1Internship in Nestle Pakistan-SKP Factory
Supervisor: Miss Iqra Ashraf & Mr. Mohsin
Area: Engineering Utilities
Assistance: Plant Managers/Team Leaders of different Plants.Area: MRU&STD, D&J, Chilled Dairy, Water
Intern: Hafiz Muhammad Bilal (Mechatronics Engineer) from University of Engineering & Technology, Lahore
2 Safety Training:Safety is not a slogan, it’s a way of Life
Plant Safety requirement during visit. LOTO Procedure Danger Alarms Nestle guidelines for plants visit Introduction to 5S Introduction to PPE’s
3 Projects:
Single Line Diagram P&ID of Compressors Raw water pumps automation Boiler’s instruments calibration Online data receiving of flow meters
4 Project1:Single Line Diagram (SLD): Assigned proper tag to each breaker
Format of tag: Output of breaker-Transformer-Panel Building-Panel #.Lock # Re-numbering of panels of all Control Rooms Updated Excel Sheet Updated SLD on AutoCAD
Format on AutoCAD:
Made a detailed REPORT describing each step of project and learning outcomes.
Learnt about power distribution and made a report on it.
ACB or MCCBCurrent RatingMakeModelTag
5 Project2:Piping & Instrumentation Diagram (P&ID):
Updated P&ID of SABROE, ATLAS & GEA Compressors. Line tracing & proper tagging for identification. Updated Excel sheets of all pipes, instruments and valves etc. Made a detailed REPORT describing each step of project and learning
outcomes.
6 Project3:WWRO Pumps Control: Cable Sizing calculation Contact with Nestle vendor (Nafees Cables) and received Cable Charts. Suggested proper LT Room for supply considering cost optimization and
efficiency. Suggested proper room for VFD panel. Made a detailed REPORT describing each step of project and learning
outcomes.
7 Project4:Boilers Instruments Calibration: Learnt about calibration of instruments. Calibrated Boiler instruments i.e. Pressure transmitters, pressure gauges
& temperature transmitters etc. Made a detailed REPORT describing each step of project and learning
outcomes.
8 Project5:Online data receiving of Flow Meters: Inspected flow meters of Raw Water, Steam and Compressed Air by
tracing Profibus. Suggested place of new installed flow meters in Profibus. Differentiated between DP & PA Profibus. Checked Profibus termination. Updated excel sheet by including new installed flow meters. Made a detailed REPORT describing each step of project and learning
outcomes.
9 Utilities Area Visit:
Compressors SABROE Compressors ATLAS COPCO Compressors GEA Compressors
Prepare a detailed REPORT on the working of all compressors and made Process Flow Diagrams of each.
All Control Rooms (HT & LT) and learnt about control panels, circuit breakers and their technical terminologies.
Transformer Room Developed a Power Distribution Flow Diagram.
10 PLC:
Basic components of PLC Types of PLC PLC Programming Software's HMI Software's Studied some Ladder Logic codes on RS Logix500.
11 Plant Orientation: Visited all plants:
MRU&STD Water Dairy & Juice Tetra Hall Chilled Dairy PLE Hall
Developed Process Flow Diagrams of each plant. Made a detailed REPORT describing each process and Working
Principles of all machines.
12 MRU:
Milk Tankers
Analysis
Pumps (15 kW)
Duplex Filters Chillers
Raw Milk Silos
Pumps (5.5 kW)
Buffers Discharge Pump
Clarifier
Pump
Heating 90 sec Holding
Cooling
Thermized Milk Silos
13 STD:Cream
Separator
Cream
Buffer
Pump (7.5kW)
PHE (90°C)
Deodorizer
Deodorizer extraction
pump(75-80°C)
PHE(30-35°C)
Homogenizer
Scanma Mixer
6 Silos
Skim Milk
Pump
PHE
60 sec holding
Chilling
Silo (64ton)
Silo (100ton)
TMS
Buffer
Pump (5.5 kW)
14 Water Treatment Plant:Deep Well Cartridge Filter UV Sand Filtration
FDP Mix Proof Valves Cartridge Filter UV
RO Mix Proof Valves Permeate Tank Re-Mineralization
Balance Tank Ozonation Filling
15Juice Plant:
Chemical Addition
Mixer Mixer Tank
Bermatic Tank
Pulp (Frozen or
Septic)Concentrate
Pulp
Pushing up drums
through Hydraulic Catcher
HopperSimPulp Tank
Fistalic Pump
Bermatic Tank
Glucose Screw Conveyer
Sugar Tank (6
ton)
Magnet Filter
Cone Filter
Bermatic Tank
16 Bermatic Tank Filter Feeding
PumpBalance
Tank
Pre Heater1(55-60°C)
De-aerator(50-55°C)
Pre-Heater2(65°C)
22sec Holding
(98-101°C)
Pasteurizer Pre-Heater2 (Cooling)
Pre-Heater1(20-25°C)
Booster Pump
Acceptic Tank
Filling Machines
17 Tetra Hall:Peper Roll ASU ASSU H2O2 Bar
Squeezy RollerHeaterAseptic
ChamberTube
Formation
Bending of Packet
Filling Product in
Tube
Head Space
InjuctionJaw
System
Infeed Conveyer
Flaps Presser
Out feed ConveyerPLE Hall
18Chilled Dairy:
19
Questions & Answers