Group Material Technology | GMTCHINA START-UP PROJECT
Speaker: Oliver N. Jäger CEO Group Material Technology
IHAA 15th Technical
Symposium
Weehawken, NJ, 25 September 2014
Page 2
GMT goes China
Content Page:
Introduction to Aalberts Industries - GMT 3 - 7
Background and Market Conditions 8 - 10
Motivation to Invest 11 -13
Executive Summary: China Start-Up 14 - 15
Main Challenges 16 - 17
Project Realization and Major Project Steps 18 - 20
Location and Offered Processes 21 -36
Page 3
IntroductionAalberts Industries
Group Material Technology- Company Network -
Page 4
Decentralised structure with significant operational management responsibilities small holding; 13 employees
Equity ratio: 52,8 %
Small team of group managers reporting to the holding
Aalberts Industries N.V.Aalberts Industries N.V.
Aalberts Industries – Organization
Page 5
Description of Aalberts´ Business Segments
Page 6
Group Material Technology Company NetworkA Group within Industrial Services
Surface treatment Heat treatment / Vacuum Brazing
Page 7
GMTGroup Presence
= Heat treatment = Surface treatment
USA
China
Turnover: approx 300m €p.a.
Sites: 60, o/w 55 in Europe
Employees: approx 2,800
North Sea
Atlantic Ocean
Mediterranean Sea
Europe
Page 8
Background & Market ConditionsGreenfield Project in China
Page 9
Mastertitelformat bearbeiten
China ApproachBackground & Market Research
Passenger car production ramped up significantly in China during the last decades and further growth is still anticipated
Due to local content requirements a local supply chain will be established
GMT/AHC was asked by their current customers to be part of the Chinese supply chain
Further market opportunities will be offered by Chinese suppliers
Assuming a comparable market share as in Germany, would let to a turnover of around USD 100 million
Key Facts
* Source chart: diverse automotive statistics
Page 10
Strategic View China ProjectSix Major Economic Automotive Zones
Chongquing, Chengdu, Liuzhou:CHANA (Chang´an Ford Mazda, Chang´an Suzuki etc.), Lifan, Sichuan FAW Toyota, FAW-VW Chengdu, SAIC-GM-Wuling, Dongfeng Liuzhou, etc.
Wuhan, Zhengzhou, Xiangtan:Dongfeng (Dongfeng Peugeot Citroen, Dongfeng Honda), Great Wall, Geely Xiangtan etc.
Guangzhou, Shenzhen, Haikou:GAIG (Guangqi Honda, Honda China, GAC Toyota), Dongfeng Nissan, BYD, Hafei Shenzhen, Haima, etc.
Shenyang, Changchun, Harbin:FAW Group (FAW-VW, FAW Car, Sichuan FAW Toyota Changchun), Brilliance Jinbei (Brilliance BMW), Shanghai GM Norsom, Hafei, etc.
Beijing, Tianjin, Dalian, Jinan, Yantai:Beijing Benz, Foton, FAW Toyota, Tianjin FAW Xiali, Chery Dalian, Siontruk, Shanghai GM, etc.
Shanghai, Nanjing, Wuhu, Ningbo:SAIC (Shanghai VW, Shanghai GM, etc.), SAIC Nanjing, Chery, Geely, etc.
Yangtse River
Delta Zone
Page 11
Motivation to Invest
Page 12
Motivation to Invest
In general:
Development and growth of Automotive Industry*
Localization
Market related:
Mainland China does not have a nationwide service network in the areas of technical, functional surface treatment as well as for the heat treatment of metals established reliably; only supplied by smaller local suppliers
Steady increasing automobile production in China, especially in the field of premium cars
Comparable price structure with the existing one in Europe
Market conditions and needs correspond with our experience and high-tech solutions in the premium segment
* German Automotive manufacterer are currently represented with approx. 200 locations in China
Page 13
Key Considerations
Initiate business in China by implementing surface treatment
Automotive shall be initial focus, starting with established European partners, followed by domestic Chinese customers
Participate in the strongly growing automotive market
– mid-term production estimate: 30 Mio. cars p.a.
– compared to 2010: 12,9 Mio. cars
Locate the plant in the Yangtze River Delta region for market entry associated with manageable risk
HART-COAT® to be implemented first followed by DURNI-COAT®
Further growth includes the introduction of heat treatment; stamping might offer an additional growth potential
Area required is 25 mu (16,667 m2 / 16.67 ha) + 25 mu (onwards)
Page 14
Executive Summary- China Start-Up -
Page 15
Hangzhou AHC Surface Treatment Ltd.Executive Summary
Group Material Technology has set up a state-of-the art plating plant in the vicinity of Shanghai
Main processes are Hart Coat (HC) and electroless nickel (DNC)
Room for further extension e.g. for corrosion protection on the basis of zinc/zinc-nickel is given
AHC China will provide full coating services for applications in automotive, aerospace and mechanical engineering
SOP: HC line in May 2014 / DNC line in July 2014
First orders acquired in June 2014
Key FactsKey FactsLocationLocation
Hangzhou
Shanghai
Ningbo
Nanjing
Page 16
Main Challenges
Page 17
Main Challenges
Local authorities
Land purchase
Inflation exchange
rate
Budget adjustment
Different mentality and
culture
Surface treatment
permit
Page 18
Project Realization & Major Project Steps
Page 19
First Activities in 2010/2011
Automotive market survey, including visits to BMW, Geely Volvo, General Motors, Mercedes and Volkswagen
Analysis of main automotive T1 suppliers, including visits to Bosch, TRW, INA, Continental, Voith, Kolbenschmidt etc. as well as domestic suppliers, e.g. Bohai Piston and Wanxiang
Select potential development zones in the Yangtze River Delta (Shanghai, Nianjing, Hangzhou, Ningbo)
Select potential plating parks (rental basis, no own plating license)
Make contact with reference companies located in the Development Zones
Compile relevant environmental data and achieve assessment by the Environmental Protection Bureau as to whether the GMT project will be granted
First & second round of interviews (> 10 candidates) for MD China
Page 20
Project Management Schedule
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1 Market analysis
2 Preparation
3 Board approval
4 Project Kick-Off
5 Management recruitment
6 Selection of Development Zone
7 Land purchase
8 Selection of equipment supplier/
general constructor
9 Authorities´ approval
10 Building / construction
11 HC - Order
12 - Installation
13 - SOP May
14 DNC - Order
15 - Installation
16 - SOP July
17 Waste water - Order
18 - Installation
19 - SOP May
2011 2012 2013 2014PROJECT PHASE
*
*
*
T
O
D
A
Y
*
*
*
Page 21
Location and Offered Processes
Page 22
Location Hangzhou Building – General Layout
Main plant characteristics:
The company will be able to employ 300 employees.
The layout has been optimized with respect to production flow and minimum distances between warehouse and process equipment.
The plant sets up its operation automatically, incl. laboratory, quality assurance and testing.
The waste water management complies with highest international standards.
Total floor space covered is 7590 m2 (66 m x 115 m)
General Production LayoutGeneral Production Layout
offices/ administration
goods warehouses
DNC plant
HC plant
extension area
waste water treatment
HC manual line
laboratory line
Page 23
HC Plant - Layout OverviewSupplier: PAL
Page 24
DNC Plant – Layout OverviewSupplier: PAL
Page 25
Location HangzhouConstruction Process
Production Hall
Street View
Page 26
Location HangzhouHART-COAT® Production Line
Page 27
Location HangzhouElectroless Nickel / DURNI-COAT® Production Line
Page 28
Location HangzhouWaste Water Treatment
Page 29
Location HangzhouManual Line
Page 30
HART-COAT®
Industrial Coatings for Aluminium Alloys
Plating window Running direction 600 mm Width 3.000 mm Depth 1.200 mm
Processes available: Hart Coat® (3 bathes) Technical Eloxal (1 bath) Blackening Cold Sealing Further extension possible
Aluminium alloys to be used: Wrought aluminium (Die)cast aluminium With Cu content up to 6 wt.%
Equipment DetailsEquipment Details
Outstanding hardness
High electrical insulation
Excellent adhesion
High thermal insulation
Good dimensional accuracy
Optimum anti-friction properties
High wear resistance
Excellent corrosion resistance
Main PropertiesMain Properties
Page 31
HART-COAT®
Process Variants and Typical Applications
Process variants HC HC – CU HC - GD HC - GL
Suitable alloys Wrought aluminiumalloys as well as sand and permanent mold cast
Aluminium alloys with a high copper content (2% to 6%)
Die-cast aluminiumalloys with high copper and/or silicon content
Wrought, cast anddie-cast aluminium alloys with limited copper, silicon and lead content
Applications Pneumatic and hydraulic cylinders, compressor wheels, lifting gear, insulators, hot-plates, screw conveyors, spacers, clamping and retaining mechanisms, cylindrical tubes, rocker arms, surgical instruments
Guide pulleys, pistons,nozzles, valves, rollerbearings, centrifuges,camera components,bearing shells, cam plates, levers, pulleys, coils
Housings, guidecylinders, guide plates,mounting plates,clothes iron plates,shock absorbers,gears and rack drives,clutch components,cylinder heads
Components requiringan especially smooth and wear-resistant surface
Layer propertiesdepending on alloy
High wear resistanceExcellent corrosion resistanceOutstanding hardnessOptimum anti-friction properties
Excellent adhesionHigh thermal insulationHigh electrical insulationGood dimensional accuracy
Resistant to temperatureSuitable for consumer goodsFood compatible
Page 32
DURNI-COAT ®
Outstanding hardness
Optimum anti-friction properties
Good dimensional accuracy
Optimum anti-friction properties
High wear resistance
Excellent corrosion resistance
Main PropertiesMain Properties
Uniform layer formation
Electrical conductivity
Plating window Running direction 600 mm Width 1.100 mm Depth 1.500 mm
Processes available: Electroless nickel (DNC) (3 bath) Electroless nickel + PTFE (1 bath) Further extension possible incl. DNC +
SiC
Coating chemistry covers a wide range from 3 to 14 wt.% of Phosphor
To be applied on aluminum as well as on zinc cast alloys
Equipment DetailsEquipment Details
Page 33
DURNI-COAT®
Process Variants and Typical Applications (I)
DNC 450 DNC 520 DNC 700 DNC-AL
Fields of use Especially ductile and corrosion resistant
Especially corrosion resistant
Especially wear resistant
Aluminium and aluminium alloys
Lead Free DNC 471 DNC 571 DNC 471
Applications Components with high corrosion and chemical loads
Pump components for use with natural gas and crude oil, food handling and processing
Mining equipment and components, metal fittings and hydraulic flaps, vehicle components
Structural parts for textile machines, printing presses, packaging machines, control system technology, electronics, electrical engineering vehicle components
Page 34
DURNI-COAT®
Process Variants and Typical Applications (II)
DNC-ZNGD
PTFE-DURNI-DISP
SIC-DURNI-DISP
SIC-9-DURNI-DISP
Fields of use Die-cast zinc Dispersion layer with embedded PTFE
Dispersion layer with embedded SiC
Function increa-sing coating
Lead Free
Applications The motor vehicle sector (e.g. carbu-rettors, lock fittings, badges), electrical engineering/ domestic appliances, light machine construction
Structural pneumatic and hydraulic components, mould construction, control levers, door lock fittings, shafts, bearing seats, textile machine parts
Brake discs, cylinder running surfaces pistons, valve plates, structural pneumatic and hydraulic parts, feeding funnels, rollers, track rollers
Friction-locked connection, transmission systems
Page 35
Contact
Dr. Jörn GroßmannExecutive Management/Business Development
(m) [email protected](p) +49 2237 502 - 332(w) www.groupmt.com
Oliver JägerCEO
(m) [email protected](p) +49 2237 502 - 340(w) www.groupmt.com
Kelly LuoGeneral Manager
(m) [email protected] (p) +86 1390 1816 850(w) www.ahc-china.com
General Material Technology GmbHBoelckestrasse 25 – 57
50171 Kerpen (North Rhine-Westphalia)
Germany
General Material Technology GmbHBoelckestrasse 25 – 57
50171 Kerpen (North Rhine-Westphalia)
Germany
Hangzhou AHC Surface Treatment Ltd.,
China
Hangzhou AHC Surface Treatment Ltd.,
China
Management Board: Oliver Jäger, Ralf Krämer, Helmut Nolte, Udo Witte | Court: Köln HRB 42489
Page 36
End of Presentation