Grounding Installation Inspection and Test Plan (ITP) Division/Department: Engineering Discipline: Page 1 of 2 Customer: Contract Number: Contract/Project Name: INPECTI!N "N# TET P$"N %or: Grounding Installation &or' area: (Insert work area) $egend I – Inspect - Monitor – Review * – Hold Point & - Witness Item Num er "cti+it, #escription peci-cation/ Code e%erence esponsi bilit, .eri%,ing #ocument s Inspection e uirements Comments eade Customer ep !0ner ep 1 Document Review of !pplicale Procedures" #peci$cations" Drawings" %ontract Documents 2 &erif' t(e electrical s'stems t(at re)uire grounded neutrals are installed/tested in accordance wit( speci$cations and drawings &erif' *rounding electrode s'stem materials are in accordance wit( speci$cations and drawings &erif' *rounding electrode s'stem installation in accordance wit( speci$cations and drawings 3 &erif' *rounding electrode s'stem is tested in accordance wit( speci$cations and drawings 4 &erif' uried/aove ground grounding s'stem conductors etween e)uipment and grounding electrode s'stem are installed" routed in accordance wit( speci$cations and drawings 5 &erif' +uried *rounding cale taps and splices are e,ot(ermicall' welded or connected wit( an approved mec(anical connector" and coated in accordance wit( speci$cations and drawings 6 &erif' *rounding conductors etween e)uipment and grounding electrode s'stem are resistance tested in accordance wit( speci$cations and drawings 7 &erif' *rounding conductors are protected ' conduit sleeves w(ere re)uired 18 &erif' *rounding connections tig(t" and are per speci$cations 11 &erif' Rear *rounded per speci$cations 12 &erif' *round conductors installed in duct .ersion: e+ision #ate: #escription o% C9ange: 1 8 !riginal Issue (is document is controlled electronicall' on t(e Meade Intranet. Printed or electronicall' transmitted copies are uncontrolled.

Upload: benz

Post on 07-Oct-2015

455 views

Category:

Documents


13 download

DESCRIPTION

ITP for grounding

TRANSCRIPT

Grounding Installation Inspection and Test Plan (ITP)

Grounding Installation Inspection and Test Plan (ITP)Division/Department: EngineeringDiscipline: ElectricalPage 1 of 2

Customer:Contract Number:Contract/Project Name:INSPECTION AND TEST PLAN for: Grounding InstallationWork area: (Insert work area)

LegendI InspectM - MonitorR ReviewH Hold PointW - Witness

Item NumberActivityDescriptionSpecification/Code ReferenceResponsibilityVerifying DocumentsInspection RequirementsComments

MeadeCustomer RepOwner Rep

1Document Review of Applicable Procedures, Specifications, Drawings, Contract Documents

2Verify the electrical systems that require grounded neutrals are installed/tested in accordance with specifications and drawings

3Verify Grounding electrode system materials are in accordance with specifications and drawings

4Verify Grounding electrode system installation in accordance with specifications and drawings

5Verify Grounding electrode system is tested in accordance with specifications and drawings

6Verify buried/above ground grounding system conductors between equipment and grounding electrode system are installed, routed in accordance with specifications and drawings

7Verify Buried Grounding cable taps and splices are exothermically welded or connected with an approved mechanical connector, and coated in accordance with specifications and drawings

8Verify Grounding conductors between equipment and grounding electrode system are resistance tested in accordance with specifications and drawings

9Verify Grounding conductors are protected by conduit sleeves where required

10Verify Grounding connections tight, and are per specifications

11Verify Rebar Grounded per specifications

12Verify Ground conductors installed in duct banks per specifications

13Verify DCS grounding is in accordance with specifications and drawings

14Verify electrical equipment grounding is visible in accordance with OSHA

15Production to inform QC of near completion of work scope prior to demobilization for final acceptance/walkdown

16Compile and Review of completed QC package and submit

NamePositionSignatureDate

**** Site Project Manager/Forman Designee:

**** Quality Manager/Designee:

Customer Quality Approval or Job Rep:

Version: Revision Date:Description of Change:

1.01/1/2013Original Issue