grand rapids public utilities commission’s hydro turbine ...1569e8a2-964f-47b3... · utilities...

76
Grand Rapids Public Utilities Commission’s hydro turbine generator December 7 2012 Jeremy Goodell, Jeffrey Lange, Tom Newville, Forrest Semmler Final Technical Report Iron Range Engineering Fall 2012

Upload: vannga

Post on 26-Apr-2018

220 views

Category:

Documents


2 download

TRANSCRIPT

Grand Rapids Public

Utilities Commission’s

hydro turbine generator

December 7

2012 Jeremy Goodell, Jeffrey Lange, Tom Newville, Forrest Semmler

Final Technical Report

Iron Range

Engineering Fall 2012

a

Contents Executive Summary ........................................................................................................................ 1

Scoping ........................................................................................................................................... 2

Company Background ................................................................................................................. 2

Company Contacts ...................................................................................................................... 2

Project Description ...................................................................................................................... 2

Expectations ................................................................................................................................ 2

Project Approaches ..................................................................................................................... 3

Engineering Standards................................................................................................................. 4

Economic Analysis ...................................................................................................................... 4

Environmental Concerns ............................................................................................................. 4

Regulations .................................................................................................................................. 4

Project Deliverables .................................................................................................................... 4

Budget ......................................................................................................................................... 5

Project Timeline .......................................................................................................................... 5

Other considerations .................................................................................................................... 5

Confidential Information/ Intellectual Property .......................................................................... 5

Background ..................................................................................................................................... 6

Hydroelectric Power Plant Operations ........................................................................................ 6

Available Power .......................................................................................................................... 6

Hydro Turbine Generator Systems .............................................................................................. 7

Hydro-Turbine Generators .......................................................................................................... 8

Hydro-Turbine Runners .......................................................................................................... 8

Specific Types of Turbines ..................................................................................................... 8

Maintenance .......................................................................................................................... 10

Wastewater Treatment Plant Effluent Pipe ............................................................................... 10

Reusing the existing pipe ...................................................................................................... 11

Relining the pipe ................................................................................................................... 11

Slipping the Existing Pipe ..................................................................................................... 11

Installing a New Pipe ............................................................................................................ 11

b

Water and sewer pipes – cast iron and polymeric type pipes ............................................... 12

Valves & Governing System ..................................................................................................... 12

Turbine Governor.................................................................................................................. 12

Wicket Gate .......................................................................................................................... 13

Needle Valve ......................................................................................................................... 13

Inlet Valve ............................................................................................................................. 14

Building Materials ..................................................................................................................... 14

Under Ground ....................................................................................................................... 14

Above Ground ....................................................................................................................... 15

Connecting the Generation Site to the Electrical Grid Network ............................................... 16

Electrical Switchgear................................................................................................................. 17

Circuit Breakers .................................................................................................................... 17

Protective Relays .................................................................................................................. 18

Transformers ............................................................................................................................. 18

Fire and Electrical Codes .......................................................................................................... 19

Environmental impact statements ............................................................................................. 19

An EIS typically has four sections: ....................................................................................... 19

Environmental Regulations ....................................................................................................... 19

Wastewater Regulations ............................................................................................................ 20

Zoning and Building Codes....................................................................................................... 21

Selling Electrical Power ............................................................................................................ 21

Financing ................................................................................................................................... 22

Grants .................................................................................................................................... 22

Loans ..................................................................................................................................... 23

Available resources ............................................................................................................... 23

Options .......................................................................................................................................... 23

Summary ................................................................................................................................... 23

Turbines ..................................................................................................................................... 23

Pipe Construction ...................................................................................................................... 24

Rerouting the existing pipe ....................................................................................................... 25

Building ..................................................................................................................................... 26

c

Grid Connections....................................................................................................................... 27

Operations ................................................................................................................................. 28

Flow regulation ..................................................................................................................... 28

Operation organization: ............................................................................................................. 29

Financing ................................................................................................................................... 30

Experiment .................................................................................................................................... 32

Summary ................................................................................................................................... 32

Introduction ............................................................................................................................... 32

Apparatus .................................................................................................................................. 33

Mathematical Model ................................................................................................................. 35

Procedure ................................................................................................................................... 35

Results ....................................................................................................................................... 35

Statistical Analysis .................................................................................................................... 36

Conclusion ................................................................................................................................. 37

Recommendations ..................................................................................................................... 37

Economic Analysis ....................................................................................................................... 38

Introduction ............................................................................................................................... 38

Client inputs .............................................................................................................................. 38

Calculations ............................................................................................................................... 38

Costs .......................................................................................................................................... 38

Revenues ................................................................................................................................... 38

Economic analysis results ......................................................................................................... 38

Conclusion ................................................................................................................................. 39

References ................................................................................................................................. 39

Physical Model.............................................................................................................................. 39

Math model ................................................................................................................................... 41

Assumptions .............................................................................................................................. 41

Description of how the math model was developed and executed ........................................... 41

Equations and Calculations ................................................................................................... 41

Evaluation Process .................................................................................................................... 44

Future Steps ............................................................................................................................... 44

d

Validation and verification ........................................................................................................... 44

Team Validation and Verification – Physical Apparatus .......................................................... 44

Team Validation and Verification – Economic Analysis.......................................................... 45

Professional Validation and Verification – Physical Apparatus ............................................... 45

Professional Validation and Verification – Economic Analysis ............................................... 45

Reliability ...................................................................................................................................... 45

Powerhouse Equipment Package .............................................................................................. 45

Polyethylene Pipe ...................................................................................................................... 46

Sustainability analysis ................................................................................................................... 47

Contextualization .......................................................................................................................... 48

Multi-disciplinary aspects of the project ................................................................................... 48

Mechanical engineers/Structural engineers .......................................................................... 48

Electrical engineers ............................................................................................................... 48

Environmental engineers ...................................................................................................... 48

Administration ...................................................................................................................... 49

Project Manager .................................................................................................................... 49

Contractors/builders .............................................................................................................. 49

Hydro dam operators............................................................................................................. 49

Wastewater treatment plant operators ................................................................................... 49

Contextual aspects of the project .............................................................................................. 49

Health .................................................................................................................................... 49

Safety .................................................................................................................................... 49

Environment .......................................................................................................................... 50

Global .................................................................................................................................... 50

Society................................................................................................................................... 50

Ethical, Moral, and Legal...................................................................................................... 50

Economic and Manufacturing ................................................................................................... 50

Engineering, Creativity, & Ingenuity ........................................................................................ 50

Future work ................................................................................................................................... 51

Conclusion .................................................................................................................................... 51

Bibliography ................................................................................................................................. 52

e

Appendix A ...................................................................................................................................... i

List of acronyms used .................................................................................................................. i

Appendix B ..................................................................................................................................... ii

Creation of the turbine used in the experiment ........................................................................... ii

Appendix C .................................................................................................................................... ix

Pictures of the economic analysis .............................................................................................. ix

Appendix D .................................................................................................................................. xiii

Pictures of the GRPUC site ...................................................................................................... xiii

1

Executive Summary The Grand Rapids Public Utilities Commission (GRPUC) asked a team of students from

Iron Range Engineering (IRE) to do a feasibility study on the possibility of placing a

hydroelectric turbine at the outlet of their wastewater treatment plant. The team scoped out the

project by determining the clients expectations, decided what could be accomplished for the

project, and researched any governmental regulations applicable to the project. Research was

done to fully understand all aspects of the project.

Options were created for the effluent pipe, project financing, hydro turbines, turbine

generator building, electrical components, and operations. These options were compared to each

other with weighted charts and using the Pugh method. An experiment was conducted to prove

the theory that different pipe sizes would produce different headlosses which would directly

affect the power output of the system. The team looked into engineering standards and

regulations required to be followed to complete the project.

The team created a computer simulation in Excel from their math model to determine the

power output of the system. This simulation was used for the economic feasibility of the project

by determining the total power output of the turbine generator. The total revenue produced by the

generator was less than the desired 5% internal rate of return (IRR) specified by the client, but it

would produce about 2% IRR for them. A physical model was created to verify the results found

in the original options, and it was found that slipping the pipe might be more difficult than was

originally planned. The team also looked at the reliability and contextual issues related to this

project, and found that the system would be very reliable with few problems.

It is the team’s recommendation to move forward with creating a hydro turbine

generation facility located at the base of the wastewater treatment plant effluent pipe. The

original concrete pipe should be slipped with a 30 inch polyethylene pipe up to the 45 degree

elbows located near the treatment plant. The pipe should then be continued to the plant with a

new trenched route directly to the effluent pipe valve house to reduce costs and increase the

lifespan of the system.

Financing will be decided by the client, but it is recommended that a combination of

loans, grants, and budgeted funds be used to fund the project. Conservation project budgeted

funds and grants should be used as much as possible which will reduce the client’s initial

financial burden. It is recommended that the system be set up for 70kW and be run for 12 hours

a day during the peak energy cost times and connected to the local GRPUC electrical grid so that

the most value can be gained from the stored energy of the water. Finally it is recommended that

a concrete block building be constructed to house the power plant near the Mississippi River due

to its aesthetics and long lifespan.

2

Figure 1 This is a picture of the holding ponds

where the water is stored before being

discharged into the river.

Scoping

Company Background GRPUC is responsible for the distribution of electricity, the treatment and distribution of

water, and the collection and treatment of wastewater for the city of Grand Rapids.

Company Contacts The group’s project contacts were, Glen Hodgson (GRPUC board member), Jim

Ackerman (wastewater treatment plant manager), and Anthony Ward (GRPUC general

manager).

Project Description GRPUC owns and operates the Grand Rapids wastewater treatment plant. The plant

treats approximately seven million gallons of wastewater per day. Discharge from the plant

travels through a pipe that has a vertical height difference of approximately 50 feet between the

holding ponds (Figure 1) and the discharge into the Mississippi River (Figure 2). The project

analyzed the technical and financial feasibility of capturing the energy of the water flowing

through the effluent pipe and converting that energy to electrical power. The team researched an

environmental impact statement and discussed the governmental and electric utilities regulations.

Expectations

GRPUC expected the IRE hydro turbine generator team to do a feasibility study on the

generation of power from the current effluence of cleaned wastewater. The team was also

expected to keep in contact with the clients and to keep them updated as to how the project was

going.

Figure 2 This picture shows the effluent pipe

discharging the water from the plant.

3

Project Approaches The main concerns for the hydroelectric generator to be used for this project can be

broken up into four main areas. The feasibility of using the existing effluent pipe will be

explored. Research will be done to find the best turbine and generator for the project. Electrical

equipment such as switchgear and transformers will be investigated. Finally, the electrical utility

company that the power will be connected to will be chosen.

The current effluent pipe is a 36 inch sewer pipe that carries the discharge of the

wastewater treatment plant to the river. This pipe is at atmospheric pressure, and will need to

hold the pressure of the water head if it is to be used for the project. A study will be completed to

understand if the existing pipe will be able to hold the pressure of the water, or if it would need

upgrades or replacement. A small section of pipe will have to be added to house the turbine.

A hydraulic turbine will remove the energy from the water traveling through the effluent

pipe from the holding ponds to the Mississippi River. There are several different types of water

turbines to be considered for this project including whether to use a single turbine or multiple

turbines in the system. Considerations for what type of turbine to be used include:

The pressure head of the water

The flow rate of the water

The location of the turbine

Total size of the system

Since water turbines generally rotate at slower speeds than gas type turbines, the

generator design will be determined by the turbine selection.

A generator converts the mechanical energy of the turbine into electrical energy. The

amount of energy that can be removed from the water will determine what size of generator will

be used for the project. The amount of energy available may fluctuate; this is due to operational

flexibility and seasonal water requirements. Generator voltage output levels will be researched.

As operating voltages are generally lower than the electrical grid they are connected to, a

transformer will be required to raise the voltage to grid level.

Switchgear and transformers are pieces of electrical equipment that will be used to

transfer the electrical power from the generator to the electrical grid. Switchgears are protective

devices similar to circuit breakers that will be used to isolate the generation site from the grid in

case of an electrical fault or down time. A large power transformer will be used to raise the

system voltage from the generator to the specific electrical grid voltage. This voltage is specified

by the electrical utility company that owns the cables to which the generated power will be

connected.

4

There are three main electrical utility companies within close vicinity of the site to which

the generator could be connected:

Minnesota Power (MP)

Lake Country Power

GRPUC

Engineering Standards The engineering standards this project used include building codes, electrical codes, pipe

codes, environmental regulations and zoning requirements. A separate standards document was

completed for the project.

Economic Analysis Part of the team’s research answered if this project is economically feasible for GRPUC.

The team’s plan was to produce an analysis of the project; this included: cost benefit ratio, IRR,

net present value (NPV), and payback period. An electrical generation plan and schedule was

also produced since electricity can generally be sold for a higher price during daytime hours.

Environmental Concerns New construction requires some form of an environmental impact statement. The

project’s impact statement will need to contain special considerations due to its close vicinity to

the Mississippi River. A short summary of an impact statement was included in the background

section. Since the end product may include fluctuations in the effluence of the wastewater

treatment plant, special attention was be paid to the environmental regulations related to this

impact statement.

Regulations Several government and electrical utility regulations had to be followed; the team

researched and mapped out the processes to be followed to complete the project. All processes

were described in detail to avoid possible project stoppage.

Project Deliverables The project deliverables to the client included a document with:

Preliminary design of the hydroelectric equipment and piping, including ideas for the

turbine building and connections to the electrical grid

Analysis of operational flexibility allowing for the generation of electrical power during

peak hours

Engineering economics analysis including potential funding, revenue, and cost-benefit

analysis

Analysis of potential regulatory constraints (environmental and business)

Recommendations for the potential project implementation

5

Budget IRE supplied the funds needed for the feasibility study, including transportation back and

forth to Grand Rapids for client meetings, the project experiment, general office equipment, and

supplies.

A budget for the client was proposed in the economic analysis section.

Project Timeline The first meeting with the client was on the 5

th of September. The next meeting was

planned for Thursday the 20th

of September. It was determined that each following meeting

would be scheduled at the end of a meeting. The client was emailed weekly updates as needed

by the team communicator. The following Gantt chart shows a very simplified view of the

teams’ deliverables for the project. A more detailed chart was created following a formal

Microsoft Project training seminar.

Other considerations GRPUC desired a feasibility study to be the primary direction for this semester’s project.

They would also like the design of the equipment and buildings for full production, which will

need to be done at a later date or during a second semester. All of the teams work was done so

that future work could be easily added. Future work could include detailed design of the

building, turbine, generator, and the controls needed for the system. Future work could also

include using this project to add hydroelectric generators to other public utilities sites.

Confidential Information/ Intellectual Property Since GRPUC is a public entity, all data for this project is open to the public and not

confidential. The team understood that any designs made during this project belong solely to

GRPUC.

Figure 3 A simple timeline showing some of the team’s outcomes, when they would be completed,

and who would be the lead author(s).

6

Background

Hydroelectric Power Plant Operations Hydroelectric power plants are operated using electronic control systems and mechanical

flow controls. There are several hydroelectric dams in Minnesota that are run by MP [1].

Currently MP controls all of their hydroelectric dams remotely from a central control station.

The operations at a small scale plant require very little oversight with minimal help from outside

agencies. The current possibilities are to give full operational control over to MP and pay them

for the service, or to give the operational control over to the current wastewater treatment

operations controller and receive help from MP only if something needs maintenance.

Operational costs could be reduced by using the current operator for the wastewater treatment

plant. The job would not vary much from the standard operations that the plant operator would

take [2], and the new technology introduced could make the operators’ job easier.

Usually the hydroelectric station operator controls the flow valves, allowing more or less

water to flow through the pipes as they watch for problems in the system. The operator also

keeps the system maintained, lubricating the system and doing minor repairs [3].

Available Power A major goal of the team is to determine the available energy output of the system which will

directly affect the financial feasibility of the project. The potential energy of the water in the

wastewater treatment ponds is transformed into kinetic energy as it enters the pipe and gains

velocity. The velocity of the water forces the turbine to turn creating mechanical energy that

turns a shaft, which turns a generator and creates electricity. Below is the equation for power

available from a stream of water:

Equation 1 Power available in a stream of water.

Where:

Power (J/s or watts)

Turbine Efficiency

Density of water (kg/m³)

Acceleration of gravity (9.81 m/s²)

Head (m)

= Flow rate (m³/s)

7

For still water, head is the difference in height between the inlet and outlet surfaces.

Moving water has an additional component added to account for the kinetic energy of the flow.

The total head equals the pressure head plus velocity head.

Hydro Turbine Generator Systems A dam stores water upstream in a reservoir. Near the bottom of the dam wall is a water

intake, which is called a penstock. Usually a trash gate is located at the intake of the penstock to

keep large debris out of the turbine. Gravity causes the water to fall through the penstock inside

the dam. A turbine is located at the end of the penstock which is turned by the moving water.

The shaft from the turbine is connected to the generator, which produces the power. Power lines

are connected to the generator, and carry the electricity to the electrical grid. The water continues

past the turbine through the tailrace into the river past the dam [4].

Figure 4 Hydro plant construction, showing all parts including the generator

A hydraulic turbine converts the energy of flowing water into mechanical energy. A

hydroelectric generator converts this mechanical energy into electricity. In a large generator,

electromagnets are made by circulating direct current through loops of wire wound around stacks

of magnetic steel laminations. These are called field poles, and are mounted on the perimeter of

the rotor. The rotor is attached to the turbine shaft, and rotates at a fixed speed. When the rotor

turns, it causes the field poles (the electromagnets) to move past the conductors mounted in the

stator. This, in turn, causes electricity to flow and a voltage to develop at the generator output

terminals [5].

Tailrace

8

Hydro-Turbine Generators

Hydro-Turbine Runners

Flowing water is directed onto the blades

of a turbine runner, creating a force on the blades.

This force on the blades creates motion, which is

force acting through a distance, also known as

work. This work turns a shaft that is connected to

the generator which converts the rotational energy

of the turbine into electrical power. The blades in

the turbine can come in many shapes and sizes.

The variables that determine the shape of the

blades are the type of turbine, available space, type

of impeller, and the water pressure. There are two

main types of turbine runners: impulse and

reaction.

Impulse turbines work by water being jetted through a nozzle onto the blades that make

up the wheel of the turbine. When the water hits the blades of the turbine wheel it is deflected in

a different direction. Most of the energy in the water is transferred to the blades causing them to

turn. Impulse turbines operate without any change in pressure at the blades and do not require

any housing. They are commonly used in applications where plenty of pressure head is available

(more than 300 meters) [6] [7].

Reaction turbines work by a propeller being spun by the passing water. They must be

completely contained in a housing or completely submerged in water. The water passing through

the blades has a pressure drop. Reaction turbines are commonly used in applications where lower

pressure head is available (less than 100 meters) [6] [7].

Specific Types of Turbines

There are many types of turbines; this report will focus on the three main types, the

Pelton, Francis, and Kaplan.

Pelton Wheel

The Pelton wheel is a water impulse turbine. It was invented by Lester Pelton in the

1870s. The design is efficient because the water is directed into the cup shaped blades called

buckets capturing all the water and the force associated with it. Other impulse type turbines

deflect a portion of the water utilizing a fraction of the force. For maximum power and

efficiency, the turbine system is designed such that the water-jet velocity is twice the velocity of

the bucket. This allows the buckets to be emptied at the same rate they are being filled. Many of

the turbines are made with two buckets side by side. This is done to keep the wheel better

balanced which causes less friction in the shaft of the turbine. Because the design depends on

Figure 5 Hydro turbine with important parts

9

Figure 7 Francis Turbine; guide vanes guide water through

this reaction turbine.

impulse momentum, the turbine works

best in applications with high head (more

than 300 meters). This increases the

velocity coming out of the nozzle

creating more force on the buckets.

The advantages of the Pelton

turbine are its simple design, low cost,

small housing, and its ability to withstand

variations in the flow of the water.

Francis Turbine

Francis turbines are the

most used water turbines today.

The Francis turbine is a reaction

type water turbine that was

developed by James B. Francis. It

is a turbine that combines radial

and axial flow concepts. Being a

reaction type turbine the Francis

operates by a change in pressure.

This means that the turbine must

have a sealed housing to capture

all the energy from the water. The

inlet is spiral shaped; this shape

causes the water to flow into the

guide vanes, which direct the water

tangentially to the turbine wheel,

known as a runner. The radial

flow acts on the runner's vanes, causing the runner to spin. As the water moves through the

runner, its spinning radius decreases, further acting on the runner [6] [7]. The turbines are almost

always mounted with the shaft vertical to keep water away from the generator and also to

facilitate access to it. The guide vanes (or wicket gate) may be adjustable to allow efficient

turbine operation for a range of water flow conditions.

Advantages of a Francis turbine are high efficiency, ability to be designed for a wide

range of heads and flows, and the ability to be used as a pump if reversed.

Figure 6 Pelton turbine, the cup shaped buckets catch

the water for this impeller turbine.

10

Kaplan Turbines The Kaplan turbine is a propeller-

type water turbine which has adjustable

blades. It was developed in 1913 by Viktor

Kaplan. The Kaplan turbine is an

improvement of the Francis turbine and

operates in the same manner. The Kaplan

turbine combines adjustable blades with

adjustable wicket gates to achieve

efficiencies over a wide range of flows and

heads.

Kaplan turbines are used around the

world and are common in places were low

head and high flow rates are found. There

are some micro Kaplan turbines that can

operate with as little as two feet of head [6]

[7].

The advantages of a Kaplan turbine are its ability to operate in high flow rate low head

conditions, and its ability to handle more sand and debris than other turbines.

Micro Turbines

Micro turbines are smaller versions of the turbines mentioned above. They can have

outputs of up to 100 kW of electricity. The same rules apply as far as head and flow for the

different types.

Maintenance

Some things that cause problems with turbines are: cavitation, cracking, and loss of

material from silt in the water acting like sand paper. Most of these problems can be fixed by

welding new material in the damaged spots. A stainless steel welding rod is generally used

because of its hardness. Other parts that should be watched for maintenance issues include

bearings, packing box and shaft sleeves, servomotors, cooling systems for the bearings and

generator coils, seal rings, wicket gate linkage, and all surfaces.

Turbines are designed to run for decades with very little maintenance; overhaul intervals

are on the order of several years. Maintenance of the runners and parts exposed to water include

removal, inspection, and repair of worn parts [6] [7].

Wastewater Treatment Plant Effluent Pipe The wastewater treatment plant currently utilizes a ductile iron, cement lined, 36 inch

sewer pipe to direct clean wastewater into the Mississippi River. Several options for pipes to be

used are discussed below including reuse of the pipe, relining the pipe, slipping the existing pipe,

or installing an entirely new pipe.

Figure 8 Kaplan turbine has adjustable blades

11

Reusing the existing pipe

The existing downfall pipe has the following specifications:

36 inch diameter

ductile iron pipe construction

class 350

cement lined (interior)

cement coated (exterior)

90 psi maximum working pressure

150 psi maximum rating

The effluent pipe will contain a maximum of 50 feet of vertical water head and must

contain this pressure along with pressure surges caused by generator power transients and valve

shutting. Four manholes must be sealed off to completely contain the water. Additionally, several

smaller pipes currently draining into the manhole junctions need to be sealed off and rerouted.

Relining the pipe

The pipe may be relined if the current condition of the interior pipe lining is considered

unsatisfactory. This will not repair any defects in the ductile iron pipe, nor repair the exterior

coating of the pipe if damaged. This option will only be pursued if the pipe is to be reused for the

hydro generation project.

There are several methods of relining the inside of a concrete sewer pipe. One method is

to spray an epoxy resin onto the interior of the pipe. Any gaps or cracks in the cement coating

will be repaired using this method. This method is not effective if the walls have broken down

significantly.

Woven polyester felt can be installed on the pipe walls. This method is used at locations

with early technology brick-sided sewer mains and is suitable for cement lined pipe. The pipe is

first cleaned and scoped with a video camera. The polyester is saturated with a thermosetting

resin, installed, and inserted into the pipe. The resin is then cured either with ambient air, hot

water, or ultraviolet light. This creates a hardy secondary wall impervious to water and air

protecting the ductile iron.

Slipping the Existing Pipe

A smaller pipe can be “slipped” inside the existing pipe to be used as the downfall pipe.

This pipe is usually constructed of polyethylene, and can be slipped the entire length of the

existing pipe. Certain turn radii can be accomplished, although angled junctions may have to be

installed at tight corners. The area between the slipped pipe and the existing pipe can then be

used for discharge of other water sources such as drain runoff.

Installing a New Pipe

A new pipe can either be installed by digging a trench or by using a horizontal drilling

machine. The major options for underground water pipe are described below.

12

Water and sewer pipes – cast iron and polymeric type pipes

Ductile iron is a form of cast iron whose major property includes nodular graphite

inclusions. These nodules are introduced into the iron by addition of spherical nodulizing

elements, instead of flakes, such as magnesium. This minimizes cracking of the iron creating a

more flexible and elastic structure. Ductile iron is formed in the shape of a pipe and is usually

lined internally and externally with some type of liner.

Ductile iron is only somewhat resistant to corrosion from potable water and sewage, and

is generally not used unprotected within these types of systems. Cement mortar is commonly

used to line the interior of the pipe which reduces corrosion of the iron. Polyurethane coating is

also used for pipes carrying water and inhibits corrosion of the pipe.

A polyethylene sleeve is placed on a large majority of ductile iron pipes. The sleeve

loosely fits over the exterior of the pipe and reduces corrosion by a number of factors. It

physically separates the iron from the soil preventing direct galvanic corrosion. Although it

provides a relatively impermeable layer to ground water, some is allowed to collect between the

sleeve and the pipe. This creates a low oxygen environment, which allows for a small amount of

corrosion to occur evenly over the length of the pipe [8].

Polymeric materials consist of polyvinyl chloride (PVC), high density polyethylene

(HDPE), low density polyethylene (LDPE), and polypropylene. All are a chemical compound or

mixture of compounds consisting of repeating structural units created through a process of

polymerization. These compounds are very light and flexible making them easy to work with.

Polymers are generally corrosion resistant, and resist degradation when protected from

UV rays and heat. Pipes of these compounds can be constructed in various diameters, wall

thicknesses, and lengths. Internal pressure may be limited due to pipe wall strength and fatigue

factors [9].

Valves & Governing System Turbine Governor

The governor uses either mechanical or electronic feedback to sense the speed of the

turbine. Proportional or directional valves controlled by the governor operate cylinders that open

and close wicket gates or needle valves to adjust the flow of water to the turbine in order to

maintain a constant turbine speed. Hydroelectric turbines rotate at relatively low speeds

compared to steam turbines, with larger hydroelectric turbines rotating at 35-75 rpm, and smaller

ones as fast as 150 rpm. The large turbine diameter combined with the massive inertia of the

water flowing through it makes precise control of rotational speed a critical concern [10] [11].

If governor proportional or directional valves do not respond instantly and accurately to

fluctuating generator loads, lagging of the wicket or needle valve position can occur. This results

in an oscillating condition whereby the turbine is constantly speeding up and slowing down. This

inefficient power production, although difficult to quantify, leads to loss in revenue for the

13

utility. Furthermore, if this oscillation exceeds the maximum allowable frequency, then the

turbine must be shut down, resulting in temporary loss of generating production.

As with steam turbines, malfunctioning of the governor could result in a dangerous

runaway (over-speed) condition. Runaway speed is the speed at which the turbine exceeds its

designed maximum rotational speed. When this occurs it is possible for the turbine to

disintegrate due to massive centrifugal forces.

Wicket Gate

These are angularly adjustable,

streamlined components that direct and

control (throttle) water flow to the runner

in reaction-type hydroelectric turbines.

They are regulated by the governor via

mechanical-hydraulic or electro-hydraulic

controls [12].

Needle Valve

The needle valve is used to regulate the

flow of water to the runner in impulse-type

hydroelectric turbines, and is regulated by the

governor via mechanical-hydraulic or electro-

hydraulic controls [12].

Figure 9 Wicket Gate, acts as the fine tuning valve for

reaction turbines.

Figure 10 Needle Valve, acts as the fine tuning

valve for the turbine.

14

Inlet Valve

The inlet valve is located upstream of the turbine and is used to cut off the flow of water

in the event of an emergency or for maintenance. These valves are often spherical or butterfly

valves, and are usually operated by hydraulic power units [12] [13].

Building Materials

Under Ground

Building materials need to be able to withstand the test of time, especially ones that are

put in the ground. This is difficult for many types of material due to the moist environment and

lack of air. Wood has a tendency to rot and be eaten by insects. Steel loses its strength because of

rust and deterioration. The building materials that are commonly used for underground

construction are concrete and concrete blocks.

Formed Concrete

Concrete walls have many advantages for

underground construction. The solid walls are more

durable than other materials and water problems are

greatly reduced. Assembly time is much shorter

with poured walls which saves money by reducing

labor cost. Formed walls have some disadvantages

also. The forms used in construction are heavy and

can require a crane to put them in place. Another

disadvantage is concrete walls can crack. The use of

Figure 13 Formed concrete, while forms are

being removed

Figure 12 Butterfly inlet valve, controls the main

flow.

Figure 11 Radial inlet gate, the main inlet and

control valve on a dam.

15

horizontal and vertical reinforcements can reduce cracks and make the wall stronger. Many of

the cracks are superficial and do not go all the way through the wall. Cracks that do go all the

way through can be repaired with sealants made for this purpose. In 2012, the average cost of

constructing a concrete wall is approximately $4.35 per square foot [14].

Concrete Block

Concrete block construction has many of the

same advantages as poured concrete. It is good at

repelling water and has a long life span. Another

advantage of block is that they are light enough for a

person to lift. This makes a project easier to complete if a

crane is not available. Block walls can be made to have

close to the same strength as a poured wall if

reinforcement is used. This is done by placing rebar

down through the holes of the block and filling the holes

with concrete. There is also a metal mesh available that

can be placed on the joints where the mortar is placed to

hold the blocks together. These techniques combined can

give a block wall the strength of a poured wall but add

additional cost to the project. A disadvantage of a block wall is there are many joints. These

joints are weak spots that can deteriorate and let water leak through the wall. In 2012, the

average cost to install concrete block walls ranged from $5.41 to $7.17 per square foot [15].

Above Ground

Construction above ground will have many of the same elements as underground.

Concrete walls and block can be considered along with wood and steel for construction

materials. Above ground construction needs to take into consideration factors like weather,

appearance, usability, safety, and security.

Wood

Wood construction is the most common type of

construction today. Advantages of using wood include:

wood is a renewable resource, can be very energy efficient,

and is a common method of construction. Also many

people are familiar with working with wood and have the

tools needed. Disadvantages of wood are: it can have

natural flaws like knots that can reduce its strength, it can

decay if not treated, it is susceptible to insects, and it is

combustible. The average cost to build a wood frame shed is

$22.85 per square foot [16].

Figure 3 wood construction

Figure 14 Concrete block

Figure 15 Wood construction, the

most common type of construction

16

Steel

Steel frame construction is not as common as

wood but has some advantages. Steel is not combustible,

it is insect resistant, does not decay, and is very uniform

in strength. There are not as many contractors that work

with steel, so finding contractors is not as easy as with

wood. Disadvantages of steel are it is less energy

efficient, and it is susceptible to moisture because of

condensation. The average cost to build a steel frame

building is between $16.00 and $20.00 per square foot

[17].

Connecting the Generation Site to the Electrical Grid Network As shown in Figure 17, the United States and

Canada are split up into several regional grids. Each

region is directly connected via a grid network of

power distribution lines and generation facilities.

One region cannot connect directly to another region

as they are not in electrical phase with each other, so

a large phase-shifting transformer is placed at the

borders of each region to allow for power to flow

from one region to another.

An electrical grid network consists of

multiple electrical utilities with interconnections

between each utility. Each utility operates and

maintains their own network, but must maintain

considerations for neighboring utilities. For

example, a utility may operate at a lower voltage than its neighboring utility. To allow for

interconnection between the two utilities, a transformer must be placed at the interconnection

between the two utilities [18].

The facility at the wastewater treatment plant will generate electricity at approximately

2000 to 3000 volts. The electrical utilities in the surrounding area that the site could possibly

connect to are MP, Lake Country Power, and GRPUC.

MP owns a 115 kilovolt substation in southeast Grand Rapids. Power cables would need

to be run approximately 5000 feet between the generation site and the substation. Connection to

the substation could be made to the low or high voltage section of the substation.

Figure 17 Map of North American

electrical grid networks [19]

Figure 16 Steel Construction, stronger

and more resilient than wood, but is

not commonly used.

17

Lake Country Power owns a large electrical distribution network spanning much of

northeast Minnesota. This utility owns electrical power lines located near the wastewater

treatment plant which operate at 46 kilovolts.

GRPUC operates a 14 kilovolt electrical distribution network within the city limits of

Grand Rapids. Power lines from their network are located within 100 feet of the generation site,

making for a fairly easy connection to their grid.

Electrical Switchgear A variety of electrical switchgear is available on the market; this section will concentrate

on the switchgear required for the site.

Circuit Breakers

A main circuit breaker will be required to connect and disconnect the generator from the

electrical grid. For this project, medium voltage circuit breakers will be discussed. These circuit

breakers are constructed to operate at voltages from one to 72 kilovolts [19].

A circuit breaker serves several functions. It makes or breaks continuity between two

electrical circuits, it serves to protect equipment and personnel from electrical faults, and it

allows personnel to de-energize a piece of equipment for maintenance or other reasons.

There are several types of circuit breakers available, each with different features. Medium

voltage breakers can be classified into how the arc is extinguished within the circuit breaker:

Vacuum circuit breakers: These circuit breakers interrupt current by creating and

extinguishing the arc in a vacuum container. They are rated at up to approximately

35,000 volts and 3000 amps. They tend to have a longer life expectancy than air circuit

breakers due to reduced contact flashover [20].

Air circuit breakers: These circuit breakers extinguish the

electrical arc in an air filled environment. This type of circuit

breaker interrupts in air between two separable contacts with

the aid of magnetic blowout coils. When the circuit breaker

opens, the current carrying contacts separate and the arc is

drawn out horizontally and transferred to a set of arcing

contacts. Simultaneously, the blowout coil provides a

magnetic field to draw the arc upward into the arc chutes.

The arc accelerates upward into the arc chute where it is

extinguished [21].

SF6 Circuit Breakers: These circuit breakers use sulfur

hexafluoride (SF6) gas to extinguish the arc between the

current carrying contacts. The entire contact chamber is filled

with SF6 gas, and a blast of SF6 gas is blown between the

Figure 18 An example of a

medium voltage SF6 circuit

breaker [22]

18

contacts during opening operations. This gas has excellent dielectric and arc quenching

properties [22].

Protective Relays

In addition to circuit breakers, protective relays are installed at generation sites to protect

all electrical equipment. These relays contain inputs from potential transformers, current

transformers, pressure sensors, temperature sensors, light sensors for arc flash, and vibration

sensors.

The relays monitor these inputs and calculate whether they are within specified ranges.

Fault conditions will drive the inputs out of preset ranges and cause the relay to initialize a

protective feature. This may be to open a circuit breaker, shut down an electrical generator, or to

alert personnel of a condition that is out of specification.

Most protective relays are microprocessor based and contain circuitry which monitors

conditions with a high degree of accuracy, data resolution, and a very low reaction time. This

allows for minimal damage to equipment and low danger to personnel during a fault condition by

removing the dangerous condition from the system. Several manufacturers produce protective

relays with a wide range of prices and features.

Transformers A transformer is a power converter that transfers electrical energy from one circuit to

another through inductively coupled conductors—the transformer's coils. A varying current in

the first or primary winding creates a varying magnetic flux in the transformer's core and thus a

varying magnetic field through the secondary winding. This varying magnetic field induces a

varying voltage, in the secondary winding. This effect is called inductive coupling [23].

By appropriate selection of the ratio of turns, a transformer enables an alternating

current (AC) voltage to be stepped up, or stepped down. The power is not changed and therefore

when the voltage goes up the current goes down, and vise-versa. The windings are coils usually

wound around a ferromagnetic core that is typically made of highly permeable silicon steel

laminated together. Each lamination is insulated from its neighbors by a thin non-conducting

layer of insulation. The steel has a permeability many times that of free space and the core serves

to greatly reduce the magnetizing current and confine the flux to a path which closely couples the

windings. Thinner laminations reduce losses, but are more laborious and expensive to

construct. Thin laminations are generally used on high frequency transformers, with some types

of very thin steel laminations able to operate up to 10 kHz. The effect of laminations is to

confine eddy currents to highly elliptical paths that contain little flux, reducing their magnitude

[24] [25].

All transformers operate on the same basic principles, although the range of designs

varies. Transformers are essential for high-voltage electric power transmission, which makes

long-distance transmission economically practical.

19

Fire and Electrical Codes This project required looking in to fire and electrical codes which will include NFPA 851

and NFPA 70E. Both of these codes describe fire prevention and mitigation of the effects of fire.

NFPA 851 is a publication from the National Fire Protection Association (NFPA) which

provides recommendations, not requirements, for fire prevention and fire protection for

hydroelectric generating plants. This includes a fire protection design process, general plant

design, fire protection systems and equipment, identification of and protection from hazards, fire

protection for the construction site, and a fire risk control program.

NFPA 70 is the National Electric Code, or the NEC. The general scope covered by this

series of documents covers the installation of electrical conductors, equipment, and raceways;

signaling and communications conductors, equipment, and raceways; and optical fiber cables

and raceways. This covers construction and operation of the hydro station building, generation

and switchgear equipment, and connection to the electrical grid [26].

Environmental impact statements An environmental impact statement (EIS) may be required for the hydro turbine project.

This document is required by the National Environmental Policy Act (NEPA) for certain actions

“significantly affecting the quality of the human environment” [27]. It provides information for

decision making and describes the negative and positive environmental effects of a proposed

action. Although during this project a preparation of this statement will not be completed, a short

summary of these statements is included below:

An EIS typically has four sections:

1) An introduction including a statement of the purpose and need of the proposed action or

project

2) A description of the affected environment.

3) A range of alternatives to the proposed action. These alternatives are considered the main

section of the EIS.

4) An analysis of the environmental impacts of each of the possible alternatives. This

section covers topics such as:

Impacts to threatened or endangered species

Air and water quality impacts

Impacts to historic and cultural sites, (particularly sites of significant importance

to Native American tribes)

Social and Economic impacts to local communities

Cost analysis for each alternative, including costs to mitigate expected impacts, to

determine if the proposed action is a prudent use of taxpayer dollars

Environmental Regulations Environmental laws and statutes cover a wide array of subjects and are enforced by

federal, state, and local governments. The purpose of these regulations is to regulate activities

20

that have an environmental impact on their surroundings. Furthermore, the mission of the

regulations is to protect human health and the environment [27].

The major environmental issue the team will consider for this project will be constructing

a structure in close vicinity to the Mississippi river. The majority of the regulations for this

project are covered under Minnesota statues and regulations. A summary of some of the

applicable regulations are covered in the following

section.

Minnesota Department of Natural Resources

(MNDNR) specifies setback requirements for

structures built on lakes and rivers. A minimum

distance must be kept from the shoreline based upon

lot width, shoreline type, and structure type. In

addition, no building may be placed within a

floodplain of a lake or river. In accordance with

Minnesota Department of Natural Resources

‘Shoreland Management Rules’ Chapter 6120, setback

requirements for placement of a structure from a bluff

require a building to be placed no less than 30 feet

from the edge of a bluff. The hydrostation building will

be placed near the bluff of the Mississippi River and

will follow this setback requirement [28] [29].

While water runoff into the river is natural and

inevitable, erosion from shoreline can occur. This creates sediment runoff into the water

degrading water quality. Standards are set by the Minnesota Pollution Control Agency (MPCA)

to minimize unfiltered water flow into waterways. Mitigation methods include ensuring natural

vegetation is kept along the shores of the water ways. Also during unavoidable disturbance of the

soil, techniques are employed to filter any water runoff. The MPCA has produced a handbook

describing these rules and regulations call the ‘Stormwater Best Management Practices Manual’

which the team will follow for the project [30].

Under Minnesota state law, the floodplain is considered to be the land adjoining lakes

and rivers that is covered by the "100-year" or "regional" flood. This area has special restrictions

for building permanent structures within this floodplain [28].

Wastewater Regulations There are many regulations concerning wastewater treatment systems. The Minnesota

Pollution Control Agency (MPCA) is in charge of instituting the regulations and making sure the

Figure 19 Overhead view of the building

site with the Mississippi River to the right.

21

regulations are being followed. The specific wastewater

regulations that are important to this project concern the

amount of chemicals and water that are being discharged from

the plant. The last stage of the wastewater treatment process is

to treat the water with chlorine; this kills the remaining bacteria

used in the process. The regulations require the chlorine to be

dissipated before leaving the holding ponds. Since water flow

may change due to this project, testing will have to be done to

make sure the state requirements can still be met. This testing is

currently done using the daily average amount of water leaving the plant. Since the team’s

project involves the hydroelectric plant only, regulations for wastewater discharge are beyond

the scope of the project.

Zoning and Building Codes This project requires looking into the building and zoning codes that the City of Grand

Rapids requires. The city of Grand Rapids has adopted the State of Minnesota’s building code

system and the shore land use standards. The State of Minnesota follows Chapter 326B

Construction Codes and Licensing statutes for building projects.

In order to put a building on the proposed sight, it has to meet zoning codes. A building

suitable to meet the project requirements would be considered an essential service structure; it

would require a conditional use permit. A conditional use permit cost $505.00. The main codes

for an essential service building refer to setbacks from the right of way, the river, and side

properties. In addition, it has to aesthetically fit in with the surrounding buildings in the

neighborhood. A distance of thirty feet from the right of way is required. A distance of fifteen

feet from the side properties is required. The river setbacks are fifty feet from the ordinary high

water mark and thirty feet from the top of the bluff. A variance permit will be needed if any of

these requirements cannot be met. The proposed variance will have to be reviewed and approved

by the zoning board for the project to proceed. A variance permit cost is $252.50 [31].

The project will require a building permit for the proposed structure. The cost of a

building permit is dependent on the cost of the proposed building project. The structure will be

engineered to meet Minnesota’s standard building codes. Some of the codes relate to snow load,

exit size, lighting, fire extinguishers, and ventilation. The City of Grand Rapids has a building

inspector who would inspect the work and make sure the building meets the requirements.

If the proposed project requires any work to be done on the river bank or in the water, a

permit may be required from the Minnesota Department of Natural Resources. The permits are

issued based on a case by case analysis.

Selling Electrical Power Since the initial estimates of power generation are not above GRPUC’s power demands,

the client would not be selling power outright. Instead they will be decreasing the amount of

Figure 20 MPCA logo

22

power they are demanding. Decreasing the amount of power demanded will decrease the cost

they have to pay for electricity and that cost savings can be considered revenue for purposes of

this project.

A power generation site over 5 megawatts capacity is considered to be “before the meter”

power generation and are regulated by the Midwest Independent Transmission System Operator,

Inc. (MISO), a conglomerate of power companies in the Midwest part of the United States.

These sites are directed when to generate power, and when to remain offline based on their

individual cost of generation. Generally less costly generation sites will operate more than other

sites. Generators under 5 megawatts capacity are considered “behind the meter” generators and

can run continually. They decrease the load of the system rather than providing power for the

load. The proposed generator at the wastewater treatment plant will produce a maximum of 70

kilowatts and will be a “behind the meter” system [32].

The cost of power varies every five minutes with a wide spread based on hourly, daily,

monthly, and yearly demands and available supply. The since there is more demand during the

16 hours that people are generally awake, the cost rises to about double what the off peak cost is.

Usually the cost of electricity increases during the winter months due to increased heating costs.

It will be possible to vary the amount of water that will be let down the pipe into the

generator; storing energy during the night and releasing it during the day. Using this, the client

will be able to increase the amount of power savings they will receive.

Financing

Financing for this project could come from three main areas: grants, loans, and funds

currently available. Grants are a source of money that comes from private organizations or the

government to be used on a specific project; this money does not have to be repaid. Loans are a

monetary source that would allow money to be spent now and repaid at a later date. There are

also funds from GRPUC that would be available for conservation projects.

Grants

There are financial grants from both the state and the federal governments [33] [34]. State

based funding relies mostly on the region that someone is working in. Since this project takes

place in the MP region, their grant could be applied for. Their grant allows for up to $50,000 to

help pay for projects like this one [35]. Their current grant period will end on December 31,

2012 [35], however a new cycle may begin the year after. Excel Energy also funds renewable

energy projects in Minnesota through their Renewable Development Fund [36]. This fund is

currently not accepting applicants, but may be a source of funding in the future [37]. Federal

grants are designed mostly for companies that pay taxes. Since the GRPUC is a governmental

body, they are not able to apply for the current federal program (U.S. Department of Treasury -

Renewable Energy Grants) that helps to create renewable energy facilities [38].

23

Loans

Loans would be given to the GRPUC from the city so the interest rate would be 5%

which is the commission’s acceptable rate of return. These loans would need to be able to be

paid off by either the savings gained from the generator or from the budgeted available

resources.

Available resources

The GRPUC has a budget that can be spent on conservation projects. Since this project

will reduce the amount of energy used, this project could be paid for with that money. Currently

the conservation project budget is 1.5% of $13.3 million, or $199,105 [39]. It may be possible

that the GRPUC could spend more than that budgeted amount.

Options

Summary This section will discuss all solutions to the project the team brainstormed and

investigated including ideas discussed in the background research section. An initial discussion

is included for each option. Decision matrices were used to weigh all options either by using a

weighted scale system or the Pugh method. Final decisions for each option are included.

Turbines The team looked into three types of turbines: Francis, Pelton, and Kaplan. Because of the

calculated energy output the turbines considered for this project will be on the micro scale level,

or less than 100 kilowatts. The criteria that went into the teams decisions included:

Cost – How much it will cost for each option.

Efficiency – Determining how well the turbine works for the conditions.

Life span – Determining how long the turbine will be useful.

Maintenance – Looking at how much maintenance each type will require.

Manufacturer’s recommendations –The turbine manufacturers recommend for the

system.

Table 1 A weighted table for the options of turbine

Turbines

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended)

Francis Pelton Kaplan

Cost 2 2 2

Efficiencies 3 1 3

Life Span 3 3 3

Maintenance 3 1 2

Manufacture Recommendation 3 1 2

Totals 14 8 12

24

The Francis turbine’s advantages are: high efficiency, ability to handle varying flows, and

it works with lower head and higher flows compared to the Pelton. A disadvantage is the Francis

turbine requires an enclosed pressurized housing. This can add cost to the project if the piping

system must be redesigned.

The Pelton turbine’s advantages include: it does not need to have an enclosed pressurized

system, it requires a small housing, and it has the ability to withstand varying flows. The main

disadvantage of the Pelton is it requires a large difference in height from the beginning of the

system to the end of the system of at least 300 feet. Because the height difference is

approximately 50 feet, the amount of pressure head is not sufficient for this type of turbine. Also,

the nozzles of this type of turbine require more maintenance.

The Kaplan turbine’s advantages are similar to the Francis. It works best with a high flow

and low pressure head and is built to handle more debris and sand than other turbines. The

Kaplan has adjustable gates and wickets which aid in its ability to have better efficiencies. These

adjustable parts also produce more maintenance.

The manufacturer’s recommendations are determined by the flow and the height of the

systems. The maintenance is based on the number and design of parts, such as nozzles and

wicket gates. The life expectancy and cost of the turbines were about the same. The team chose

to use the Francis turbine based upon manufacturer’s recommendations and its application to the

site based upon total head and water flow rate [6] [7].

Pipe Construction Four options were chosen for the effluent pipe from the wastewater treatment plant to the

turbines: reuse the existing pipe, reline the existing pipe, install a new pipe, and slip the existing

pipe with a smaller pipe. The criteria for the team’s decision were:

Price – How much it will cost for each option.

Complexity – How complex each option will be to install.

Ease of Install – How difficult each option will be to install.

Life expectancy – Looking at whether the pipe will have to be replaced over the lifetime

of the generation site.

Headloss (pipe size) – Determining if the size of the pipe have to be reduced from the

original pipe size.

Headloss (pipe type) – How the coefficient of friction affects the system.

Client recommendation – This was not considered in decision matrix, but it was worth

noting.

25

Table 2 Weighted table for pipe construction

Pipe Construction

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

Reuse Reline New Slip

Price (x3) 9 6 3 6

Complexity (x1) 1 2 2 2

Ease of Install (x2) 4 4 2 6

Life Expectancy (x2) 2 4 6 6

Headloss (pipe size) (x3) 9 9 9 6

Headloss (pipe type) (x2) 2 4 6 6

Client Recommendation *

Totals 27 29 28 32

Reusing the existing pipe will require capping off all manholes existing on the pipe since

it will be pressurized. There are existing drains from other systems that will need to be rerouted.

This will require installing a new smaller drain pipe approximately 3/4 of the length of the

effluent pipe to the Mississippi River. Additionally, the integrity of the existing pipe is unknown.

Relining the existing pipe will have the same challenges of reusing the old pipe, although

the physical integrity of the pipe will be improved and the coefficient of friction of the pipe

sidewalls will be reduced.

Installing a new pipe would be ideal for many reasons. A new pipe would have a long

lifespan, with a low coefficient of friction. The integrity of the pipe would be known, and the

pipe size would be large enough to have a low headloss. This option does become cost

prohibitive and would also be a more complex option.

Slipping the pipe will create a high integrity pipe with a low coefficient of friction. A 30

inch pipe can be installed inside the existing pipe, and other systems draining into the existing

pipe would be able to flow outside of the slipped pipe.

After weighing all the options the team’s recommendation is to slip the existing pipe with

a smaller pipe. Polyethylene pipe would probably be used.

Rerouting the existing pipe An option to reroute the top section of the effluent pipe was considered by the team. The

pipe would take a more direct route to the wastewater ponds and would reduce the overall length

of the pipe.

Price – How much it will cost for each option.

Ease of install – Expense of rerouting the pipe verses using the existing route.

Headloss – Determining which route creates less pipe headloss.

26

Land ownership – Determining if new easements will need to be created by rerouting the

pipe.

Table 3 Weighted table for rerouting the pipe

Reroute

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

Yes No

Price (x3) 6 9

Ease of Install (x1) 2 3

Headloss (x2) 6 4

Land Ownership (x1) 2 3

Totals 16 19

Rerouting the pipe would create less overall headloss in the system due to a shorter pipe

length. It would also make the project more complex and expensive, and possibly create a need

for new easements through other people’s land.

Keeping the pipe on its original route would create higher headloss, although it would be

less expensive and less complex with no additional property easements required.

The team’s recommendation is not to reroute the pipe, mainly due to its high cost.

Building The building options were split into two categories, underground and above ground. The

underground options included formed concrete walls and block concrete walls. This area would

house the turbine and the shaft. The above ground options included formed concrete, block,

wood, and metal. This area would house the generator and other electrical devises needed. The

criterion that was used to evaluate the building included:

Cost – How much it will cost for each option.

Appearance – Determining which structure looks the best.

Maintenance – Maintenance amount that will be required for each option.

Life expectancy – How long the structure will last.

Complexity to build – How easy and common the option is to build.

27

Table 4 Weighted table for building materials

Building Material

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

Formed

Concrete

Concrete

Block Wood Metal

Cost (x3) 9 9 3 6

Lifespan (x2) 6 6 2 4

Appearance (x2) 2 4 6 6

Maintenance (x2) 6 6 2 4

Complexity (x1) 2 2 3 1

Totals 25 27 16 21

The underground options were narrowed down to the formed concrete and block options

because of the moisture problems that could arise underground. The advantages of the formed

concrete are: it structurally stronger, easier to maintain, and costs less to build because less labor

is needed. The disadvantage is contactors have to use cranes to move the forms.

Many of the advantages to concrete blocks are the same as the poured walls. Additionally

block walls are light weight and the walls can be constructed by hand, although the joints are

more susceptible to leaks than poured walls.

Since appearance is not an issue underground, the team recommends using poured

concrete walls for the underground option due to its reduced leak susceptibility.

The above ground options included wood and metal plus the two underground options.

The advantages of the wood are its ease to work with and it can be very energy efficient. The

disadvantages include: it is combustible, susceptible to insects, and can have natural flaws in the

material. Wood also proved to be more expensive than concrete products.

The advantages of using metal are: it is not combustible, it is insect resistant, and it is

very uniform in strength. The disadvantages are: it will corrode if moisture builds up, and it is

not as energy efficient.

After weighing all the options the team recommends using concrete block to build the

upper and lower parts of the building.

Grid Connections For the grid connections there are four possible options:

MP

Lake Country Power

GRPUC

Wastewater treatment plant

28

These options were rated on three criteria, which were:

Price – The expected price of connected the generator to a specific grid network.

Complexity – How complex it will be to attach the generator to a specific grid network.

Availability – If connecting to the certain section of the grid would be feasible.

Table 5 Weighted table for the electrical grid connections

Electrical Grid Connection

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

MN Power Lake Country Power GRPUC WWTP

Price (x3) 6 3 9 3

Complexity (x3) 6 3 9 3

Availability (x1) 3 1 3 3

Totals 15 7 21 9

The option of connecting to MP involves running approximately 5000 feet of power

cables from the generation site to MP’s substation. It is a 115 kilovolt substation in southeast

Grand Rapids which contains a low voltage side for distribution. A connection would most likely

be on the low voltage side of the substation.

Lake Country Power owns a large electrical distribution network spanning much of

northeast Minnesota. This utility owns electrical power lines located near the wastewater

treatment plant which operate at 46 kilovolts. A connection could be made into their system.

GRPUC operates a 14 kilovolt electrical distribution network within the city limits of

Grand Rapids. Power lines from their network are located within 100 feet of the generation site,

making for a fairly easy connection to their grid.

A connection could be made directly into the wastewater treatment plant. This would

involve running power cables approximately 1500 feet from the generation site back up to the

wastewater treatment plant.

The team’s recommendation for the grid connection is to connect to the GRPUC grid.

This will be the least expensive, easiest, and least complex option [18].

Operations Operations were divided into two areas: how the water flow would be regulated, and who

will operate the generator on a daily basis.

Flow regulation

The two options for flow regulation are to operate the turbine 24 hours per day at a

constant flow rate, or to allow the water to store up in the ponds for part of the day and operate

the turbine during the other times at a higher flow rate. Criteria used to evaluate each option:

29

Initial cost – The initial cost of installing the needed equipment to allow for flow control.

Headloss – Water’s potential energy that is wasted while traveling through the pipe at

higher flow rates.

Income –Money made by changing when the generator operates.

Complexity – How complex it will be to create a system to allow for different flows.

Table 6 Weighted table for the operational time

Operations - Time

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

1/2 Day Full Day

Initial Cost (x3) 6 6

Headloss (x1) 1 3

Income (x3) 9 3

Complexity (x1) 1 3

Totals 17 15

An advantage of allowing the water to flow constantly is that operation of the generators

and wastewater treatment plant would be less complex. A constant pond level would be

maintained and power would be produced from the overflow. Also, less head loss would be

produced due to a smaller flow rate through the effluent pipe, increasing the efficiency of the

system. A major disadvantage is that power generated during off-peak hours cannot be sold for

as much as power produced during peak hours.

The other option is to allow the water to build up in the ponds during off-peak hours and

to allow the water to flow twice the rate through the generator during on-peak hours. The power

generated during on-peak hours is worth more, likely twice as much as off-peak hours. However,

this will add complexity to the operator’s job, since they will be required to turn the generator on

and off one or two times per day. While this should be very easy, it will require additional

training and time for the operators. The flow will also produce more head loss as the water will

be traveling twice the flow rate through the pipes.

It is recommended that the facility be run half the day since it will produce more income

for the client.

Operation organization: There are two options for who could operate the generator: MP and the Grand Rapids

wastewater treatment plant. The criteria used to evaluate each option were:

Cost –Money that will need to be spent to operate the facility.

Complexity –complexity of allowing the control of the facility by different groups.

Willingness – How willing the companies will be to operate the facility.

Expertise – Background the company may have in running a hydroelectric facility.

30

Table 7 Weighted table showing operator options

Operations - who will

operate the facility

Impact Level (1 = Not recommended, 2 = Acceptable,

3 = Recommended) x (Importance Factor)

MP Power GRPUC

Cost (x3) 6 9

Complexity (x1) 2 3

Willingness (x1) 1 3

Expertise (x2) 6 2

Totals 15 17

If MP is used as the operator of this facility, they will take some of the money that is

earned for operating costs. Some advantages of using MN Power are they already oversee many

hydroelectric stations, and are well trained in hydroelectric operations. However, they may not

be willing to operate such a small generator. The wastewater treatment plant also needs to be

able to regulate the levels of the ponds which could cause some issues.

The Grand Rapids wastewater treatment plant could use their operators to run the facility.

One major advantage is that they will have the ability to regulate the level of the ponds. In

general, setting up the system will be less costly and less complex if controlled by the

wastewater treatment facility, although the operators for the facility will have to be trained to

operate the system.

It is recommended that the client operate the facility.

Financing The funding for this project may come from many sources. The advantages and

disadvantages were analyzed by the team using the Pugh method. The criteria used to evaluate

each option were:

Availability – How available these resources are.

Cost – Extra money a financing method may cost the city.

Ease of acquiring – Amount of work that will have to be put forth to make this method of

funding possible.

Public perception – Determining if the public likes this form of payment.

Amount available – Determining if this funding method contains enough money to cover

the project.

The first stage of the Pugh method evaluated grants, loans, and budgeted money; the

default was to use grants.

31

Grants are money that could be sought out from state governmental agencies along with

local businesses to pay for the project. This option would use only the money from the

grants as a source of funds.

Loans can be obtained by the GRPUC to finance projects at an interest rate of 5%. This

option would use loans to pay for the entire project.

The GRPUC has a budget and they can spend that money however they need to. This

option would use that budget to pay for the entire project.

Table 8 Table for financing, initial Pugh method

Financing - Pugh Method(1) Grants Loans Budget

Availability d + +

Cost d - -

Ease of acquiring d + +

Public perception d - -

Amount($) available d + -

Totals +1 -1

Looking at the options of using loans or the budget compared to the default, grants, it was

found that loans would be a better option. Loans then became the default for the second run of

the Pugh method. Options of special funds and bonds were added, while other options were

combined.

GRPUC has a special fund that pays for projects designed to conserve energy. This

option would use those special funds to pay for the entire project.

Bonds are a funding option for governmental agencies that allow private individuals to

give loans to a governmental entity for a specific interest rate, often at lower rates than a

standard loan. This option would use bonds to pay for the entire project.

Options added together will use previously explained methods of payment while

combining their strengths.

Table 9 Table for financing, second iteration of Pugh method

Financing - Pugh Method(2) Loans

Grants

+

Budget

Special

Funds

Loans

+

Budget

Grants

+

Loans Bonds

Ease of availability d - + + - -

Cost d + + + + +

Ease of acquiring d - + + - 0

Public perception d + + + + +

Amount($) available d - - + + 0

Totals -1 +3 +5 +1 +1

32

Looking at the new options compared to the default of loans, it was found that loans

added to the budget would be a better option. Loans added to the budget then became the default

for the final run of the Pugh method. No options were added, but several options were combined

into financing packages.

Table 10 Table for financing, final iteration of Pugh method

Financing - Pugh Method(3)

Loans +

Budget

Special Funds +

Loans + Grants +

Budget

Special Funds +

Loans + Grants +

Budget + Bonds

Ease of availability d - -

Cost d + +

Ease of acquiring d - -

Public perception d + -

Amount($) available d + +

Totals +1 -1

It was determined that the best way to finance the project would be to seek out as much

grant money as possible while paying as much as possible from the special funds and the general

budget. The remainder of the cost would be taken out in loans. This is the team’s

recommendation to finance the project.

Experiment

Summary The team did an experiment to test the energy lost from headloss in different pipe sizes.

This was done to verify the mathematical model that postulated that headloss would increase

with smaller pipe size. The team used a turbine and generator to test the energy output from the

flow of water from each of the different sized pipes. The water flow came from a reservoir

approximately six feet above the turbine. The results verified the mathematical model. Statistical

analysis was done to verify how consistent the results were. The team then discussed the findings

so they could make a recommendation to the client of what pipe size to use.

Introduction The objective of this experiment was to verify the mathematical model, which postulated

that a smaller pipe size would increase headloss. To do this, the team recorded the power output

of a turbine fed by different pipe sizes. These different pipe sizes caused head losses throughout

the length of the pipe and directly affected the energy delivered to the turbine.

The following equation shows how headloss is calculated in pipes. The important

variables for the experiment are V (velocity of water) and D (diameter of the pipe). As velocity

of the water increases, the headloss increases exponentially. As the diameter of the pipe

33

decreases, the headloss of the pipe also increases. These factors will be proven in the experiment

and the mathematical model.

Equation 2 Headloss of a fluid through a pipe

Various fluids textbooks were reviewed prior to the experiment including “Core

Engineering Concepts” textbook. Pressure of fluid vs. height, headloss, kinetic energy of fluids,

and turbines were reviewed.

A hydraulic turbine generator system will be simulated in this experiment. A constant

pressure height will be achieved and will not be changed. The turbine will be operated at

maximum output with no limitations to flow. The generator will produce a power output at an

unregulated speed and voltage with a constant load attached. None of the generator variables will

be changed. The pipe lengths will all be approximately 10 feet long, and will not be varied. The

changing variable will be the pipe size. 1/2”, 3/4”, and 1” pipe sizes will be used for the

experiment.

Apparatus

A turbine was needed for the experiment. The team looked to purchase an inexpensive

turbine, but could not find any. The team then looked to see if any pumps could be used

backwards, to act as a turbine. One option was found that could output a little energy, but this

option was very inefficient, so the team decided to pursue creating their own turbine.

Figure 21 Side view of all components cut for the turbine.

34

Figure 23 Final design of the impeller cut from

plastic

The team decided to construct a turbine from 1/4” acrylic sheets. The sheets were cut by

IRE’s Hurricane Laser CNC cutter.

The parts that were created included a bladed impellor, the inside, and outside walls. All

of the parts were fashioned with holes to allow for easy manufacturing. After the pieces were cut,

the parts were assembled. The bearings and the impeller were press fit into the outside wall and

onto the drive shaft.

A ten gallon capacity clear plastic tub was used for the upper reservoir. Three holes were

drilled into the bottom portion of the tub to allow for different sizes of pipes to be attached to the

tub. 1/2”, 3/4”, and 1” clear plastic hoses approximately 10 feet long were attached to the tub.

This tub was placed approximately 8 feet above the floor. The turbine was placed above a second

clear plastic reservoir on the floor. A 12VDC water pump was used to pump this water from the

bottom tub to the top tub. The hoses were connected to the turbine with a one inch ball valve to

shut the water off and on. A 12VDC generator was connected to the turbine with a slip collar. A

10 ohm resistor was connected to the generator for a load with a digital ammeter connected in

series with the load. A digital voltmeter was connected across the generator terminals to monitor

voltage.

Figure 22 Here is a side view of the apparatus with

the reservoir on top and the hose connected to the

turbine on the bottom.

Figure 24 Here is the generator connected to the

turbine along with the bottom reservoir.

Figure 25 Top reservoir with hoses.

35

Mathematical Model The team looked at how much power would be available to be produced based on what

size the pipe was, and how much water was flowing down the pipe. The calculations were run

using the economic analysis spreadsheet which contained a headloss calculator. The one inch

pipe was ten feet long with a six inch by ¾ inch section to connect it to the turbine. The water

flowed at 7.74 gallons per minute through the one inch pipe which had a static head of 77 inches.

Using these numbers the maximum power was calculated to be seven watts. The headloss was

calculated to be 17 inches. The ¾ inch pipe was nine and a half feet long directly connected to

the turbine. The water flowed at 7.06 gallons per minute through the ¾ inch pipe which also had

a static head of 77 inches. These numbers resulted in a maximum power of one watt, and a

headloss of 63 inches. The calculations for the half inch pipe showed a larger calculated

headloss of 512 inches than the static head of 77 inches, so there was no calculated power output.

Procedure The top reservoir was filled to a measured level creating approximately 80 inches of head

from the water level to the turbine. The ¾ inch hose was connected to the turbine with the ball

valve shut. The 12VDC pump was primed and readied to allow the pumping of water back up to

the top reservoir. Instrumentation was connected and turned on. The valve was then opened and

the water level was allowed to drop reaching 77 inches of head at which time the voltage and

current of the generator were recorded. This was repeated four times for the ¾ inch hose, and

four times for the 1 inch hose. An attempt was made for the ½ inch hose, but so much head was

lost over the length of the hose that the turbine did not spin.

Results There was approximately a 60% increase in power output from the 3/4 inch to 1 inch

hose. The 1/2 inch hose did not turn the turbine at all due to a large headloss experienced by the

smaller hose. The results were consistent with the math model that showed headloss would

increase as pipe size decreased.

Table 11 Results for ¾ and 1 inch hoses.

3/4 inch hose

Test run Voltage (DC) Amperes (DC mA) Power (milliwatts)

1 1.40 120.0 168.0

2 1.30 117.0 152.1

3 1.30 115.0 149.5

4 1.24 110.0 136.4

1 inch hose

Test run Voltage (DC) Amperes (DC mA) Power (milliwatts)

1 1.68 145.7 244.8

2 1.64 141.9 232.7

3 1.71 147.0 251.4

4 1.66 143.9 238.9

36

Statistical Analysis The team used Microsoft’s Excel program to do a descriptive statistical analysis of the

data it received from doing the experiment. The reason this was done was to analyze the

variability of the data. The variability ended up being 6.38x10-5

for the one inch hose and

1.6x10-4

for the ¾ inch hose. The standard deviation ended up being 7.98x10-3

for the one inch

hose and 1.29x10-2

for the ¾ inch hose while using a confidence level of 90%. This data can be

seen in Table 12. This showed that the results were very consistent within each sample set.

After going through the criteria for what test to use, it was decided that the Pearson

Correlation test was the best option to use. The Pearson Correlation shows the correlation

between a dependent variable and an independent variable. The dependent variable was the

power output from the turbine/generator; the independent variable was the size of the pipe. The

team used Microsoft Excel to compute this data. The computed correlation coefficient shows

how much correlation there is between the variables. A coefficient of one means that there is a

perfect correlation between the variables and zero means there is no correlation. The correlation

coefficient for this experiment was 0.979 which showed a strong positive correlation between

pipe size and the amount of power output from the turbine/generator. This result was graphed to

show the correlation. This also supports the teams hypothesis that as pipe size increases so would

the power.

37

Table 12 Statistical analysis data

Conclusion The findings confirmed that as the pipe size on the inlet of a turbine increased, the

amount of headloss decreased causing the power produced by the turbine to also increase. The

only unexpected result was that the ½ inch pipe caused so much headloss the turbine did not

spin. These results show that the size of the pipe does matter for the project.

Recommendations The results of this experiment show, a large effluent pipe will transfer more power to the

turbine. The recommendation is to install the largest pipe that can be slipped into the existing

pipe. This will allow the most power output possible from the turbine.

voltage amperage Watts Diam. Voltage amperage watts Diam. Power Diam.

1.68 0.1457 0.244776 1 1.4 0.12 0.168 0.75 0.244776 1

1.64 0.1419 0.232716 1 1.3 0.117 0.1521 0.75 0.232716 1

1.71 0.147 0.25137 1 1.3 0.115 0.1495 0.75 0.25137 1

1.66 0.1439 0.238874 1 1.24 0.11 0.1364 0.75 0.238874 1

0.168 0.75

1 inch hose data 3/4 inch hose 0.1521 0.75

0.1495 0.75

Mean 0.241934 Mean 0.1515 0.1364 0.75

Standard Error 0.003994269 Standard Error 0.006484726

Median 0.241825 Median 0.1508

Mode #N/A Mode #N/A R= 0.979377967

Standard Deviation 0.007988537 Standard Deviation 0.012969451

Sample Variance 6.38167E-05 Sample Variance 0.000168207

Kurtosis -0.976508403 Kurtosis 1.359105362

Skewness 0.066951549 Skewness 0.318241884

Range 0.018654 Range 0.0316

Minimum 0.232716 Minimum 0.1364

Maximum 0.25137 Maximum 0.168

Sum 0.967736 Sum 0.606

Count 4 Count 4

Confidence Level(90.0%) 0.009399966 Confidence Level(90.0%) 0.015260916

1 inch hose 3/4 inch hose

0

0.05

0.1

0.15

0.2

0.25

0.3

0 0.2 0.4 0.6 0.8 1 1.2

Power

Power

38

Economic Analysis

Introduction An economic analysis was performed as part of the feasibility study. The initial data for

the analysis came from information the team collected of economic costs. A modifiable Excel

spreadsheet was produced with all known variables for the project. The spreadsheet can be

easily modified to analyze the feasibility of any other possible hydroelectric turbine projects for

public utilities. The following is an explanation of each section of the spreadsheet.

Client inputs The client inputs were the required data that were needed to run the economic analysis.

Data was collected from the client and from other sources to populate the economic analysis

spreadsheet. Required inputs included economic data (grants available, rate of return, economic

life), electricity cost data (demand charge, average energy cost, peak energy cost), pipe (pipe

size, length, and height), run data (water flow rate, efficiency), and whether or not the generator

would be operated constantly or just for half of the day during peak hours. All of this

information was supplied by the client.

Calculations There are several calculations that the spreadsheet runs in order to supply the correct

information. With the data from the client inputs, the headloss calculator worksheet determined

the headloss depending on the pipe size. The turbine head was then calculated by subtracting the

headloss and velocity head from the head of the pipe. The turbine head then was used to

calculate the average power produced. In this case, it was found to be around 35.4 kW.

Costs The costs of the project included the cost of slipping or replacing the pipe, the turbine and

generator and associated electrical equipment, building costs, additional initial costs (excavation,

foundation, etc), operational and maintenance costs, and the allocated overhead. The full

purchase and install costs were estimated to be $437,679, while the annual cost was calculated to

be $2,892.

Revenues The revenues from this project included the savings on the monthly peak demand charge,

and the energy savings from the power produced by the generator. The annual revenue was

estimated to be $22,888.

Economic analysis results The economic results were calculated using NPV, IRR, annual net income (accrual

basis), annual cash flow from the project, and payback period. The following chart shows the

capital budgeting calculations, using the best estimates, for this project.

39

Table 13 Economic analysis results showing a positive income, but a negative NPV

-$114,576 NPV

2% IRR

$5,739 annual net income from project (accrual basis)

$19,995 annual cash flow from project

22 payback period (years)

Conclusion The NPV is negative, but this project may be worth pursuing. Qualitative factors such as

energy conservation, environmental, political, and public perception should be considered in

addition to the quantitative results found.

References This document contains information related to the economic analysis of the GRPUC

hydroelectric turbine project and the spread sheet that that information was calculated with. To

view the economic analysis spreadsheet contact IRE or Jeffrey Lange at

[email protected].

Physical Model The team created two physical models for the project. One was created for the

experiment to look at headloss and how it would affect the power output with different pipe

sizes. In order to be a scale model of the project, the model needed to have a head of six inches

and a ¼ inch diameter pipe that ran 12 feet long. The team decided that this would not work for

the experiment, and used a larger head and pipe. Pictures of the model used in the experiment

can be found in the experiment section of the report. The team then decided to create a

computerized model using Autodesk Inventor. This model was able to show the pipe and the

manholes along it.

Figure 26 A three dimensional layout of the pipe system with manholes

40

The model was used to see how well a slip piping would work, since the common rule of

thumb for slipping a pipe is that the pipe can turn on a radius 25 times greater than the diameter

of the slipped pipe [40]. Since the pipe would be around three feet in diameter, this meant that

the pipe would have to be able to turn on a 75 foot radius. The blue pipe in the figures below is a

slipped pipe with a 75 foot radius. It can be seen that while it manages to fit in the smaller curve

(Figure 30), the sharper curve does not have enough distance for it to fit (Figure 29), this showed

that a slipped pipe would not curve in this junction, so something else will have to be considered.

A calculation of the maximum turn radius of the 30 inch polyethylene pipe was required

to verify the recommendation to slip the pipe through specific pipe junctions, or to create a cut in

the pipe and not slip the pipe through these junctions. A maximum of 25 times the diameter of

the pipe was used for the turn radius for the calculations. This validates the recommendation to

slip the pipe through one of the pipe junctions, and to create a cut in the pipe at other junctions.

Figure 29 Shows the blue slip

pipe failing to make the curve

in the sharp angle seen circled

in the top view (Figure 27)

Figure 30 Shows the blue slipped pipe making the curve seen

circled in the side view (Figure 28)

Figure 28 A side view showing the rise over the length of the pipe

Figure 27 A top view showing the sharp curves that the pipe undergoes at the manholes.

41

Math model The mathematical model was used to determine if a pipe with a reduced area could still

be used to transport the effluent water from the wastewater treatment plant to the river, with a

high enough flow rate to justify putting a turbine in the line.

Assumptions The assumptions that were made were: that the daily flow rate would be seven million gallons

per day, the dynamic viscosity of water is 1.002 centipoise, the relative roughness of

polyethylene pipe is .0015 mm, and the velocity of the water in the ponds is zero using the big

tank assumption.

Description of how the math model was developed and executed The math model was developed to determine if a smaller pipe could handle the increased

flow and how much power could be generated by the turbine. The power calculations were done

in Microsoft Excel. The calculations for the increased flow were also done by hand.

Equations and Calculations

The equation used for the power calculation was the energy equation. The equation for

power produced by a turbine was also used.

Using the spreadsheet, the headloss calculations could be calculated quickly for any pipe. See

Appendix C to view pictures of the spreadsheet used.

The spreadsheet used equations such as, the Colebrook equation, the headloss equation,

the relative roughness equation, and the equation for Reynolds number.

The equations used to verify that the smaller pipe could handle the increased flow were

the full flow free outfall equation on page number 21-28/29 of the Core Engineering Concepts

book [41]. The graph for the coefficient of discharge was used to find the coefficient using the

Reynolds number. These equations were used to determine what the flow rate could be if there

was not a turbine in the effluent line to restrict the flow; and there was no governing system at

the pond, allowing them to drain as fast as possible.

42

Figure 31 Description of full flow free outfall, from the Engineering Core Concepts book [41]

43

Figure 32 Description of and graph to determine Coefficient of Discharge [41]

The calculations for the full flow free outfall showed that even if there was no turbine in

the effluent line the pipe would be able to handle the increased flow of running the turbine for

only half the day. The reason for this is because the flow rate for the full flow free outfall was

about 12 times as much as the targeted seven million gallons per 12 hours, or 162 gallons per

second, which is shown below.

Figure 33 The full flow free outfall calculations

44

Evaluation Process Using the calculations from the full flow free outfall equations with a 30 inch pipe

running for half a day there could be about 82.8 million gallons that could be discharged. If it

was run the full day the pipe could discharge about 171.7 million gallons. Both of these values

are well above the required outflow of the seven million gallons that the wastewater treatment

plant must discharge daily. This means there is no doubt that the smaller pipe will be able to

discharge the amount of required water even with the added restriction of the turbine; and from

the headloss calculations there will still be enough head left in the water to generate power with

the turbine.

Future Steps The future steps to be taken for this are to verify the size of the turbine to be

recommended using the headloss spreadsheet for the amount of head that will be available to the

turbine. The amount of power the turbine produces can be used as the amount of electrical

energy that this project will be saving the GRPUC, and thus the amount of money that will be

saved as a result of the installation of the turbine can be calculated.

Validation and verification There are two major areas which require validation and verification for this project, the

power output of the physical apparatus and the economic analysis. The team looked at both of

these aspects, and both will also be looked at by professionals for approval.

Team Validation and Verification – Physical Apparatus The project contains two major aspects to the physical apparatus: the effluent pipe and

the powerhouse equipment. The pipe to be used for the project is a 30 inch polyethylene pipe

which will be slipped inside of the existing pipe. A fluids analysis was produced by the team

using headloss equations. These were placed in a Microsoft Excel spreadsheet which allowed the

team to change variables such as flow rate, pipe size, pressure head, and coefficient of friction.

By performing this analysis the team verified the estimated total power output of the system.

They were also able to validate recommendations to the client to operate the turbine only during

peak electrical load periods which produced the greatest amount of income for the client.

Fluid headloss through pipes were verified by the team through an experiment. Different

sized pipes were used in a hydro turbine generation model to measure varying power outputs of

the system. By using smaller pipes, the team showed that less power was produced due to greater

headloss through the system. This validates the team’s recommendation to use a 30 inch pipe in

the project at the wastewater treatment plant.

The team received a quote from a hydro turbine generator manufacturer. This company

gave a recommendation for a micro turbine which was sized for a specific amount of power

output based upon information they received from the team. The team then verified this power

45

output information by independently verifying this information through calculations. This

validates the recommendation for the size of the turbine generator recommended to the client.

A free flow water analysis was calculated to ensure the flow rate of water used in

calculations for power is valid. This calculation produced the maximum amount of water which

could flow through the pipe with no limitations to the inlet water flow. A flow rate of

approximately 82 million gallons can flow through the pipe in a 12 hour period with a constant

head of 50 feet. This is much greater than the required seven million gallons of water per 12 hour

period used for the model.

Team Validation and Verification – Economic Analysis The team researched all economic impacts for this project and how they will affect the

feasibility study. A financial spreadsheet was produced with all aspects of the project built into

it. Each separate component of the spreadsheet was changeable by the user and described how

each individual component affects the project of the whole. The end result of the spreadsheet

verified that the project would produce positive income over the lifetime of the project for the

client. This was used to validate if the project is economically feasible to go forward with, or if

the project is not worth pursuing by GRPUC.

Professional Validation and Verification – Physical Apparatus The physical apparatus requires validation and verification of power output as calculated

per the mathematical model. The power output was based upon available water flow, headloss of

the system, turbine efficiency, and generator efficiency. These will be validated and verified by

professional engineers and by manufacturers of the turbine generator.

Professional Validation and Verification – Economic Analysis The team’s economic model of the system requires validation and verification to ensure

the project will successfully meet its financial goals. An examination by GRPUC’s management

team as well as their financial team will be performed prior to moving forward with the project.

Additionally, an examination of the team’s plan to sell electrical power will be inspected by MP

and GRPUC’s financial team.

Reliability A major factor in the feasibility of this project depends on a long lasting system. The

system contains two major sub systems which are relatively independent when projecting their

sustainability: the powerhouse equipment package and the piping.

Powerhouse Equipment Package The powerhouse equipment package includes a variable flow turbine, induction

generator, gear drive, drive couplings, switchgear and controls panels, turbine inlet valve,

hydraulic power unit, and structural steel mounting frames. This package contains two limiting

components. The turbine runner has a minimum lifespan of 25 years, and the turbine bearings are

rated for a 100,000 hour lifespan or approximately 11 years of continuous use. A monthly

46

maintenance schedule of greasing the turbine and generator bearings must be performed to reach

this life cycle.

Figure 34 This is a top view of a Canyon Hydro crossflow hydro turbine generator [42].

Polyethylene Pipe Polyethylene pipe has a variable life cycle based upon operating temperature, fluid

erosivity, pipe wall thickness, fluid velocity, and pressure cycling. The pipe will be operating at

temperatures matching the water temperature of the discharge from the wastewater treatment

plant. These temperatures do not fluctuate drastically over a 24 hour period, but do change a lot

over a 12 month period. The water flowing through the pipe is pure filtered water offering a

minimum erosivity. Pipe wall thickness will be designed for maximum steady state conditions of

50 feet of head or 21.65 psi. The fluid velocity will be 4.41 feet per second at the 12 hours per

day operation schedule. The water flow will cycle on and off once per day with slow operating

valves which produce a small amount of water pressure cycling.

47

These factors produce conditions which contribute to a long lifespan of polyethylene

pipe. Using these conditions as a standard and based upon studies from Performance Pipe, a

polyethylene pipe manufacturer, a 30” pipe installed for this project should last in excess of 100

years [43].

ure 36

Sustainability analysis The team received a quote for a micro turbine of sufficient size for the project from

Canyon Hydro, Deming, Washington. The information in this section is based upon their

specifications and recommendations. Canyon Hydro warranties their powerhouse equipment

packages for one year from installation or 18 months from delivery if not installed. This package

includes the turbine, generator, geardrive, hydraulic control system, electrical control system,

valves, and switchgear.

Resources required over the lifespan of this facility will be minimal based upon

manufactures specifications and the overall simplicity of its design. The effluent pipe has

minimal moving components such as valves which will cycle open and shut once per day. These

parts are available from the original manufacturer and are also widely available on the open

market if replacement is necessary.

The powerhouse equipment package contains bearings which are designed to last at least

11 years or 100,000 hours of operating time. When replacement is necessary, direct replacement

bearings will be purchased from the original manufacturer. The turbine runner is designed to last

a minimum of 25 years. When the turbine runner requires replacement it will be purchased

directly from the original manufacturer. A disadvantage of relying on direct manufacturer parts is

if the company goes out of business, these parts will require replacement by another

manufacturer’s parts. Bearings may be replaced by parts available on the open market. A

Figure 35 This table from Performance Pipe shows lifespan in years of polyethylene pipe with fluid

flow at four feet per second cycling on and off every 15 minutes. The pipe wall thicknesses a re shown

on the top of the table [43].

48

replacement runner may be more difficult to locate since these are a more specialized part. A

runner may be retrofitted for the turbine, or one may be machined by a specialty shop if required.

Generators and switchgear will be replaced if needed from the original manufacturer.

Upon unavailability of these original replacement parts it will be very easy to replace these parts

with other manufacturer’s equipment. Electrical equipment including generators, switchgear, and

transformers are widely available from many manufacturers on the open market.

The success of the project directly relies on the effluent flow of the wastewater treatment

plant. The majority of this flow is received from Blandin Paper Company which is used in their

processes. If this flow is cut off for some reason such as the paper company shutting down, the

effluent flow of the pipe would be reduced to below one million gallons per day from seven

million gallons per day. This will directly affect the power output of the hydroelectric plant, and

would make the plant uneconomical to operate. This possibility is impossible for the team to

predict, but should be considered by the GRPUC if deciding to go forward with the project.

Contextualization

Multi-disciplinary aspects of the project Many disciplines need to be involved with the construction and implementation of the

hydro turbine generator project. All of the disciplines in this report have special attributes that

contribute to the feasibility and functionality of the project.

Mechanical engineers/Structural engineers

Mechanical and structural engineers will have many inputs into this project. The piping,

turbine, valves, and the building will all be designed by these engineers. The expertise that is

needed to size the pipes and the turbine for the correct amount of flow will be the responsibility

of the mechanical engineer. The way the building is designed for size and safety will be decided

by the structural engineer.

Electrical engineers

The electrical engineers will be responsible for getting the energy from the turbine to the

electrical system, for this project. This will include deciding the best generator to use, the

switchgear that will be needed, and the circuit breakers that are right for the system. They will

also design the electronics to operate the system, including water flowage control and sampling

systems that need to be implemented because of wastewater regulations.

Environmental engineers

Environmental engineers will be needed to look into the regulations and implementation

of the amount of water being discharged into the river. They will also be responsible for any

work done on the land by the river and how the project will affect the natural drainage of the

area. The environmental engineer will also need to make sure that the project is following the

regulations regarding the amount of undesirable chemicals being put into the river.

49

Administration

GRPUC administration will have to look at the financial aspects of the project and decide

if it is something they want to take to the board of directors for approval. This will include the

financial manager, the general manager, and the wastewater treatment manager.

Project Manager

The project manager will have to oversee the project if it is to be built. This will include

managing the project from start to finish and making sure it is being built to the specs in a timely

manner. This position will be looking out for GRPUC’s best interest and making sure the project

is kept to budget.

Contractors/builders

The contractors and builders that are hired for the job will need to have the tools and the

knowledge to follow the plans the engineers have designed. It is very important that the builders

can do the job safely and make the building aesthetically pleasing. They must also have the

proper equipment to do the job.

Hydro dam operators

The hydro dam operators will need to have the knowledge of how the system works and

how to control the water flowage and the amount of electricity that is being produced. The

operators will also have to know how to maintain the system within specifications.

Wastewater treatment plant operators

The wastewater treatment operators will be required to have knowledge of how the

system will work. To maintain the proper treatment of the wastewater, the operators need to have

input on the flowage through the treatment system.

Contextual aspects of the project Health

The health of the people who will have to operate the system and do maintenance on it is

a big concern for the project. Proper ventilation will have to be installed into the building, to

allow for fresh air to be exchanged as needed. The operators will also need to make sure that the

treated water has time to complete its process before entering the river. If too many chemicals

enter the river it could affect people that use the river for recreation.

Safety

Safety will be a big concern for this project. The people who will operate and maintain

the system will need to be sure that all safety procedures are followed. If safety measures are

violated or missing the situation must get resolved as soon as possible. In the design of the

system, all regulations need to be followed to meet safety standards. This will include hand

railings, grounding systems, guards, and locks to keep people away from equipment that could

injure them. Safety measures will have to be put into place to protect the workers and bystanders

during construction. This will require signage and fencing around deep openings and

construction areas.

50

Environment

This project will have to take into consideration the environmental impact the project will

have on the land and river surrounding the project. The big concern will be what is being put into

the river. Special run off blockades will have to be installed during construction to help reduce

any top soil erosion that could end up in the river. Another concern is that the wastewater that is

being discharged into the river has to maintain its cleanliness and be as chemical free as possible.

A final environmental concern is how the fish in the river will be affected by the change in the

flowage of the water. A positive environmental impact that should come from this project is that

energy is being captured from a source that is not putting any emissions into the air.

Global

On a global scale this project will not have a big effect. This project will reduce some

carbon emissions and make the world a little cleaner. It may also show that this system can be a

feasible way to capture energy that would otherwise go to waste. This could lead to similar

implementations around the world.

Society

This project will not affect society as a whole, but it could have an impact on local

residents. It could have economical and image impacts. By installing the system, it could reduce

the cost of electricity for GRPUC which in turn could reduce utility bills for the residents of

Grand Rapids. The image GRPUC would be showing is that they care about the environment and

that they are always looking for ways to implement green energy. This would make the

customers of that utility feel good the about the commission.

Ethical, Moral, and Legal

The main concern about the ethics of this project is how much money should be spent if

the project is not feasible but is good for the environment. This question is one that GRPUC may

have to decide for the people who are their customers.

Economic and Manufacturing This project could have economic benefits for the community of Grand Rapids. As

mentioned above, if the hydro turbine saves the utility money, that money could be passed on to

the residents. It also could add jobs to the community. This may be done with the addition of

operators or in the form of the construction workers who would be needed to build the project. It

would also create jobs where the pipes, turbine, and other parts are made.

Engineering, Creativity, & Ingenuity The engineering creativity, for this project, is to find a way to capture the potential

energy that is resting in the ponds, at the wastewater treatment facility. If the team can find a way

to do this feasibly, it could be implemented in many places around the world. The biggest

obstacle to overcome in this project is the amount of head loss in the piping system and the

efficiencies of the turbine generator system.

51

Future work The next step for this project is for this feasibility study to be reviewed by GRPUC. The

board will need to determine whether or not to move forward with the project. If the board

chooses to move forward, then the next stage will be to ask MP if GRPUC will be able to create

this generator without violating their contract. Once MP says it is ok, the next stage will be to

have the numbers in this feasibility study verified by an engineering firm. Bids should be sought

out from manufacturers of all of the needed equipment and the new numbers could be reinserted

into the economic analysis spreadsheet to determine the new values for IRR, NPV, and payback

period. If these numbers still look good, then GRPUC can hire a firm to construct the hydro

turbine generator and pipe systems. If this system turns out to be useful for GRPUC they may

choose to offer this feasibility study to other public utilities so that they may check to see if

installing a system like this could work for them as well.

Conclusion The team used a computer simulation from their math model to determine the power

output of the system. This simulation was used for the economic feasibility of the project by

determining the total power output of the turbine generator. The total revenue produced by the

generator was less than the 5% IRR desired by the client, but it would produce about 2% IRR for

them. A physical model was created to verify the results found in the original options, and it was

found that slipping the pipe might be more difficult than was originally planned. The team also

looked at the reliability and contextual issues related to this project, and found that the system

would be very reliable with few problems.

It is the team’s recommendation to move forward with creating a hydro turbine

generation facility located at the base of the wastewater treatment plant effluent pipe. The

original concrete pipe should be slipped with a 30 inch polyethylene pipe up to the 45 degree

elbows located near the treatment plant. The pipe should then be continued to the plant with a

new trenched route directly to the effluent pipe valve house to reduce costs and increase the

lifespan of the system.

Financing will be decided by the client, but it is recommended that a combination of

loans, grants, and budgeted funds be used to fund the project. Conservation project budgeted

funds and grants should be used as much as possible which will reduce the client’s initial

financial burden. It is recommended that the system be set up for 70kW and be run for 12 hours

a day during the peak energy cost times and connected to the local GRPUC electrical grid so that

the most value can be gained from the stored energy of the water. Finally it is recommended that

a concrete block building be constructed to house the power plant near the Mississippi River due

to its aesthetics and long lifespan.

52

Bibliography

[

1]

"Operating Hydropower Sites in Minnesota," [Online]. Available:

http://www.dnr.state.mn.us/waters/surfacewater_section/stream_hydro/hydropower_sites.ht

ml. [Accessed October 2012].

[

2]

"Hydro Plant Operator," [Online]. Available: http://www.mymajors.com/education-

requirements/Hydro-Plant-Operator. [Accessed October 2012].

[

3]

"Hydroelectric-Station Operator," [Online]. Available: http://dot-job-

descriptions.careerplanner.com/HYDROELECTRIC-STATION-OPERATOR.cfm.

[Accessed October 2012].

[

4]

"How Hydropower Plants Work," [Online]. Available:

http://science.howstuffworks.com/environmental/energy/hydropower-plant1.htm. [Accessed

October 2012].

[

5]

"Hydroelectric power: How it Works," [Online]. Available:

http://ga.water.usgs.gov/edu/hyhowworks.html. [Accessed October 2012].

[

6]

"Water Tubine," [Online]. Available: http://en.wikipedia.org/wiki/Water_turbine.

[Accessed October 2012].

[

7]

[Online]. Available: http://otherpower.com/otherpower_hydro.html. [Accessed

October 2012].

[

8]

ASTM by Committee, ASTM A746-09 Standard Specification for Ductile Iron

Gravity Sewer Pipe, ASTM, 2009.

[

9]

L. B. M. Brown, Chemistry the Central Science 11E, Upper Saddle River, NJ:

Pearson Education, Inc., 2009.

[

10]

[Online]. Available: http://hydro.org/. [Accessed October 2012].

[

11]

[Online]. Available: http://www.venezuelatuya.com/guayana/gurieng.htm. [Accessed

October 2012].

[

12]

"Power Generation," PALL, [Online]. Available:

http://japanese.pall.com/pdf/PGHYDEN.pdf. [Accessed October 2012].

[ "Butterfly Valves," Vaphydro, [Online]. Available:

53

13] http://www.vaphydro.bg/butterfly.valves.php. [Accessed October 2012].

[

14]

"Concrete Price Considerations- Cost of Concrete," [Online]. Available:

http://www.concretenetwork.com/concrete-prices.html. [Accessed October 2012].

[

15]

"Cost to Install a Concrete Block," [Online]. Available:

http://www.homewyse.com/services/cost_to_install_concrete_block_wall.html. [Accessed

October 2012].

[

16]

"Build a Storage Shed Cost," [Online]. Available: http://www.fixr.com/costs/build-

storage-shed. [Accessed October 2012].

[

17]

"Cost for 20x40 Garage," Armstong Steel, [Online]. Available:

http://www.armstrongsteelbuildings.com/steel-buildings-faqs/need-20x40-garage-cost.php.

[Accessed October 2012].

[

18]

NERC, "The Energy Fix," 02 12 2011. [Online]. Available: www.theenergyfix.com.

[Accessed 08 10 2012].

[

19]

National Fire Protection Association, NFPA 70: National Electrical Code, NFPA,

2010.

[

20]

IEC, IEC Standard.

[

21]

"High Voltage Circuit Breaker About," Engineering Edge, Solutions By Design,

[Online]. Available:

http://www.engineersedge.com/instrumentation/components/high_voltage_circuit_breaker.ht

m. [Accessed October 2012].

[

22]

"The ABB Group - Automation and Power Technologies," ABB, [Online]. Available:

www.abb.com. [Accessed October 2012].

[

23]

"Transformer," [Online]. Available: http://hyperphysics.phy-

astr.gsu.edu/hbase/magnetic/transf.html. [Accessed October 2012].

[

24]

"Hydroelectric Power Generation," [Online]. Available:

http://users.owt.com/chubbard/gcdam/html/hydro.html. [Accessed October 2012].

[

25]

"Application Note: Introduction to Current Transformers," Elkor, [Online].

Available: http://www.elkor.net/pdfs/AN0305-Current_Transformers.pdf. [Accessed

October 2012].

54

[

26]

National Fire Protection Association, NFPA 70: National Electrical Code, NFPA,

2010.

[

27]

"National Enviornmental Policy Act," NEPA, [Online]. Available:

http://ceq.hss.doe.gov/. [Accessed October 2012].

[

28]

"Minesota Department of Natural Resources," MNDNR, [Online]. Available:

http://www.dnr.state.mn.us/index.html. [Accessed October 2012].

[

29]

M. D. o. N. Resources, Shoreland Management Rules, Chapter 6120.

[

30]

M. P. C. Agency, Stormwater Best Management Practices Manual, Saint Paul, MN:

Minnesota Pollution Control Agency, 2000.

[

31]

C. D. Department, Interviewee, [Interview]. October 2012.

[

32]

Kevin, Interviewee, Personal interview with: Kevin (LASTNAME) at Minnesota

Power on 10/14/2012. [Interview]. 14 October 2012.

[

33]

"Minnesota — Incentives/Policies for Renewables & Efficiency," DSIRE, [Online].

Available:

http://dsireusa.org/incentives/index.cfm?re=0&ee=0&spv=0&st=0&srp=1&state=MN.

[Accessed October 2012].

[

34]

"Options for Grants and Loans," Minnesota Department of Commerce, [Online].

Available: http://mn.gov/commerce/energy/topics/financial/Grants-Loans.jsp. [Accessed

October 2012].

[

35]

"Minnesota Power - Power Grant Program," DSIRE, [Online]. Available:

http://dsireusa.org/incentives/incentive.cfm?Incentive_Code=MN22F&re=0&ee=0.

[Accessed October 2012].

[

36]

"Renewable Development Fund (RDF)," DSIRE, [Online]. Available:

http://dsireusa.org/incentives/incentive.cfm?Incentive_Code=MN09R&re=0&ee=0.

[Accessed October 2012].

[

37]

"Overrview," Xcel Energy, [Online]. Available:

http://www.xcelenergy.com/Environment/Renewable_Energy/Renewable_Energy_Grants/R

enewable_Development_Fund?stateSelected=true. [Accessed October 2012].

55

[

38]

"Federal - Incentives/Policies for Renewables & Efficiency," DSIRE, [Online].

Available:

http://dsireusa.org/incentives/incentive.cfm?Incentive_Code=US53F&re=0&ee=0.

[Accessed October 2012].

[

39]

Client, Interviewee, [Interview]. 2012.

[

40]

[Online]. Available:

http://uuc1.poly.edu/ProfessionalTrainingProgram/Trenchless%20Technologies%20Manual.

pdf.

[

41]

P. Michael R. Lindeburg, Core Engineering Concepts for Students and Professionals,

Belmont, California: Professional Publications, Inc., 2010.

[

42]

Canyon Hydro, Small Crossflow Example Elevation, Deming, WA: Canyon Hydro,

2012.

[

43]

Performance Pipe, "Performance Pipe," 2012. [Online]. Available:

http://www.performancepipe.com/en-us/Documents/PP402%20Fatigue.PDF?Redirect=1.

[Accessed 23 11 2012].

[

44]

"List of NFPA Codes & Standards," NFPA, [Online]. Available:

http://www.nfpa.org/AboutTheCodes/List_of_codes_and_Standards.asp. [Accessed October

2012].

i

Appendix A

List of acronyms used

GRPUC – Grand Rapids Public Utilities Commission

IRE – Iron Range Engineering

IRR – Internal rate of return

NPV – Net present value

MP – Minnesota Power

NEC – National Electric Code

HVAC – Heating, ventilation, and air conditioning

PVC – Polyvinyl chloride

HDPE – High density polyethylene

LDPE – Low density polyethylene

ii

Appendix B

Creation of the turbine used in the experiment

iii

A turbine was needed for the GRPUC hydro turbine generator groups experiment. The

team looked to purchase an inexpensive turbine online but could not find any. The team then

looked to see if any pumps could be used backwards to act as a turbine. Most pumps were found

to not work well enough, but one option was found that could output a little energy. This option

was very inefficient and the team decided to pursue creating their own.

The team decided to construct a turbine using cut 2D sheets to construct into a whole.

The sheets were cut by IRE’s Hurricane laser CNC laser cutter (Figure 37).

The parts that were created included: a 10 bladed impellor (Figure 39), the inside walls

(Figure 40), and the outside walls, one with an outlet (Figure 41), one without (Figure 38). All

of the parts were fashioned with holes to allow for easy manufacturing. The Impellor had a

302mm hole in the center which was 6mm smaller than the diameter of the shaft that would fit

Figure 37 Hurricane Laser CNC laser cutter

Figure 39 Impeller Figure 40 Inside wall Figure 41 Outside with

outlet

Figure 38 Outside wall

without outlet

iv

through it. This caused a tight press fit and allows the impellor to spin the shaft. The outside

walls also required a press fit with the bearings that were used.

The pieces were then assembled and saved in a .idw Inventor drawing which was then

convertible into the .dxf format that was needed to run on the CNC laser cutter (Figure 42).

Figure 42 Assembled pieces ready to be cut by the laser printer

The Hurricane laser machine uses inputs from a .dxf file created by Autodesk Inventor.

From the file it creates a cutting path. The laser then needs to be set to run at specific speeds and

intensities. There are specific given values to run the machine at for different materials. Once

the speed and the intensity are set, the laser is ready to cut the parts.

The laser cuts the inside path of all of the lines it is given. That means that it cuts exactly

the distance on the inside cuts, or holes, but it cuts on the inside of the outer lines, that means the

outside cuts will be off by the width of the laser. Since this is small, and this part did not require

close tolerances, this was mentioned, but ignored while building the parts in Inventor.

The pieces were first cut out of wood (Figure 44,Figure 43), since the wood is cheaper

and easier to cut, it makes for a good practice cut to see how effective the parts will be.

Figure 44 Outer wall and inner wall cut from wood Figure 43 Broken wooden impeller

v

The walls looked good (Figure 44), but the impeller was breaking (Figure 43), this lead to

the second impeller design being thicker.

The second design was good but a few improvements were needed. First off the sharp

edges on the outside were creating leftover material to hang from the edges after it was cut on the

machine. The second problem was that the sharp edges on near the center were allowing the

impeller to crack if handled roughly (Figure 45). Finally the inner diameter of the whole was

expanded so that it would not crack when press fit onto the shaft. Fixing these problems lead to

the third, and final, design of the impeller (Figure 47).

Figure 46 Second design of the impeller cut from

plastic

Figure 45 Second design of the impellor breaking

on the inside

Figure 47 Final design of the impeller cut from plastic

vi

Figure 48 Failed drill hole and the top is a failed

jig saw cut

In order for water to flow into the impeller there needed to be a hole in the side of the

walls. A few ways to complete this were to drill a hole in the material after it was screwed

together, another option was to cut a hole in the sides and create a square piece to put into the

hole. The team experimented with these options and found that while you can drill a hole going

into the material, it was not practical to try to drill one in the side (Figure 49); and cutting the

material with a jig saw left the material scared but actually still together (Figure 48). It was

finally decided to cut out a new set of side walls that had the hole already missing (Figure 40)

and find a way to get a square piece to connect to the inlet hose.

The pieces were cut out of a large sheet of plastic (Figure 50) and the remainder of the

plastic was kept for other projects.

Figure 49 Failed drill hole into the sidewall

Figure 50 Large sheet of plastic with the designed pieces cut

from it

vii

Figure 51 Drill press used to press fit the impeller onto the

drive shaft

After the pieces were cut, the parts were assembled. The bearings and the impeller were

press fit into the outside wall and the drive shaft respectively (Figure 51).

The final product was screwed together and was ready for use. The only thing missing

was a square peg to fit into the hole to attach the turbine to the input hose. It was decided to buy

a ¾ inch metal pipe cap and have the end milled down so that it would fit into the hole. The

team found a hobbyist millwright who was willing to help them out and milled down the cap to

the perfect shape. The cap was placed into the final product and the turbine was ready to run.

Figure 53 Final assembly with second stage

pieces

Figure 52 Final assembly with final designs and

square plug inserted into the end to allow connection

to input hose

viii

The final product (Figure 55) was used to test the GRPUC hydro turbine generator groups

experiment (Figure 54).

Figure 55 Final product with input connector

Figure 54 Experimental setup using the crafted turbine

ix

Appendix C

Pictures of the economic analysis

x

xi

xii

xiii

Appendix D

Pictures of the GRPUC site

xiv

xv