Green Line Project Vision
Green Line improves mobility choices
In its entirety, the Green Line will deliver high-quality transit service to Calgarians in north-central and southeast communities.
Green Line connects people and places
Construction of the Green Line is our next step towards completing Calgary’s transit network, as described in RouteAhead: A Strategic Plan for Transit in Calgary.
Green Line enhances quality of life
Along with the new MAX bus rapid transit lines, Calgarians will have fast, frequent and reliable transit service that strategically connects communities, employment hubs, and key destinations across the city.
Bow River
Bow River
Bow River
Elbow River
Elbo
w R
iver
Glenmore Reservoir
Brentwood
Saddletowne
Saddletowne Ci
Martindale Bv
Falshire Dr
44 Av NE
Whitehorn Dr
32 Av NE
Castleridge Bv
University
Ban� Trail
Lions ParkNorth
Hill
4 St NW
SAIT
Dalhousie
Crowfoot
Tuscany
28 Av N
40 Av N
64 Av N
96 Av N
Thorncli�e
Beddington
North Pointe
144 Av N
160 Av N
Aurora
Aero36 St N
E
Airport Terminal
88 Av NE
Country Hills Bv
128 Av NEStonegate
16 Av NEdmonto
n Tr
Russet R
d
19 St NE
Rundleside Dr
Rundle
Whitehorn
McKnight-Westwinds
Martindale
AlbertaChildren’sHospital
31 St NW
45 St SW
26 Av SW26 Av SW
33 Av SWRichmond Rd
Sarcee Rd
17 Av SW
69 St SW
Sirocc
o
Westbrook
ShaganappiPoint
Mount Royal University
Currie
MRU West
Victoria Park/Stampede
Erlton/Stampede
39 Av S
Chinook
Fairm
ount Dr
Deerfoot
Meadows
Riverglen D
r
Quarry Park Bv
Douglas Glen Bv
Douglas Glen
Quarry Park
South Hill
Ogden
Lynnwood/Millican
Southland
Anderson
Canyon Meadows
Fish Creek-Lacombe
Shawnessy
Silverado
210 Av S
Somerset-Bridlewood
Sunnyside
2 Ave SW
9 Ave N
High�eld
26 Av SE
4 St SE
Bridgeland/
Memorial
Barlow/
Max Bell
Franklin
Zoo
Marlborough
Prestwick
Auburn Bay/Mahogany
Seton
70 St SE
East Hills
61 St SE
44 St SE
36 St SE
28 St SE
19 St SE
12 St SE
33 St SE
6 St SE
Shepard
McKenzie Towne
South Hospital
Centre St S
54 Av SW
Elbow Dr
Heritage
90 Av SW
SouthlandLeisure Centre
Oakridge
Braeside Dr
Woodview Dr
Woodpark Bv
Rockyview Hospital
Heritage Park
Sunalta DowntownWest/Kerby
Foothills MedicalCentre
Ramsay/Inglewood
Northland
Edgemont
Sherwood
Sage Hill
144 Av NW
61 St SW
53 St SW
45 St SW
37 St SW
24 St SW
Bridleridge Wy
James McKevitt Rd
Shawbrooke Dr
Shawinigan Dr
26 Av NE
Rundlehorn Dr
Marbank Dr
Memorial Dr
8 Av SE
Erin Woods N
Erin Woods S
50 Av SE
61 Av SE
72 Av SE
86 Av SE
94 Av SE
106 Av SE
114 Av SE
Canada Olympic Park
14 St NW
19 St NW
Crowchild Tr
29 St NW
Point Dr
46 St NWHome Rd
Bowwood Dr
63 St NW70 St N
W
77 St NWBowfort Rd
17 Av/52 St S
E
N
Future Rapid Transit Network
R Red LineTuscany – 210 Av S
G Green Line160 Av N – Seton
B Blue LineStonegate – 69 St. S.W.
MAX
MP MAX PurpleEast Hills – City Centre
MO MAX OrangeBrentwood – Saddletowne
MY MAX YellowWoodpark Bv – City Centre
Future Rapid Transit ProjectsAirport Link, Shaganappi Tr, 52 St E, 162 Av S, Bowness Rd
MT MAX TealWestbrook – Douglas Glen
CTrain
B
B
R
R
G
G
MO
MO
MT
MT
MY
MP
19-0001409
Green Line serves the mobility needs of Calgarians
INGLEWOOD/RAMSAY
26 AVENUE SE
HIGHFIELD
LYNNWOOD/MILLICAN
OGDEN
SOUTH HILL
QUARRY PARK
DOUGLAS GLEN
SHEPARD
PRESTWICK
McKENZIE TOWNE
AUBURN BAY/MAHOGANY
HOSPITAL
SETON
144 AVENUE N
160 AVENUE N
16 AVENUE N
28 AVENUE N
McKNIGHT BOULEVARD
64 AVENUE N
BEDDINGTON
96 AVENUE N
NORTH POINTE
40 AVENUE N
2 AVENUE SW
7 AVENUE SW
CENTRE STREET S
4 STREET SE
INGLEWOOD/RAMSAY
26 AVENUE SE
HIGHFIELD
LYNNWOOD/MILLICAN
OGDEN
SOUTH HILL
QUARRY PARK
DOUGLAS GLEN
SHEPARD
PRESTWICK
McKENZIE TOWNE
AUBURN BAY/MAHOGANY
HOSPITAL
SETON
144 AVENUE N
160 AVENUE N
16 AVENUE N
28 AVENUE N
McKNIGHT BOULEVARD
64 AVENUE N
BEDDINGTON
96 AVENUE N
NORTH POINTE
40 AVENUE N
2 AVENUE SW
7 AVENUE SW
CENTRE STREET S
4 STREET SE
STA
GE
1
N
Evaluating options for a updated Stage 1The Green Line team undertook a planning process to evaluate and identify an updated Stage 1 alignment that can be built within our budget of $4.9 billion, minimizes project risks, and helps achieve the project vision.
To do this, the team reviewed the whole Council Approved Stage 1 alignment from 16 Avenue N to Shepard to �nd cost reductions.
Stage 1 Evaluation
Goal: Review Stage 1 from 16 Avenue N to Shepard focused on reducing risk, controlling cost and improving customer experience while respecting the community the project is moving through.
Options evaluated for Stage 1 include the following in the Centre City:
• Shortening the length of the tunnel
• Reducing the number of underground stations
• Surface running trains on Centre Street N, and along 10, 11 and 12 Avenue S
• Shifting the underground alignment from 2 Street S.W. to 1 Street S.W.
• Elevated track through the Centre City
• Bridge over Bow River
• Value Engineering south of 4 Street S.E.
Outside of the Centre City, the complete Stage 1 alignment was evaluated from a value engineering perspective to reduce cost and deliver greater value.
Six evaluation criteria
Updated Stage 1 Option
EnvironmentalCost and value Connecting people to places
Improves mobility
Risk and constructability
Urban and regional development
9 AVENUE N
RAMSAY/INGLEWOOD
26 AVENUE SE
HIGHFIELD
OGDEN
SOUTH HILL
QUARRY PARK
DOUGLAS GLEN
SHEPARD
2 AVENUE SW
7 AVENUE SW
CENTRE STREET S
4 STREET SE
26 AVENUE SE
HIGHFIELD
LYNNWOOD/MILLICAN
OGDEN
SOUTH HILL
QUARRY PARK
DOUGLAS GLEN
SHEPARD
2 AVENUE SW
7 AVENUE SW
CENTRE STREET S
4 STREET SE
RAMSAY/INGLEWOOD
16 AVENUE N16 AVENUE N 16 AVENUE N
NORTH POINTE
16 AVENUE N
NORTH POINTE
9 AVENUE N9 AVENUE N
6 AVENUE S2 AVENUE S
144 AVENUE N
160 AVENUE N
28 AVENUE N
McKNIGHT BOULEVARD
64 AVENUE N
BEDDINGTON
96 AVENUE N
40 AVENUE N
144 AVENUE N
160 AVENUE N
28 AVENUE N
McKNIGHT BOULEVARD
64 AVENUE N
BEDDINGTON
96 AVENUE N
40 AVENUE N
Maintenance and Storage Facility
N
This alignment can be constructed within budget, reduces construction risks, and delivers best value to Calgarians while achieving the Green Line Vision.
The updated Stage 1 alignment includes the following changes compared to the 2017 approved alignment:
• North Central BRT with MAX level service upgrades
• Surface-running LRT on Centre Street N
• Bridge over the Bow River
• 2.4 km of tunnel and three underground stations in the Centre City
• Shallower tunnel in Beltline on 11 Avenue S
From Elbow River to Shepard, there are no alignment changes from the 2017 Council approved alignment.
Segm
ent 1
Segm
ent 2
Updated Stage 1 alignment