Habitat Management Plan Cherry Street Pump Station #7 & Force Main Upgrade City of Sumner, WA Prepared By: Widener & Associates 10108 32 nd Ave W Ste. D Everett, WA 98204 July 2015

Upload: others

Post on 05-Sep-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan

Cherry Street Pump Station #7 & Force Main Upgrade

City of Sumner, WA

Prepared By: Widener & Associates

10108 32nd Ave W Ste. D Everett, WA 98204

July 2015

Page 2: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

This page intentionally left blank for printing purposes.

Page 3: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Contents 1.0 Introduction ...................................................................................................................................... 5

2.0 Project Description ............................................................................................................................ 6

3.0 Existing Environmental Conditions ................................................................................................. 21

4.0 Species and Habitat Presence ......................................................................................................... 21

4.1 Puyallup River ............................................................................................................................... 21

4.2 Floodplain ...................................................................................................................................... 22

4.3 Wetlands ....................................................................................................................................... 22

5.0 Project Effects on Fish and Wildlife Habitat ................................................................................... 22

6.0 Minimization and Mitigation Measures .......................................................................................... 22

6.1 Minimization/Avoidance for Temporary Impacts ................................................................... 22

6.2 Mitigation for permanent impacts.......................................................................................... 23

6.3 Monitoring and Maintenance ................................................................................................. 23

6.4 Performance Standards and Contingency Plan....................................................................... 24

7.0 Local Management Recommendations .............................................................................................. 26

8.0 Conclusion ........................................................................................................................................... 26

9.0 References ........................................................................................................................................... 29

Figure 1: Vicinity Map ................................................................................................................................... 7

Figure 2: Project Area ................................................................................................................................... 9

Figure 3: Shoreline Impacts ........................................................................................................................ 13

Figure 4: Project Plans................................................................................................................................. 13

Figure 5: Mitigation Areas ........................................................................................................................... 27

Page 4: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

This page intentionally left blank for printing purposes.

Page 5: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

5 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

1.0 Introduction This habitat management plan has been prepared for the Cherry Street Pump Station #7 and Force Main

Upgrade project (herein referenced as the Cherry Street Pump Station project or the project) in

accordance with Sumner Municipal Code (SMC) 16.56.080. The Code requires a management plan for

any proposed development within 1,000 feet of fish and wildlife habitat areas. These fish and wildlife

habitat areas include1:

A. Areas with which federally or state-listed endangered, threatened, or sensitive species of fish,

wildlife, or plants have a primary association;

B. Areas with habitats and species of local importance, including the following:

1. Areas with which state-listed monitor or candidate species or federally listed candidate species

have a primary association, and which, if altered, may reduce the likelihood that the species will

maintain and reproduce over the long term;

2. Special habitat areas which may provide specific habitats which certain animals and plants

require such as breeding habitat, winter range, and movement corridors;

C. Naturally occurring ponds under 20 acres and their submerged aquatic beds that provide fish and

wildlife habitat;

D. Waters of the state, including all water bodies classified by the Washington State Department of

Natural Resources water typing classification system as detailed in WAC 222-16-031;

E. Lakes, ponds, streams, and rivers planted with game fish by a governmental or tribal entity;

F. State natural area preserves and natural resource conservation areas. (Ord. 2071 § 34, 2003: Ord.

1546 § 1 (part), 1992)

As the proposed project will occur within 1,000 feet of the Puyallup River, a water of the state, a habitat

management plan is required.

1 SMC 16.56.050 http://www.codepublishing.com/wa/sumner/

Page 6: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

6 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

2.0 Project Description The Cherry Street Pump Station project proposes to upgrade the pump station adjacent to and south of

SR410, at 70th St Ct E and directly across from Cherry Street. The existing structure’s subgrade dry well

will be abandoned. The wet well inlet/outlet will be reconfigured, and a new 12-foot diameter wet well

submersible pump station will be constructed. It will have a pumping capacity of 1,900 gallons per

minute. The force main leading to the waste water treatment plant located at the junction of the

Puyallup and White Rivers will be upgraded to a 10-inch diameter line (approximately 3,150 linear feet).

The force main will be installed approximately 3 – 8 feet below ground surface and will be directionally

bored where it crosses the BNSF tracks and E Main Avenue.

Though the project will be within the 200-foot shoreline jurisdiction of the Puyallup River, no in-water or

above-water work will be required for this project and all unimproved disturbed areas will be replanted

with native vegetation. Additional shoreline area will be enhanced as mitigation for a proposed gravel

maintenance access trail over a portion of the alignment (Sta. 14+20± to 29+00±). The force main will be

installed approximately 100 feet north of the river, at its closest point. This work will require the

removal of up to 30 deciduous trees (mostly cottonwoods). Native conifers will be planted to mitigate

for the removed trees. While work will occur within portions of the designated floodway and 100-year

floodplain of the Puyallup River, there will be no net fill within these areas. This project is located in

Sections 23, 25, and 26 of Township 20 North and Range 4 East (Figure 1). Refer to Figures 2, 3, and 4 for

details on the alignment, shoreline impacts, and project plans.

Page 7: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Figure 1. VicinityCherry St. Pump Station and Forcemain Upgrade

City of SumnerPierce County, WA

S 23/25/26, T 20N, R 04EJuly 29, 2015

Project Area

± 0 1,000 2,000500Feet

Page 8: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

8 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.

Page 9: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Cherry St

¬«410

E Main

Ave

Waste Water Treatment Plant

Puyallup River

White River

BNSF

± 0 250 500 750 1,000Feet

River ChannelPuyallup River OHW Urban Conservancy Shoreline (200 ft)FEMA FloodwayFEMA 100-Year FloodplainProject Area

Figure 2. Project AreaCherry St. Pump Station and Forcemain Upgrade

City of SumnerPierce County, WA

S 23/25/26, T 20N, R 04EJuly 29, 2015

Page 10: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

10 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.

Page 11: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Cherry St

¬«410

E Main

Ave Puyallup River

BNSF

Clearing LimitsPuyallup River OHW Urban Conservancy Shoreline (200 ft)River ChannelFEMA FloodwayFEMA 100-Year FloodplainTemporary Shoreline ImpactsPermanent Shoreline Impact

Figure 3. Shoreline ImpactsCherry St. Pump Station and Forcemain Upgrade

City of SumnerPierce County, WA

S 23/25/26, T 20N, R 04EJuly 28, 2015

± 0 500 1,000250Feet

Permanent Shoreline Impact: 23,700 sq. ft. (0.54 acre)Temporary Shoreline Impact: 26800 sq. ft. (0.62 acre)

Page 12: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

12 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.

Page 13: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L ENGINEER

TYL

ERJA

MES WHITEHO

USE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG I NEER

KELYST

AT

EOF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

D-1

X X

P14-10347_D-1EXISTING PUMP STATION

SITE AND DEMOLITION PLAN

1" = 5'-0"T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

NOTES:

1. SURVEY CONTROL NUMBERS & , SEE DWG G-4.2. THE LOCATION OF EXISTING UTILITIES SHOWN ARE APPROXIMATE; TAKEN FROM

UTILITY LOCATE MARKINGS AND/OR AVAILABLE RECORD INFORMATION. EXACTLOCATION AND DEPTH OF UTILITIES SHALL BE DETERMINED BY THE CONTRACTORPRIOR TO AND DURING CONSTRUCTION. THE CONTRACTOR SHALL BERESPONSIBLE FOR ALL DAMAGES CAUSED DUE TO FAILURE TO LOCATE ANDPRESERVE EXISTING UTILITIES.

3. DEMOLITION OF EXISTING PUMP STATION FACILITIES SHALL OCCUR ONLY AFTERTHE NEW PUMP STATION IS INSTALLED, TESTED, PLACED INTO OPERATION, ANDACCEPTED, UNLESS OTHERWISE APPROVED BY THE CITY.

4. SEE SPECIFICATION SECTION 02050 FOR ADDITIONAL DEMOLITION AND SALVAGEREQUIREMENTS.

5. SEE SPECIFICATION SECTION 01014 FOR CONSTRUCTION SEQUENCING ANDCONSTRAINTS.

6. PROTECT EXISTING UTILITIES, STRUCTURES, FACILITIES, TREES, ETC. UNLESSOTHERWISE INDICATED.

7. BACKFILL AND COMPACT WITH CSTC ALL VOIDS FROM DEMOLITION ACTIVITIESUNLESS OTHERWISE INDICATED, MATCH EXISTING GRADE.

8. MAINTAIN ACCESS TO EXISTING PUMP STATION AND SITE FACILITIES FOR CITYSTAFF AT ALL TIMES DURING CONSTRUCTION.

9. CONTRACTOR SHALL ESTABLISH LIMITS OF EXISTING ROW AS REQUIRED TOENSURE LIMITS OF CONSTRUCTION ARE WITHIN CITY PROPERTY LIMITS.

##

1

23

4

5

67

8

9

10

CONSTRUCTION NOTES:

DECOMMISSION AND REMOVE PUMP STATION MECHANICAL, ELECTRICAL, ANDMISCELLANEOUS EQUIPMENT FROM DRY WELL. REMOVE CONC PAD AT GRADEAND STEEL ACCESS SHAFT TO 3 FEET BELOW GRADE. DRILL MINIMUM TWENTY(20) 1-INCH DIAMETER HOLES COMPLETELY THROUGH FLOOR AND BASE SLAB OFSTRUCTURE, EVENLY SPACE. FILL STRUCTURE TO 3 FEET BELOW EX GRADE WITHAPPROXIMATE 15 CY OF DRAIN ROCK. PLACE SOIL STABILIZATION GEOTEXTILEAND BACKFILL AND COMPACT REMAINING WITH CSTC, MATCH EXISTING GRADE.REMOVE STANDBY GENERATOR AND CONCRETE EQUIPMENT PAD.REMOVE 7 FEET TALL CHAIN LINK FENCE, GATE, AND CONCRETE POST FOOTINGS.PROVIDE TEMPORARY FENCING WITH ACCESS TO SECURE STANDBY GENERATORIF FENCING IS REMOVED DURING CONSTRUCTION OF NEW PUMP STATIONFACILITIES.PLUG AND ABANDON PIPE ENTERING AND EXITING ABANDONED STRUCTURE WITHCONCRETE.REMOVE BURIED AND EXPOSED ELECT CONDUIT AND WIRE AND CONCRETE IFENCASED.REMOVE PUMP STATION POWER/CONTROL PANEL AND SUPPORT STRUCTURE.TEMPORARILY PLUG 8-INCH SEWER AND BYPASS SEWAGE FROM MANHOLELOCATED APPROXIMATE 80 FEET UPSTREAM TO NEWLY CONSTRUCTED PUMPSTATION WET WELL PER SPECIFICATION SECTION 01015.REMOVE MISCELLANEOUS INSTRUMENTS, PIPING AND SUPPORTS. PATCH WALLPENETRATIONS WITH GROUT. SEE CIVIL DRAWINGS FOR CONVERSION TO FLOWTHRU MANHOLE.REMOVE CONDUIT AND WIRE AND CONCRETE IF ENCASED. SEE ELECTRICALDRAWINGS FOR POWER RE-ROUTING.POTHOLE AND VERIFY DEPTH AND LOCATION OF EXISTING PIPE/STRUCTURE ANDNOTIFY THE ENGINEER OF ANY CONFLICTS PRIOR TO CONSTRUCTION.VERIFY INVERT ELEVATION OF EXISTING 8" SEWER PRIOR TO CONSTRUCTION OFNEW PUMP STATION FACILITIES, NOTIFY ENGINEER OF ANY DISCREPANCIES. SEEDETAIL 1/C-4 FOR REFERENCE.

11

EX 4"CONC S

ABANDONEX 8" AC FM

EX 30"CONC S

EX 8" AC W

EX 1" PVC ELECTCONDUIT

EX BONNEY LAKE FLOWMETERING FACILITY, BELOWGRADE CONC VAULT

EX 1 1/2" PVCELECT CONDUIT

EX BONNEY LAKE FLOWMONITORING FACILITY BLDG

EX 2" PVC ELECTCONDUIT W/ 5/8"SAMPLE TUBEINSIDE

EX PERMANENTEASEMENT FORBONNEY LAKESEWER TRUNK

EX STANDBYGENERATOR

EX MHCOVER

EX 30"CONC S

10

9

10

10

10

5EXPOWERPOLE

2

EX GRASS AREA

EX FENCE/GATE 3

EX 1" ELECTCONDUIT

SILTATIONFENCE PER CITYSTD DETAILSD5-9, TYP

5 EX ELECTCONDUIT

8 EX CONCWET WELL

1

EX ABOVEGROUNDACCESSHATCH

1EX STEEL DRYPIT PUMP STATION 4

TYP

EXPOWERPOLE

6 EX POWER/CONTROL PANEL

7 EX 8" S

11

Page 14: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L ENGINEER

TYLE

RJA

MES WHITEHOU

SE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG INEER

KELYST

AT

EOF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

MA

TCHLIN

ESTA

9+00- SEE

BELOW

D-2

X X

P14-10347_C-7-8-9FORCE MAIN

DEMOLITION AND CLEARING PLANSTA 1+00 TO 22+00

Horiz: 1" = 50'-0"Vert: 1" = 5'-0"

T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

NOTES:

1. SURVEY CONTROL NUMBERS & , SEE DWG G-4.2. THE LOCATION OF EXISTING UTILITIES SHOWN ARE APPROXIMATE; TAKEN FROM UTILITY LOCATE

MARKINGS AND/OR AVAILABLE RECORD INFORMATION. EXACT LOCATION AND DEPTH OF UTILITIESSHALL BE DETERMINED BY THE CONTRACTOR PRIOR TO AND DURING CONSTRUCTION. THECONTRACTOR SHALL BE RESPONSIBLE FOR ALL DAMAGES CAUSED DUE TO FAILURE TO LOCATEAND PRESERVE EXISTING UTILITIES.

3. SEE SPECIFICATION SECTION 02050 FOR ADDITIONAL DEMOLITION AND SALVAGE REQUIREMENTS.4. SEE SPECIFICATION SECTION 01014 FOR CONSTRUCTION SEQUENCING AND CONSTRAINTS.5. PROTECT EXISTING UTILITIES, STRUCTURES, FACILITIES, TREES, ETC. UNLESS OTHERWISE

INDICATED.6. MAINTAIN ACCESS TO SUMNER WWTP AND STORM DRAINAGE FACILITIES FOR CITY STAFF AT ALL

TIMES DURING CONSTRUCTION.7. CONTRACTOR SHALL ESTABLISH LIMITS OF EX ROW AS REQUIRED TO ENSURE LIMITS OF

CONSTRUCTION ARE WITHIN CITY PROPERTY LIMITS.

MA

TCH

LIN

EST

A9+

00- S

EEA

BO

VE MA

TCH

LINE

STA22+00

- SEED

WG

D-3

##

1

2

3

4

5

CONSTRUCTION NOTES:

REMOVE 6 FOOT CHAIN LINK BARBWIRE FENCE AND REPLACE WITH TEMPORARY CHAIN LINKBARBWIRE GATE TO BE USED DURING CONSTRUCTION. LOCK GATE WHEN NOT IN USE. REPLACEFENCE TO MATCH EXISTING AT COMPLETION OF CONSTRUCTION.

CONTRACTOR SHALL ESTABLISH AND MAINTAIN LIMITS OF CONSTRUCTION BY INSTALLINGSILTATION FENCE PER CITY STANDARD DETAIL SD5-9. ALL WORK SHALL BE PERFORMED WITHINTHESE LIMITS. SILTATION FENCE SHALL BE INSTALLED PRIOR TO ANY WORK WITHIN THE LIMITSAND REMOVED ONLY DURING FINAL RESTORATION OF THE AREA. THE ENTIRE AREA WITHIN THEESTABLISHED LIMITS BY THE CONTRACTOR SHALL BE RESTORED AS NOTED ON THE CIVILDRAWINGS. ANY WORK, EQUIPMENT ACCESS, DISRUPTION, ETC. NECESSARY OUTSIDE THEMAXIMUM NOTED LIMITS OF CONSTRUCTION SHALL BE APPROVED BY THE CITY. THECONTRACTOR SHALL RESTORE DISTURBED AREAS OUTSIDE THE LIMITS OF CONSTRUCTION TOMATCH EXISTING CONDITIONS AND WILL NOT RECEIVE ADDITIONAL COMPENSATION FORRESTORATION OF THESE AREAS.

THE AREA WITHIN THE CONSTRUCTION LIMITS BETWEEN APPROXIMATE STA 14+15 AND 27+50SHALL BE CLEARED, GRUBBED, CUT, FILLED, GRADED AND SHAPED TO THE SURFACE PROFILESHOWN ON THE CIVIL DRAWINGS.

INSTALL TEMPORARY CONSTRUCTION ACCESS PER CITY STANDARD DETAIL M-8.1/2 STARTING ATEDGE OF ROW AND EXTENDING ONTO CITY PROPERTY.

TERMINATE SILTATION FENCE AT EDGE OF GRAVEL ROAD.

1+002+00

3+00

4+00

5+00

6+00

7+008+00

9+00

EX CITY OFSUMNER WWTP

CONTRACTOR STAGING AREA,COORDINATE LIMITS WITH CITY

CONSTRUCTION C/L,TYP

1

2

CONSTRUCTIONACCESS THRUSUMNERWWTP, COORDROUTE W/CITY

APPROX LIMITS OFCONSTRUCTION,25' MAX, TYP

2

1

2

10"±TYP

15"±TYP

9+0010+00 11+00

12+0013+00

14+0015+00

16+00

17+00

18+00 19+0020+00 21+00

22+00

EM

AIN

AVE

BNSF

WSDOTSR 410

100'-0"3

4

5

PROTECT EX STORMDRAINAGE FACILITIES

REMOVE TREE, TYP

EM

AIN

AVE

BNSF

WSDOTSR 410CONSTRUCTIONACCESS FROM SR 410

TYP

TYP

58

9

101

3

3

4

EX 30" CONC S

EX 42" CPP SDAPPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEAR FLOODELEVATION

Alicia
Text Box
4 trees removed (maple, cottonwoods 12" - 28")
Page 15: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L ENGINEER

TYL

ERJA

MES WHITEHO

USE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG INEER

KELYST

AT

E OF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

D-3

X X

P14-10347_D-2-3FORCE MAIN

DEMOLITION AND CLEARING PLANSTA 22+00 TO 32+50±

Horiz: 1" = 50'-0"Vert: 1" = 5'-0"

T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

MA

TCHLIN

ESTA

22+00- SEE

DWG

D-2

NOTES:

1. SURVEY CONTROL NUMBERS & , SEE DRAWING G-4.2. THE LOCATION OF EXISTING UTILITIES SHOWN ARE APPROXIMATE; TAKEN FROM UTILITY LOCATE

MARKINGS AND/OR AVAILABLE RECORD INFORMATION. EXACT LOCATION AND DEPTH OF UTILITIESSHALL BE DETERMINED BY THE CONTRACTOR PRIOR TO AND DURING CONSTRUCTION. THECONTRACTOR SHALL BE RESPONSIBLE FOR ALL DAMAGES CAUSED DUE TO FAILURE TO LOCATEAND PRESERVE EXISTING UTILITIES.

3. SEE SPECIFICATION SECTION 02050 FOR ADDITIONAL DEMOLITION AND SALVAGE REQUIREMENTS.4. SEE SPECIFICATION SECTION 01014 FOR CONSTRUCTION SEQUENCING AND CONSTRAINTS.5. PROTECT EXISTING UTILITIES, STRUCTURES, FACILITIES, TREES, ETC. UNLESS OTHERWISE

INDICATED.6. MAINTAIN ACCESS TO EXISTING PUMP STATION AND SITE FACILITIES FOR CITY STAFF AT ALL TIMES

DURING CONSTRUCTION.7. CONTRACTOR SHALL ESTABLISH LIMITS OF EX ROW AS REQUIRED TO ENSURE LIMITS OF

CONSTRUCTION ARE WITHIN CITY PROPERTY LIMITS.

CONSTRUCTION NOTES:

##

1

2

3

CONTRACTOR SHALL ESTABLISH AND MAINTAIN LIMITS OF CONSTRUCTION BY INSTALLING SILTATIONFENCE PER CITY STANDARD DETAIL SD5-9. ALL WORK SHALL BE PERFORMED WITHIN THESE LIMITS.SILTATION FENCE SHALL BE INSTALLED PRIOR TO ANY WORK WITHIN THE LIMITS AND REMOVED ONLYDURING FINAL RESTORATION OF THE AREA. THE ENTIRE AREA WITHIN THE ESTABLISHED LIMITS BY THECONTRACTOR SHALL BE RESTORED AS NOTED ON THE CIVIL DRAWINGS. ANY WORK, EQUIPMENTACCESS, DISRUPTION, ETC. NECESSARY OUTSIDE THE MAXIMUM NOTED LIMITS OF CONSTRUCTIONSHALL BE APPROVED BY THE CITY. THE CONTRACTOR SHALL RESTORE DISTURBED AREAS OUTSIDETHE LIMITS OF CONSTRUCTION TO MATCH EXISTING CONDITIONS AND WILL NOT RECEIVE ADDITIONALCOMPENSATION FOR RESTORATION OF THESE AREAS.THE AREA WITHIN THE CONSTRUCTION LIMITS BETWEEN APPROXIMATE STA 14+15 AND 27+50 SHALL BECLEARED, GRUBBED, CUT, FILLED, GRADED AND SHAPED TO THE SURFACE PROFILE SHOWN ON THECIVIL DRAWINGS.INSTALL TEMPORARY CONSTRUCTION ACCESS PER CITY STD DETAIL M-8.1/2 STARTING AT EDGE OFROW AND EXTENDING ONTO CITY PROPERTY.

22+00

23+0024+00

25+0026+00

27+0028+00

29+0030+00

31+0032+00 33+00

SEE DWG D-1

SR 410WSDOT

10', TYP

EX PERMANENTEASEMENT FORSTORM DRAINAPPROX LOCATION

6

7

REMOVE TREE, TYP

SR 410WSDOT CONSTRUCTION

ACCESS FROMSR 410APPROX LIMITS OF

CONSTRUCTION,25' MAX, TYP

TYP

7

6

42

1

3

5

15'±TYP

10'±TYP

EX SD

EX 30"CONC S

CONSTRUCTIONC/L, TYP

APPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEARFLOODELEVATION

Alicia
Text Box
25 cottonwoods removed 12" - 30"
Page 16: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L ENGINEER

TYL

ERJA

MES WHITEHO

USE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG INEER

KELYST

AT

E OF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

C-1

X X

P14-10347_PPPUMP STATION

SITE PLAN

1" = 5'-0"T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

NOTES:

1. SURVEY CONTROL NUMBERS & , SEE DRAWING G-4.2. EXISTING LIFT STATION FACILITIES ARE SHOWN AS THEY SHALL REMAIN IN

SERVICE THROUGHOUT CONSTRUCTION. SEE DEMO DWGS FORDECOMMISSIONING, DEMOLITION AND ABANDONING OF EXISTING LIFTSTATION FACILITIES.

3. SEE SPEC SECTION 01014 FOR CONSTRUCTION SEQUENCING ANDCONSTRAINTS.

4. PIPE TRENCH SECTION PER DETAIL 1/C-11.

COORDINATE TABLE PT NORTHING EASTING DESCRIPTION

1 683440.64 1207120.71 CENTER, WET WELL2 683432.99 1207114.24 SW CORNER, WET WELL3 683448.30 1207127.17 NE CORNER, WET WELL4 683453.15 1207113.30 SW CORNER, VALVE VAULT5 683460.86 1207125.36 NE CORNER, VALVE VAULT6 683468.87 1207113.31 SW CORNER, FLOWMETER VAULT7 683476.44 1207119.70 NE CORNER, FLOWMETER VAULT8 683453.64 1207104.77 SW CORNER, GEN EQPT PAD9 683440.27 1207100.88 NE CORNER, GEN EQPT PAD

#

##

CONSTRUCTION NOTES:

INSTALL WATER SERVICE CONNECTION PER CITY STANDARD DETAILW3-1. METER BOX AND LID SHALL BE TRAFFIC BEARING. FINALLOCATION AS DIRECTED BY CITY IN FIELD.INSTALL RPBA PER DETAIL W3-8.1. PROTECTIVE COVERING SHALLBE A HEATED, INSULATED, FLIP TOP, LOCKABLE FIBERGLASSENCLOSURE, 120V, SINGLE PHASE, HOT BOX, OR APPROVED EQUAL.ENCLOSURE SHALL BE SIZED PER RPBA. INSTALL ON CONC PAD,SIZE AS RECOMMENDED BY ENCLOSURE MFR. PROVIDE SCH 80 PVCSLEEVES FOR PIPE THROUGH CONC PAD. FINAL LOCATION ASDIRECTED BY CITY IN FIELD.AT COMPLETION OF CONSTRUCTION, RESTORE ACCESS ROAD WITH3 INCHES COMPACTED CSTC TO MATCH EXISTING GRADE. CUT,REMOVE AND DISPOSE OF EXISTING GRAVEL/BASE MATERIAL ASREQUIRED.AT COMPLETION OF CONSTRUCTION, ALL DISTURBED GRASS AREASSHALL BE REMOVED TO THE SATISFACTION OF THE CITY, REPLACEDWITH 4 INCHES TOPSOIL AND HYDROSEEDED. FINISHED GRADESHALL MATCH EXISTING.VERIFY INVERT ELEVATION OF EXISTING 8" SEWER PRIOR TOCONSTRUCTION OF NEW PUMP STATION FACILITIES, NOTIFYENGINEER OF ANY DISCREPANCIES. SEE DETAIL 1/C-4 FORREFERENCE.

1

2

3

4

5

8" SDI

8" FMDI

EX 4"CONC S

8" S

TYP

14" SDIEX 30" CONC S

EX 8" AC W

EX 1" PVCELECTCONDUIT

EX BONNEY LAKE FLOWMETERING FACILITY,BELOW GRADE CONCVAULT

EX 1 1/2" PVCELECT CONDUIT

EX BONNEY LAKE FLOWMONITORING FACILITY BLDGEX 2" PVC

ELECT CONDUITW/ 5/8" SAMPLETUBE INSIDE

VALVE VAULT PLAN,SEE DETAIL 1/C-3

WET WELL PLAN,SEE DETAIL 1/C-2

EX MHCOVEREX CONC

WET WELL

EX STEEL DRY PITPUMP STATION

MAIN POWER ANDCONTROL PANEL,SEE ELECT DWGS

POWER/CONTROL TERMINALBOXES, SEE ELECT DWGS

STANDBY GENERATOR,SEE ELECT DWGS

EX 30"CONC S

CONVERT TO FLOWTHRU MANHOLE,SEE DETAIL 1/C-4

10" SDI

EXPOWERPOLE

STANDBY GENERATORFENCED ENCLOSURE,SEE DETAIL 1/C-55' x 13' GENERATOR EQPTPAD, SEE DETAIL 4/C-4

WET WELL VENT,SEE DETAIL 2/C-4

4" VPVC

EXPOWERPOLE

TYP

1" NPWPE

3" DCISP, TYP

X

X

X

XX

X

X

X

X

X X

X

X

X

X

X

FREEZELESSYARD HYDRANT,SEE DETAIL 3/C-4

1" WPE

PIPE CROSSING,SEE DETAIL 1/C-3

1

2

3

4

56

732

4

1

5

EX PERMANENTEASEMENT FORBONNEY LAKESEWER TRUNK

8" AC FM

DI, TYP

9

8

EX STANDBY GENERATORFENCED ENCLOSURE, EXGENERATOR NOT SHOWNFOR CLARITY

EX POWER/CONTROL PANEL

EX 8" S

4' MIN

APPROXIMATE100 YEAR FLOODELEVATION

16'-0"

TYP4

HATCH SWING DIRECTION, TYP

5

3" VPVC

WET WELL VENT, SEE DETAIL 2/C-4

FLOWMETERVAULT PLAN,SEE DETAIL1/C-3

ELECTRICAL EQUIPMENT FENCEDENCLOSURE, SEE DETAIL 1/C-5

4'-0"

Page 17: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L ENGINEER

TYL

ERJA

MES WHITEHO

USE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG INEER

KELYST

AT

E OF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

MA

TCHLIN

ESTA

9+00- SEE

DWG

C-8

MA

TCH

LIN

EST

A9+

00-S

EED

WG

C-8

C-7

X X

P14-10347_C-7-8-9FORCE MAIN

PLAN AND PROFILESTA 1+00 TO 9+00

Horiz: 1" = 50'-0"Vert: 1" = 5'-0"

T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

NOTES:

1. SURVEY CONTROL NUMBERS & , SEE DWG G-4.

2. LIMIT BEND RADIUS OF HDPE FORCE MAIN TO TWICE MFRSALLOWABLE MINIMUM BEND RADIUS.

##

CONSTRUCTION NOTES:

1 INSTALL FORCE MAIN WITH GENERAL SLOPE AS SHOWNWITHOUT INTERMEDIATE SAGS OR HIGH POINTS, EXCEPTWHERE IDENTIFIED/APPROVED BY THE ENGINEER.

CONNECT TO EXISTING 10" DI FM WITH HDPE FLANGEADAPTER WITH BACKUP RING AND RFCA.

21+00

2+00

3+00

4+00

5+00

6+00

7+008+00

9+00

10" FM

CONNECT TOEX 10" DI FMSTA 1+00

HDPE

EX 10" DI FMBY OTHERS

EX CITY OFSUMNER WWTP

2

1

APPROX LIMITS OFCONSTRUCTION, TYP

2

1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+0

30

35

40

45

50

55

60

65

70

30

35

40

45

50

55

60

65

70

EX / FINISHEDGRADE AT C/LFORCE MAIN

HDPE10" FM

3'-6" MIN,TYP

EX 10" DI FMBY OTHERS

HDPE

1 SLOPE

FORCE MAIN RESTORATIONSTA 1+00 TO 5+50± PER DETAIL 2/C-11

FORCE MAIN RESTORATIONSTA 5+50± TO 10+60± PER DETAIL 3/C-11

TRENCH SECTION PER DETAIL 1/C-11

2

Page 18: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L EN GINEER

TYL

ERJA

MES WHITEHOU

SE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG I NEER

KELYST

ATEOF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

MA

TCH

LIN

EST

A9+

00- S

EED

WG

C-7

MA

TCH

LIN

EST

A9+

00-S

EED

WG

C-7

C-8

X X

P14-10347_C-7-8-9FORCE MAIN

PLAN AND PROFILESTA 9+00 TO 22+00

Horiz: 1" = 50'-0"Vert: 1" = 5'-0"

T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

NOTES:

1. SURVEY CONTROL NUMBERS & ,SEE DWG G-4.

2. LIMIT BEND RADIUS OF HDPE FORCE MAINTO TWICE MFRS ALLOWABLE MINIMUMBEND RADIUS.

MA

TCH

LIN

EST

A22

+00

-SEE

DW

GC

-9

MA

TCH

LIN

EST

A22

+00

-SEE

DW

GC

-9

CONSTRUCTION NOTES:

1 GRAPHICAL PRESENTATION SHOWN FORILLUSTRATION PURPOSES ONLY. ACTUALLOCATION AND SIZE TO BE DETERMINEDBY CONTRACTOR.

INSTALL FORCE MAIN WITH GENERALSLOPE AS SHOWN WITHOUTINTERMEDIATE SAGS OR HIGH POINTS,EXCEPT WHERE IDENTIFIED/APPROVEDBY THE ENGINEER.

FINAL LOCATION OF MH COVER ASDIRECTED BY THE CITY IN THE FIELD.

##

2

3

00 10+00 11+00 12+00 13+00 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+

30

35

40

45

50

55

60

65

70

30

35

40

45

50

55

60

65

70

EX GRADE ATC/L FORCE MAIN

EXG

EX12

"CON

CSD

IE61

.21±

EXW,

DEPT

HUN

KNOW

NEX

12"C

ONC

SDIE

61.48

±

EX RRTRACKS (2)

EXFO

DEPT

HUN

KNOW

NEX

GUY

WIRE

S(4)

EX42

"CPP

SDCU

LVER

TIE

37.7±

24" DIASTEELCASING

HDPE10" FM

BNSF

ROW

BNSF

ROW

HDPE

3'-6"MIN,TYP1'-0" CLR

3'-6"± TOTOP OFCASING

RECE

IVING

PIT

1

JACK

ING

PIT

1

EX / FINISHEDGRADE AT C/LFORCE MAIN

CASI

NGVE

NTPE

RDE

TAIL

PER

2/C-10

,TY

PEAE

ND

SEE DETAIL 3/C-10,TYP EA END

MATCH EXGRADE

2

APPROX FINISHEDGRADE AT C/LFORCE MAIN

MATCHEXGRADE

MATCHEXGRADE

2"SE

WAGE

CAV

ASSE

MBLY

SLOPE

FORCE MAIN RESTORATIONSTA 14+20± TO 27+50± PER DETAIL 4/C-11

TRENCH SECTION PER DETAIL 1/C-11

365± LF JACK AND BORESEE SPEC SECTION 02500

TRENCH SECTIONPER DETAIL 1/C-11

FORCE MAIN RESTORATIONSTA 5+50± TO 10+60±

PER DETAIL 3/C-11

4"BL

OW-O

FFAS

SEMB

LY

SLOPE TOBLOWOFF

9+0010+00 11+00

12+0013+00

14+0015+00

16+00

17+00

18+00 19+0020+00 21+00

22+00

EM

AIN

AVE

BNSF

10" FM

10" FMHDPE

HDPE

WSDOTSR 410

RECEIVING PIT1100'-0"

15'-0

JACKING PIT 1

5

4

3

APPROX LIMITS OFCONSTRUCTION, TYP

3

110

9 8APPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEARFLOODELEVATION

2" SEWAGE CAVASSEMBLY PERDETAIL 1/C-10STA 20+24, 10' RT

EX 30" CONC S

EX 42"CPP SD

4" BLOW-OFFASSEMBLY ATLOW PT PERDETAIL 4/C-10STA 20+92±, 10' RT

3

3

Page 19: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Scale:

One Inch at Full Scale

No. Revision Date By App'd

Drawn:

Approved:

Checked:

Designed:

Scale AccordinglyIf Not One Inch

Drawing:

Sheet:

File:

Date:

of

January 2015COPYRIGHT © 2015 BHC CONSULTANTS, LLC. ALL RIGHTS RESERVED

CHERRY STREET PUMP STATION #7 AND FORCE MAIN UPGRADE

X

1-800-424-5555UNDERGROUND SERVICE

Call 48 HoursBefore You Dig

City of SumnerPublic Works Department1104 Maple Street, Suite 260Sumner, WA 98390253-299-5700 FAX 253-299-5539

49545

STATE OF WASHINGTON

R

E G I S T E R E DPROFESSION A L EN GINEER

TYL

ERJA

MES WHITEHOU

SE

37386R

E G I S T E R E D

PROFE S S I ONAL ENG I NEER

KELYST

ATEOF WASHINGTON SE

.

H

EHP

TSIR

WR

CTO

BHC Consultants, LLC950 Pacific Avenue, Suite 710Tacoma, Washington 98402253.344.5084253.244.7165 (fax)www.bhcconsultants.com

MA

TCH

LIN

EST

A22

+00

-SEE

DW

GC

-8

C-9

X X

P14-10347_C-7-8-9FORCE MAIN

PLAN AND PROFILESTA 22+00 TO 32+50±

Horiz: 1" = 50'-0"Vert: 1" = 5'-0"

T. Whitehouse, P.E.

P. Simon

A. Schuyler, P.E.

MA

TCHLIN

ESTA

22+00- SEE

DWG

C-8

NOTES:

1. SURVEY CONTROL NUMBERS & ,SEE DWG G-4.

2. LIMIT BEND RADIUS OF HDPE FORCE MAIN TOTWICE MFRS ALLOWABLE MINIMUM BENDRADIUS.

##

CONSTRUCTION NOTES:

1 INSTALL FORCE MAIN WITH GENERALSLOPE AS SHOWN WITHOUTINTERMEDIATE SAGS OR HIGH POINTS,EXCEPT WHERE IDENTIFIED/APPROVEDBY THE ENGINEER.

+00 23+00 24+00 25+00 26+00 27+00 28+00 29+00 30+00 31+00 32+00 33+00

30

35

40

45

50

55

60

65

70

30

35

40

45

50

55

60

65

70

EX GRADE ATC/L FORCE MAIN

EX30

"CON

CSS

IE46

.2±

HDPE10" FM

SEE DWGS C-1AND C-3FOR CONT

HDPE

3'-6"MIN,TYP

1'-6" MIN

EXSD

,SIZE

AND

DEPT

HUN

KNOW

N

MATCHEXGRADE

APPROX FINISHEDGRADE AT C/LFORCE MAIN

MATCHEXGRADE

1SLOPE

FORCE MAIN RESTORATIONSTA 14+20± TO 27+50± PER DETAIL 4/C-11

SEE DWG C-1FOR RESTORATION

REQUIREMENTS

FORCE MAIN RESTORATIONSTA 27+50± TO 32+50± PER DETAIL 3/C-11

TRENCH SECTION PER DETAIL 1/C-11

22+00

23+0024+00

25+0026+00

27+0028+00

29+0030+00

31+0032+00 33+00

SEE DWG C-1

SR 410WSDOT

10" FMHDPE

10', TYP10', TYP

EX PERMANENTEASEMENT FORSTORM DRAINAPPROX LOCATION

6

7PIGGING VAULTPLAN, SEEDETAIL 2/C-3

APPROX LIMITS OFCONSTRUCTION, TYP

7

6

4

5

APPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEARFLOODELEVATION

APPROXIMATE100 YEARFLOODELEVATION

EX SD

EX 30" CONC S

Page 20: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

20 Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.

Page 21: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 21

Cherry Street Pump Station and Force Main Upgrade

3.0 Existing Environmental ConditionsThe project is located on the north side of the Puyallup River, near approximately river mile (RM) 10.5.

The project alignment is located between the river and SR410. The river runs northwestward along the

length of the project area. Surrounding areas are zoned as low density residential (8.5 and 12) according

to the City of Sumner zoning map.

The pipeline alignment is situated at the top of the bank of the Puyallup River. Soils in the area consist of

Pilchuck fine sand and Puyallup fine sandy loam, according to the Natural Resources Conservation

Service Web Soil Survey. The geotechnical survey conducted for this project also identified some deeper

coarse alluvium, non-fibrous peat, and silt.

The river at this location is buffered by an approximately 150-foot buffer of deciduous trees (primarily

alders, cottonwoods, and willows).

4.0 Species and Habitat Presence Habitat within 1,000 feet of the project area includes the Puyallup River. There are no other waterbodies (including wetlands) in the immediate vicinity.

4.1 Puyallup River The Puyallup River is within WRIA 10 and drains an area of approximately 1,065 square miles. It

originates from the Klapatche area and the Puyallup glacier on the southwest slopes of Mt. Rainier

(Kerwin 1999). The river adjacent to the project area flows in a northwesterly direction outletting into

Commencement Bay approximately 10.5 miles from the project area. Small segments of the Puyallup

River are listed on the Department of Ecology’s (DOE) List of Impaired Waterbodies as a Category 5

Water for mercury and bacteria (DOE 2012). The segment in the project vicinity is not listed. The

Puyallup River Watershed has a Total Maximum Daily Load (TMDL) for fecal coliform.

Significant human alteration of the Puyallup River and surrounding habitat began in the late 1800’s with

major dredging activities of the lower Puyallup River. There was significant loss of estuarine habitat and

function in Commencement Bay. In 1906, a major flood event caused a log jam on the White River,

diverting it into the Puyallup River basin. In the years following, major channel realignment, bank

stabilization, and diking projects were constructed in the lower Puyallup and by 1917, the Puyallup River

relocation project was complete (Kerwin 1999). Because of flood control efforts, habitat elements such

as large woody debris (LWD), habitat variety, refugia, and off channel habitat are virtually non-existent

in the lower Puyallup River.

A search of the Washington State Department of Fish and Wildlife (WDFW) Priority Habitat and Species

(PHS) and SalmonScape databases was conducted to identify the presence of habitats and species at the

site. Salmonid species documented to utilize the Puyallup River in the project vicinity include: Chinook,

Coho, Chum, and Pink salmon as well as Bull trout and Steelhead trout (WDFW 2014a, b). Of these

species, Chinook salmon, Bull trout and Steelhead trout are listed under the Endangered Species Act.

There no priority terrestrial habitats in or near the project.

Page 22: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 22

Cherry Street Pump Station and Force Main Upgrade

4.2 Floodplain The proposed project will be in portions of the floodway and 100-year floodplain of the Puyallup River as

mapped by FEMA and the City of Sumner. As the project will upgrade existing facilities, it will not

increase flood elevations compared to existing conditions. There will be no net fill in the floodway or

floodplain as a result of this project.

4.3 Wetlands A search of the National Wetland Inventory and City maps was conducted. No wetlands were identified within or near project limits. The project is located at the top of a steep bank leading down to the river and there are no conditions for wetland formation.

5.0 Project Effects on Fish and Wildlife Habitat The proposed project will not require in-water work. All work will occur at least 100 feet landward of the

OHWM of the Puyallup River. Therefore, little to no impacts to aquatic habitat are anticipated.

As the project will involve ground disturbing work, there is the potential of erosion and sedimentation to

occur. Silt fencing will be installed to prevent sediment from sloughing down the bank where necessary.

The project will require approximately 1.5 acre of clearing. Up to 30 deciduous trees (primarily

cottonwoods) will be removed for pump station and force main upgrades. These trees are far enough

from the river that they do not contribute shade or leaf litter to the river.

The project will not result in a substantial increase in impervious surfaces as it only involves

replacement/installation of a pipeline and pump station equipment. The areas for the wet well, vaults

and electrical equipment pads will be the only impervious surfaces resulting from the project.

6.0 Minimization and Mitigation Measures

6.1 Minimization/Avoidance for Temporary Impacts During the course of the entire project, standard best management practices (BMPs) and other

minimization measures will be implemented prior to and maintained throughout construction in order

to avoid or reduce impact to fish and wildlife habitat. These BMPs include, but are not limited to:

Installation of appropriate sediment and erosion control devices where appropriate, including: o Silt fence o Straw wattle o Hydroseeding

Limiting ground disturbance to the minimum amount necessary and marking clearing limits with high visibility fencing.

Implementation of a spill prevention, control and countermeasures (SPCC) plan to ensure that all potential contaminants are properly contained and handled.

Implementation of the stormwater pollution prevention plan (SWPPP) and monitoring requirements in accordance with the NPDES permit.

Restoration of all temporarily impacted areas with native seed mixes and vegetation, as appropriate.

Prevent materials, debris, and equipment from entering the water.

Page 23: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 23

Cherry Street Pump Station and Force Main Upgrade

Containing and properly disposing of all waste materials in accordance with federal, state, and local laws.

6.2 Mitigation for Temporary and Permanent Impacts To mitigate for loss of vegetation, all unimproved disturbed areas will be seeded, mulched, and/or

planted with native woody species as appropriate. Disturbed soils will be hydroseeded with a native

upland seed mix as soon as possible. Removed trees will be replaced at a ratio of 3:1 and will include the

planting of coniferous trees such as Douglas fir (Pseudotsuga menziesii), Western Hemlock (Tsuga

heterophylla), and Western Red Cedar (Thuja plicata). They will be planted on 20-foot centers and

provided with a 3-foot bark ring. Other native woody vegetation will be planted such as snowberry

(Symphoricarpos albus), beaked hazelnut (Corylus cornuta), and red osier dogwood (Cornus sericea).

Removed trees will be kept on site and utilized as LWD within the designated shoreline as deemed

suitable. This will provide improved habitat conditions in the form of cover and organic input. The

installation of LWD and native plantings will provide increased opportunity for LWD recruitment, natural

shading, organic litter input, bank stabilization, and habitat for small animals.

In addition to the 0.62 acre of temporarily-disturbed shoreline that will be restored, 0.54 acre of

additional area outside the clearing limits for the project will be enhanced as mitigation for the 0.54 acre

of shoreline permanently impacted by the proposed gravel maintenance access trail (Figure 5). This

enhancement will involve initial treatment of invasive species, particularly Himalayan blackberry (Rubus

armeniacus) and Japanese knotweed (Polygonum cuspidatum), followed by planting of the same native

plant species utilized for the restored shoreline areas. The areas proposed for enhancement currently

lack woody cover and are largely dominated by invasive species typical of disturbed areas. The proposed

shoreline restoration and enhancement will result in no net loss of shoreline and floodplain habitat

within the project vicinity.

6.3 Monitoring and Maintenance All restoration and enhancement areas will be monitored for a period of ten years, or until success

standards have been met. This is in accordance with the requirements of SMC 16.16.060(I)(10). Upon

project completion, an “As Built” report will be submitted to the City of Sumner documenting the final

design of the restoration areas. This report will include both the proposed planting plan and the “As

Built” planting plan showing densities, sizes, and locations of planted vegetation as well as which

nurseries supplied the plants, the time of plantings, locations of reference points established as photo

points, and sampling plot locations. It will also provide an analysis of any changes to the mitigation plan

that occurred during construction.

Approval of the “As Built” report will establish the beginning of the monitoring period. A site visit will be

made the summer after planting and survival rates of plantings will be assessed. Formal monitoring

procedures will be performed in years one, two, three, five, seven and ten after initial acceptance of the

“As Built” report. Successful mitigation will be measured by attainment of the performance standards

described in this habitat management plan document.

The variables that will be measured during each monitoring year include stem density of woody plants

and percent cover of herbaceous, shrub, and tree strata within each established sampling plot. Photo

points will also be established to create a representative view of the entire planted restoration and

enhancement areas. A total of 6 photo points will be established, with photos taken in each cardinal

Page 24: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 24

Cherry Street Pump Station and Force Main Upgrade

direction (N, S, E, and W) during each monitoring year. 2 photo points will be established in the

shoreline enhancement area and 4 photo points will be established in the shoreline restoration area.

Panoramic photos will also be created showing as much of the restoration areas as possible. These

photos will be submitted with each monitoring report.

Sampling plots will be randomly established throughout the restoration and enhancement areas. Two

plots will be randomly established in both the enhancement and restoration areas, respectively. These

sampling plots will be 10 feet by 10 feet square plots demarcated in the field with a steel post as the

center of the plot. Some of the plot centers will likely be used as photo points.

Formal monitoring will be performed during the growing season in years one, two, three, five, seven,

and ten after approval of the “As Built” report. Monitoring reports will be submitted to the City of

Sumner before the end of each monitoring year. Monitoring plans will be prepared as described in SMC

16.16.060(I)(10).

The City of Sumner Department of Public Works will be responsible for the long-term maintenance of the restoration site after the monitoring period has concluded. Site inspections will occur every 8 years at the same time the City of Sumner completes required Growth Management Act (GMA) updates per RCW 36.70A.130(5)a. Management/maintenance activities will include the inspection of mitigation site planting areas to assess plant survival with replacement as necessary. Pierce County listed noxious weeds will also be assessed and controlled as necessary. Trash will also be removed, vandalism will be repaired, and signage/fencing will be repaired/replaced as necessary. Long-term maintenance and management will be funded by the City of Sumner.

6.4 Performance Standards and Contingency Plan

6.4.1 Performance Standards The following performance standards provide quantifiable standards to measure mitigation success. Mitigation will be deemed successful when the restoration and enhancement areas exhibit all of the Year 10 performance standards (success standards) below. In accordance with SMC 16.20.090, during monitoring years 1 and 2 all planted trees and shrubs will exhibit 100% survival. The contractor will be responsible for replacing any dead plants during these first two years. Herbaceous cover will also have attained complete coverage within one growing season. If not, any areas of bare soil will be reseeded with appropriate native species. The following performance standards will be met during each respective monitoring year: Year 1 Performance Standards

100% plant survival

100% coverage of herbaceous groundcover

Less than 20% aerial coverage of all noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning Year 2 Performance Standards

100% plant survival

Less than 20% aerial coverage of noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning

Page 25: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 25

Cherry Street Pump Station and Force Main Upgrade

Year 3 Performance Standards

5 woody stems per 100 sq. ft.

Less than 20% aerial coverage of noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning Year 5 Performance Standards

35% aerial coverage of woody plants (trees/shrubs)

Less than 20% aerial coverage of noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning Year 7 Performance Standards

50% aerial coverage of woody plants (trees/shrubs)

Less than 20% aerial coverage of noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning Year 10 Performance Standards/Success Standards

70% aerial coverage of woody plants (trees/shrubs)

Less than 20% aerial coverage of noxious weeds, 0% coverage of Class A noxious weeds

Installed habitat features secure and functioning

6.4.2 Contingency Plan The following contingency actions may occur if deemed necessary to promote successful development

of the site:

Failure to meet a 100 percent survival rate at any of the aforementioned sites within two years after

planting will result in the following contingency actions:

Replanting will be conducted to replace all dead woody (tree/shrub) plantings.

Failure to meet the aforementioned aerial cover or stem density performance measures in a given year

within planted areas will result in the following contingency actions:

A review of vegetation management will be conducted with the City of Sumner to determine a

corrective course of action if the aerial coverage or stem density performance measures are not

met.

Failure to meet non-native invasive species performance measures and standards in a given year at a

given site will result in the following contingency actions:

The area in question will receive biological and/or mechanical weed control, and if deemed

necessary, chemical applications will be made by licensed applicators with a valid aquatic

endorsement in accordance with Washington State Department of Ecology guidelines.

Significant mortality due to herbivory will result in the following contingency action:

Herbivory guards will be added to any new plantings.

Any revisions to this mitigation plan will be coordinated with and approved by the City of Sumner prior

to implementation.

Page 26: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 26

Cherry Street Pump Station and Force Main Upgrade

7.0 Local Management Recommendations In September of 2008, the National Marine Fisheries Service (NMFS) issued their Biological Opinion

(BiOp) (tracking # 2006-00472) for the National Flood Insurance Program (NFIP) within the Puget Sound

Region. The NFIP BiOp concluded that the Federal Emergency Management Agency’s (FEMA) minimum

standards for floodplain development did not adequately protect federally-listed anadromous fish

species or their critical habitats. Based on this BiOp, FEMA directed local jurisdictions to review their

floodplain management regulations to ensure that they are adequate to ensure that any future

development within the limits of the designated 100-year floodplain will not adversely affect federally-

listed species or their habitats.

In February of 2012, the City of Sumner formally requested FEMA and NMFS to confirm that the existing

floodplain development regulations in the City of Sumner’s municipal code (SMC) are adequate to

satisfy the conditions of the BiOp. FEMA confirmed that the revisions to SMC 16.56, that were

developed in response to the Section 7 consultation on the SR 167: North Sumner Interchange Project,

would satisfy the conditions of the NFIP BiOp. These changes to SMC 16.56 in 2003 included the

requirement for habitat management plans within 1000 feet of designated fish and wildlife habitat

areas. Therefore, the preparation and implementation of this habitat management plan document

satisfies the NFIP BiOp.

In addition, as work will occur within the designated 200-foot Urban Conservancy shoreline environment

of the Puyallup River, the project will comply with all relevant sections of the City of Sumner’s Shoreline

Master Program (SMP). The SMP allows non-water-dependent utility construction within the Urban

Conservancy shoreline as a conditional use provided that the project complies with the variance and

conditional use criteria in Parts III(A)(3) and III(B)(4) of Chapter 8 of the SMP and the utility-specific

policies and regulations in Part XXI of Chapter 7 of the SMP. These criteria have been addressed in the

variance and conditional use permit application for the proposed project.

8.0 Conclusion The proposed project is not anticipated to have an adverse impact on fish and wildlife habitat or any

sensitive species. This project will not involve any in-water or over-water work as all activities will occur

at least 100-feet landward of the OHWM. There are no sensitive terrestrial species known to occupy the

area within 1,000 feet of the project. Appropriate temporary sediment and erosion control BMPs and

construction measures will be implemented and maintained throughout construction to

minimize/prevent indirect impacts to the Puyallup River. There will be no impact to wetlands as there

are none in the project vicinity. All unimproved disturbed areas will be restored upon project completion

and additional area will be enhanced as mitigation for permanent impacts. Habitat value will be

improved with the planting of native conifers and shrubs in the unimproved disturbed areas and

enhanced areas within the shoreline jurisdiction.

Page 27: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Cherry St

¬«410

Puyallup River

Puyallup River OHW Urban Conservancy Shoreline (200 ft)River ChannelFEMA FloodwayFEMA 100-Year FloodplainClearing LimitsProposed Crushed Rock TrailShoreline RestorationShoreline Enhancement

Figure 5. Mitigation AreasCherry St. Pump Station and Forcemain Upgrade

City of SumnerPierce County, WA

S 23/25/26, T 20N, R 04EJuly 29, 2015

± 0 500 1,000250Feet

Shoreline Restoration: 26,800 sq. ft. (0.62 acre) Shoreline Enhancement: 23,700 sq. ft. (0.54 acre)

Page 28: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 28

Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.

Page 29: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 29

Cherry Street Pump Station and Force Main Upgrade

9.0 References DOE 2012. Department of Ecology. Water Quality Assessment for Washington. Web mapping

application. Accessed November 5, 2014.

https://fortress.wa.gov/ecy/wqamapviewer/default.aspx?res=1536x864

Kerwin J. 1999. Salmon Habitat Limiting Factors Report for the Puyallup River Basin. July. Washington

Conservation Commission. Olympia, Washington.

Sumner 2003. City of Sumner Flood Hazard Area Map. Accessed November 10, 2014.

http://ci.sumner.wa.us/wp-content/uploads/2013/10/Flood_Hazard_Map.pdf

Sumner 2007. City of Sumner Wetland Inventory Map 2007. Accessed November 5, 2014.

http://www.ci.sumner.wa.us/Documents/Environmental%20Maps/Wetland_Map_2007.pdf

USFWS 2014. US Fish and Wildlife Service. National Wetlands Inventory. Wetlands Mapper application.

Accessed November 5, 2014. http://www.fws.gov/wetlands/Wetlands-Mapper.html.

WDFW 2014a. Washington Department of Fish and Wildlife. PHS on the Web. Priority Habitats and

Species web mapping application. Accessed November 6, 2014.

http://wdfw.wa.gov/mapping/phs/

WDFW 2014b. Washington Department of Fish and Wildlife. SalmonScape web mapping application.

Accessed November 6, 2014. http://wdfw.wa.gov/mapping/salmonscape/

Page 30: Habitat Management Plan - Sumner · Habitat Management Plan Cherry Street Pump Station and Force Main Upgrade 1.0 Introduction This habitat management plan has been prepared for the

Habitat Management Plan 30

Cherry Street Pump Station and Force Main Upgrade

This page intentionally left blank for printing purposes.