graber - dam removal project overview

Upload: restoration-systems-llc

Post on 07-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Graber - Dam Removal Project Overview

    1/54

    Dam RemovalDam RemovalProject OverviewProject Overview

    Dam Removal DemystifiedDam Removal Demystified

    North CarolinaNorth Carolina

    June 14, 2011June 14, 2011

    Brian GraberBrian Graber

    American RiversAmerican Rivers

  • 8/6/2019 Graber - Dam Removal Project Overview

    2/54

    Removing a dam seems like

    an intimidating process

  • 8/6/2019 Graber - Dam Removal Project Overview

    3/54

    Youd like to manage a

    project

  • 8/6/2019 Graber - Dam Removal Project Overview

    4/54

    Goals:

    1) Understand thedam removal process

    2) Be able to scope

    out the componentsof a project

  • 8/6/2019 Graber - Dam Removal Project Overview

    5/54

  • 8/6/2019 Graber - Dam Removal Project Overview

    6/54

    Expect that projects will take3 years to complete

    Year 1: Recon. andPrelim. Design Year 2: Designand Permitting Year 3:Implementation

    Overall Process: Project StepsOverall Process: Project Steps

  • 8/6/2019 Graber - Dam Removal Project Overview

    7/54

    The basic steps cover 4 major topics

    Design/ConstructionDesign/ConstructionPermittingPermitting

    FundraisingFundraising Social IssuesSocial Issues

    Overall Process: Project StepsOverall Process: Project Steps

  • 8/6/2019 Graber - Dam Removal Project Overview

    8/54

    Determine the challenges specific to your project

    Sediment quantity

    Sediment quality

    Dam size

    Dam condition

    Impoundment size

    Impoundment shape

    Surrounding infrastructure

    Surrounding environment

    The depth of analysis should reflect the scale of the project:make easy projects easy and complex projects complex

    Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance

  • 8/6/2019 Graber - Dam Removal Project Overview

    9/54

    Step 1: The dam owner must be on

    board with the project

    Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance

  • 8/6/2019 Graber - Dam Removal Project Overview

    10/54

    Several factors separate easyprojects from difficult projects

    Land ownership Current dam uses Public interest

    Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance

    l f

  • 8/6/2019 Graber - Dam Removal Project Overview

    11/54

    Several factors separate easyprojects from difficult projects

    Contaminants T & E species Infrastructure

    Overall Process: Initial ReconnaissanceOverall Process: Initial Reconnaissance

    l /d

  • 8/6/2019 Graber - Dam Removal Project Overview

    12/54

    Dam removal science/design

    includes 6 components

    DataDataCollection/Collection/

    SurveyingSurveying

    ProtectingProtecting

    InfrastructureInfrastructure

    SpeciesSpecies

    ProtectionProtection

    Hydrology/Hydrology/

    HydraulicsHydraulicsSedimentSediment

    ManagementManagement

    SiteSite--SpecificSpecific

    IssuesIssues

  • 8/6/2019 Graber - Dam Removal Project Overview

    13/54

    Consider long-term benefits vs. short-term impacts

    ComplexityComplexityContinuityContinuity

    Flow RegimeFlow Regime

    Water QualityWater Quality

    Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm

  • 8/6/2019 Graber - Dam Removal Project Overview

    14/54

    Some short-term impacts occurduring construction

    Sediment movement Construction access Habitat change

    Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm

  • 8/6/2019 Graber - Dam Removal Project Overview

    15/54

    There are 3 potential long-term impactsif not managed well

    Contaminants T & E species Infrastructure

    Design Components: LongDesign Components: Long--Term Benefits/ShortTerm Benefits/Short--TermTerm

  • 8/6/2019 Graber - Dam Removal Project Overview

    16/54

    Data Collection and Surveying

    DataDataCollection/Collection/

    SurveyingSurveying

  • 8/6/2019 Graber - Dam Removal Project Overview

    17/54

    Survey dam structure, longitudinal profile,cross sections, and sediment depths

  • 8/6/2019 Graber - Dam Removal Project Overview

    18/54

    Survey long profile through impoundment;survey cross sections to capture change

    Design Components: Data Collection/SurveyingDesign Components: Data Collection/Surveying

  • 8/6/2019 Graber - Dam Removal Project Overview

    19/54Design Components: Data Collection/SurveyingDesign Components: Data Collection/Surveying

  • 8/6/2019 Graber - Dam Removal Project Overview

    20/54

    Hydrology/Hydraulics

    Hydrology/Hydrology/HydraulicsHydraulics

    Wh h diff b h d l

  • 8/6/2019 Graber - Dam Removal Project Overview

    21/54

    Whats the difference between hydrologyand hydraulics?

    Hydraulics:

    Depths and velocitiesof flows

    Hydrology:

    Magnitudes andprobabilities of flows

    Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics

    D d id

  • 8/6/2019 Graber - Dam Removal Project Overview

    22/54

    Does your dam provideflood control?

    Probably not

    Flood Storage Potential:has storage volume and flow

    through a controlled outlet

    No Flood Storage Potential:

    has full impoundment and

    constant flow over spillway

    Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics

  • 8/6/2019 Graber - Dam Removal Project Overview

    23/54

    Whats a HEC-RAS and when do you need one?

    Infrastructure protection

    To prove fish passage

    Post-project water levels for stakeholders

    Advanced sediment transport modeling To address flood control?

    Design Components: Hydrology/HydraulicsDesign Components: Hydrology/Hydraulics

  • 8/6/2019 Graber - Dam Removal Project Overview

    24/54

    Sediment Management

    SedimentSediment

    ManagementManagement

  • 8/6/2019 Graber - Dam Removal Project Overview

    25/54

    Some general sediment thoughts

    Not all sediment movesNot all sediment movesNot all dams have a lot of sedimentNot all dams have a lot of sediment

    Consider background yieldConsider background yield Sediment can be beneficial or harmfulSediment can be beneficial or harmful

    Design Components: Sediment ManagementDesign Components: Sediment Management

    Assess the quantity particle sizes quality and

  • 8/6/2019 Graber - Dam Removal Project Overview

    26/54

    Assess the quantity, particle sizes, quality, andpotential mobility of impounded sediment

    Potential mobilityPotential mobilityQualityQuality

    QuantityQuantity Particle sizesParticle sizes

    Design Components: Sediment ManagementDesign Components: Sediment Management

  • 8/6/2019 Graber - Dam Removal Project Overview

    27/54

    The longitudinal profile is a fundamentalsediment analysis tool

    Ox Pasture Brook Longitudinal Profile - 8/22/06

    76.00

    78.00

    80.00

    82.00

    84.00

    86.00

    88.00

    90.00

    92.00

    94.00

    96.00

    0.0 200.0 400.0 600.0 800.0 1000.0 1200.0 1400.0

    Distance (ft)

    Relative

    Eleva

    tion

    (ft)

    Sediment Surface

    Water Surface

    Bed Surface

    Design Components: Sediment ManagementDesign Components: Sediment Management

    T t di t f t i t d t

  • 8/6/2019 Graber - Dam Removal Project Overview

    28/54

    Test sediment for contaminants and compare toecological and human risk thresholds

    Complete due diligence

    Assess quantity of sediment

    Collect sediment cores (notgrabs)

    Test for organics and heavymetals

    Compare test concentrations

    to human risk and ecologicalthresholds

    Design Components: Sediment ManagementDesign Components: Sediment Management

  • 8/6/2019 Graber - Dam Removal Project Overview

    29/54

    There are several approaches to managing cleansediment (depending on quantity and particle sizes)

    Natural erosion

    Sediment removal (dredging) Stabilize in place

    Open dam gates

    Remove dam slowly

    Remove dam in stages

    Combined approaches

    Design Components: Sediment ManagementDesign Components: Sediment Management

  • 8/6/2019 Graber - Dam Removal Project Overview

    30/54

    There are fewer approaches to managingcontaminated sediment

    Management options

    Remove and dispose Isolate and cap

    If contaminant management is necessary,can greatly add to cost of project

    Conundrum: dams are not goodhazardous waste containment facilities

    Design Components: Sediment ManagementDesign Components: Sediment Management

  • 8/6/2019 Graber - Dam Removal Project Overview

    31/54

    Protecting Infrastructure

    ProtectingProtecting

    InfrastructureInfrastructure

    L k i d l i d t d i th d

  • 8/6/2019 Graber - Dam Removal Project Overview

    32/54

    Look in and along impoundment and in the damfor at-risk bridges, retaining walls, or utilities

    Design Components: Protecting InfrastructureDesign Components: Protecting Infrastructure

  • 8/6/2019 Graber - Dam Removal Project Overview

    33/54

    Assess whether any infrastructure is at riskConsider if infrastructure can be moved first; next consider direct stabilization

    Design Components: Protecting InfrastructureDesign Components: Protecting Infrastructure

    Bridges Retainingwalls

    Utilities

    Species Protection and Additional

  • 8/6/2019 Graber - Dam Removal Project Overview

    34/54

    Species Protection and AdditionalRestoration (beyond structure removal)

    SpeciesSpecies

    ProtectionProtection

  • 8/6/2019 Graber - Dam Removal Project Overview

    35/54

    Identify if species of concern could beaffected by dam removal

    Submit species info request to North Carolina

    Natural Heritage Program (http://www.ncnhp.org/)

    Design Components: Species ProtectionDesign Components: Species Protection

    M f A i S i

  • 8/6/2019 Graber - Dam Removal Project Overview

    36/54

    Manage for Aquatic Species

    Monitor during constructionMonitor during constructionRelocate speciesRelocate species

    Time the removalTime the removal Manage sedimentManage sediment

    Design Components: Species ProtectionDesign Components: Species Protection

  • 8/6/2019 Graber - Dam Removal Project Overview

    37/54

    Site-Specific Issues

    SiteSite--SpecificSpecific

    IssuesIssues

  • 8/6/2019 Graber - Dam Removal Project Overview

    38/54

    Dam uses can oftenbe replaced

    Design Components: SiteDesign Components: Site--Specific IssuesSpecific Issues

  • 8/6/2019 Graber - Dam Removal Project Overview

    39/54

    Other site-specific issues:

    well impacts, ice jams, parks, walkingtrails, renderings, etc.

    Design Components: SiteDesign Components: Site--Specific IssuesSpecific Issues

  • 8/6/2019 Graber - Dam Removal Project Overview

    40/54

    DataData

    Collection/Collection/SurveyingSurveying

    ProtectingProtectingInfrastructureInfrastructure

    SpeciesSpeciesProtectionProtection

    Hydrology/Hydrology/

    HydraulicsHydraulics

    SedimentSediment

    ManagementManagement

    SiteSite--SpecificSpecificIssuesIssues

  • 8/6/2019 Graber - Dam Removal Project Overview

    41/54

    What will a dam removal cost?

    The data set

    225 total projects nationwide with cost data

    median dam height is 9 feet

    range 2 ft to 85 ft 92% were less than 25 ft

    $77,582 median total project cost

    in 2010 dollars

    range $1,769 to $5.9 million

    60 projects from PA

    M di t t l j t t

  • 8/6/2019 Graber - Dam Removal Project Overview

    42/54

    Median total project costs:

    can be standardized by dam height

    Dam Removal Costs

  • 8/6/2019 Graber - Dam Removal Project Overview

    43/54

    Feasibility + Design + Permitting is25% of total project cost (median)

    Dam Removal Costs

    Wh t i it th t h

  • 8/6/2019 Graber - Dam Removal Project Overview

    44/54

    What is it worth to havea streamlined process?

    Dam Removal CostsDam Removal Costs

  • 8/6/2019 Graber - Dam Removal Project Overview

    45/54

    Many funding sources exist

    US Fish and Wildlife Service

    National Oceanic and Atmospheric Administration

    Natural Resources Conservation Service

    State funds (Clean Water, DWR, EEP)

    Corporate Donations

    Private foundations

    Funding for Dam RemovalFunding for Dam Removal

  • 8/6/2019 Graber - Dam Removal Project Overview

    46/54

    Most funding hooks are environmental

    Diadromous Fish Resident Species Listed Species

    Funding for Dam RemovalFunding for Dam Removal

    Who does the work?

  • 8/6/2019 Graber - Dam Removal Project Overview

    47/54

    Who does the work?

    Along with experience look for non-

  • 8/6/2019 Graber - Dam Removal Project Overview

    48/54

    Along with experience, look for non-technical skills and integration of skills

    Important non-technical skills:

    Responsiveness and project

    management Permitting

    Presentation skills

    Willingness to advocate forresource and project

    No one firm is truly good

    at all of these

    Hiring Consultants

    Integration of technical skills:

    Engineering

    Geomorphology Ecology

    Traditional engineers may miss river context and habitat

  • 8/6/2019 Graber - Dam Removal Project Overview

    49/54

    Hiring Consultants: Skill Integration

    g y

    Blend geomorphology ecology and engineering skills:

  • 8/6/2019 Graber - Dam Removal Project Overview

    50/54

    Blend geomorphology, ecology, and engineering skills:

    There are several approaches to

  • 8/6/2019 Graber - Dam Removal Project Overview

    51/54

    There are several approaches toremoving a structure

    Explosives Heavy Machinery By Hand

    Fi l l d i h i d

  • 8/6/2019 Graber - Dam Removal Project Overview

    52/54

    First, slowly drain the impoundment

    Most commonly a backhoe with a hydraulic hammer will

  • 8/6/2019 Graber - Dam Removal Project Overview

    53/54

    Most commonly a backhoe with a hydraulic hammer willbreach one side and then move across

    Construction ApproachesConstruction Approaches

  • 8/6/2019 Graber - Dam Removal Project Overview

    54/54

    Brian GraberBrian Graber

    American RiversAmerican Rivers

    [email protected]@americanrivers.org

    Dam Removal Clearinghouse:Dam Removal Clearinghouse:http://www.lib.berkeley.edu/WRCA/damremoval/index.htmlhttp://www.lib.berkeley.edu/WRCA/damremoval/index.html