graber - dam removal project overview
TRANSCRIPT
-
8/6/2019 Graber - Dam Removal Project Overview
1/54
Dam RemovalDam RemovalProject OverviewProject Overview
Dam Removal DemystifiedDam Removal Demystified
North CarolinaNorth Carolina
June 14, 2011June 14, 2011
Brian GraberBrian Graber
American RiversAmerican Rivers
-
8/6/2019 Graber - Dam Removal Project Overview
2/54
Removing a dam seems like
an intimidating process
-
8/6/2019 Graber - Dam Removal Project Overview
3/54
Youd like to manage a
project
-
8/6/2019 Graber - Dam Removal Project Overview
4/54
Goals:
1) Understand thedam removal process
2) Be able to scope
out the componentsof a project
-
8/6/2019 Graber - Dam Removal Project Overview
5/54
-
8/6/2019 Graber - Dam Removal Project Overview
6/54
Expect that projects will take3 years to complete
Year 1: Recon. andPrelim. Design Year 2: Designand Permitting Year 3:Implementation
Overall Process: Project StepsOverall Process: Project Steps
-
8/6/2019 Graber - Dam Removal Project Overview
7/54
The basic steps cover 4 major topics
Design/ConstructionDesign/ConstructionPermittingPermitting
FundraisingFundraising Social IssuesSocial Issues
Overall Process: Project StepsOverall Process: Project Steps
-
8/6/2019 Graber - Dam Removal Project Overview
8/54
Determine the challenges specific to your project
Sediment quantity
Sediment quality
Dam size
Dam condition
Impoundment size
Impoundment shape
Surrounding infrastructure
Surrounding environment
The depth of analysis should reflect the scale of the project:make easy projects easy and complex projects complex
Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance
-
8/6/2019 Graber - Dam Removal Project Overview
9/54
Step 1: The dam owner must be on
board with the project
Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance
-
8/6/2019 Graber - Dam Removal Project Overview
10/54
Several factors separate easyprojects from difficult projects
Land ownership Current dam uses Public interest
Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance
l f
-
8/6/2019 Graber - Dam Removal Project Overview
11/54
Several factors separate easyprojects from difficult projects
Contaminants T & E species Infrastructure
Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance
l /d
-
8/6/2019 Graber - Dam Removal Project Overview
12/54
Dam removal science/design
includes 6 components
DataDataCollection/Collection/
SurveyingSurveying
ProtectingProtecting
InfrastructureInfrastructure
SpeciesSpecies
ProtectionProtection
Hydrology/Hydrology/
HydraulicsHydraulicsSedimentSediment
ManagementManagement
SiteSite--SpecificSpecific
IssuesIssues
-
8/6/2019 Graber - Dam Removal Project Overview
13/54
Consider long-term benefits vs. short-term impacts
ComplexityComplexityContinuityContinuity
Flow RegimeFlow Regime
Water QualityWater Quality
Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm
-
8/6/2019 Graber - Dam Removal Project Overview
14/54
Some short-term impacts occurduring construction
Sediment movement Construction access Habitat change
Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm
-
8/6/2019 Graber - Dam Removal Project Overview
15/54
There are 3 potential long-term impactsif not managed well
Contaminants T & E species Infrastructure
Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm
-
8/6/2019 Graber - Dam Removal Project Overview
16/54
Data Collection and Surveying
DataDataCollection/Collection/
SurveyingSurveying
-
8/6/2019 Graber - Dam Removal Project Overview
17/54
Survey dam structure, longitudinal profile,cross sections, and sediment depths
-
8/6/2019 Graber - Dam Removal Project Overview
18/54
Survey long profile through impoundment;survey cross sections to capture change
Design Components: Data Collection/SurveyingDesign Components: Data Collection/Surveying
-
8/6/2019 Graber - Dam Removal Project Overview
19/54Design Components: Data Collection/SurveyingDesign Components: Data Collection/Surveying
-
8/6/2019 Graber - Dam Removal Project Overview
20/54
Hydrology/Hydraulics
Hydrology/Hydrology/HydraulicsHydraulics
Wh h diff b h d l
-
8/6/2019 Graber - Dam Removal Project Overview
21/54
Whats the difference between hydrologyand hydraulics?
Hydraulics:
Depths and velocitiesof flows
Hydrology:
Magnitudes andprobabilities of flows
Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics
D d id
-
8/6/2019 Graber - Dam Removal Project Overview
22/54
Does your dam provideflood control?
Probably not
Flood Storage Potential:has storage volume and flow
through a controlled outlet
No Flood Storage Potential:
has full impoundment and
constant flow over spillway
Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics
-
8/6/2019 Graber - Dam Removal Project Overview
23/54
Whats a HEC-RAS and when do you need one?
Infrastructure protection
To prove fish passage
Post-project water levels for stakeholders
Advanced sediment transport modeling To address flood control?
Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics
-
8/6/2019 Graber - Dam Removal Project Overview
24/54
Sediment Management
SedimentSediment
ManagementManagement
-
8/6/2019 Graber - Dam Removal Project Overview
25/54
Some general sediment thoughts
Not all sediment movesNot all sediment movesNot all dams have a lot of sedimentNot all dams have a lot of sediment
Consider background yieldConsider background yield Sediment can be beneficial or harmfulSediment can be beneficial or harmful
Design Components: Sediment ManagementDesign Components: Sediment Management
Assess the quantity particle sizes quality and
-
8/6/2019 Graber - Dam Removal Project Overview
26/54
Assess the quantity, particle sizes, quality, andpotential mobility of impounded sediment
Potential mobilityPotential mobilityQualityQuality
QuantityQuantity Particle sizesParticle sizes
Design Components: Sediment ManagementDesign Components: Sediment Management
-
8/6/2019 Graber - Dam Removal Project Overview
27/54
The longitudinal profile is a fundamentalsediment analysis tool
Ox Pasture Brook Longitudinal Profile - 8/22/06
76.00
78.00
80.00
82.00
84.00
86.00
88.00
90.00
92.00
94.00
96.00
0.0 200.0 400.0 600.0 800.0 1000.0 1200.0 1400.0
Distance (ft)
Relative
Eleva
tion
(ft)
Sediment Surface
Water Surface
Bed Surface
Design Components: Sediment ManagementDesign Components: Sediment Management
T t di t f t i t d t
-
8/6/2019 Graber - Dam Removal Project Overview
28/54
Test sediment for contaminants and compare toecological and human risk thresholds
Complete due diligence
Assess quantity of sediment
Collect sediment cores (notgrabs)
Test for organics and heavymetals
Compare test concentrations
to human risk and ecologicalthresholds
Design Components: Sediment ManagementDesign Components: Sediment Management
-
8/6/2019 Graber - Dam Removal Project Overview
29/54
There are several approaches to managing cleansediment (depending on quantity and particle sizes)
Natural erosion
Sediment removal (dredging) Stabilize in place
Open dam gates
Remove dam slowly
Remove dam in stages
Combined approaches
Design Components: Sediment ManagementDesign Components: Sediment Management
-
8/6/2019 Graber - Dam Removal Project Overview
30/54
There are fewer approaches to managingcontaminated sediment
Management options
Remove and dispose Isolate and cap
If contaminant management is necessary,can greatly add to cost of project
Conundrum: dams are not goodhazardous waste containment facilities
Design Components: Sediment ManagementDesign Components: Sediment Management
-
8/6/2019 Graber - Dam Removal Project Overview
31/54
Protecting Infrastructure
ProtectingProtecting
InfrastructureInfrastructure
L k i d l i d t d i th d
-
8/6/2019 Graber - Dam Removal Project Overview
32/54
Look in and along impoundment and in the damfor at-risk bridges, retaining walls, or utilities
Design Components: Protecting InfrastructureDesign Components: Protecting Infrastructure
-
8/6/2019 Graber - Dam Removal Project Overview
33/54
Assess whether any infrastructure is at riskConsider if infrastructure can be moved first; next consider direct stabilization
Design Components: Protecting InfrastructureDesign Components: Protecting Infrastructure
Bridges Retainingwalls
Utilities
Species Protection and Additional
-
8/6/2019 Graber - Dam Removal Project Overview
34/54
Species Protection and AdditionalRestoration (beyond structure removal)
SpeciesSpecies
ProtectionProtection
-
8/6/2019 Graber - Dam Removal Project Overview
35/54
Identify if species of concern could beaffected by dam removal
Submit species info request to North Carolina
Natural Heritage Program (http://www.ncnhp.org/)
Design Components: Species ProtectionDesign Components: Species Protection
M f A i S i
-
8/6/2019 Graber - Dam Removal Project Overview
36/54
Manage for Aquatic Species
Monitor during constructionMonitor during constructionRelocate speciesRelocate species
Time the removalTime the removal Manage sedimentManage sediment
Design Components: Species ProtectionDesign Components: Species Protection
-
8/6/2019 Graber - Dam Removal Project Overview
37/54
Site-Specific Issues
SiteSite--SpecificSpecific
IssuesIssues
-
8/6/2019 Graber - Dam Removal Project Overview
38/54
Dam uses can oftenbe replaced
Design Components: SiteDesign Components: Site--Specific IssuesSpecific Issues
-
8/6/2019 Graber - Dam Removal Project Overview
39/54
Other site-specific issues:
well impacts, ice jams, parks, walkingtrails, renderings, etc.
Design Components: SiteDesign Components: Site--Specific IssuesSpecific Issues
-
8/6/2019 Graber - Dam Removal Project Overview
40/54
DataData
Collection/Collection/SurveyingSurveying
ProtectingProtectingInfrastructureInfrastructure
SpeciesSpeciesProtectionProtection
Hydrology/Hydrology/
HydraulicsHydraulics
SedimentSediment
ManagementManagement
SiteSite--SpecificSpecificIssuesIssues
-
8/6/2019 Graber - Dam Removal Project Overview
41/54
What will a dam removal cost?
The data set
225 total projects nationwide with cost data
median dam height is 9 feet
range 2 ft to 85 ft 92% were less than 25 ft
$77,582 median total project cost
in 2010 dollars
range $1,769 to $5.9 million
60 projects from PA
M di t t l j t t
-
8/6/2019 Graber - Dam Removal Project Overview
42/54
Median total project costs:
can be standardized by dam height
Dam Removal Costs
-
8/6/2019 Graber - Dam Removal Project Overview
43/54
Feasibility + Design + Permitting is25% of total project cost (median)
Dam Removal Costs
Wh t i it th t h
-
8/6/2019 Graber - Dam Removal Project Overview
44/54
What is it worth to havea streamlined process?
Dam Removal CostsDam Removal Costs
-
8/6/2019 Graber - Dam Removal Project Overview
45/54
Many funding sources exist
US Fish and Wildlife Service
National Oceanic and Atmospheric Administration
Natural Resources Conservation Service
State funds (Clean Water, DWR, EEP)
Corporate Donations
Private foundations
Funding for Dam RemovalFunding for Dam Removal
-
8/6/2019 Graber - Dam Removal Project Overview
46/54
Most funding hooks are environmental
Diadromous Fish Resident Species Listed Species
Funding for Dam RemovalFunding for Dam Removal
Who does the work?
-
8/6/2019 Graber - Dam Removal Project Overview
47/54
Who does the work?
Along with experience look for non-
-
8/6/2019 Graber - Dam Removal Project Overview
48/54
Along with experience, look for non-technical skills and integration of skills
Important non-technical skills:
Responsiveness and project
management Permitting
Presentation skills
Willingness to advocate forresource and project
No one firm is truly good
at all of these
Hiring Consultants
Integration of technical skills:
Engineering
Geomorphology Ecology
Traditional engineers may miss river context and habitat
-
8/6/2019 Graber - Dam Removal Project Overview
49/54
Hiring Consultants: Skill Integration
g y
Blend geomorphology ecology and engineering skills:
-
8/6/2019 Graber - Dam Removal Project Overview
50/54
Blend geomorphology, ecology, and engineering skills:
There are several approaches to
-
8/6/2019 Graber - Dam Removal Project Overview
51/54
There are several approaches toremoving a structure
Explosives Heavy Machinery By Hand
Fi l l d i h i d
-
8/6/2019 Graber - Dam Removal Project Overview
52/54
First, slowly drain the impoundment
Most commonly a backhoe with a hydraulic hammer will
-
8/6/2019 Graber - Dam Removal Project Overview
53/54
Most commonly a backhoe with a hydraulic hammer willbreach one side and then move across
Construction ApproachesConstruction Approaches
-
8/6/2019 Graber - Dam Removal Project Overview
54/54
Brian GraberBrian Graber
American RiversAmerican Rivers
[email protected]@americanrivers.org
Dam Removal Clearinghouse:Dam Removal Clearinghouse:http://www.lib.berkeley.edu/WRCA/damremoval/index.htmlhttp://www.lib.berkeley.edu/WRCA/damremoval/index.html