ground improvement project – large water storage tanks ...€¦ · settlement (mm) 700 250 to 300...
TRANSCRIPT
![Page 1: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/1.jpg)
Ground Improvement Project –Large water storage tanks
Carrington NSWDouglas Partners’ Technical Seminar 2019
Scott McFarlane & Richard Merifield
![Page 2: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/2.jpg)
![Page 3: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/3.jpg)
![Page 4: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/4.jpg)
Background
• Douglas Partners are a trusted consultant to PWCS;
• PWCS needed to upgrade their stormwater management system;
• PWCS engaged GHD as the design consultant (civil, hydraulic, mechanical,
electrical & geotechnical);
• PWCS provided GHD previous nearby geotechnical data (by DP) to assist
GHD with conceptual geotechnical ground improvement options for tank;
• PWCS provided DP the concept geotechnical design options by GHD to
develop scope of works (i.e. data report).
![Page 5: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/5.jpg)
Stormwater Management System
• Manage stormwater to minimise
off-site uncontrolled discharge;
• Above ground steel tanks;
• Supported on concrete slab;
• Tank 1 – 20 m dia, 11 m high, 5Ml;
• Tank 2 – 32 m dia, 11 m high, 8 Ml;
• Tank 3 – 32 m dia, 11 m high, 8 Ml;
• Pipeline to connect into existing
pond. Trench to be excavated
adjacent to rail line.
![Page 6: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/6.jpg)
Previous Data
Soft Clay VL Sand
Very Stiff to Hard Clay
Dense Sand
Clay / Silt and Sand
Stiff Clay
Fill
Rock-40
-30
-20
-10
-0
![Page 7: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/7.jpg)
GHD Concept Ground Improvement Options
Ground
Improvement
Option
Do nothing Preload CFA piles Driven Piles Cutter Soil
Mixing (CSM)
Design Details - 8 m high
preload
(3 month
wait)
600 mm dia;
Installed to
>35 m,
3 m c/c
400 mm sq;
Installed to
>35 m,
2.5 m c/c
CSM to 35 m
15% area
replacement
ratio
Estimated
Post
Construction
Settlement
(mm)
700 250
to
300
5 to 10 5 to 10 With preload:
20 mm
Without:
100 mm
Constraints Settlement Space,
time
Depth of
piles, ASS
Depth of
Piles
Depth of Piles
PWCS – very risk adverse with any ground improvement (past experience)
![Page 8: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/8.jpg)
DP DifferenceCalculation of the Settlements and Vertical Stresses beneath Uniformly Loaded, Flexible, Rectangular Footings on Multi Layered Elastic SolidLimitns: 1.Maximum 10 layers, 10 flexible footings, 4 cross sections
2.Units: metres and kPa3.Enter data in coloured cells & adjust settlement plot axes4.Settlements & stresses calculated along Xsections at Zdepth
Footing Uniform No. X ordinate Y ordinate X ordinate Y ordinate Pressure1 0.00 0.00 32.00 32.00 120.002345678910
Xsection Xord left Yord left Xord right Yord right Zdepth1 0.00 0.00 32.00 32.00 0.00234
Max Settlement along Xsections = 250 mmSoil Layer Base Depth Layer Thick Soil Moduli Psn's Ratio Description
1 2.00 2.00 40000.00 0.35 gravel2 4.00 2.00 2000.00 0.35 clay3 5.00 1.00 25000.00 0.35 sand4 10.00 5.00 5000.00 0.35 sand5 15.00 5.00 60000.00 0.35 sand6 23.00 8.00 12000.00 0.30 clay7 37.00 14.00 15000.00 0.30 clay8910
version 1.1 © Douglas Partners Pty Ltd Date: Calcs by: Check:CLIENT: PWCSPROJECT: Carrington Project No: NALOCATION: PWCS Bore No: NA
Coords closest to Origin Coords far from Origin
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00
Layout of Uniformly Loaded, Flexible Footings
Ftg1 Ftg2 Ftg3 Ftg4 Ftg5Ftg6 Ftg7 Ftg8 Xsect1 Xsect2Xsect3 Ftg9 Ftg10 Xsect4
0.000
0.050
0.100
0.150
0.200
0.250
0.300
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00
250 mm
![Page 9: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/9.jpg)
DP Revised Scope• Investigation – Provide data to
GHD to undertake Design;
• Parallel modelling to compare
with GHD design;
• Review technical specification;
• Review tenders methodology;
• Review preferred tenderers
design, QA and alternate design.
![Page 10: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/10.jpg)
InvestigationGeotechnical Risks
• Soft clay layer?
• Sand stratum?
• Deeper clay?
• Ground water?
• Rock strength?
![Page 11: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/11.jpg)
Subsurface ProfileTank 1 – 20 m dia Tank 2 – 32 m dia
![Page 12: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/12.jpg)
Design & Analysis
![Page 13: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/13.jpg)
Tank Design Loads
Design Life = 50 years
![Page 14: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/14.jpg)
Serviceability Criteria• Max settlement at centre ≤ 100 mm;
• Max settlement around perimeter ≤ 100 mm;
• Max settlement between centre and edge ≤ 40 mm;
• Max edge to edge tilt ≤ 30 mm;
• Differential settlement ≤ 1 in 500.
![Page 15: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/15.jpg)
Conceptual Time-Settlement Behaviour
![Page 16: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/16.jpg)
Max Total Settlement: Case 1 – 300 mmCase 2 – 225 mm
Initial Ground Improvement Options• No Ground Improvement;
• Piles with Pile Transfer Layer (PTL);
• Deep Soil Mixing (GHD preference);
• Tank Interaction (3D analysis).
7
10
11
12
5
2
45
45
45
45 50
50
50
50
55
55
55
55
60
60
60
60
65
65
65
65
70
7070
70 70
70
70
75
75
75
75
75
75
80
80
80
80
80
80
80
80
80
80
80
80
80
80
85
8585
85 85
85
85 85
8585
7
10
11
12
5
2
495051
5253
53
53
54
54
54
55
5555
55
55
56
56
56
5656
57
57
57
57
57
58
58
58
58
58
59
59
59
59
59
60
60
6060
61
61
61
61
62
62
62
63
63
64
64
6566
67
68
Max Total Settlement: Case 1 – 80 mmCase 2 – 60 mm
Max Total Settlement: Case 1 – 71 mmCase 2 – 53 mm
Max Total Settlement: Case 1 – 76 mm
![Page 17: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/17.jpg)
Initial Tender Review – Mix Soil Option• Large QA component in design spec by GHD:
• Sampling and lab mix design to
determine strength properties;
• Additional CPTs;
• Trial sites (curing time);
• Core sampling of mixed soil;
• Lab testing during mixing;
• Column Penetration Test or Pull-out
resistance test.
• 1 m preload.
![Page 18: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/18.jpg)
Alternative Tender – Rigid Inclusions• Concrete Injected Columns (CIC);
• Controlled Modulus Columns (CMC);
• Controlled Stiffness Columns (CSC).
![Page 19: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/19.jpg)
![Page 20: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/20.jpg)
a) A “unit cell” axisymmetric model consisting of the CSC and its surrounding soils was analysed;
b) Based on the results from a), an equivalent set of soil properties was generated;
c) Using the result from b), a larger model was generated.
Plaxis 2D Unit Cell Model of CSC
![Page 21: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/21.jpg)
Plaxis 2D axisymmetric model (half model) with equivalent composite CSC/Soil Zone
![Page 22: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/22.jpg)
Tank Total Settlement mmSustained Constant Load – 120 kPa
Keller Prediction DP Prediction
Tank 1 (20 m dia) 74 62Tank 2 (32 m dia) 86 71
![Page 23: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/23.jpg)
QA During Construction• Proof rolling & Plate Load Testing rather than
density testing of working platform;
• Additional CPTs;
• Concrete testing (by others);
• Review of concrete takes & penetration depths;
• Plate load testing of installed columns
(similar to pile test)
![Page 24: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/24.jpg)
Plate Load Testing – Working Platform
![Page 25: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/25.jpg)
Installation of Trial Columns
![Page 26: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/26.jpg)
Installation of Trial Columns
![Page 27: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/27.jpg)
Production Rate of Columns
0
10
20
30
40
50
60
050
100150200250300350400450
5/18/201
8
5/20/201
8
5/22/201
8
5/24/201
8
5/26/201
8
5/28/201
8
5/30/201
8
6/1/20
18
6/3/20
18
6/5/20
18
6/7/20
18
Num
ber o
f Met
res
Noof
Pile
s per
day
Stats No. Metres per day
No. of Piles per Day
Range 72 – 400 8 – 53Average 264 35
![Page 28: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/28.jpg)
Column Load Testing (10 MPa – 7 days)
![Page 29: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/29.jpg)
Typical Column Load Test Result
050
100150200250300350400
0 5 10 15 20
Pile
Load
(kN)
Deflection (mm)
Column Diameter – 0.4 mColumn Depth – 7.5 m
Total No. of Column Tests – 9Range of Max Deflection – 2.1 to 28 mm
![Page 30: Ground Improvement Project – Large water storage tanks ...€¦ · Settlement (mm) 700 250 to 300 5 to 10 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space,](https://reader033.vdocuments.mx/reader033/viewer/2022060706/60722a1630bbf323c33a7441/html5/thumbnails/30.jpg)
Thanks to All Involved with this Project
310.5
66.25
487.5
41.75
Ground Test
Melbourne Lab
Newcastle Geo
Newcastle Lab