.00 CM & CD Work.

ii. Distributory system to feed an ayacut

of 5100 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s Shushee

Hitech Con (P) Ltd.,

Agreement Amount : Rs. 55.35 Crs.

Agreement Date : 25-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007

Investigation : Total length of 23.00 Km is completed

Qty of earth work done : 1.00 Lakh cum

Execution : Length KM 0.6 KM in progress against KM 2.3

Designs of CM&CD works : Not Programmed

Expenditure : Rs. 2.76 Crs (inc. mob. Adv. Rs. 2.76 Crs.)

against Rs. 55.35 Crs

2004-05 : Rs. 2.76 Crs. (Mob. Adv.)

Land Acquisition : Required – 219.29 Ha. Requisitioned ---

219.29 Ha

Bottle Necks : Work could not be taken up because of

standing corps

Page 12: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.28 / Cat – II

i. Excavation of Main canal from Km

100.00 to Km.114.00 including CM &

CD works

ii. Distributory system to feed an ayacut

of 29200 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor: G.Venkata Reddy

& Co.

Agreement Amount : Rs.82.90

Crs.

Agreement Date : 28-2-2005

Period of Completion : 24 Months

Target date of Completion: 2/2007 Investigation : Total length of 14 Kms is completed

Designs of CM&CD Works : Not Programmed during this Period

Machinery : Nil

Expenditure : Rs. 8.30 Crs. (including Mob. Adv. Rs. 8.30 Crs.)

against Rs. 82.90 Crs

2004-05 : Rs. 4.15 Crs. (Mob. Adv.)

2005-06 : Rs. 4.15 Crs. (Mob. Adv.)

Land Acquisition : Required – 189.4 Ha; Requisitioned – 189.40 Ac;

Acquired – Nil;

Bottle Necks : Work could not be taken up because of standing

crops

Page 13: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.29 / Cat – II

i. Formation of Pathikonda Reservoir

and distributory system to feed an

ayacut of 32200 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECTName of the Contractor : M/s R.M. Mohite & Co.,

Bhooratnam Construction Co.,

Pvt. Ltd (JV)

Agreement Amount : Rs.68.69 Crs.

Agreement Date : 10-3-2005

Period of Completion : 24 Months

Target date of Completion : 3/2007

Investigation : Total length of 4.00 Kms is completed and

distributory system completed

Design of CM&CD works : Not Programmed during this Period

Expenditure : Rs. 3.71 Crs. (Inc. Mobi. Adv. Rs. 3.43 Crs.)

against Rs. 68.69 Crs

2004-05 : Rs. 3.43 Crs. (Mob. Adv.)

2005-06 : Rs. 0.28 Crs.

Land Acquisition : Required – 629 Ha. Requisitioned –629 Ha.

Acquired – Nil;

Bottle Necks : Work could not be taken up because of

standing crops

Page 14: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.30 / Cat – II

i. Excavation of main canal from Km

114.00 to Km.134.00 CM & CD Works.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s Engineering

Projects (I) Ltd.,

Agreement Amount : Rs.39.08 Crs.

Agreement Date : 23-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007

Investigation : Total length of 20.00 Kms completed

Design of CM&CD works : Not Programmed during this Period

Machinery : Deployed 18 Nos (Proclain 2, Tippers 8, Dozers 2,

Rollers 2, Water Tankers 2, Compressors 2

Expenditure : Rs. 11.40 Crores (Inc. Mobi. Adv. Rs. 3.9 Crs.) LA

Rs.2.16 Ha against Rs. 39.08 Crs.

2004-05 : Rs. 1.95 Crs. (Mob. Adv.)

2005-06 : Rs. 9.45 Crs. (Inc Mob Adv. Rs. 1.95 Crs.)

Land Acquisition : Required 205.53 Ha. Requisitioned 205.53Ha.

Acquired – Nil;

Page 15: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.31 / Cat – II

i. Excavation of main canal from Km

134.00 to Km.155.00 including CM &

CD Works.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s

RMN – GVR (JV)

Agreement Amount : Rs.

65.62 Crs.

Agreement Date : 27-2-2005

Period of Completion : 24

Months

Target date of Completion : 2/2007

Investigation : Total length of 21.00 Kms is completed

Design of CM&CD works : Not Programmed during this Period

Expenditure : Rs. 13.34 Crs. (Incl. Mobi. Adv. Rs. 6.56 Crs.)

against Rs. 65.62 Crs.

* 2004-05 : Rs. 3.28 Crs. (Mob. Adv.)

* 2005-06 : Rs. 10.06 Crs. (Inc. Mob. Adv. Rs. 3.28 Crs.)

Land Acquisition : Required – 264.42 Ha. Requisition 264.42 Ha.

Acquired – Nil;

Page 16: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.32 / Cat – II

i. Excavation of main canal from Km

155.00 to Km.176.000 including

CM&CD Works

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s Back

Bone Projects Ltd.,

Agreement Amount : Rs. 77.04 Crs.

Agreement Date : 25-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007

Investigation : Total length of 21.00 Kms completed

Design (CM&CD works) : Not Programmed during this Period

Expenditure : Rs. 39.43 Crs (including Mobi. Advance Rs. 7.70 Crs.)

2004-05 : Rs. 3.85 Crs. (Mob. Adv.)

2005-06 : Rs. 35.58 Crs. (inc. Mob. Adv. Rs. 3.85 Crs)

Land Acquisition : Required – 255 Ha. Requisitioned 124 Ha. Acquired –

123.6 acres

Page 17: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.33 / Cat – II

i. Excavation of main canal from Km 176.00 to

Km.192.00 including CM& CD Works.

ii. Distributory system to feed an ayacut of

20,900 acres Khariff ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s Engineering

Project (I) Ltd.,

Agreement Amount : Rs. 58.32 Crs.

Agreement Date : 23-2-2005

Period of Completion : 24 Months

Target date of Completion : 2/2007 Investigation : Total length of 15.15 Kms is completed.

Design of CM&CD Works : Not Programmed during this Period.

No. Machinery : Deployed 14 Nos. (Excavator – 1, Dumpers-4, Tippers-4, Dozers-1, Compressor-2, Tractors-2)

Qty. of earth work done : 2,30,550 cum against 36,00,000 cum

Expenditure : Rs. 11.23 Crs (incl. Mobi. Advance Rs. 4.38 Crs.)

2004-05 : Rs. 2.92 Crs. (Mob. Adv.)

2005-06 : Rs. 8.31 Crs. (Inc. Mob. Adv. Rs. 1.46 Crs.)

Land Acquisition : Required – 199.5 Ha; Requisitioned – 199.50 Ha ;

Bottle Necks : Work could not be taken up in full swing because of standing crops.

Page 18: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.34 / Cat – II

i. Excavation of main canal from Km

192.00 to Km.210.00 including CM &

CD Works.

ii. Distributory system to feed an ayacut

of 4200 acres Kharif ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s Reddy Veeranna (Con) Pvt. Ltd.,

Agreement Amount : Rs. 62.83 Crs.

Agreement Date : 10-3-2005

Period of Completion : 24 Months

Target date of Completion : 3/2007

Investigation : Total length of 18.00 Kms is completed.

Design of CM&CD Works : Not Programmed during this Period.

No. of Machinery deployed : 12 (Excavators 4, Dozers 2, Dumpers and

trippers 5, Compressor-1)

Expenditure : Rs. 4.64 Crores (incl. Mobi. Advance Rs. 3.140 Crs)

against Rs. 62.83 Crs.

2004-05 : Rs. 3.14 Crs. (Mob. Adv.)

2005-06 : Rs. 1.5 Crs.

Land Acquisition : Required – 258 Ha; Requisitioned- 258 Ha;

Bottle Necks : Work could not be taken up because of standing

crops.

Page 19: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.35 / Cat – II

i. Excavation of main canal from Km

210.00 to Km.216.00, CM&CD Works.

ii. Formation of Jeedipalli Reservoir at

Km.216.300.

HANDRI NEEVA SUJALA SRAVANTHI PROJECT

Name of the Contractor : M/s RMN-

GVR (JV),

Agreement Amount : Rs. 97.89 Crs.

Agreement Date : 16-3-2005

Period of Completion : 24 Months

Target date of Completion : 3/2007 Investigation : Main Canal and Reservoirs are completed.

Execution : 2 Km against Km 14.475

Qty. of earth work done: 2.1 Lakh cum against 57,18,650 cum

Machinery : Deployed 5 Nos (Proclain 1, Tippers 3 , Dozer 1)

Expenditure : Rs. 25.12 Crs paid (Incl. Mob. Adv. Rs. 8.81 Crs.)

against Rs. 97.89 Crs.

2004-05 : Rs. 4.89 Crs. (Mob. Adv.)

2005-06 : Rs. 20.23 Crs. (Inc. Mob. Adv. Rs. 3.92 Crs.)

Land Acquisition : Required – 1166 Ha; Requisitioned – 441 Ha;

Page 20: HANDRI NIVA SUJALA SRAVANTHI (IRRIGATION SCHEME) (1.98 LAKH ACRES) SCHEMATIC DIAGRAM OF LIFT PROPOSAL PHASE- 1 ULTIMATE STAGE Utilisation – Ayacut 6,02,500

Package No.36 / Cat – II

i. Excavation of main canal (Perur Branch

Canal) from Km 0.00 to Km.6.00 including

CM&CD Works.

ii. Distributory system to feed an ayacut of

80,600 acres Khariff ID.

HANDRI NEEVA SUJALA SRAVANTHI PROJECTName of the Contractor : M/s OM-RAY

(JV),

Agreement Amount : Rs. 93.296 Crs.

Agreement Date : 10-5-2005

Period of Completion : 24 Months

Target date of Completion : 5/2007

Investigation : (a) Peruru Branch Canal of total length 6.00 Kms

completed.

(b) Distributory System for 80,600 acres is in

Progress.

Expenditure : Rs. 1.36 Crs. Mob. Advances paid – Nil against

93.296 Crs.

2005-06 : Rs. 0.01 Crs.

Land Acquisition : Required – 67.75 Ha; Requisitioned : 67.75 Ha

Bottle Necks : Work could not be taken up because of standing

crops