grade separated interchange at the intersection of … stgec - grade...need for project: “the...

48
Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Upload: others

Post on 17-Jul-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Jeff Sizemore, P.E.

Geotechnical Design Support Engineer

SCDOT

Ed Tavera, P.E.

Principal

Geotechnical Engineer

Geoengineers

Grade separated interchange

at the intersection of

U.S. Hwy 17 Bypass and

Farrow Parkway

Page 2: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Need for Project:

“The purpose of the project is to

improve traffic flow, increase

intersection capacity, and improve

safety within the intersection and

along US 17. The US 17 and SC 707/

Farrow Parkway intersection is

currently experiencing substantial

congestion during peak morning and

afternoon travel periods.”

Page 3: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Project Site

Enlarged Map

Zone Project Site

Page 4: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Existing US 17 Bypass

US17 BP

East

Page 5: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Proposed US17 Bypass

US 17 BP

Page 6: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Project Layout

South Bridge

Approach

Ramp BRamp A

Ramp CRamp D

North Bridge

Approach

Backgate Bridge

End

Bent 1

End

Bent 7

Page 7: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

South Subsurface Profile

Page 8: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

North Subsurface Profile

Page 9: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Project Design Constraints

• Project Geometry and Layout – Project Constructed on

Existing Alignment

• Complex Traffic Control Staging Plan (Geotechnical

Designs Constructed in Stages 2, 3, and 4)

• Total Project Construction Time Requirements – Approx.

3.5 years

• High Traffic Volume Combined with Limited Construction

Staging Areas

Page 10: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Geotechnical Key Issues

• Consolidation Settlement

• Seismic Slope Stability (Liquefaction)

• Bridge Abutment Foundation Performance

Extreme Event I and II

Page 11: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Settlement At Bridge Abutments(Normal Weight Fill)

Page 12: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Longitudinal Seismic

Slope Instability

Page 13: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Transverse Seismic

Slope Instability

Page 14: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Bridge Abutment Unimproved

Foundation Performance

Bridge

Sa

nd

Me

diu

m C

lay

Sti

ff C

lay

(Pe

e D

ee

Fo

rma

tio

n)

Row 3 2 1

Lateral Load

Axial

Load

66 -

HP

14

X11

7 X

10

0 f

t lo

ng

40 feet

90 feet

End Bent 7

(North Abutment)

Extreme Event II

Extreme Event I

Excessive

Page 15: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Ground Improvement Methods

• Lightweight Aggregate Borrow Material – Reduce

Magnitude of Settlement

• Prefabricated Vertical Drain (PVD) / Granular

Surcharges – Increased Rate of Settlement during

Construction

• Deep Soil Mixing – Seismic Slope Stability and Bridge

Abutment Foundation Improved Performance

• Mechanically Stabilized Earth (MSE) Walls –

Permanent and Temporary Retaining Walls

Page 16: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Lightweight Aggregate (Rotary Kilin Produced)

Required Properties:

• Internal Friction Angle 40 degrees

• Unit Weight: 60 pcf minimum (Long-term 70 pcf maximum)

• MSE Wall Reinforced Backfill Properties

Page 17: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Settlement South

Bridge Abutment (End Bent 1)

Page 18: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Settlement North

Bridge Abutment (End Bent 7)

Page 19: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Prefabricated Vertical Drains (PVD)

Page 20: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

PVD

PVD Triangular Installation Pattern

PVD

S

2’ Drainage Sand Layer

Geotextile Separator Fabric

PVD Installation

Page 21: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Granular Surcharges

Lightweight Aggregate Borrow Material

Granular Surcharge

Required Properties:

• Internal Friction Angle 32 degrees

• Unit Weight: 120 pcf

Page 22: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Seismic Slope Stability Improved

Deep Soil Mixing

Page 23: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Stage 4 – Ground Improvement

North/South Abutment (Typical)

Page 24: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Deep Soil MixingLime-Cement Columns

Block Type Pattern - Overlapping(Dry Mix Method)

• Seismic Slope Stabilization – Shear Key

• Improved Performance of Bridge Abutment Foundations

Page 25: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Legend

Test Lime-Cement Columns (Test LCC)

DSM-LCC Test Section 1

(Block Type Pattern)

DSM-LCC Test Section 2

(Single Line Pattern)

10 Feet Min.

10 F

eet

Min

.

Test LCC

No.

1 2 3 4

Test Pile 1 (HP

14x117)

Test LCC Sampling

Quadrants

1 2

4 3

DSM-LCC Test Sections

Page 26: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

End Bent 7

(North Abutment)

Extreme Event II

(Case 3)

< 1/8”

Bridge Abutment Improved

Foundation Performance

End Bent 7

(North Abutment)

Extreme Event I

< ¼”

Page 27: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Settlement Monitoring

• 12 VW Settlement Sensors (SS)

• 15 VW Piezometers (P)

• 2 VW Data Collection Centers

• 10 Settlement Plates (SP)

• 2 Magnetic Extensometer (ME)

Slope Stability

• 6 Slope Indicator

Geotechnical Instrumentation

Page 28: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Control

Stage 2

Ramp BRamp A

Page 29: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Stage 2 – Ground Improvement

Ramp BRamp A

• MSE Walls

• Lightweight Aggregate Borrow Material

• 2’, and 3’ Granular Surcharge (Normal Weight)

• 3’ and 4’ Triangular Spacing PVD

• Geotechnical Instrumentation

Page 30: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Control

Stage 3

Ramp CRamp D

Page 31: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Stage 3 -Ground Improvement

Ramp CRamp B

• MSE Walls

• Lightweight Aggregate Borrow Material

• 1’, 2’, and 4’ Granular Surcharge (Normal Weight)

• 3’ and 4’ Triangular Spacing PVD

• Geotechnical Instrumentation

Page 32: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Control

Stage 4

South Bridge

Approach

North Bridge

Approach

Backgate Bridge

Page 33: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Traffic Stage 4 -Ground Improvement

BridgeSouth

Bridge

Approach

South

Bridge

Approach

• MSE Walls

• Lightweight Aggregate Borrow Material

• 1’, 2’, and 3’ Granular Surcharge (Normal Weight)

• 3’ Triangular Spacing PVD

• Geotechnical Instrumentation

• Bridge Abutment DSM-LCC

(South 30’ x 133’ x 50’deep – North 30’ x 141’ x 70’deep )

• Longitudinal DSM-LCC (South 5’ Wide / North 8’ Wide)

Page 34: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

X- Section End Bent 7 (250+26)

Page 35: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

X- Section End Bent 7 (252+00)

Page 36: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Initial MSE Wall Construction(2 & 3 Stage Wall Construction)

Drainage

Pipe

MSE Wall Soil Reinforcement

BReqLight Weight Aggregate

Flexible

Wire

Facing

Geotextile Separator Fabric

Page 37: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Light Weight Aggregate

Borrow Material

Sand Surcharge Sand Surcharge

2-Stage MSE Wall Construction(Stage 1 of 2)

Flexible

Wire

Facing

Page 38: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Lightweight Aggregate

1’ Minimum

2’ Maximum

Fill Void

w/Light Weight Fill

Precast Concrete

Segmental Panel

Flexible Wire

Facing

Precast

Concrete

Panel

Connector

Permanent Precast Concrete Segmental Panel

Page 39: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

6” Maximum Void

Precast or

Cast-In-Place

Full Height

Concrete Panel

Facing

Flexible Wire

Facing

Deadman Anchor

Permanent Full Height Concrete Panel

(Pre-Cast or Cast-In-Place)

Fill Void

w/Lightweight

Aggregate

Lightweight Aggregate

Page 40: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

MSE WallsPermanent MSE Walls

• Two-Stage Construction

• Three-Stage Construction (w/Drainage Structures)

Temporary MSE Walls

(Welded Wire Mesh Facing)

Page 41: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Light Weight Fill

Sand Surcharge Sand Surcharge

3-Stage MSE Wall Construction

With Drainage Structure (Stage 1 of 3)

Flexible Wire

Facing Drainage Structure Blockout Area

Page 42: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Lightweight Aggregate

Flexible Wire

Facing Drainage Pipe

3-Stage MSE Wall Construction

With Drainage Pipe (Stage 2 of 3)

Page 43: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Lightweight Aggregate

Flexible Wire

FacingStructural Frame

3-Stage MSE Wall Construction

With Drainage Structure (Stage 2 of 3)

Page 44: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Light Weight Fill

3-Stage MSE Wall Construction

With Drainage Structure (Stage 2 of 3)

Flexible Wire

Facing

Page 45: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

2 Feet Thick Cover of Borrow

Silty or Clayey Soil Materials

Lightweight Aggregate

Borrow Material

4 Feet Long Biaxial

Geogrids Placed on 2 Feet

Vertical Spacing

Minimum 2 Feet

Drainage Layer

Page 46: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Project Construction Phase

(North Abutment – Sta. 252+00)

Ramp B

Stage 2

Ramp D

Stage 3

Bridge Approach Embankment

Stage 4

Page 47: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Bridge Abutment Construction

(North Abutment – End Bent 7)

Page 48: Grade separated interchange at the intersection of … STGEC - Grade...Need for Project: “The purpose of the project is to improve traffic flow, increase intersection capacity, and

Thank YouAny Questions?

US 17- Bypass Over SC707/Farrow Parkway (Backgate Bridge)Myrtle Beach, SCHorry County