Providing Clean Affordable Drinking Water North Dakota Water Users Joint Summer Meetings and Executive Briefing July 14, 2021 Grand Forks Regional Water Treatment Plant

Upload: others

Post on 01-Feb-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Grand Forks Regional Water Treatment Plant

Providing Clean Affordable Drinking Water

North Dakota Water UsersJoint Summer Meetings and Executive Briefing

July 14, 2021

Grand Forks Regional Water Treatment Plant

Page 2: Grand Forks Regional Water Treatment Plant

2

Page 3: Grand Forks Regional Water Treatment Plant

CONCEPT PLANNING & INTEGRATED

SYSTEM BUILDOUT

PILOTING/ENGINEERING

PROCESS

Funding & Implementation

COMBINING FOR THE FUTURE OF WATER IN GRAND FORKS

Page 4: Grand Forks Regional Water Treatment Plant

CONCEPT PLANNING & INTEGRATED SYSTEM BUILDOUT

Page 5: Grand Forks Regional Water Treatment Plant

Original WTP Site

5

Restricted Site Access

Constrained Process Areas

No Expansion Footprint

Security/Safety Concerns

Historical Neighborhood1968

Future Floodwall

1984

1956

Red River

Red Lake River

Page 6: Grand Forks Regional Water Treatment Plant

6

1997Major Flood Event

• $7 Million in Flood Recovery at WTP

• $3 Million in Flood Recovery in Distribution System Upgrades

• Demonstrated Need for a New Plan

Page 7: Grand Forks Regional Water Treatment Plant

Building Around a Unified Concept

7

$52 M in investment 2002 - 2012RESIDUALS PONDS

EXISTING RESIDUALS FORCE MAIN

TRANSMISSION MAINS

INTAKE

CLEARWELL & PUMP STATION

Page 8: Grand Forks Regional Water Treatment Plant

GFWTP Condition Evaluation▷ Identified major challenges at existing facility ▷GFWTP is in poor condition

Technology Pilot Testing▷ Ozone with biological filtration▷ Pretreatment plate settlers▷ Ultrafiltration▷ Reverse osmosis

8

1898

HISTORICAL RECENT PAST CURRENT1894 1968 1997 2021

2007

2007-

2014

Grand Forks Regional WTP Technology and Capacity Evaluation▷ Water demand & capacity projections▷ Long-term technology evaluation▷ Facility tours▷ Pilot testing recommendations

2010-

2014

2012 Devils Lake Impacts▷ New and changing water quality

issues

2014

Kepner-Tregoe Analysis▷ Compared 3 Treatment Alts▷ Incorporated Non-Monetary

Considerations into Decision ProcessResulting Hybrid Treatment Approach

2015-

2020Design & Construction of GFRWTP▷ Included Value Engineering to reduce

cost

July 17

2020Regional WTP Operational

2008$2.8 Million in Interim Improvements▷ Extend Useful Life for Long-term

planning

Timeline of WTP Development

Page 9: Grand Forks Regional Water Treatment Plant

New WTP Design

PILOTING/ENGINEERING PROCESS

Page 10: Grand Forks Regional Water Treatment Plant

Source Water Issues SOURCE WATERS BLENDED TO OPTIMIZE

WATER QUALITY AND OPERATIONS

• Lower Turbidity• Lower Hardness• Lower Sulfate Content• Higher Organics

CONVENTIONAL

LIME SOFTENING TREATMENT

PLANT

RAW WATER INTAKE

• Higher Turbidity• Higher Hardness• Higher Sulfate Content• Lower Organics

Page 11: Grand Forks Regional Water Treatment Plant

Kepner-Tregoe Analysis

11

Clarify Purpose and Goals

Evaluate Alternatives

Assess Risks & Opinions

Make a Balanced Decision

Engage Stakeholders

Page 12: Grand Forks Regional Water Treatment Plant

Selected Approach

12

GRAND FORKS REGIONAL WATER TREATMENT FACILITY▪ Selected Conventional Lime / Membrane Hybrid Facility ▪ 20 MGD Facility - Expandable to 40 MGD▪ Long-term building footprint – 50-year asset on a 100-year Campus ▪ Industrial Park site to tie into future Economic Development

Page 13: Grand Forks Regional Water Treatment Plant

FUNDING AND IMPLEMENTATION

Page 14: Grand Forks Regional Water Treatment Plant

Funding Partnership

14

Loss of Federal Participation

Federal/State/Local becomes

State/Local

Page 15: Grand Forks Regional Water Treatment Plant

Delivery Process

▪ Construction Manager at Risk

15

TOTAL BID PACKAGES

55 Allowed for SRF / Non-SRF Bidding

Page 16: Grand Forks Regional Water Treatment Plant

Local Buy-In & Choice

16

• 2017 Voters Enacted a New ½ Cent Sales Tax

• Dedicated to Street Investment & Water Infrastructure

• Funds Portion of Local Cost-Share Debt Service

Page 17: Grand Forks Regional Water Treatment Plant

RESULTS

Page 18: Grand Forks Regional Water Treatment Plant

Critical Piece to City-wide Planning

18

Page 19: Grand Forks Regional Water Treatment Plant

Grand Forks Regional WTP

Page 20: Grand Forks Regional Water Treatment Plant

Control Room

Page 21: Grand Forks Regional Water Treatment Plant

Training/Breakroom Area

Page 22: Grand Forks Regional Water Treatment Plant

Pretreatment

Page 23: Grand Forks Regional Water Treatment Plant

Pretreatment

Page 24: Grand Forks Regional Water Treatment Plant

Softening Basin

Page 25: Grand Forks Regional Water Treatment Plant

Ozone Generation

Page 26: Grand Forks Regional Water Treatment Plant

Biological Activated Carbon Gravity Filters

Page 27: Grand Forks Regional Water Treatment Plant

Ultrafiltration Membrane Basins

Page 28: Grand Forks Regional Water Treatment Plant

Ultrafiltration Equipment

Page 29: Grand Forks Regional Water Treatment Plant

Reverse Osmosis Membrane Skids

Page 30: Grand Forks Regional Water Treatment Plant

Reverse Osmosis Pre-Filters & Pumps

Page 31: Grand Forks Regional Water Treatment Plant

Thanks!

For more information visit: grandforksgov.com

Regional WTP Tour –tomorrow Starting at 8AM