Foundation in Natural and Built Environment (FNBE) Introduction to the Construction Industry [ QSB30105 ] Final project: Development Proposal Name : Ong Jie En (0323835) ; Shum Li Sze (0322822) Tutor : Puan Hasmanira Mokhtar Submission date: 27 July 2015

Upload: liszee

Post on 18-Aug-2015

24 views

Category:

Education


0 download

TRANSCRIPT

Foundation in Natural and Built Environment (FNBE)

Introduction to the Construction Industry [ QSB30105 ]

Final project:

Development Proposal

Name : Ong Jie En (0323835) ;

Shum Li Sze (0322822)

Tutor : Puan Hasmanira Mokhtar

Submission date: 27 July 2015

SITE INTRODUCTION

For this project, we need to select a specific empty land which is between

2500km² to 3500km² to initiate a small construction project. Then, we need to come

out with proposals and plans of our construction project base on 1 or 2 combination of

purpose such as recreational area, commercial area, industrial area, agricultural area,

tourism area and residential area.

For the site we have selected, it is located at Persiaran Damai Utama 2, Taman

Damai Utama, 47180 Puchong Selangor. It is a 3070km² site and it is a bare and

undeveloped land. The site is located at the residential area at Puchong and it is

potential to be developed.

There are residential areas like Kinrara Residence and PUJ residential. There

are shoplots and restaurants around the site and there is an abandoned lake at the

North of the proposed site. There are bus stops near the proposed area for the

residents and there is a forest at the west of the proposed site.

Proposed site : Persiaran

Damai Utama 2, Taman

Damai Utama, 47180

Puchong, Selangor.

Size: 30.7km²

SITE PLAN

SITE CONTEXT

1

2

2

2 3

2

2

2

Proposed site

Shop lots

( commercial area )

Houses (Residential

area )

Lake

1

2

3

2

2

2

LEGEND

Site Observation

This is the drain infront of our site there’s a TNB station beside our site

This two images above show the shop lots opposite our site across a roadway.

This is our site. It covers by a land of tiny small stones.

This is the view of our site from the opposite row of shop lots.

This is another residential area nearby, This is a Car Wash Centre nearby.

named Taman Damai Utama.

This is a church nearby Bandar Kinrara.

This is a restricted area, an unwanted lake is fenced.

SITE ANALYSIS

North point, Sun Path and Wind Path

The sun travels from west to east at the proposed site. The site receives maximum

sunlight at 12pm and the hottest area of the site is at the east as there are minimum

of plants. The site is windy and the wind flows from the south.

N

8am 6pm

Sun path

Wind

path

Topography

Selected site

The topography of

the selected site is a

flat ground and has a

slight slope which is

around 5 degree.

Lower area Slope

Higher area

Topography of the surrounding of the selected site

Ground

Landscape and Existing Structure

The landscape of the site is not managed and the vegetation of the site is not

specific and not well-maintained. They are mainly wild plants.

Climbing plants Bushes and wilt turfs Wooden trees

The ground of the selected site is covered with stones, rocks and sand.

The site has no existing structure except for the main drainage that surrounds the

site.

Circulation, traffic and accessibility

The traffic flow is usually fast in the site area as the site is surrounded by residential

areas and shop lots. The residents at the site usually travel with bicycle and cars.

Weekdays morning Weekdays evening

Weekend morning Weekend evening

Traffic flow legend Fast Slow

There are no

rapid station or

bus station and

other access at

the site except for

the bus stop.

Public amenities Distance from proposed site

Walking time Driving time

School ( SMK Seksyen 4 Bandar Kinrara )

2.9km 35min 5min

Clinic ( Poliklinik Soo )

0.5km 5min 2min

Supermarket ( MyMydin )

0.35m 3min 1min

Mosque 2.5km 30min 5min

Police station Puchong

2km 30min 4.5min

Bomba ( Balai Bomba dan Penyelamat Bukit Jalil )

4.6km 1 hour 8min

Weakness and Strength of proposed site

1.The TNB sub power station is a constraint

to the site as it will emit radioactive that will

affect the humans’ health. The TNB sub

power station is a disturbing view to the

landscape of the site too.

2.The drainage system around the selected site is also a

constraint to the site as the unpleasant odour that is produced

by the drain water will affect the residents’ health. Other than

that, it also affect the visual landscape of the site.

3.The crossroad near the site is

one of the strength as it increase

the population and cars to go to

the selected site.

WEAKNESS

STRENGTH

1

3

2

Proposed site