FAIRGmbH|GSIGmbH 1PaoloGiubellino,QNP2018,November2018
GSI-FAIRTheUniverseintheLaboratory
8thInterna9onalConferenceonQuarkandNuclearPhysics(QNP2018),Tsukuba,November2018
PaoloGiubellino,FAIRandGSI
FAIRGmbH|GSIGmbH
§ ExisAngacceleratorfacilityhasbeenupgradedtoserveasinjectorforFAIRand–inthemeanAme–forFAIRphase0
GSI–Almost50YearsofScien9ficandTechnicalCompetence
Phelix Laser
CRYRING
2
FAIRGmbH|GSIGmbH
ResearchInfrastructuresavailableatGSI-opentoexternalusers,inpar9cularfromuniv.
UNILAC/SIS18
TASCA SHIP
Cryring
R3B
HADESPHELIX
ESR
UNILAC
SIS18
ESR
3
FRS
CRYRING
HITRAP
FAIRGmbH|GSIGmbH3March2017 4
§ ESFRILandmark§ ToppriorityforEuropean
NuclearPhysicsCommunity§ DriverforInnova9onin
ScienceandTechnology
FAIR:FacilityforAn9protonandIonResearch–AWorld-WideUniqueAcceleratorFacility
Sweden France India Finland Germany Poland Romania Russia Slovenia UK 4
FAIRGmbH|GSIGmbH
FAIR:Interna9onalCoopera9on
§ RealizaAonandoperaAonofFAIRininterna9onalcoopera9on§ Nineinterna9onalFAIRshareholders§ ParAcipaAonof3.000scien9stsfromallcon9nents
5
FAIRGmbH|GSIGmbH
FAIR–TheFacility
RingacceleratorSIS100
ProducAonofnewexoAcnuclei
ProducAonofanAprotons
Collector ring CR
Antiproton ring HESR
Linearaccelerator
RingacceleratorSIS18
100 meters
ExisAngfacilityPlannedfacilityExperiments
ESR
CRYRING
UNILAC
“Gainfactors”rel.toGSI• 100–1000xintensity• 10xenergy• anAprotonbeams• systemofstoragecoolerrings
6
FAIRGmbH|GSIGmbH7
SIS100
ProducAonofanAprotons
100 meters
ExisAngfacilityPlannedfacilityExperiments
CBM
Super-FRS
APPA
PANDA
NUSTAR
FAIR–fourresearchpillars
HESR
FAIRGmbH|GSIGmbH
FAIRResearchPillars:-afore-frontscien9ficprograminmanyareas
§ AtomicPhysicsandFundamentalSymmetries,§ PlasmaPhysics,§ MaterialsResearch,§ RadiaAonBiology,§ CancerTherapywithIonBeams/SpaceResearch
§ DenseandHotNuclearMaYer
§ NuclearStructureandReacAonStudieswithnucleifaroffstability,
§ PhysicsofExplosiveNucleosynthesis(r-process)
§ HadronStructure&DynamicswithcooledanAprotonbeams
APPA
CBM
NUSTAR
PANDA
8
FAIRGmbH|GSIGmbH 9
GravitaAonalWaveSignal
Theoretical prediction by GSI researchers (2010):
Neutron star mergers are the astrophysical site of the r-process producing the very heavy elements
like Pt, Au and beyond, thereby exhibiting a characteristic electromagnetic “Kilonova” signal.
Confirmation by Ligo, Virgo and other astronomer groups (2017)
via detection of both gravitational and electromagnetic waves
emerging from such an event.
FAIR was designed to study the properties of neutron star matter and to trace back the production paths of
the heavy elements!
ElectromagneAc“Kilonova”Signal
Metzger, Martinez-Pinedo, Arcones et al. (2010)
Cowperthwaite, et al. (2017) Kilonova observations
Further push of FAIR science motivation …bymul9messengerstudyofaneutron-starmergerlastsummercombinedwiththeory&simula9ons
FAIRGmbH|GSIGmbH
Neutron Star Mergers
§ Equation of State (Hades, CBM) § Gravitational wave signal § Amount of ejecta
§ Baryon-Baryon interaction (PANDA)
§ Exotic neutron-rich nuclei (NUSTAR) § r-process nucleosynthesis and
abundancies of the heaviest elements gold, platinum and beyond
§ Plasma and atomic opacities (APPA) § Kilonova electromagnetic transient
Copyright: Dana Berry, SkyWorks Digital, Inc
FAIR Research Pillars
The FAIR experiments offer unique opportunities for studying and solving these fundamental questions!
10
Neutron Star Mergers and FAIR research …
FAIRGmbH|GSIGmbH
Status of FAIR: Civil Construction rapid progress since official start on 4th of July 2017
11
Excavation SIS100 tunnel Upgraded SIS18 completed ready for FAIR and FAIR phase 0
Start of concrete shell works for SIS100 Excavation transfer building & CBM cave
FAIRGmbH|GSIGmbH 12
§ SerialproducAonformajorcomponentsforSIS100isprogressingwithonequarterofthedipolemagnetsalreadymanufactured.
SIS100 Dipole Magnets Cryo Catcher
Quadrupole Unit Bunch Compressor
Cryo-Bypass Line
RF Cavity System
Status of FAIR: accelerators: construction / procurement progresses well
FAIRGmbH|GSIGmbH
First of Series of SIS100 Quadrupole Magnets successfully cold-tested at JINR…
Cold-Test Facility at JINR, Dubna
SIS100 quadrupole unit mounted in the test cryostat (blue) at JINR, Dubna
FAIRGmbH|GSIGmbH
24 SIS100 (of 120) dipole magnets have been delivered and are being cold-tested …
FAIR GmbH | GSI GmbH
New CRYRING@GSI/FAIR
View from local injector to the ring
• ready for experiments and tests
15
FAIRGmbH|GSIGmbH
Status of FAIR: experimentsdetector R&D and construction well on track …
A P P A
TRD
MUCH
P
A
N
D
A
C
B
M
N U
S T
A
R
16
FAIRGmbH|GSIGmbH
green IT cube
October 4, 2018 mCBM@SIS18 - a CBM full system test-setup for high-rate nucleus-nucleus collisions at GSI/FAIR
Ø CBM prototype detector systems Ø free streaming read-out and data
transport to the mFLES Ø up to 10 MHz collision rate Ø first commissioning beam in
December 2018
mcbm@SIS18 cave
FAIRGmbH|GSIGmbH 4
HADESupgrades
✓ RICH(HADES/CBMphase0project)–finished,readyforbeam- GaininleptonpairdetecAonefficiency(x3)
- Improvedbackground/noiserejecAon:- BeYerconversionpairrejecAon- PreciseAmeinformaAon(downto300psprecision)
- Joint(CBM/PANDA/HADES)developmentofread-outsystembasedonTRB3plajorm.✓ Electromagne9cCalorimeter–4sectorsreadyforbeamin2019
- π0andηdecaysintoγγchannel- ElectromagneAcdecaysofbaryonicresonances- Improvede/πseparaAon:importantfordi-electronspectroscopy- Proventechnology:leadglassmodulesreadoutwithHamamatsuPMTs
✓ MDCreadoutupgrade–Installa9onin2020
HADESCalorimeter
MDCreadoutupgradeInstallaAonin2020
RICHUpgrade
ForwardDetector–InstallaAonin2019
- MulA-hitTDC(TRBbased)–essenAalforhighrateexperiments- Read-outtriggerrateincreasefrom50kHzto200kHz
✓ ForwardDetector(HADES/PANDAphase0project)–installa9onin2019- EnhanceHADEScapabiliAesforexclusivechannels–forwardregion- HyperonproducAonandEMdecays- PIDviaTOF,dE/dx(strawtube)–nomagneAcfield
4
HADESSpectrometer
Finished, Ready for Beam 4 Sectors Ready for Beam
FAIRGmbH|GSIGmbH
HADESreadyfortheAgdatatakingcampaign
19 11/14/18
Ag+Ag at 1.65A GeV Spring 2019 Goal: 5 Billion recorded most central events (0 – 40%)
Measure thermal radiation out to beyond the low-mass vector meson pole region.
Access to chiral 𝜌− 𝑎↓1 mixing.
Differential measurement of mu l t i - s t range baryons . Unravel the mystery of
e n h a n c e d Ξ ↑ − production observed in Ar+KCl / p+Nb
FAIRGmbH|GSIGmbH
StartversionforPhase0(Status2018)
NeuLAND (Germany, Russia, Netherlands): 1/3 ready in 2018
Tracking system (Germany): Reduced start version in 2018
CALIFA (Sweden, Spain, Germany, Russia): Barrel without backward part ready in 2018 + 80% of the endcap ready in 2019
Si tracker (UK): ready in 2019
GLAD (France, Germany): Commissioning in August 2018
Proton arm (Russia) : ready in 2022
Exploring the extremes with NUSTAR@FAIR
FAIRGmbH|GSIGmbH
HowNaturemakesthebuildingblocksoflife
Alpha fusion on 12C is the stellar reaction of paramount importance, W.A. Fowler, Nobel lecture 1983
12C
4He 16O Experiment in inverse kinematics (Coulomb
dissociation) requires high energies -> GSI/FAIR
rate insufficiently known at astrophysically energies
DESPEC in FAIR Phase-0 (2018/19)
22 Exploring the extremes with NUSTAR@FAIR
Spectroscopy & lifetimes of neutron-rich nuclei close to N=126 FATIMA fast-timing array - ready for experiments (S452, S460 & S468) FATIMA & AGATA at GANIL AIDA DEGAS & FATIMA (2019)
AGATA+VAMOS+FATIMA
AIDA implantation and decay detector (1/3 of full size available in 2018) Commissioned in RIKEN, Japan
FAIRGmbH|GSIGmbH 23
§ WorkingtowardsthecompleAonofFAIRby2025§ MajorthrustisonconstrucAonofFAIRacceleratorsand
experiments§ ButatthesameAmewepursueastagedapproachtoFAIR
scienceandtotheprogressivecommissioningofacceleratorsanddetectors:§ FAIRphase0:startin2018/2019§ FAIRday1/phase1withFAIRacceleratorsprogressively
approachingdesignparameters§ FullFAIRoperaAon
Schedule for Realizing FAIR
FAIRGmbH|GSIGmbH 24
FAIRPhase-0intermediateresearchprogram
§ ObjecAves:§ Commissioningofacceleratorsanddetectors
§ ForefrontresearchbyemployingandtesAngnewFAIRdetectors
§ ExploiAngupgradedGSIacceleratorfaciliAesincl.thenewlyinstalledCRYRING
§ EducaAonofyoungscienAsts§ MaintainandextendskillsandexperAse
§ ServenaAonalandinternaAonalusercommunity
§ requirescarefultechn.preparaAon:§ fullre-commissioningoftheUNILAC/SIS18/ESRcomplexincl.newcontrols
§ gradualimplementaAon
FAIRGmbH|GSIGmbH
Scien8ficStepstowardsimplemen9ngFAIRPhase-0
• ScienAficprogrammeandbeamparametersdefined,takingintoaccountscienAficandtechnicalprioriAesoftheFAIRCollaboraAons
• 110daysofbeamAmein2018planned,similaramountofbeamAmeenvisagedfor2019
• ‘CallforProposals’opened2017• Nearly150submifedexperimentproposalsbywellover1000
scien9sts“overbook”availablebeam9mebyafactorof2-3• High-profileinternaAonalProgramAdvisoryCommiYees,Overall
PACchairedbyProf.SydneyGalèsevaluatedproposals(G-PACmeeAngheldon19.-21.Sept.2017)
25
FAIRGmbH|GSIGmbH 26
Evaluation of proposals for first FAIR Phase-0 Campaign 2018/19
Results G-PAC (overall): beamtime recommendations in 8 h-shifts
Session SummainSumpara. Total SummainSumpara. Total SummainSumpara. Total
ESR/CRYRING 555 0 555 188 0 188 278 0 278
SIS18:HADES/CBM 183 81 191 94 81 102 134 81 142
SIS18:NUSTAR-R3B 264 20 266 85 34 88 120 34 123
SIS18:NUSTAR-S-FRS 185 69 192 62 38 66 102 59 108
SIS18:NUSTAR-DESPEC 221 40 225 58 22 60 58 40 62
UNILAC/SHE 570 261 596 294 174 311 327 174 344
∑ 1978 471 2025 781 349 816 1019 388 1058
Shiftsextended(AandA-)Shiftsrequested Shiftsrecommended(A)
Total requested
Total recommended
Total recomm. plus
“flexible reserve”
FAIRGmbH|GSIGmbH
FAIRGmbH|GSIGmbH
Beam time schedule foreseen for 2018
FAIRGmbH|GSIGmbH
Accident: ER1 fire and RF ventilation contamination
images: B. Schlitt
• Fire in the ER1 transformer • Power-off in the entire rf gallery
• Separation of the ER1 system • No single gap resonators
• Cleaning of all amplifiers AND all transformers
• No rf operation until mid. Oct.
! No more physics beam time 2018
FAIRGmbH|GSIGmbH
Main other challenges of the machine
RFQ
Limited amplitude causes limitation of m/q
⇒ Very heavy ions: No high intensity yet
New control system
FAIR control system not completed
⇒ Complex operating
⇒ ESR not in operation
⇒ Still a lot commissioning needed
⇒ Limited parallel operation
images: P. Gerhard
FAIRGmbH|GSIGmbH
NewPlan
§ FollowingtheinterrupAonofthephysicsrunduetotheaccidentandtheresulAngextendeddownAme,newplanshadtobedeveloped.AteracarefulanalysisofthedamageandthesituaAon,themachineoperaAonstrategyistoshitthetwodatatakingperiodsforeseenforfall2018andfall2019byafewmonths.Theynowwillbeperformedinearly2019andearly2020respecAvely,andcommissioningAmehasbeenaddedfortheacceleratorsinordertoaddresssomeofthetechnicalissuesinanopAmisedway.
FAIRGmbH|GSIGmbH
NewPlan:Goalsandboundarycondi9ons
§ Engineeringrun:Nov.2018–Dec.2018§ Goal:toestablishbasicoperaAoncondiAonsthatarerequiredforthePhysics
programin2019§ boundarycondiAons:
§ limitedcapabiliAesofnewFAIRcontrols§ Notyetcomprehensivetoolsincludinguptodatelaucelayoutsforbeamlinetuning§ nostoragemodecapabiliAesavailableforcomprehensiveESRcommissioning
§ Physicsrun:March2019–April2019§ Goal:toprovidereliableoperaAonforthescheduledPhysicsprograms§ boundarycondiAons
§ limitedchoiceofheavyionsduetoHSIRFQtechnicallimitaAon§ Nosinglegapresonatorsattheendofpoststriper§ NoparalleloperaAoninplanningtoensurereliability
§ Engineeringrun:Nov.2019–Dec.2019§ Goal:1)toestablishESRstoragemode2)toestablishdeceleraAoninESR3)to
completethecomissioningofCRYRINGwithESRbeam§ newlyintroducedFAIRcontrolsforESRmustallowstoragemode
§ ExpecttobeavailableforcommissioningnoearlierthanSept.2019
FAIRGmbH|GSIGmbH
Engineering run
Main focus of the engineering run • establilsh slow extraction beam to HADES • start ESR commission controls • FRS commissioning, mCBM detector setup
FAIRGmbH|GSIGmbH
Engineering run
Planned shutdown major activities • UNILAC HSI RFQ new electrodes
• in progress. Expect installation ~mid 2019 • UNILAC UHV upgrade: full scale: 8 month • TGA fire protection renovation
FAIRGmbH|GSIGmbH 35
FAIR2025
Thank You!