global tender notice for mtm,sambalpur 1 · global tender notice ... odisha government of odisha,...
TRANSCRIPT
GLOBAL TENDER NOTICE
Invitation for Qualification for Modern Terminal Market at Sambalpur, Odisha
Government of Odisha, hereinafter referred to as AWARDER, invites applications for Request for Qualification
(RFQ) from reputed players in the field of Agribusiness*or Infrastructure Development (hereafter referred to as
APPLICANTS), as individual applicant or as Consortium for setting up a Terminal Market Complex (TMC) at Nildunguri,
Dist::Sambalpur in Odisha. This is for facilitating effective marketing of perishable agricultural/horticultural and allied
commodities. As per the Guidelines of National Horticulture Mission, a two-stage competitive bidding process will be
adopted for awarding the project. The RFQ is being called to shortlist competitive parties who will be subsequently
requested to bid for the TMC through a RFP. The successful bidder at the end of the bidding process of Request for Proposal
(RFP) may be awarded a Contract by the AWARDER to implement the Project on a Build, Own and Operate (BOO) basis.
The successful Bidder shall be responsible for the Designing, Constructing, Developing, Engineering, Financing,
Procurement, Construction, Operation and Maintenance of the project for which the successful bidder will sign an
agreement, Operation, Management and Development Agreement (OMDA),which will be made available at the stage of
RFP. The minimum project cost of the proposed Terminal Market Project Complex at Sambalpur is estimated at Rs. 73.21
crores as per the Project Information Memorandum (copy available with RFQ documents). This is only a model project;
bidders may submit their own business plan as per the guidelines at the RFP stage.
The successful bidder shall have to constitute a Special Purpose Vehicle (SPV) to be registered as a Company (hereinafter
referred to as “Private Enterprise”) under the Companies Act, 1956 for the purpose of implementation and operation of TMC
before the award of bid. Private Enterprise would ensure equity participation by Producers’ Association as prescribed. The
Private Enterprise shall be entitled to collect User charges from the Users during the Period of the Agreement to compensate
for the capital cost and the operating expenses of the Project and returns thereon. However, for a period of first three years
from date of commencement of operations of TMC, the charges for providing basic services of aggregation at collection
centres and auction at the TMC should not exceed 2% of value of produce. All other services including value added services
may be market based and Private Enterprise will have freedom to fix these service charges. In the competitive bidding, all
bidders will be eligible to quote bid subsidy from 25% to 40% of their respective project cost (cost of infrastructure and land
excluding the cost of infrastructure of non-marketing infrastructure and limiting the portion of cost of land to a level as
allowed under wholesale market component of National Horticulture Mission for calculating subsidy) with maximum
subsidy of INR 50 Crores. The Project will be awarded to the bidder quoting minimum subsidy amount in Indian Rupees
(INR). For the purpose of calculation of subsidy, the unit cost ceiling shall be 150.00 crore. The details of subsidy including
stages of release are given in the RFQ document.
. Important Particulars regarding the Modern Terminal Market
at Sambalpur and the RFQ document are tabled below:
Land
60 acres ** (approximately)
Location of the Proposed MTM Nildungri, 14 kilometers east of Sambalpur on NH-6 from Kolkata to
Mumbai
Sale of RFQ document Up to 35 days from the date of release of this Notice on all working days
between 1000 hrs and 1700 hrs IST
Cost of RFQ Document Rs. 5,000 (USD 100) in the form of a crossed demand draft (non-refundable)
drawn in favor of Director of Horticulture & Secretary, Odisha Horticulture
Development Society payable at Bhubaneshwar
Last Date for submission of completed RFQ Document 24th May, 2012
Note: In case the reference date is a holiday, next working day will be considered.
* Agribusiness will include entities involved in Agriculture/Horticulture / Floriculture/ Fisheries/ Dairy / Processed Food including Farmers
Associations and entities providing basic facilities, services, and installations needed for agricultural operations including post harvest
operations and processing of agricultural products. Also includes commodity exchanges
** The mentioned land has been proposed by the Odisha Horticulture Development Society, Govt. of Odisha. The site visit can be facilitated
by the said authority subject to prior approval.
The RFQ Document could be obtained by post/courier upon a written request accompanied by the cost of the document.
Alternatively, the same could be downloaded from AWARDER website [www.orissa.gov.in/
www.orissa.gov.in/dhc/Index.html /www.nhm.nic.in, www.orihort.in, www.ilfsclusters.com.]. Applicants submitting the downloaded version would need to pay the cost of the RFQ Document along with their
Application in the manner described above. No hand delivery of applications will be entertained. Schedule of tentative time
frame for the bidding process is given in Para 1.3. Submission of application should be in the office of Nodal Officer cum
Principal Secretary, Department of Agriculture, Government of Orissa. AWARDER will not be responsible for any delay,
loss or non-receipt of RFQ Document sent by post/courier. Principal Secretary, Department of Agriculture, reserves the right to cancel or modify the project implementation
schedule. For any query please contact, Mr. Sanjeev Kumar Chadha, IFS, Director Horticulture and Secretary, Orissa
Horticulture Development Society at Phone no. 0674-2551831 and e-mail [email protected]/ [email protected] or
Project Consultant (Financial Institution), IL&FS Clusters, 2nd Floor, Niryat Bhawan, Rao Tula Ram Marg, New Delhi-
110057, e-mail: [email protected] and [email protected], Phone no. 011 46002200/46002220 .
The RFQ Document containing the Introduction to the Project, Instructions to Applicants and Criteria for Evaluation along
with a copy of Project Information Memorandum, may be obtained from the Office of Nodal Officer for MTM-cum-
Director Horticulture, Directorate of Horticulture, Udyan Bhawan, Bhubaneshwar- 751015 (between 1000 hrs and 1700
hrs on all working days) Sd/- S.K. Chadha
Nodal Officer for MTM-cum-Director of Horticulture & Secretary, Odisha Horticulture Development Society, Bhubaneshwar
DEPARTMENT OF AGRICULTURE
Directorate of Horticulture
(GOVERNMENT OF ODISHA)
Prepared By
IL&FS Cluster Development Initiative Limited
PROJECT
INFORMATION
MEMORANDUM
TERMINAL
MARKET
COMPLEX,
SAMBALPUR,
ODISHA
ODISHA
1 Project Information Memorandum, TMC, Sambalpur, Odisha
DEPARTMENT OF AGRICULTURE
Directorate of Horticulture
(GOVERNMENT OF ODISHA)
Project Information Memorandum
Terminal Market Complex,
Sambalpur, Odisha
Prepared By
IL&FS Cluster Development Initiative Limited
Project Information Memorandum, TMC, Sambalpur, Odisha 1
Table of Contents
Table of Contents ...................................................................................................................................... 1
List of Exhibit ............................................................................................................................................ 4
List of Tables ............................................................................................................................................. 4
Background and Introduction to the Project Information Memorandum ................................................. 6
Chapter 1:................................................................................................................................................. 8
Introduction to the Concept of Terminal Markets .................................................................................... 8
1.1 Terminal Market Complex- An Innovative Market Mechanism ...................................................... 9
1.2 Potential for a Terminal Market in Odisha .................................................................................. 12
1.3 The Proposed Terminal Market- Nildunguri, Sambalpur ............................................................. 15
Chapter 2:............................................................................................................................................... 17
Introduction to the State ......................................................................................................................... 17
2.1 Introduction to Odisha .................................................................................................................. 18
2.2 Agricultural Produce in the State .................................................................................................. 20
Chapter 3:............................................................................................................................................... 21
Production of Perishable Horticulture and Other Produce in the State ................................................ 21
3.1 Overview of Horticultural Produce in the State ............................................................................ 22
3.2 Vegetable Production in Odisha ................................................................................................... 22
3.3 Fruit Production in Odisha ............................................................................................................ 22
3.4 Spices Production in Odisha .......................................................................................................... 23
3.5 Flower Production/Growth in Odisha ........................................................................................... 23
Chapter 4:............................................................................................................................................... 24
Feasibility for a Terminal Market in the State ....................................................................................... 24
4.1 Backward Linkages – Modern Terminal Market ........................................................................... 25
4.1.1 Sundergarh ............................................................................................................................ 27
4.1.2 Bargarh .................................................................................................................................. 28
4.1.2 Deogarh ................................................................................................................................. 30
4.1.4 Jharsuguda ............................................................................................................................ 31
4.1.5 Kalahandi ............................................................................................................................... 33
4.1.6 Sonepur .................................................................................................................................. 34
4.1.7 Bolangir ................................................................................................................................. 35
4.1.8 Angul ...................................................................................................................................... 37
4.1.9 Bauda ..................................................................................................................................... 38
4.1.10 Nuapada .............................................................................................................................. 40
Project Information Memorandum, TMC, Sambalpur, Odisha 2
4.1.11 Sambalpur............................................................................................................................ 41
Chapter 5 ................................................................................................................................................ 45
Forward Linkages – Terminal Market ................................................................................................... 45
5.1 Forward Linkages- Modern Terminal Market ............................................................................... 46
5.1.1 Mapping of Major Markets for TM ........................................................................................ 47
Chapter 6:............................................................................................................................................... 50
Terminal Market Complex Sambalpur ................................................................................................... 50
Chapter 7:............................................................................................................................................... 54
Project Structure .................................................................................................................................... 54
7.1 Broad Mandatory Infrastructure at TM ........................................................................................ 55
7.1.1 Auction Platforms .................................................................................................................. 56
7.1.2 Large Halls for Loading, Unloading, Grading and Packing .................................................... 56
7.1.3 Packaging & Labeling Unit and Drying Yard .......................................................................... 56
7.1.4 Cold Storage & Warehousing Units ....................................................................................... 56
7.1.5 Parking Space for Containers, Trucks, Small Vehicles etc ...................................................... 56
7.1.6 Traditional Shops for Traders ................................................................................................ 57
7.1.7 Display Areas ......................................................................................................................... 57
7.1.8 Viewing Galleries ................................................................................................................... 57
7.1.9 Office Areas/Quarters ............................................................................................................ 57
7.1.10 Logistics Hub ........................................................................................................................ 57
7.1.11 Circulation Pattern of the Market Facility ........................................................................... 57
7.1.12 Allied Shops and Food Court ................................................................................................ 57
7.1.13 Non Marketing Infrastructure ............................................................................................. 58
7.1.14 Other Service Areas ............................................................................................................. 58
7.1.15 Additional Facilities ...................................................................................................... 58
7.2 Collection Centers ......................................................................................................................... 58
Chapter 8:............................................................................................................................................... 59
Project Cost and Major Assumptions ..................................................................................................... 59
8.1 Project Cost ................................................................................................................................... 60
8.2 Means of Finance .......................................................................................................................... 60
8.3 Details of Project Cost ................................................................................................................... 61
8.3.1 Land ....................................................................................................................................... 61
8.3.2 Land Development ................................................................................................................. 61
8.3.3 Buildings ................................................................................................................................ 61
8.3.4 Equipment .............................................................................................................................. 61
Project Information Memorandum, TMC, Sambalpur, Odisha 3
8.3.5 Miscellaneous Fixed Assets / Utilities .................................................................................... 62
8.3.6 Preliminary & Pre-operative Expenses ................................................................................... 62
8.3.7 Working Capital Requirement ............................................................................................... 63
8.3.8 Contingencies......................................................................................................................... 63
8.4 Operating Cost Assumptions ........................................................................................................ 63
8.4.1 Arrival Assumptions ............................................................................................................... 63
8.4.2 Power Cost ............................................................................................................................. 63
8.4.3 Fuel Cost ................................................................................................................................ 64
8.4.4 Raw Material for packaging .................................................................................................. 64
8.4.5 Employee Cost ....................................................................................................................... 64
8.4.6 Maintenance Cost .................................................................................................................. 64
8.4.7 Cost of insurance ................................................................................................................... 64
8.4.8 Admin & Selling Overheads ................................................................................................... 64
8.5 Financial Assumptions .................................................................................................................. 64
8.5.1 Taxes ...................................................................................................................................... 64
8.5.2 Depreciation Rates................................................................................................................. 65
8.5.3 Interest................................................................................................................................... 65
8.6 Revenue Assumptions ................................................................................................................... 65
8.6.1 User Charges .......................................................................................................................... 65
8.6.2 Rental from Traders Shop ...................................................................................................... 65
8.6.3 Income from Agri Mall, Parking, Etc. ..................................................................................... 65
8.6.4 Crates User Charges............................................................................................................... 66
8.6.5 Cold Store ............................................................................................................................... 66
8.6.6 Ripening ................................................................................................................................. 66
8.6.7 Sorting, grading, packaging facility ....................................................................................... 66
8.6.8 Warehouse............................................................................................................................. 66
8.6.9 Non Marketing Activities ....................................................................................................... 66
8.7 Projected Financial Performance .................................................................................................. 67
Annexure................................................................................................................................................. 69
Project Information Memorandum, TMC, Sambalpur, Odisha 4
List of Exhibit
Exhibit 1: Picture of an APMC Market ........................................................................................................................ 9
Exhibit 2: Concept of Terminal Market Complex ...................................................................................................... 10
Exhibit 3: Flow of Produce in a Terminal Market Complex ....................................................................................... 11
Exhibit 4: The Location of the TMC........................................................................................................................... 15
Exhibit 5: Road Network in Odisha ........................................................................................................................... 19
Exhibit 6: Terminal Market at Sambalpur-Mapping of Catchment Districts ............................................................ 25
Exhibit 7: Mapping of Consumption Markets Linked to TM ..................................................................................... 49
Exhibit 8: The Site .................................................................................................................................................... 52
Exhibit 9: Proposed Entrances .................................................................................................................................. 52
Exhibit 10: The Sitemap ............................................................................................................................................ 53
List of Tables
Table 1: Food Grain Production in Odisha ................................................................................................................ 20
Table 2: Vegetable Production in Odisha ................................................................................................................. 22
Table 3: Fruits Production in Odisha ........................................................................................................................ 23
Table 4: Spices Production in Odisha........................................................................................................................ 23
Table 5: Flowers Production in Odisha ..................................................................................................................... 23
Table 6: Distance Matrix- Terminal market Vs. Catchment Districts (in km) ........................................................... 26
Table 7: Distance Matrix- Terminal market Vs. Catchment Mandis (in km) ........................................................... 26
Table 8: Production of major fruits and vegetables in Sundergarh ......................................................................... 27
Table 9: Production of Major Fruits and Vegetables in Bargarh ............................................................................ 29
Table 10: Production of Major Fruits and Vegetables in Deogarh ......................................................................... 31
Table 11: Production of Major Fruits and Vegetables in Jharsuguda ..................................................................... 32
Table 12: Production of Major Fruits and Vegetables in Kalahandi ....................................................................... 33
Table 13: Production of Major Fruits and Vegetables in Sonepur .......................................................................... 35
Table 14: Production of Major Fruits and Vegetables in Bolangir ......................................................................... 36
Table 15: Production of Major Fruits and Vegetables in Angul .............................................................................. 38
Table 16: Production of Major Fruits and Vegetables in Bauda ............................................................................. 39
Table 17: Production of Major Fruits and Vegetables in Nuapada ......................................................................... 40
Table 18: Fruits and Vegetable Production in Sambalpur ...................................................................................... 42
Table 19: Fruits and Vegetable Production Catchment Districts of TM .................................................................. 43
Table 20: District wise Production Figure in Catchment ........................................................................................ 43
Table 21: Fruits and Vegetable Arrival in Catchment Mandis of TM ...................................................................... 43
Table 22: Distance Matrix to Various Consumption Markets from the Catchment of Terminal Market .................. 47
Project Information Memorandum, TMC, Sambalpur, Odisha 5
Table 23: Basic-Minimum Infrastructure Facilities to be provided at the TMC & CC ............................................... 55
Table 24: Project Cost of MTM, Sambalpur.............................................................................................................. 60
Table 25: Means of Finance for MTM, Sambalpur ................................................................................................... 60
Table 26: Cost Break up of Machinery and Equipments ........................................................................................... 61
Table 27: Utilities and Misc Assets ........................................................................................................................... 62
Table 28: Preliminary and Pre-operative Expenses .................................................................................................. 62
Table 29: Working Capital Requirement .................................................................................................................. 63
Table 30: Employee details ...................................................................................................................................... 64
Table 31: Depreciation Rates ................................................................................................................................... 65
Table 32: Estimated Capacity Utilization ................................................................................................................. 66
Table 33: Projected Profitability Statement (Rs. Lakh) ............................................................................................ 67
Table 34: Financial Performance indicators ............................................................................................................. 67
Table 35: Projected Cash Flow Statement (Rs. Lakh) ............................................................................................... 68
Table 36: Sensitivity Analysis ................................................................................................................................... 68
Project Information Memorandum, TMC, Sambalpur, Odisha 6
Background and Introduction to the Project Information Memorandum
In 2007, the Directorate of Horticulture, Government of Odisha, decided to set up
three Terminal Market Complexes in the state under the Terminal Market Complex
Scheme of the National Horticulture Mission. The locations selected for setting up
these markets included Cuttack, Berhampur and Sambalpur. Subsequently,
Directorate of Horticulture, Odisha engaged National Institute of Agriculture
Marketing (NIAM), Rajasthan to prepare a Detailed Project Report for the proposed
Terminal Market Complex at Sambalpur. NIAM submitted the DPR in 2008.
However, the Private Entrepreneur (PE) selection process could not be completed.
Govt. of India came out with revised Guidelines for Setting up of Terminal Market
Complex in 2009. Consequently, the state started afresh the process of selection of
Financial Institution (FI) and IL&FS Cluster Development Initiative Limited (IL&FS
Clusters) was selected as the FI who would be responsible for executing the bid
management process (including preparation of the Project Information Memorandum,
Global Tender Notice, Request for Qualification and Request for Proposal
documents) leading to the selection of the PE who would ultimately execute the
project.
This Project Information Memorandum (PIM) has been prepared by IL&FS Clusters
keeping in mind the PIM preparation framework laid down in Annexure 2 of the
Operational Guidelines for Setting up a Terminal Market Complex 2009. This PIM
document elaborates on aspects such as site and location details, production and
arrivals of horticultural produce in the catchment area, mandatory infrastructure
required for setting up the TMC, a tentative project cost and revenue projections along
with cost and operating assumptions. The objective of preparing a comprehensive
PIM is to inform prospective investors about the nature and scope of investment that
the project envisages and answer the queries they may have regarding project
implementation. It may be highlighted here that the project cost and subsequent
revenue projections have been arrived at keeping in mind two scenarios- one in which
land cost is assumed at circle rates and the other in which land cost is assumed at
market rates proposed by Directorate of Horticulture. It may ultimately be decided by
the State Government as to which scenario it finds more suitable for attracting
investors to execute this project.
The proposed facilities, tentative project cost and subsequent revenue projections are
in no way binding on the private entrepreneur who would be selected to execute the
project and the private entrepreneur will have the liberty to make his own business
plan in accordance with the Operational Guidelines.
Project Information Memorandum, TMC, Sambalpur, Odisha 7
To prepare the PIM, data and information has been collected from both primary and
secondary sources. Secondary data for the study was obtained from documents
provided by the Odisha Horticulture Development Society, office of the Deputy
Director of Horticulture, Sambalpur and various other documents of the National
Horticulture Board. Documents released by the Industrial Promotion and Investment
Co-operation of Odisha Ltd. from time to time, Operational Guidelines for Setting up
a Terminal Market Complex 2009 and the Detailed Project Report prepared by NIAM
for Setting up of Terminal Market Project at Sambalpur have also been referred to.
In order to validate the data obtained from the above mentioned secondary sources,
the team conducted an extensive two-week field survey of the proposed site and
markets/mandis in the catchment area. Some of the places visited and surveyed
included Sambalpur and Bargarh. The activities during these visits included
interviews and focused group discussions with officials of Horticulture Department at
Sambalpur, horticulturalists from various districts, farmers, farmers‟ clubs,
commission agents, food processors, owners of cold chains and various other
stakeholders in the marketing system in the catchment areas.
Project Information Memorandum, TMC, Sambalpur, Odisha 8
Chapter 1:
Introduction to the Concept of
Terminal Markets
Project Information Memorandum, TMC, Sambalpur, Odisha 9
1.1 Terminal Market Complex- An Innovative Market
Mechanism
The marketing of agricultural produce in the country has been mostly regulated over
the years. This regulation has been aimed at achieving a two-fold objective. The first
and foremost objective has been to ensure food security for the country‟s large and
growing population. The other important aim of regulation has been to create a
mechanism that would help farmers earn remunerative prices for their produce which
would in turn encourage them to produce more. Thus, it was aimed at protecting the
interests of the farmers who, it was felt, would be deprived of their just returns by
traders.
To achieve the said objectives, state governments and union territories enacted
Agricultural Produce Marketing Committee Act (APMC), which facilitated setting up
of network of physical markets across the country. These markets were aimed at
providing easy market access to the farmers and ensure a fair price realization for
them in a transparent manner.
Exhibit 1: Picture of an APMC Market
However, over the years it was realized that, ironically, these markets, instead of
protecting the interests of farmers, often became restrictive as the farmers became
compelled to bring their produce to the market yard and were often at the mercy of
traders and commission agents for sale of their produces. The license system for
traders and commission agents further made the APMC markets function in a non-
transparent manner and led to high marketing costs. As the food retail market makes
rapid progress and consumers become more discerning, it has been found that the
APMC markets are coming in the way of free market play restricting choices of both
the farmers and consumers. It is against this background that National Horticulture
Mission came with the concept of Terminal Market Complexes.
Project Information Memorandum, TMC, Sambalpur, Odisha 10
It has been envisaged that the successful implementation of the Terminal Market
Scheme may lead to larger price realization for farmers, facilitate larger investment &
increased productivity, reduce wastages and create an efficient food distribution
network.
India is witnessing high inflation rates of food commodities and supply side inflation
happens to be one of the ingredients causing this price rise. Wastages caused due to
lack of infrastructure for transportation and storage of agricultural produce is
contributing to inflationary pressures. In such a scenario, reforms in the agricultural
marketing and distribution mechanism may help in containing food inflation and
ensuring food security.
The Concept/Envisaged Model of the Terminal Market Complex
The Terminal Markets (TM) are envisaged to be implemented in a Public Private
Partnership (PPP) mode. To make these TM sustainable, the model provides for
modern post harvest infrastructure in these markets along with backward linkages.
These markets are proposed to operate on a Hub-and-Spoke Format wherein the
Terminal Market (the hub) would be linked to a number of Collection Centres (CC)
(the spokes). The Terminal Markets are envisaged to establish backward linkages with
farmers through the collection centres and forward linkages through wholesalers,
distribution centres, processing units and exporters. Collection Centres in the villages
are supposed to integrate producers and retailers, processing units and exporters into
the market system. An electronic auction system in these markets is to be provided for
transparency in price fixation and competition. The exhibit below shows the concept
of the Terminal Market Complex.
Exhibit 2: Concept of Terminal Market Complex
The Terminal Markets are to be built, owned and operated by the selected Private
Enterprise (PE) through Competitive Bidding process. PE may be individuals, Group
Project Information Memorandum, TMC, Sambalpur, Odisha 11
of Farmers/Growers/Consumers, Partnership/ Proprietary firms, Companies,
Marketing Boards, Corporations, Co-operatives, Producer Organizations and Self
Help Groups. It could also be a consortium of entrepreneurs from, inter-alia, agri-
business, cold chain, logistics, warehousing, agri-infrastructure and related
background.
The Terminal Markets can market all perishable commodities including fruits,
vegetables, flowers, aromatics, herbs, milk, dairy, poultry, meat, fish and marine
products etc. However, the annual throughput for perishable horticultural products
such as fruits, vegetables, flowers, medicinal plants, aromatics, herbs etc handled by
TMC should not be less than 70% of the throughput capacity of the TMC. Though
Non-perishables can also be handled in the TMC, its volume with other perishable
products (other than horticultural produce) shall not exceed 30% of throughput
capacity of TMC. The Exhibit below shows the envisaged flow of produce in a
Terminal Market Complex.
Exhibit 3: Flow of Produce in a Terminal Market Complex
To incentivize the Private Entrepreneur, a floor subsidy of 25% of the respective
project cost is offered to private entrepreneurs to bid for setting up Terminal Market
Complex. In the competitive bidding, all bidders will be eligible to quote bid subsidy
from 25% up to 40% of their respective project cost with maximum subsidy of INR
50 crore. For the purpose of calculation of subsidy, the unit cost ceiling shall be Rs
150.00 crore. The Project will be awarded to the successful bidder quoting least
subsidy amount in INR. PE can charge 2% as aggregation and auction charges for
first three years. Afterwards it can fix the suitable charges based on commercial
viability. Also, the PE has been given full freedom to fix the service charges based on
Project Information Memorandum, TMC, Sambalpur, Odisha 12
commercial and viability considerations for ancillary services provided in the market.
However, PE has to meet the service levels as prescribed in the Operation
Management Development Agreement (OMDA) for the Terminal Markets.
1.2 Potential for a Terminal Market in Odisha
Odisha- A Preferred Investment Destination
In the last few years, Odisha has emerged as a preferred investment destination in the
country. In the year 2009, Odisha was second top Domestic Investment destination in
the country, only behind Gujarat, according to an analysis of ASSOCHAM
Investment Meter (AIM) Study on Corporate Investments. Odisha's share was 12.6
percent in total investment in the country. During 2009, it received investment
proposal worth INR 200,846 crore. In 2009, the state was also adjudged as „3rd best
place to do business in India‟ as per a World Bank Study. Being able to attract
investment has been a significant achievement for a state which was not considered
favorably by investors till a few years ago. The project implementation rate in the
state has also been growing steadily and has increased from 34 per cent in 2005 to 45
per cent in 2010 as per a study conducted by Industrial Promotion and Investment Co-
operation of Odisha Ltd.
“Odisha has now achieved the Indian national average in terms of the time spent by
management in dealing with regulations and government authorities”- United
Nations Industrial Development Organization Survey
Odisha- Inherent Advantages in Agriculture
Despite fast growing tertiary and secondary sectors, Odisha‟s economy is still more
agriculture-dependent when compared to many other Indian states. The state‟s
agriculture sector offers employment and sustenance to more than 60% of total work-
force.
The National Commission on Farmers has concluded that Eastern India (which
includes Odisha) presents uncommon opportunities for becoming another “fertile
crescent” even as the present fertile zone comprising Punjab, Haryana and Western
UP has reached a state of economic and ecological distress.
Even as the country faces the prospects of stagnation in agriculture, Odisha is being
talked about as a destination of immense potential due to several inherent advantages.
Project Information Memorandum, TMC, Sambalpur, Odisha 13
As per a study conducted by Industrial Promotion and Investment Co-operation of
Odisha Ltd., net area sown and forest area jointly account for more than 73 per cent of
total land in Odisha. The State has a cultivated area of 61.80 lakh hectares out of
which 29.14 lakh hectares is high land, 17.55 lakh hectares is medium land and 15.11
lakh hectares is low land. The Area Sown More than Once (ASMO) has been on a rise
in the state and hence an overall cropped area of approximately 122 lakh hectares
offers huge investment potential to the food processing and agro industry. In addition,
Odisha possesses 10 agro-climatic zones and 8 major soil types. The cropping
intensity for Odisha has grown over the years from 157 per cent in 2005-06 to 163 per
cent in 2009-10. The state also presents immense scope for the growth of organic food
industry since historically; the use of fertilizers and pesticides by farmers has been
low in the state as compared to other states.
As regards production, Odisha boasts of a wide variety of crops, vegetables, fruits and
flowers. The agro-climatic conditions in the state are suited to growth of perennial
fruit crops like mango, litchi, guava, orange, lime and annual fruit crops like banana,
pineapple and papaya; vegetables like brinjal, cabbage among others and spices like
turmeric. The low-temperature hilly areas offer ideal conditions for growing off-
season vegetables. Floriculture is also expanding. Major vegetables grown in the state
include brinjal, tomato, cole crops, pea, okra and potato. Major flowers grown in the
state include marigold, rose and gladiolus. The production and variety has increased
manifold since implementation of various schemes under the National Horticulture
Mission. The details of various kinds of produce in the State are given in Chapter 3.
To summarize, increasing total area under irrigation and enhanced usage of fertilizers
and pesticides coupled with providing better know-how, technology and financing
channels to farmers and implementation of several other initiatives under the National
Horticulture Mission augurs well for the development of agriculture and allied
activities in Odisha.
Odisha- Agriculture a Thrust Sector for the Government
To realize the large potential the agriculture and allied services sector stands to offer,
the government has initiated policy reforms and a range of interventions are under
implementation. A few prominent ones are highlighted as follows:
Agriculture Policy 2008: State Government brought out a “New Agricultural
Policy” to enhance productivity of major crops and for shifting the emphasis
from “subsistence” agriculture to profitable commercial agriculture.
The Government has a Farm Mechanization Programme that aims at promoting
easy availability of the appropriate farm machines.
Project Information Memorandum, TMC, Sambalpur, Odisha 14
Odisha Agro Industries Corporation (OAIC) assists in marketing various
agricultural inputs and farm machineries through a network at district and sub-
district levels.
Development and promotion of markets and complexes like Krushak Bazaars
(aim to train farmers, create primary rural markets, and launch awareness
campaigns), Terminal Market Complexes (TMCs) near Cuttack, Sambalpur &
Berhampur under the PPP mode to provide a fair share of consumer price to the
producer as well as ensure high quality and hygiene of the produce, Market
yards under the Revised Long Term Action Plan (RLTAP) scheme for Koraput,
Bolangir and Kalahandi (KBK) districts (aim at facilitating the selling and
procurement of crop products, and ensure farmers can get a reasonable price for
their produce) and Agri-export Zones (AEZs) proposed to be established in PPP
mode.
Promotion of strengthening marketing channels of agricultural produce through
bodies like Odisha State Marketing Federation (OSMF) which functions as
the apex organization with 51 regional cooperative marketing societies that
undertake several marketing initiatives, Regulated Market Committees which
facilitate backward and forward market integration of agricultural produce and
formation of Rural Producers’ Organizations for specific commodities to
enable them to have appropriate market linkages through Federations.
Odisha has several other organizations such as Odisha State Oilseeds Growers‟
Federation and large-sized Agricultural Multi-purpose Societies (LAMPS) to
cater to needs to different stakeholders in agricultural marketing.
To promote private participation in the sector, agro-processing sector has been
identified as one of the thrust sectors in Industrial Policy Resolution (IPR) 2007
provided the project cost is a minimum of Rs. 25 crore and creates direct
employment generation for at least 100 people. The fiscal incentives for such
projects range from stamp duty, VAT and entry tax exemption to interest and
investment subsidies.
Odisha- An Expanding Consumption Basket
On the demand side, too, Odisha, with a population of approximately 41.9 million
(Source: Census of India 2011- Provisional Population Totals), growing at about 14
percent between 2001 and 2011, is a large and growing market for food products.
Project Information Memorandum, TMC, Sambalpur, Odisha 15
As per the data of Directorate of Economics & Statistics, Odisha, the state‟s per capita
income in 2010-11 stood at Rs. 36,000. The per capita incomes in the state have
increased at a CAGR of 14.1 percent in the last decade (Source: CMIE).
In view of growing population and per capita incomes, Odisha offers an opportunity
as an expanding consumption basket since expenditure on food products contributes
approximately 55 percent share in the total expenditure incurred by the people of the
state.
Odisha has also enacted reforms to the APMC Act by including in the Act
provisioning of activities like direct marketing, contract farming and markets in
Private/Co-op Sector. Implementation of these provisions, along with setting up of the
proposed terminal market, has the potential of reforming the agricultural marketing
scenario in the state.
1.3 The Proposed Terminal Market- Nildunguri, Sambalpur
The Odisha Horticulture Development Society has under its possession 60 acres of
land in Nildunguri, District Sambalpur to set up a Terminal Market Complex. The
Site is situated on National Highway 6, sixteen kilometers from Sambalpur town.
Exhibit 4: The Location of the TMC
The proposed terminal market has been designed so as to address the infrastructure
issues in the existing agri-produce value chain and aims to establish strong and
seamless supply chain mechanism under a hub-and-spoke model. The objective of the
proposed market is to enable farmers realize a higher value for their produce.
The proposed terminal market would stand to offer significant opportunity for private
investors, as it is strategically located and well connected by rail and road. The
Project Information Memorandum, TMC, Sambalpur, Odisha 16
Terminal Market has a strong catchment area in the radius of 100 km and is the hub of
horticulture crop production in the state. Also, due to sound connectivity through
national highways and rail network and located close to Sambalpur, it offers an easy
access to various consumption markets both in and outside the state. The location of
terminal market is shown in the picture below.
Details of the location, site, connectivity, availability of water & power and other
details have been elaborated in a later chapter.
Project Information Memorandum, TMC, Sambalpur, Odisha 18
2.1 Introduction to Odisha
Location/Geography
Odisha has an area of approximately 156,000 sq km which makes it the ninth largest
state in India by area. It is surrounded by the Bay of Bengal on the East, Jharkhand
and West Bengal on the North, Chhattisgarh on the West and Andhra Pradesh on the
South. Twelve rivers flow across the state with Mahanadi, Brahmani and Indirabati
being a few prominent ones.
Connectivity
The total road network in the state is estimated at 2.38 lakh km including
approximately 3700 km of National Highway and 28,300 km of state highway.
National Highways 5, 6, 23 and 43 pass through the state. The state has approximately
2300 km of railway routes including 91 km of narrow gauge. The state government is
also in the process of building a 50-mile long sub-urban rail link from Chandikhol to
Khurdha on National Highway 5, which is one of the busiest roads in India. The
government has also proposed to introduce Mass Rapid Transit System (MRTS). Biju
Patnaik Airport in Bhubaneshwar is the only airport in the state. In addition, there are
13 airstrips and 16 helipads at several places in the state. The Airport Authority of
India (AAI) plans to add another domestic terminal to the existing airport in
Bhubaneswar, with an investment of Rs.1600.0 million. Moreover, AAI is looking to
modernize and expand the Jharsuguda airport. Odisha is a principal maritime state and
has a coastline of 480 km. Paradeep Port located in Odisha is one of the 12 major
ports in the country.
Administration
The capital of the state is Bhubaneshwar and other prominent cities are Cuttack,
Rourkela, Berhampur, Sambalpur, Baleshwar and Puri. Administratively, the state is
divided into 30 districts, 58 sub-divisions, 316 tahasils, 314 blocks, 6234 gram
panchayats and 51,349 villages.
Project Information Memorandum, TMC, Sambalpur, Odisha 19
Exhibit 5: Road Network in Odisha
Demographics
According to the 2011 census of India, the total population of Odisha is 41,947,358,
of which 21,201,678 (50.54%) are male and 20,745,680 (49.46%) are female, or 978
females per 1000 males. This represents a 13.97% increase over the population in
2001. The population density is 269 per sq km. The literacy rate is 73.45% with
82.4% of males and 64.36% of females being literate, according to 2011 census. Data
on life expectancy shows that the life expectancy in the state is over 62 years, higher
than the national average.
Economy
In the five-year period between 2004–05 and 2008–09, Odisha's Gross State Domestic
Product (GSDP) has grown by approximately 8.50 percent making it the fourth fastest
growing state, behind Gujarat, Bihar and Uttarakhand. In 2009-10, the GSDP at
current prices stood at INR 150,946 crore, growing at 12.98 percent per annum from
the previous year. GSDP at Constant Prices stood at INR 90,229 crore, growing at
8.35 percent per annum compared to the previous financial year.
In recent years, the contribution of the services sector has become more pronounced,
accounting for approximately 47 percent in the state GSDP. The share of the
industrial sector stands at about 23 percent and that of agriculture and allied activities
Project Information Memorandum, TMC, Sambalpur, Odisha 20
stands at approximately 30 percent of GSDP. (Source: Govt. of Odisha, Annual
Budget 2010-11)
2.2 Agricultural Produce in the State
Food grains (cereals and pulses) production, with a share of more than 85 percent,
continues to dominate in the total agricultural production. Food grain production has
been witnessing an increasing trend in production since 2002-03, reaching 7.5 million
MT in 2009-10.
Paddy accounts for nearly 79 percent of the total crop production. The table below
shows the food grain production trends of crops in the State over the past five years.
Table 1: Food Grain Production in Odisha
(in ‘000 MT) 2005-06 2006-07 2007-08 2008-09 2009-10
Cereals
Rice 6,859 6,825 7,541 6,813 6,917
Maize 102 103 147 135 175
Ragi 40 43 47 41 37
Others 22 22 26 23 24
Total Cereals 7,023 6,993 7,761 7,012 7,153
Pulses
Gram 23 24 26 25 34
Tur 98 106 113 119 112
Other 216 221 245 237 252
Total Pulses 337 351 384 381 398
Total Food Grains 7,360 7,344 8,145 7,393 7,551
Source: Economic Survey of Odisha 2010-11
Project Information Memorandum, TMC, Sambalpur, Odisha 21
Chapter 3:
Production of Perishable
Horticulture and Other Produce
in the State
Project Information Memorandum, TMC, Sambalpur, Odisha 22
3.1 Overview of Horticultural Produce in the State
The agro-climatic diversity of Odisha, with its high rainfall distributed over a 5-month
monsoon and a reasonably long and moderate winter, allows for a variety of
horticultural crops to be grown.
Currently, horticulture crops are grown in an area of over 1.2 million hectares (Ha)
having a potential of increasing up to 2 million hectares. Out of the 1.2 million
hectares in which horticultural crops are grown, fruits constitute 0.23 million hectares,
vegetables 0.63 million hectares, coconut and cashew 0.17 million hectares and spices
approximately 0.17 million hectares.
3.2 Vegetable Production in Odisha
The major vegetables grown in the State are Brinjal, Tomato, Cole crops, Pea, Okra
and Potato. The productivity of vegetables in the State is 12.27 MT/Ha as against the
national average of 13.92 MT/Ha. The table below shows the vegetable production in
the state.
Table 2: Vegetable Production in Odisha
Vegetable Area in Ha. Production in MT
Brinjal 132408 2135217
Cabbage 35808 999939
Cauliflower 46484 675387
Okra 73930 651813
Pea 5082 45194
Tomato 102926 1394689
Onion 32085 297056
Potato 13137 178836.4231
Sweet Potato 50462 438821
Other Vegetables 194506 2006680
Watermelon 7301 137308.0185
Muskmelon 56 920
Total 694188 8961861
3.3 Fruit Production in Odisha
The major fruits grown in the State are Mango, Guava, Citrus, Sapota, Banana, Litchi,
Papaya and Ber. While Mango is grown all over the State, prime growing areas are
Keonjhar, Mayurbhanj, Angul, Sambalpur, Rayagada, Phulbani and Sundergarh.
Banana is mainly grown in Khorda, Puri, Cuttack, Nayagarh, Rayagada, Koraput and
Project Information Memorandum, TMC, Sambalpur, Odisha 23
Balasore. Sapota is grown in Ganjam, Puri, Cuttack and Balasore. The table below
shows the fruit production in the state.
Table 3: Fruits Production in Odisha
Fruit Area in Ha. Production in MT
Banana 24591 429156
Citrus 27412 258801
Guava 14155 100017
Litchi 4334 17138
Mango 177626 577476
Papaya 2087 45734
Pineapple 725 8390
Pomegranate 212 823
Sapota 3336 16577
Other Fruit Crops 47585 419817
Total 302063 1873929
3.4 Spices Production in Odisha
Odisha is one of the most important States in the country in the production of spices.
Spices grown in the State are Ginger, Turmeric, Chilli, Coriander, Garlic and Onion.
Table 4: Spices Production in Odisha
Spices Area in Ha. Production in MT
Coriander 19063.36 9445
Ginger 16841 117715
Garlic 11050 35714
Turmeric 25315.0043 189348
Chilli 75530 64319
Total 147798 416540
3.5 Flower Production/Growth in Odisha
The climatic conditions in certain parts of the State are congenial for the production of
flowers. Flowers grown in the State include Marigold, Gladiolus and Rose.
Table 5: Flowers Production in Odisha
Flower Area in
Ha.
Production
Rose 1750 3174 lakh stems
Gladioli 2245 2182 lakh spikes
Tuberose 491 12908 quintals
Marigold 2625 240031 quintals
Total 7111
Project Information Memorandum, TMC, Sambalpur, Odisha 24
Chapter 4:
Feasibility for a Terminal Market
in the State
Project Information Memorandum, TMC, Sambalpur, Odisha 25
4.1 Backward Linkages – Modern Terminal Market
The catchment area of terminal market has been assumed to be within a radius of 150
km (except in the cases of a few districts which are located further away). Districts
proposed to be in the catchment are Sambalpur, Deogarh, Jharsuguda, Bargarh,
Kalahandi, Sonepur, Bolangir, Angul, Bauda, Sundergarh and Naupada. The
catchment along with the proposed terminal market is mapped below:
Exhibit 6: Terminal Market at Sambalpur-Mapping of Catchment Districts
The mapping of the Terminal market with its catchments has been done keeping in
view the transportation time, accessibility and connectivity. It is estimated that the
transit time of the produce from the farthest catchment district shall not take more
than three hours once the aggregation is complete at the respective collection centers.
Below is the distance matrix of TM with its catchments. It may also be noted that the
distances have been mapped from the district headquarters. Since the catchments are
in the periphery of the TM, most of collection centers are envisaged to be en- route
towards the proposed TM. Despite Kalahandi, Angul and Nuapada being more than
150 km away from the proposed TM, they have been considered due to unavailability
of any formal market system in the districts. Further, some of the producing areas in
these districts are within a 100 km distance from the proposed TM.
Project Information Memorandum, TMC, Sambalpur, Odisha 26
Table 6: Distance Matrix- Terminal market Vs. Catchment Districts (in km)
District Bargarh Deogarh Jharsuguda Kalahandi Sonepur
Distance From
Sambalpur
53 91 50 208 80
District Bolangir Angul Bauda Sundergarh Naupada
Distance From
Sambalpur
129 161 100 83 195
Table 7: Distance Matrix- Terminal market Vs. Catchment Mandis (in km)
District Market Distance from the Proposed Site
in Kms.
Sambalpur Kochinda 105
Redhakol 90
Padiabahal 40
Deogarh Deogarh 110
Jharsuguda Jharsuguda 70
Bargarh Bargarh 53
Barpalli 65
Padampur 120
Prakashpur 90
Kalahandi Bhawanipatna 240
Sonepur Sonepur 110
Bolangir Titlagarh 290
Patnagarh 160
Bolangir 120
Angul Boinda 137
Bauda Bauda 100
Sundergarh Sundergarh 102
Baneigarh 262
Naupada Khariar 230
A brief introduction of the districts in the catchment area of the proposed Terminal
Market in respect of raw material availability, major mandis with catchment villages
and connectivity is given below:
Project Information Memorandum, TMC, Sambalpur, Odisha 27
4.1.1 Sundergarh
Profile of Sundergarh
Sundergarh district of Odisha is spread over an area of 9712 sq. km. with a
population of approximately 2 million. The district comprises of 3 sub-divisions and
17 Blocks. The district has a total forest area of 4232 Sq. km. which is 43% of the
total area of the district. Total land under cultivation in the district is 336000
hectares. Sundargarh district have big industries at Rourkela, Rajgangpur and
Kansbahal. Sundergarh is well connected to most parts of the country by rail through
Raurkela station. Nearest Airport is Ranchi (Jharkhand). NH 23 and state highways
connect this district to other parts of the country.
Availability of Horticultural Produce
Sundergarh district produces about 3.8 lakh MT of vegetables annually. The major
vegetables grown in the district are Cabbage, Tomato, Brinjal, and Cauliflower.
Cabbage constitutes around 18 percent of total vegetables production, cauliflower
constitutes around 14 percent. Brinjal, Okra and Tomato contribute around 12
percent. Fruits production in district is around 97 thousand MT. Major fruits
produced are Mango, Banana and Citrus.
Table 8: Production of major fruits and vegetables in Sundergarh
Vegetable Production Fruit Production Spices Production
Brinjal 49660 Banana 20618 Coriander 217
Cabbage 71847 Citrus 13322 Ginger 1028
C. Flower 54606 Guava 5446 Garlic 1410
Okra 45786 Litchi 3089 Turmeric 596
Pea 2457 Mango 27360 Chilly 2849
Tomato 44076 Papaya 1342
Onion 12129 Pineapple 95
Sweet Potato 29684 Pomegranate 28
Watermelon 3701 Sapota 115
Other
Vegetables
67619 Other Fruit
Crop
25784
Total 381564 Total 97199 Total 6100
Project Information Memorandum, TMC, Sambalpur, Odisha 28
Profile of the Major Mandis in the District
The major mandi in the district is situtated in Sundergarh named Krushak Bazar.
Located in Sundargarh block, Krushak Bazar is spread in an area of 2 acres and
around 200 retailers are working for the market. Around 16500 MT of produce
arrives annually in the Krushak Bazar consisting mainly of Brinjal, Cauliflower,
Cabbage, French Beans, Pumpkin, Green chili and Sweet Potato. The catchment
area of the market consists of 89 villages and 1 block.
Market District Vegetables Fruits Potato & Onion Spices Total
Sundergarh Sundergarh 11495 3782 690 589 16556
Baneigarh Sundergarh 5780 1667 259 95 7801
Apart from above mandi, there is one more mandi in Baneigarh. Arrival in
Baneigarh mandi is approximately 8000 MT mainly consist of Brinjal, Cabbage and
Cauliflower.
4.1.2 Bargarh
Profile of Bargarh
The district is spread over 5837 Sq. Km and constitutes of 12 development blocks
having total population of about 1.48 million. All-season irrigation
from Hirakud dam on the Mahanadi River makes the northern half of Bargarh
District rich in agriculture. Bargarh is at a distance of 50 Kilometers from
Sambalpur city, 370 Kilometers from the state capital Bhubaneswar and 230
Kilometers away from Raipur city (Chhatisgarh). Bargarh is well connected by road
(National Highway – 6, Kolkata-Mumbai) and (National Highway – 201, Bargarh-
Boriguma NH towards Visakhapattnam of Andhra Pradesh).
Availability of Horticultural Produce
Bargarh district produces about 4.5 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Tomato, Cabbage, Cauliflower and
Okra. Brinjal and Cabbage constitute the major share of the vegetable production of
the district contributing around 26 % and 11% of the total vegetable production
respectively. Other vegetables like beans, cowpea, pumpkin, radish, ridge gourd,
yam and watermelon etc. constitute 20 percent. Bargarh District produces around 35
thousand MT of fruits annually. The major fruits grown in Bargarh District are Banana
and Mango.
Project Information Memorandum, TMC, Sambalpur, Odisha 29
Table 9: Production of Major Fruits and Vegetables in Bargarh
Vegetable Production Fruit Production Spices Production
Brinjal 144917 Banana 7322 Coriander 264
Cabbage 52376 Citrus 1706 Ginger 1359
C. Flower 51932 Guava 1147 Garlic 1144
Okra 24120 Litchi 135 Turmeric 384
Pea 302 Mango 6116 Chilly 2125
Tomato 44620 Papaya 396
Onion 19178 Pineapple 65
Sweet Potato 16024 Pomegranate 16
Watermelon 3400 Sapota 965
Other
Vegetables
89820 Other Fruit
Crop
17612
Total 446689 Total 35480 Total 5275
Profiles of the Major Mandis in the district
Major Mandis in the districts are Sarandapalli, Padampur, Prakashpur and Bargarh.
Below are a few images of the mandi at Bargarh.
The table below gives a brief description of the major mandis and their characteristics.
Market District Vegetables Fruits Potato & Onion Spices Total
Barpalli Bargarh 5854 144 260 772 7030
Padampur Bargarh 16231 99 60 492 16882
Bargarh Bargarh 15762 419 1404 1,388 18973
Prakashpur Bargarh 3388 445 310 642 4785
Located in Barapalli block, Sarandapalli market is spread over 4 Acres and around
60 retailers work for the market. Around 7000 MT of produce arrives annually in the
Sarandapalli market consisting of mainly Brinjal, Cauliflower, Chilli, Pumpkin,
Project Information Memorandum, TMC, Sambalpur, Odisha 30
Cucumber, Bitter Gourd, Cabbage and Tomato. The catchment area of the market
consists of 74 villages and 1 block. Operating time of the market is between 6 am to
2 pm.
Located in Padmapur block, Padmapur market is spread in an area of 4 Acres and
around 10 commission agents, 2 wholesellers and 450 retailers. Around 17000 MT
of produce arrives annually in the Padmapur market consisting of mainly Tomato,
Cauliflower, Cabbage, Brinjal and Radish. The catchment area of the market
consists of 278 villages and 2 blocks (Padmapur & Paikmal). Operating time of
market is 5 am – 2 pm.
Apart from above mentioned mandis, there are two more mandis in Bargarh, one is
local F&V market and other is Prakashpur. Arrival in Bargarh mandi is
approximately 19000 MT mainly consist of Brinjal, Tomato and Cauliflower. Total
Arrival in Prakashpur is approximately 5000 MT per annum.
4.1.2 Deogarh
Profile of Deogarh
The district is spread over 2781 Sq. Km and constitutes of 3 development blocks.
Total population of the district is approximately 3 Lakh. As there is no industry
present in the district major profession of local inhabitant is agriculture. Town is 90
K.Ms. to the east of Sambalpur on N.H.-6. National Highway No.6 passes through
the district acts as the main artery of inter-regional trade and other links. The
nearest rail heads for Deogarh are at Sambalpur (90 KMs.), Bamra on the Nagpur-
Hawrah Section of South Eastern Railway (103 KM), Jharsuguda (98 Kms.) and
Rourkela (115 Kms.). The nearest airports for Deogarh District are at Bhubaneswar
(280 Kms.) and Raipur (376 Kms.).
Availability of Horticultural Produce
Deogarh district produces about 1 lakh MT of fruits & vegetables annually. The
major Vegetables grown in the district are Brinjal, Cabbage, Cauliflower and
Watermelon. Brinjal contributes 20 percent while cabbage & cauliflower contributes
5 per cent towards the total Production of vegetables. Watermelon is produced in
large quantities and contributes 5 per cent. Other vegetables like beans, cowpea,
pumpkin, ridge gourd, pointed gourd, colocasia, coccinia, green vegetables etc.
constitute 35 percent. Deogarh District produces around 24 thousand MT of fruits
annually. The major fruits grown in Deogarh District are Banana, Mango and Citrus.
Project Information Memorandum, TMC, Sambalpur, Odisha 31
Table 10: Production of Major Fruits and Vegetables in Deogarh
Vegetable Production Fruit Production Spices Production
Brinjal 20093 Banana 2441 Coriander 141
Cabbage 2912 Citrus 3852 Ginger 261
C.Flower 2615 Guava 728 Garlic 655
Okra 2338 Litchi 2063 Turmeric 443
Pea 494 Mango 8613 Chilly 1450
Tomato 2828 Papaya 462
Onion 5722 Pineapple 138
Sweet Potato 6241 Pomegranate 24
Watermelon 5464 Sapota 120
Other
Vegetables
34370 Other Fruit
Crop
5967
Total 83077 Total 24408 Total 2950
Profile of Major Mandis in District
There are no major mandis in the district apart from a local market in Deogarh.
Located in Tileibani block, Deogarh market is spread in an area of 2 Acres and
around 50 retailers are present there. Around 15000 MT of produce arrives annually
in the market consisting of mainly Tomato, Brinjal, Cabbage, Cauliflower and
Garlic. The catchment area of the market consists of 240 villages and 1 block.
Operating time of market is 6Am - 1Pm & 3 pm - 7 Pm. Below is the brief
description of the arrival of Deogarh mandi:
Market District Vegetables Fruits Potato &
Onion
Spices Total
Debgarh Debgarh 9330 3796 1014 767 14907
4.1.4 Jharsuguda
Profile of Jharsuguda
The district is spread over an area of 2081 Sq. Km. and constitutes of 1 sub-division
and 5 blocks. The population of the district as per 2011 census is estimated to be 5.8
Lakh. Total cultivated area in the district is approximately 90000 hectares. This
region is rich in coal and other mineral reserves. Many small and medium scale iron
and steel units have been set up in the vicinity of Jharsuguda town, fueling industrial
growth of the district. Jharsuguda town is situated at the western border of Odisha
Project Information Memorandum, TMC, Sambalpur, Odisha 32
on the State High way No. 10. It is situated at a distance of 515 K.M. from Calcutta
and 616 Km. from Nagpur.
Availability of Horticultural Produce
The district produces about 64 thousand MT of vegetables annually. The major
vegetables grown in the district are Brinjal and cauliflower. Brinjal constitutes the
major share of the vegetable production of the district contributing around 30 % of
the total vegetable production. Other vegetables like Beans, Cowpea, Pumpkin,
Ridge gourd, Pointed gourd, Colocasia, Coccinia, green vegetables, Yam and
Watermelon etc. constitute around 40 percent. Jharsuguda produces around 28
thousand MT of fruits annually with major fruits grown being Mango, Banana,
citrus and Guava.
Table 11: Production of Major Fruits and Vegetables in Jharsuguda
Vegetable Production Fruit Production Spices Production
Brinjal 20191 Banana 4219 Corriander 45
Cabbage 2369 Citrus 3974 Ginger 1165
C. Flower 5352 Guava 1968 Garlic 440
Okra 1569 Litchi 65 Turmeric 193
Pea 34 Mango 8451 Chilly 851
Tomato 3379 Papaya 396
Onion 2826 Pineapple 137
Sweet Potato 130 Pomegranate 8
Watermelon 3674 Sapota 227
Other
Vegetables
24291 Other Fruit
Crop
8555
Total 63816 Total 27999 Total 2694
Profile of Major Mandis in the District
There are no major mandis in the districts apart from local market Sukar Bazar in
district headquarter. Located in Jharsuguda block, Sukar Bazaar is spread in an area
of 2 Acres. This is a Haat type of market. Around 5000 MT of produce arrives
annually in the Sukar Bazaar consisting mainly of Tomato, Cabbage, Cauliflower,
Okra, Brinjal, Carrot and Pointed Gourd. The catchment area of the market consists
of 74 villages and 1 block. Below is the brief description of the arrival of Jharsuguda
mandi:
Market District Vegetables Fruits Potato & Onion Spices Total
Jharsugdha Jharsugdha 3852 1815 613 231 6511
Project Information Memorandum, TMC, Sambalpur, Odisha 33
4.1.5 Kalahandi
Profile of Kalahandi
The district headquarter is at Bhawanipatna which stands almost in the central
location of the district. The district is spread over an area of 7920 Sq. Km. and
constitutes of 2 sub-divisions and 13 blocks. The district has a population of 1.34
million. Kalahandi is largely an agriculture based economy. Since 2000s the
Indravati Water Project, second biggest in the state has changed the landscape of
southern Kalahandi, leading to two crops in a year. Forest based products like
Mahua, Tendu leaf, wood, timber and bamboos are also contributing local economy
largely. Kalahandi supplied substantial raw materials to paper mills in neighboring
Rayagada and Jeypore. National Highway 201 and 217 pass through Kalahandi.
Kesinga is the gateway of Kalahandi for rail connectivity, a major railway station in
the district. It is directly linked with most of the major cities in India. The nearest
airport is located in Raipur (200–250 km). Vishakhapatnam airport is located in
300 km and Bhubaneswar airport in 450 km.
Availability of Horticultural Produce
Kalahandi district produces around 3 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Okra and Tomato. Brinjal contributes
around 40 percent of vegetables production, Okra contributes around 4 percent and
Tomato contributes around 7 percent towards the total production of vegetables.
Kalahandi District produces around 1.7 lakh MT of fruits annually. The major fruits
grown in Kalahandi District are Citrus, Banana and Mango.
Table 12: Production of Major Fruits and Vegetables in Kalahandi
Vegetable Production Fruit Production Spices Production
Brinjal 122360 Banana 13695 Coriander 361
Cabbage 10629 Citrus 103456 Ginger 134
C.Flower 6298 Guava 10492 Garlic 1565
Okra 13485 Litchi 321 Turmeric 2168
Pea 1194 Mango 25598 Chilly 1552
Tomato 93801 Papaya 1188
Onion 22928 Pineapple 277
Sweet Potato 2430 Pomegranate 24
Watermelon 4416 Sapota 246
Other
Vegetables
18777 Other Fruit
Crop
18957
Total 296318 Total 174253 Total 5779
Project Information Memorandum, TMC, Sambalpur, Odisha 34
Profile of Major Mandis in the District
There is one major mandi in the district known as Bhabanipatna. Located in
Bhabanipatna block, Bhabanipatna market is spread in an area of 2 Acres and
around 50 retailers work for the market. This is Municipality Haat type of market.
Around 19000 MT of produce arrives annually in the Bhabanipatna market
consisting of mainly Cabbage, Tomato, Pumpkin and Radish. The catchment area of
the market consists of 253 villages and 1 block. Operating time of market is 6 Am-2
Pm. The arrival data of the mandi is given below:
Market District Vegetables Fruits Potato & Onion Spices Total
Bhawanipatna Kalahandi 9492 5337 1267 3,098 19194
4.1.6 Sonepur
Profile of Sonepur
The district is spread over an area of 2284 Sq. Km. and constitutes of 2 sub-
divisions and 6 blocks. The district has a population of approximately 5.4 lakh.
Sonepur is situated on the confluence of river "The Mahanadi" and "The Tel". It is
famous for Silk Handloom and known as second Benaras(Uttar Pradesh). The
nearest airport is at Raipur and Bhubaneswar. It is connected to rail with major
Indian cities via Sambalpur station. It is well connected via road with Sambalpur.
Availability of Horticultural Produce
Sonpur district produces about 2 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Tomato and Okra. Brinjal and Tomato
contribute 19 and 14 percent respectively, while okra contributes 7 per cent towards
the total production of vegetables. Sonpur District produces around 35 thousand MT
of fruits annually. The major fruits grown in Sonpur District are Banana, Mango,
Citrus and Guava.
Project Information Memorandum, TMC, Sambalpur, Odisha 35
Table 13: Production of Major Fruits and Vegetables in Sonepur
Vegetable Production Fruit Production Spices Production
Brinjal 38122 Banana 8480 Coriander 140
Cabbage 13206 Citrus 3563 Ginger 37
C.Flower 12827 Guava 2783 Garlic 769
Okra 14408 Litchi 33 Turmeric 32
Pea 370 Mango 9290 Chilly 767
Tomato 28954 Papaya 771
Onion 9187 Pineapple 52
Sweet Potato 2446 Pomegranate 20
Watermelon 9462 Sapota 37
Other
Vegetables
73109 Other Fruit
Crop
10235
Total 202091 Total 35265 Total 1744
Profile of Major Mandis in the District
There is one major mandi in the district known as Sonepur. Located in Sonepur
block, Sonepur market is spread in an area of 0.5 acre and around 30 retailers work
for the market. Around 15000 MT of produce arrives annually in the Sonepur
Market consisting mainly of Tomato, Cauliflower, Cabbage, Radish and Brinjal. The
catchment area of the market consists of 157 villages and 1 block. Operating time of
market is 6 am- 2 pm. Given below is the brief description of this mandi:
Market District Vegetables Fruits Potato & Onion Spices Total
Sonepur Sonepur 12416 2322 680 120 15538
4.1.7 Bolangir
Profile of Bolangir
The district is spread over an area of 6575 Sq. Km. and constitutes of 3 sub-
divisions and 14 blocks. The district has a population of approximately 13.4 lakh. It
has 332000 hectare of cultivated land. Mahanadi and Tel rivers are flowing through
the district. The nearest airport is at Raipur and Bhubaneswar. It is connected to rail
with major Indian cities. It is well connected via road with Sambalpur.
Project Information Memorandum, TMC, Sambalpur, Odisha 36
Availability of Horticultural Produce
Bolangir district produces about 3.6 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Cabbage and Tomato. Brinjal and
Cabbage contribute around 20 percent of vegetables production and tomato
contributes around 17 percent of vegetables production. Bolangir District produces
around 73 thousand MT of fruits annually. The major fruits grown in Bolangir
District are Banana and Mango.
Table 14: Production of Major Fruits and Vegetables in Bolangir
Vegetable Production Fruit Production Spices Production
Brinjal 71012 Banana 18705 Coriander 153
Cabbage 70883 Citrus 3509 Ginger 75
C.Flower 19917 Guava 1808 Garlic 683
Okra 21073 Litchi 101 Turmeric 42
Pea 1992 Mango 12094 Chilly 2717
Tomato 63785 Papaya 1490
Onion 43110 Pineapple 110
Sweet Potato 35867 Pomegranate 24
Watermelon 23430 Sapota 1397
Other
Vegetables
13531 Other Fruit
Crop
33784
Total 364599 Total 73022 Total 3670
Profile of Major Mandis in the District
There are three major mandis in the district known as Patnagarh, Titlagarh and
Bolangir. Below is a brief description of these mandis and their features:
Located in Patnagarh block, this market is spread on an area of 1 Acres. The number
of traders linked with the market is 40. The market is Haat type of market. Around
12000 MT of produce arrives annually in the market consisting mainly of Tomato,
Market District Vegetables Fruits Potato & Onion Spices Total
Patnagarh Bolangir 7559 4021 708 30 12318
Titlagarh Bolangir 10209 4562 1923 30 16724
Bolangir Bolangir 7070 2172 432 15 9689
Project Information Memorandum, TMC, Sambalpur, Odisha 37
Brinjal, Cabbage, Radish and Chillies. The catchment area of the market consists of
164 villages and 1 block. Operating time of market is 9 am-6 pm.
Located in Titlagarh block, this market is spread on an area of 2 acres. The number
of traders associated with this market is 100. Around 17000 MT of produce arrives
annually in the market consisting mainly of Tomato, Potato, Onion, Cabbage,
Cauliflower and Okra. The catchment area of the market consists of 133 villages and
1 block. Operating time of market is 6 am-2 pm.
Located in Bolangir block, the market is spread over 2 Acres and consist of 70
retailers. The market is Municipality Haat type of market. Around 10000 MT of
produce arrives annually in the Bolangir market consisting of mainly Cauliflower,
Cabbage, Tomato, Chilli and Brinjal. The catchment area of the market consists of
125 villages and 1 block. Operating time of market is 9 am-8 pm.
4.1.8 Angul
Profile of Angul
The district is spread over an area of 6232 Sq. Km. and constitutes of 4 sub-
divisions and 8 blocks. The district has a population of approximately 11.4 lakh.
The river Mahanadi passes through the district. It has cultivable area of 216403
hectares. Many industrial players in mining, steel and power like NTPC, NALCO,
Jindal Steel, Bhushan Steel etc. are operating in the district. Angul is connected with
NH 6, 23 and 42. The Talcher line and Sambalpur line of the south-eastern railway
runs in the district. The nearest airport is at Bhubaneswar.
Availability of Horticultural Produce
Angul district produces about 3.7 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Cabbage and Tomato. Brinjal and
Cabbage contribute 20 and 10 per cent respectively, while tomato contributes 16 per
cent towards the total production of vegetables. Angul District produces around 1.1
lakh MT of fruits annually. The major fruits grown in Angul District are Banana,
Mango and Citrus.
Project Information Memorandum, TMC, Sambalpur, Odisha 38
Table 15: Production of Major Fruits and Vegetables in Angul
Vegetable Production Fruit Production Spices Production
Brinjal 74590 Banana 22055 Coriander 795
Cabbage 38063 Citrus 14191 Ginger 703
C.Flower 27644 Guava 3919 Garlic 4300
Okra 25412 Litchi 1924 Turmeric 784
Pea 1926 Mango 41252 Chilly 3974
Tomato 60842 Papaya 720
Onion 28522 Pineapple 353
Sweet Potato 15876 Pomegranate 28
Watermelon 4269 Sapota 271
Other
Vegetables
96174 Other Fruit
Crop
28658
Total 373316 Total 113370 Total 10555
Profile of Major Mandis in the district
In Angul catchment mandi will be Angul itself. There are also other mandis present
there but they are mainly supplying directly to Cuttack and Bhubaneswar:
Market District Vegetables Fruits Potato & Onion Spices Total
Angul Angul 2969 6037 679 550 10235
Approximately 10000 MT of produce comes to the market annually consisting of
various fruits. Catchment of the market is spread in around 2 blocks of the district.
Operating time of market is 9 am-6 pm.
4.1.9 Bauda
Profile of Bauda
The district lies in central Odisha, to the south of the Mahanadi River, which forms
the western and northern boundary of the district. The district is spread over an area
of 3098 Sq. Km. The district has a population of approximately 4.4 lakh. Total
cultivated area is 85500 hectare in the district. Bouda is well connected with road
and rail with other district headquarter and the state capital Bhubaneswar. The
distance of Bouda from Bhubaneswar is 240 km. Bouda is connected to road
Project Information Memorandum, TMC, Sambalpur, Odisha 39
network via State Highway No. 1 & 14 and by National Highway No. 42. Regular
train services are available from Bhubaneswar. The nearest airport is Bhubaneswar.
Availability of Horticultural Produce
Bouda district produces about 2.1 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Cabbage and Tomato. Brinjal
contributes around 30 percent of vegetables production, Cabbage contributes around
18 percent and Tomato contributes around 13 percent. Bauda district produce around
22 thousand MT of fruits annually. Major fruits produced are Mango, Banana and
Citrus.
Table 16: Production of Major Fruits and Vegetables in Bauda
Vegetable Production Fruit Production Spices Production
Brinjal 63668 Banana 2818 Coriander 266
Cabbage 39622 Citrus 2332 Ginger 278
C.Flower 15051 Guava 1521 Garlic 636
Okra 17367 Litchi 68 Turmeric 331
Pea 671 Mango 5591 Chilly 817
Tomato 28217 Papaya 454
Onion 3792 Pineapple 66
Sweet Potato 3374 Pomegranate 20
Watermelon 2637 Sapota 29
Other
Vegetables
40942 Other Fruit
Crop
10019
Total 215339 Total 22918 Total 2328
Profile of Major Mandis in the District
There is one major mandi in the district known as Bouda market (Ganesh market).
Located in Bouda block, ganesh market is spread in an area of 3 Acres. There are
around 280 retailers trading in the market. Around 16000 MT of produce arrives
annually in the Ganesh Market consisting of mainly Brinjal, Cauliflower, Cabbage,
Pumpkin, Yam and Water Melon. The catchment area of the market consists of 401
villages and 1 block. Operating time of market is 9 am-6 pm. Arrival figure of this
mandi is as follows:
Market District Vegetables Fruits Potato & Onion Spices Total
Bauda Bauda 13350 896 1548 181 15975
Project Information Memorandum, TMC, Sambalpur, Odisha 40
4.1.10 Nuapada
Profile of Nuapada
The district is spread over an area of 3408 Sq. Km. and constitutes of 1 sub-division
and 5 blocks. The district has a population of approximately 5.4 lakh. Jonk is the
principal river of the district. District has cultivable land of approximately 190000
hectares. There is no large-scale and medium scale industry in the district. The
nearest airports are at Raipur and Bhubaneswar. A railway line from Vizianagaram
on the South-Eastern Railways passes through the district on its way to Raipur
(Chhattisgarh). State Highway No.3 passes through this district and it maintains
direct communication with the adjoining districts apart from all the important places
within the district.
Availability of Horticultural Produce
Nuapada district produces around 1.8 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Okra and Tomato. Brinjal contributes
around 30 percent of vegetables production, Okra constitutes around 7 percent and
Tomato constitutes around 6 percent. Total fruits production in the district is around
53 thousand MT. Major fruits produced are Mango, Guava and Banana.
Table 17: Production of Major Fruits and Vegetables in Nuapada
Vegetable Production Fruit Production Spices Production
Brinjal 56597 Banana 6938 Coriander 138
Cabbage 9991 Citrus 3992 Ginger 239
C.Flower 9534 Guava 6392 Garlic 266
Okra 12157 Litchi 110 Turmeric 205
Pea 784 Mango 20800 Chilly 1574
Tomato 10403 Papaya 959
Onion 9520 Pineapple 172
Sweet Potato 1398 Pomegranate 20
Watermelon 1129 Sapota 300
Other
Vegetables
65686 Other Fruit
Crop
13735
Total 177198 Total 53417 Total 2423
Project Information Memorandum, TMC, Sambalpur, Odisha 41
Profile of Major Mandis in the district
There is one major mandi in the district known as Khariar in Nuapada. Below is the
arrival of this mandi and:
Market District Vegetables Fruits Potato & Onion Spices Total
Khariar Naupada 16419 - 1666 1,822 19907
Approximately 20000 MT of produce comes to the market annually consisting of
Cauliflower, Okra and Radish. Catchment of the market is spread in 3 to 4 blocks of
the district. Operating time of market is 9 am-6 pm.
4.1.11 Sambalpur
Profile of Sambalpur
Sambalpur district of Odisha is spread over an area of 6702 sq. km. with a
population of approximately 1 million. The district comprises of 9 Blocks. It has a
total forest area of 3986.27 Sq. km which is 59.46% of the total area of the district.
Total land under cultivation in the district is 173540 hectares.
Located in Sambalpur, Gol Bazar is one of the largest mandis in the district. Gol
Bazaar is spread in an area of 4 acres. Around 88000 MT of produce arrives
annually in the Gol Bazaar including arrivals from outside the district and state.
Main commodities traded include Tomato, Brinjal, Cabbage, Pumpkin, Carrot and
Banana.
The market, apart from arrivals from its catchment spread in radius of 100 KM, also
witnesses large quantities of arrivals of fruits and vegetables from other parts of the
country, which are not locally produced. Such products include Orange, Grape, and
Apple among fruits and Onion and Potato among vegetables.
The estimated daily arrival in this mandi is around 200-300 MT with the peak arrival
even crossing 400 MT during the season.
Connectivity
As Sambalpur is considered the commercial capital of Western Odisha, it has a well-
established road and rail transportation network. National Highway 6, which
connects Surat to Kolkata, passes through this town. It is connected to Bhubaneswar
through National Highway 42. Sambalpur is the Divisional Headquarter of East
Coast Railway. The nearest Airports are Mana Airport, Raipur and Biju Patnaik
Project Information Memorandum, TMC, Sambalpur, Odisha 42
Airport, Bhubaneswar, both approximately 300 km from the Sambalpur town. A
new airport is being constructed at Jharsuguda (50 km away from the town). The
district has the advantage of being surrounded by major horticultural producing
areas comprising of districts Bargarh, Jharsugda, Deogarh, Angul and Sonapur.
Availability of Horticultural Produce
Sambalpur district produces about 2 lakh MT of vegetables annually. The major
vegetables grown in the district are Brinjal, Tomato, Cole crops and Okra. Brinjal
and cauliflower constitute the major share of the vegetable production of the district
contributing around 15 % and 11 % of the total vegetable production respectively.
Other vegetables like Pea, Cowpea, Knolkhol, Ridge gourd, Yam and Watermelon
etc. constitute 25 percent. Sambalpur District produces around 21 thousand MT of
fruits annually. The major fruits grown in Sambalpur District are Mango, Banana
and Citrus.
Table 18: Fruits and Vegetable Production in Sambalpur
Vegetable Production Fruit Production Spices Production
Brinjal 29618 Banana 6568 Coriander 468
Cabbage 14739 Citrus 7808 Ginger 1315
C.Flower 22358 Guava 2379 Garlic 1174
Okra 14497 Litchi 3138 Turmeric 374
Pea 613 Mango 18323 Chilly 3708
Tomato 17171 Papaya 858
Onion 16692 Pineapple 79
Sweet Potato 15917 Pomegranate 32
Watermelon 12010 Sapota 156
Other
Vegetables
50404 Other Fruit
Crop
16704
Total 194018 Total 56045 Total 7039
Total Availability in Catchment Areas
The total production of fruits and vegetables in the identified catchment of Sambalpur
TM is estimated to be approximately 35 lakh MT.
Project Information Memorandum, TMC, Sambalpur, Odisha 43
Table 19: Fruits and Vegetable Production Catchment Districts of TM
Vegetable Total Fruit Total Spices Total
Brinjal 690828 Banana 113859 Coriander 2986
Cabbage 326637 Citrus 161705 Ginger 6593
C. Flower 228133 Guava 38583 Garlic 13042
Okra 192210 Litchi 11046 Turmeric 5550
Pea 10836 Mango 183488 Chilly 22385
Tomato 398075 Papaya 9036
Onion 173606 Pineapple 1542
Sweet Potato 129386 Pomegranate 244
Watermelon 73593 Sapota 3863
Other
Vegetables
574721 Other Fruit
Crop
190010
Total 2798026 Total 713376 Total 50557
Table 20: District wise Production Figure in Catchment
Name of the District Production
Vegetables Fruits Spices
Bolangir 364599 73022 3670
Sonepur 202091 35265 1744
Angul 373316 113370 10555
Kalahandi 296318 174253 5779
N. W. Pur 177198 53417 2423
Boudh 215339 22918 2328
Sambalpur 194018 56045 7039
Deogarh 83077 24408 2950
Bargarh 446689 35480 5275
Jharsuguda 63816 27999 2694
Sundargarh 381564 97199 6100
Total 2798026 713376 50557
Table 21: Fruits and Vegetable Arrival in Catchment Mandis of TM
Particular Vegetables Fruits Potato & Onion Spices Total
Total 172030 39070 15588 12,511 239199
Project Information Memorandum, TMC, Sambalpur, Odisha 44
Existing Marketing Mechanism in Sambalpur
The existing marketing system is largely unorganized and manual. As a prevailing
practice in F&V trade, it is mostly middlemen driven. Fruits and vegetables are
collected by the aggregators/ consolidators and brought to the nearest commission
agent to whom the aggregator is attached and then the commission agent sells the
produce to the wholesalers. The retailers subsequently purchase from the
wholesalers. Since there are no regulated markets for fruits and vegetables in the
entire state, they are mainly sold as per the above mentioned existing chain except
onions and potato which are sold through the Regulated Market System. On an
average, the retailer sells 60-70% of his produce at market rate and rest 30-40 %
below the market rate. Since he has the compulsion to sell the produce the same day,
this selling pattern is common in fruit and vegetable retail.
In the value chain, the flow of information is restricted to certain levels only. The
producers do not have proper information about the demand and supply situation in
the consumption market and hence are not able to accurately capture the price
arbitrage in the distant market.
Since there is no organized marketing system for F&V, the farmer sells his produce
on prices decided by middlemen and not on prices that may actually be prevalent in
the market. During the field study and through focused group discussions with
various stakeholders, the lack of an organized and formal mechanism of marketing
horticultural produce emerged as a major issue/constraint. Most farmers engage in
distress selling of some proportion of their produce. Middlemen have formed cartels
and decide the prices at which they would procure the produce. In some cases, in
order to deflate price trends in the local market, they even resort to dumping of
produce from other states in the local market.
In view of the above facts, the proposed TM would be able to provide an alternate
market mechanism to the farmers for selling their produce. While the above
mentioned facts point out the existing inefficiency in the value chain, they also offer
an opportunity for a prospective private entrepreneur to create value by setting up a
Terminal Market. The images below are of the Gol Market mandi, one of the
prominent mandis in the Sambalpur district.
Project Information Memorandum, TMC, Sambalpur, Odisha 45
Chapter 5
Forward Linkages – Terminal
Market
Project Information Memorandum, TMC, Sambalpur, Odisha 46
5.1 Forward Linkages- Modern Terminal Market
Out of the total production of more than 35 Lakh MT of fruits and vegetables in the
major catchment districts of Sambalpur Terminal Market, it is estimated that around
50% is marketable surplus and traded in local markets. Such markets are located in
Jharkhand, West Bengal, Chhattisgarh and Andhra Pradesh. Also, since Odisha has
potential to produce manifold of F&V distant market can also be linked to
Sambalpur TM. It can be linked with major metros like New Delhi, Mumbai,
Bangalore, and Nagpur for supply of Vegetables.
It is estimated that 15% of marketable surplus will come to TM, which is estimated
to be around 2.5 lakh MT. At present, there is a only a small market in Sambalpur.
But with the establishment of a terminal market in Sambalpur, huge quantities are
expected to be traded due to following reasons-
1. No existing formal market in catchment.
2. Sambalpur is the most developed area in the catchment and is distribution
centre for the catchment area. There is deficit of potato and onion in catchment
area. Approximately 30000 MT of potato comes from outside and distributed
in catchment area. This can be traded through Sambalpur TM.
3. Brinjal, Cabbage, Cauliflower and ginger are in surplus in region alongwith
some other vegetables. Also farmers are not cultivating total landholding for
vegetables due to inaccessibility to the market. Though some of the produce is
going to other states but with the TM higher produce will go out. This will
lead to higher demand and production of vegetables.
4. Constant effort from Horticulture Department in last decade, Mango and
Banana production has increased sharply in the area.
5. Odisha is big producer of organic crops due to lesser reliance on fertilizers.
This provides a unique opportunity for catchment area to supply organic
produce to various parts in India.
For the proposed Terminal Market, the annual handling capacity in the beginning
shall be pegged at 2.5 lakh MT while keeping the provision of capacity enhancement
over a period of time. During our field study and analysis of the existing supply
chain, it was highlighted by various stakeholders that the proposed Terminal Market
shall be catering to markets like Bhubaneswar, Ranchi, Raipur, Hyderabad, and
Kolkata. The field study also brought to light the fact that various catchment districts
of Terminal Market were already feeding some of the above mentioned geographies.
Project Information Memorandum, TMC, Sambalpur, Odisha 47
The distance matrix to various consumption markets from the catchment of terminal
market is shown below:
Table 22: Distance Matrix to Various Consumption Markets from the
Catchment of Terminal Market
Distance Matrix - Production Areas to Major Consumption Markets (In KM)
Bhuba
neswar
Jamshe
dpur
Ranchi Raipur Hyde
rabad
Kolk
ata
Bilaspur Nagp
ur
Delhi
Sambalpur 300 407 355 262 1054 589 258 564 1370
Major consumption markets like Bhubaneswar, Cuttack, Raipur, Ranchi, Bilaspur
etc are located within a radius of 250-300 kilometers from the proposed site and can
be reached by road and rail within a time span of 4-5 hours. Even distant markets
like Kolkata, Hyderabad, Nagpur etc are well connected by both rail and road
networks thus ensuring smooth and timely supply of materials to these markets.
Therefore, the private enterprise (PE) can target such markets for supplying fresh
fruits and vegetables.
5.1.1 Mapping of Major Markets for TM
Twin Cities of Bhubaneswar and Cuttack
The urban agglomeration formed by Bhubaneswar and Cuttack is the largest town
and capital of the state. The metropolitan area formed by the twin cities has a
population of 1.4 million. Total population including rural population is 4.4 million.
The city has strong connectivity network with other states. The East Coast
Railway has its headquarters in Bhubaneswar. It is connected to major cities of the
country such as New Delhi, Mumbai, Kolkata, Chennai, Bangalore, Jamshedpur,
Raipur, Ranchi, Guwahati, Ahmedabad, Hyderabad, Lucknow, Bokaro etc. by
daily express and passenger trains.
Bhubaneswar is connected to the rest of the country by NH 5, NH 203, which
ensure strong connectivity of the city with other parts of the country via road
network. Apart from rail and road connectivity, the city has good air connectivity
also. Daily directs flights from Bhubaneswar to cities like Delhi, Kolkata, and
Mumbai provides good air connectivity.
Project Information Memorandum, TMC, Sambalpur, Odisha 48
Market size for fresh fruits and vegetables in Bhuvaneshwar
Bhubaneswar, being the capital of the state and the largest town, offers a big market
for fresh vegetable and fruits. Below is the monthly expenditure pattern of both rural
and urban consumer:
The share of vegetables and fruits in the total food expenditure of urban consumer is
estimated at around 15% while the same for a rural consumer is 14%. In view of the
ongoing developments and emerging opportunities in the capital and state as well,
the overall lifestyle and income is expected to improve and these figures are likely to
go up. The estimated annual consumption of fresh vegetables and fruits in
Bhubaneswar & Cuttack (Urban) is estimated to be 5.25 Lakh MT approximately.
Kolkata
It is estimated that approximately 4 Lakh MT of fruits and vegetable annually are
sent to Kolkata from various outside markets. Further, if other cities of West Bengal
like Durgapur, Burdwan and Asansol are also considered, annual inflow from
outside is more than 5 Lakh MT. As Kolkata is well connected by rail and road this
can be huge potential market for supplying of F&V from TM.
Ranchi
Though Jharkhand is a surplus state in vegetable production, it still depends on
Odisha for vegetables like Cabbage, Cauliflower etc. The estimated inflow from
outside to major consumption markets of Jharkhand like Ranchi, Dhanbad,
Jamshedpur and Bokaro is approximately 3-4 Lakh MT which mainly constitutes of
fruits from Bihar. As production of fruits is continuously increasing and it is going
to be manifold in future Jharkhand can be major place of consumption of fruits from
TM.
Raipur
Raipur is the capital of Chhattisgarh and it is a major distribution centre to various
markets in Chhattisgarh along with Bilaspur. Large quantities of vegetables are
supplied to Raipur and Bilaspur from catchment areas. Approximately 10000 MT of
Brinjal, Cabbage and Cauliflower is being supplied to Chhattisgarh. It is a very well
connected market and fresh produce can be supplied within 5-6 hours to Raipur and
Bilaspur.
Therefore, it will be a significant opportunity for the terminal market to explore such
markets and meet their demand. Apart from markets mentioned above, the TM can
also tap opportunities in various other markets especially for supply of Brinjal,
Cabbage and Cauliflower. This becomes even more important in the current context
Project Information Memorandum, TMC, Sambalpur, Odisha 49
where major corporate entities are now looking at Odisha both in terms of sourcing
of various produce as a retail market opportunity. A big corporate has already
commenced its operations in Odisha and is procuring F&V from the catchment area.
Exhibit 7: Mapping of Consumption Markets Linked to TM
*The linkages to distant markets like Hyderabad, Delhi and Mumbai are seasonal and
produce specific.
Project Information Memorandum, TMC, Sambalpur, Odisha 50
Chapter 6:
Terminal Market Complex
Sambalpur
Project Information Memorandum, TMC, Sambalpur, Odisha 51
Location Details
The Directorate of Horticulture, Odisha has under its possession 60 acres of land in
Nildunguri, District Sambalpur to set up a Terminal Market Complex. The location
connectivity details are as follows:
The Site is situated on National Highway 6. Access proposed through under
construction 150‟ and 300‟ roads from NH-6.
16 kms from Sambalpur town towards Deogarh, Pallahara, Baripada, Kolkata.
Surrounding villages: In Jujumura block, Khaliapali, Pudapada, Kabarapal etc
RMC yard is 400 meters away from the site.
Nearest Railway Station is 7-8 kms away
Water Source Availability Details
Shasan canal of Hirakud Canal System (North) is 500 meters away from the
site but water use is not permitted for industrial use. The water available is soft
water.
Ground water availability is low as per hydrological report of the area. It
fluctuates between 10-20 meters depending on season.
Nearest bore well available in the location was bored 90 meters having free
surface level at 20 meters discharge. Open wells available ½ a km from MTM
site.
Nearest water body (canal) is approximately 7 kilometers away from the Site
Power Source Details
11 KVA line is passing through the Site and a 33 KVA line is 7 kms. From the
Site
Nearest transformer is at Kudapali, 7 kms. From the Site
Other Details
Slope gradient of the proposed Site is approximately 2% on an average
The Site will require negligible to moderate filling
At present, the Site is covered by trees and shrubs
Nature of soil: rocky and morrum soil
Two petrol pumps within 1 km of the Site
Rice Mill located opposite the Site (other side of NH 6)
Source: Office of the Deputy Director, Horticulture, Sambalpur and site visit carried
out by IL&FS Clusters team.
Project Information Memorandum, TMC, Sambalpur, Odisha 52
Exhibit 8: The Site
Exhibit 9: Proposed Entrances
Project Information Memorandum, TMC, Sambalpur, Odisha 55
7.1 Broad Mandatory Infrastructure at TM
The major activity of this market will be handling of large-scale produce of
horticultural produce. This will involve providing various facilities for receiving the
produce, their movement within the TM, display, auction, packaging, storage,
dispatch etc.
Systems like automatic weighing platforms, price discovery mechanisms, cold & dry
storages, cleaning sorting and grading facilities etc have to be provided in the TM.
In addition, proper information capturing system is to be maintained for monitoring
the entry and exit of trucks, and record their contents and movement within the
market complex.
A Service Core has to be provided in each building for internal movement of the
produce. Each service core shall have staircases, ramps, lifts, toilets etc.
Also, in the layout, provisioning shall be done for future expansion. The layout
enables phase-wise execution of the market facilities. Following are the minimum
infrastructure requirements for the Modern Terminal Market.
Table 23: Basic-Minimum Infrastructure Facilities to be provided at the TMC
& CC
Core Facilities Support Infrastructure Service
Infrastructure Automatic weighing platforms Water Supply Rest Rooms
Auction Platforms Power Parking Facility
Loading, Unloading & Dispatch
section and Logistics hub
Drainage Sanitary Facilities
Cleaning, Sorting & Grading facilities Room for Posts & Telephones Agri Mall
Price Display Mechanism Room for Banking Facilities
Office Rooms Input/Daily Necessity outlets
Information Centers Price on-line facility
Packaging & labeling unit Computerized systems
Drying yards Rain proofing
Storage/Cold rooms
Ripening Chambers
Conference Rooms/Public Address
system
Details of the facilities are given below. Area has been calculated based on area
occupied for auctioning in various mandis in India. As these mandis are facing
problem of congestion and functioning above capacity, greater space for core facilities
in comparison to other mandis have been proposed.
Project Information Memorandum, TMC, Sambalpur, Odisha 56
7.1.1 Auction Platforms
Auction hall with an area of 1500 sq mt. has been proposed. The auction halls
should have receiving areas, display areas, electronic auction areas and distribution
areas. The halls should have fairly large spaces and flexibility for their division into
smaller areas, which could be used for fruits, vegetables, as per requirements so that
the activities can be divided easily without disturbing other areas. It will be
connected to the loading-unloading area, sorting-grading area, drying yard and
packaging facility.
7.1.2 Large Halls for Loading, Unloading, Grading and Packing
For loading, unloading, cleaning, grading and sorting, 5500 sq mt area has been
apportioned. This area has to be provided near the Auction and Display areas. From
the auction and display areas, the goods will be brought to the Grading and Packing
Zone where modern machines will be installed for the same. These are connected to
freight lifts whereby through mechanical means like conveyor belts, goods will be
transported to dispatch areas or cold storage. The consignments will be graded and
packed for immediate dispatch to the local markets, distribution to distant wholesale
markets and repacked for export.
7.1.3 Packaging & Labeling Unit and Drying Yard
For packing, grading and drying facilities, a total space of 3750 MT has been
proposed. These facilities are required for better price realization of horticulture
produce.
7.1.4 Cold Storage & Warehousing Units
5000 MT of cold storage has been proposed for the proposed TM. This cold storage
will be operated on CA technology. Total area required for the cold chambers will
be 5000 sq mt. These units have to be provided at the rear end of the complex.
Goods will be received and stored. The cold storages can also be hired out to the
wholesalers, buyers and sellers for storage of goods.
5000 MT of dry storage space has been proposed for TM. Area required for the
facility will be 2500 sq mt. This facility will be used by traders, wholesalers and
farmers.
7.1.5 Parking Space for Containers, Trucks, Small Vehicles etc
Designated parking areas have been provided on Leased out/rent basis for Long term
parking, short-term parking and docking areas for trucks, light motor vehicles, two –
wheelers. Total area allocated for parking is 5000 sq mt., out of which 3750 sq mt
are will be assigned for trucks and the remaining area for other vehicles. Truck
parking has been planned based on peak arrival of trucks per day.
Project Information Memorandum, TMC, Sambalpur, Odisha 57
7.1.6 Traditional Shops for Traders
A total of 50 shops have been planned for the TM. Twenty five big shops of 50 sq
mt each and 25 small shops of 25 sq mt each have been proposed. These shops will
have two levels, one for storage and one for office. It will be possible to have a
display area in the front. Corridors have to be provided in front of the shops for
buyers to visit, discuss and negotiate.
7.1.7 Display Areas
Provision of display areas has to be made outside the Auction areas as the
wholesalers, retailers and exporters will mainly require access to these areas for
inspection of goods.
7.1.8 Viewing Galleries
These have to be provided at the mezzanine floor level of the auction hall for getting
a complete view of the process. It should be equipped with all kinds of electronic
gadgets like cameras etc. This will control and monitor the various activities like
loading / unloading, packaging, distribution etc being carried out.
7.1.9 Office Areas/Quarters
Administrative buildings of 500 sq mt each have been proposed for the facility.
Apart from this, it will have 800 sq mt of conference rooms and halls for organizing
meetings, seminar etc. Besides these, other supplementary facilities like bank
counters, ATM centers, etc could be housed.
7.1.10 Logistics Hub
A logistics hub has been planned inside TM. It will provide solutions for logistics
services at single place. Area of 500 sq mt has been proposed for the same.
7.1.11 Circulation Pattern of the Market Facility
This market facility will generate heavy traffic movement of vehicles like trucks,
containers, etc. Easy vehicular access has to be provided for all the activities being
carried out within the complex. Roads, approaches and entry exit points of vehicles
have to be designed in such a manner that the various movements of vehicles are
segregated. Docking areas for trucks is to be provided in each zone wherever
required.
7.1.12 Allied Shops and Food Court
Shops for various agri inputs like fertilizer, seed and pesticides has been proposed
along with other agriculture extension facilities. Lodging facility of farmers along
with food court is also proposed. Total area proposed for the facilities is 2500 sq mt.
Project Information Memorandum, TMC, Sambalpur, Odisha 58
7.1.13 Non Marketing Infrastructure
Non marketing facilities like guest houses, motel, auto repairing and parts shop etc.
have been planned for the proposed TM. Total area planned for the facility is 3200
sq mt.
7.1.14 Other Service Areas
Administrative areas are to be provided which will have cash desk, service
providers, public conveniences such as cafeterias, toilets, etc. Public Conveniences
such as rest rooms, washrooms, toilets, cafeterias etc. also are to be provided for
large number of truck drivers coming to these areas.
7.1.15 Additional Facilities
A Central Library and information center is to be provided which will give
information regarding produce, cost, etc. Information sharing channels need to be
created to connect to nodal centers in catchment areas to ensure connectivity with
farmers, to establish forward linkages. Ten nodal centers are already present.
7.2 Collection Centers
Concept of modern terminal market revolves around the hub and spoke model. TM
will act as hub and collection centers will act as spokes for the TM. Initially, only
five collection centres have been proposed to be set up. These will be located in
following districts-
1. Bargarh
2. Kalahandi
3. Sundergarh
4. Nuapada
5. Bauda
These collection centers have been proposed based on production of fruits and
vegetables and geographical presence in the district. Basic facilities like grading,
sorting and pre-cooling will be carried out at these collection centers. Though specific
locations have not yet been identified for collection centers, it is assumed that the PE
will identify the suitable location for collection centers.
Collection centers have not been proposed at Deogarh, Jhasuguda, Bolangir, Angul
and Sonapur as these locations will directly supply to proposed TM. However, in the
future, if PE finds it suitable, it can establish collection centers in these districts.
Project Information Memorandum, TMC, Sambalpur, Odisha 59
Chapter 8:
Project Cost and Major
Assumptions
Project Information Memorandum, TMC, Sambalpur, Odisha 60
8.1 Project Cost
Project cost has been calculated taking land cost at circle rate of Rs. 2.0 lakh per
acre. The Project is estimated to cost Rs. 7321 lakh. The cost estimates are based on
industry standard. The detailed breakup of the cost of the Project is given below:
Table 24: Project Cost of MTM, Sambalpur
Particulars Amount in Rs. Lakh
Land 145.00
Land Development 917.50
Buildings 2787.45
Plant Machinery & Equipments 2,193.25
Utilities & other fixed assets 528.50
Preliminary and Pre-Operative
Expenses
373.63
Contingencies 340.02
Margin Money for Working Capital 35.86
Total Project Cost 7,321
Note: The project cost considered for grant does not include Margin Money for
Working Capital and Non Marketing Infrastructure cost of Rs.384 lakh.
8.2 Means of Finance
The cost of the project is proposed to be financed through a mix of equity, grant
from National Horticulture Mission (NHM) and term loans from banks/ FIs.
Table 25: Means of Finance for MTM, Sambalpur
Particulars Amount in Rs.
Lakh
Share
Equity 1,464 20.0%
Grant-NHM 2,761 37.7%
Debt 3,096 42.3%
Total 7,321 100.0%
For the purpose of financial projections, grant component has been considered as
40% of the eligible project cost. Further, various scenarios have been presented in
following section by considering grant at various levels from 25 to 40 percent.
Project Information Memorandum, TMC, Sambalpur, Odisha 61
8.3 Details of Project Cost
8.3.1 Land
Cost of land (60 Acres) is taken at Rs 2 lakh per acre based on circle rates provided
by Directorate of Horticulture. Currently, land is under the possession of the
Directorate of Horticulture and same will be transferred to the PE. For Collection
centers, land cost has been assumed as Rs. 10.0 lakh per acre as these centers will be
situated in interior areas.
8.3.2 Land Development
Cost of land development has been estimated at Rs. 15.0 lakh/acre. Land
development includes activities such as land filling, leveling, boundary wall,
sewerage lines, storm water drainage, internal roads etc.
8.3.3 Buildings
Cost of buildings have been estimated at Rs1687.60 lakh and includes major
components such as
Civil construction for cold storage (5000 sqm @ Rs 12000/ sqm, including
puff panels)
Ripening chambers-8 chambers of 10 MT each (200 sqm @ Rs
14000/sqm)
Warehouse-5000 MT (2500 sqm @ Rs 10000/sqm)
Office building and traders shop (5050 sqm @ Rs 9200/sqm)
Loading/ unloading and auction halls (5000 sqm @ Rs 5750/sqm)
Sorting, grading area (2000 sqm @ Rs 5750/sqm)
Packaging facilities (750 sqm @ Rs 5750/sqm) etc.
8.3.4 Equipment
The break-up of the estimated cost of major machinery is provided below:
Table 26: Cost Break up of Machinery and Equipments
Plant, Machinery & Equipments Unit No of
units
Rate/ Unit
(Rs)
Amount
(Rs. Lakh)
Cold Store-2000 MT MT 5 5000000 250.00
Ripening Chambers (8 chambers of 10 MT
each)
TPD 20 640000 128.00
Sorting, grading, packaging facility-5
MT/Hr
Nos. 6 4500000 270.00
Conveyer based handling system Nos. 5 3500000 175.00
Project Information Memorandum, TMC, Sambalpur, Odisha 62
Electronics Auction System Ls 150.00
Weigh Bridge (30 MT) Nos. 2 3000000 60.00
Loading Unloading facilities-Dock
Levelers
Nos. 10 800000 80.00
Crate Nos. 200000 270 540.00
Pallates Nos. 6000 3300 198.00
Fork Lifts Nos. 3 1200000 36.00
Weighing Machines Nos. 30 30000 9.00
Testing & Certification Lab Ls 75.00
Vehicles (Refer (2) and Normal (4)) Ls 88.00
Total-Main Market Complex 2059.00
8.3.5 Miscellaneous Fixed Assets / Utilities
The breakup of the estimated cost of the miscellaneous fixed assets and utilities is
provided below:
Table 27: Utilities and Misc Assets
Utilities and Misc Assets Amount (Rs. Lakh)
DG Sets (320 KVA x 3) 105.00
Power Supply system & control panels 150.00
Water supply treatment and distribution system 150.00
ETP/STP 50.00
Others 60.00
Total Utilities & other Assets 515.00
8.3.6 Preliminary & Pre-operative Expenses
The provision towards preliminary & pre-operative expenses includes expenses like
salaries & administrative expenses, travel expenses, market development expenses,
interest during construction period (interest for three quarters) etc. It is also assumed
that the project will be completed over a period of one and half year. The interest
during construction period is capitalized in the project cost. The detailed breakup is
given below:
Table 28: Preliminary and Pre-operative Expenses
Particulars Amount in Rs. Lakh
Interest on term loan during Construction 301.90
Administration related expenses 71.73
Total 373.63
Project Information Memorandum, TMC, Sambalpur, Odisha 63
8.3.7 Working Capital Requirement
The major revenue stream for the MTM (Modern Terminal Market) will be from
market fee (user charges), rentals from shops, rentals of cold storage, sorting-
grading-packaging facilities, income from crates, ripening chambers and other
facilities like agri-mall, parking space etc. As the Terminal Market is mainly a
service provider for its users, the firm will not be involved in trading of raw material
for its business operations. Hence, the major component of working capital will be
contributed to debtor due to current trade practices. At present, the credit cycle
ranges from 15-30 days. The other major component will be short term liabilities
like salary, wages, monthly electricity bills, debt component due within one year and
other recurring expenses. The firm‟s working capital requirements for the first year
are calculated as described below:
Table 29: Working Capital Requirement
Particulars Holding Period
(Days) Amount in Rs. Lakh
Business expenses 30 66.26
Debtors 30 77.19
Total 143.45
Margin Money 25% 35.86
8.3.8 Contingencies
The amount is calculated at 5% of cost of site development, civil work, plant &
machinery, other fixed assets and pre-op expenses.
8.4 Operating Cost Assumptions
8.4.1 Arrival Assumptions
Arrivals have been estimated at 250000 MT per annum at peak capacity. This figure
has been arrived keeping in mind the annual production, annual arrivals in nearby
mandis and arrivals in similar type of mandis. Total annual production in the
catchment area is approximately 35 lakh MT. This will grow in future when there will
be established market linkage of horticulture produce and better price realization.
8.4.2 Power Cost
The total connected load of the project is estimated at about 1200 KVA. The power
tariff has been assumed at the currently prevalent tariff of Rs 5 per unit for industries
with HT connection. Average Daily requirement of power is estimated to be about
11000 KWH at 70% average power factor.
Project Information Memorandum, TMC, Sambalpur, Odisha 64
8.4.3 Fuel Cost
Fuel cost for DG set is assumed as consumption of diesel 40 liters/ hr and average
running of DG set for 10 hrs/ day. The cost of diesel is assumed at Rs 42/ liter.
8.4.4 Raw Material for packaging
The average cost of raw material for packaging facility is taken as Rs 100/ MT. It
will be simple poly packaging/ shrink wrapping.
8.4.5 Employee Cost
The employee cost has been assessed based on an organization structure required for
this type of facility. The managerial and the support staff and estimated cost for the
proposed level of operations are tabulated below:
Table 30: Employee details
Grade/ Employee Number Salary/ pm (RS) Total Monthly Cost (Rs)
General Manager 1 40000 40000
Manager Operations 2 15000 30000
Business Development 2 15000 30000
Operators (For cold storage plant etc.) 5 10000 50000
Maintenance (Electricians etc.) 3 8000 24000
Account & Admin 2 8000 16000
Security & Support Staff 6 4500 27000
Total Employee Cost (Per Month) 21 217000
Labour 50 4000 24
8.4.6 Maintenance Cost
Maintenance cost is assumed at 2% of cost of fixed assets, with 2.5% annual
increment.
8.4.7 Cost of insurance
The cost of insurance has been assumed as 1.0% of WDV (Written down Value) of
plant & machinery, miscellaneous fixed assets and other assets.
8.4.8 Admin & Selling Overheads
Admin & Selling overhead Cost has been assumed @ 2.0% of revenues
8.5 Financial Assumptions
8.5.1 Taxes
The Income Tax rate is assumed as flat 33.22%.
Project Information Memorandum, TMC, Sambalpur, Odisha 65
8.5.2 Depreciation Rates
Depreciation has been provided on straight-line method, as per the Companies Act,
1956, for book purposes, whereas for tax purposes, written down value method is
employed. The rate of depreciation for plant & machinery and miscellaneous fixed
assets is taken as 10% for book purposes by straight line method and 15% for tax
purposes by WDV method. The assumed depreciation rates for various assets are
given as below:
Table 31: Depreciation Rates
Assets Category Book Depreciation Tax Depreciation
Plant & Machinery 10.34% 15.00%
Miscellaneous Fixed Assets 10.34% 15.00%
Buildings-Plant 3.34% 5.00%
Buildings-Non Marketing 1.63% 5.00%
8.5.3 Interest
Interest would be charged to the Project at 13.00% p.a. for Term Loan and at
13.50% for working capital loan. Duration of the term loan will be 40 quarters
including the moratorium period for initial six quarters.
8.6 Revenue Assumptions
Revenue assumptions of the Project are detailed in following sections-
8.6.1 User Charges
2% of value of arrivals will be taken as user charges for auction and market fees.
Average value of produce has been considered at Rs.8000 per MT. From 4th
years
onwards user charges will be 4% of value of produce.
8.6.2 Rental from Traders Shop
Rental of Rs.200 per sq mt has been proposed for traditional mandi shops. Rental
will be collected monthly.
8.6.3 Income from Agri Mall, Parking, Etc.
The revenue from these facilities includes rent from buildings such as agri-mall,
canteen, lodging for farmers, parking space etc. The rental for commercial space
(agri-mall) is taken as Rs 300/ sqm/month (for constructed area of 4000 sqm),
parking as Rs 150/ truck (assuming about 21000 vehicles will visit the facility per
Project Information Memorandum, TMC, Sambalpur, Odisha 66
annum), weigh bridge rental is considered at Rs 250/ vehicle and for testing lab
1000 sample per month will be tested by charging an average price of Rs 500/
sample.
8.6.4 Crates User Charges
200000 crates have been proposed to be bought for the facility. User charges of Re.
1/day/crate have been proposed. Approximately 60% of crates have to be replaced
every year. So we have deducted crate replenishment cost from crates user charges
earned.
8.6.5 Cold Store
The charges assumed for cold storage facility are comparable to prevailing market
rates in most part of the country. The average rental is taken as Rs 700/ MT per
month.
8.6.6 Ripening
The ripening charges are assumed as Rs 1400/MT of ripened banana. The ripening
quantity is taken as 20 MT per day throughout the year.
8.6.7 Sorting, grading, packaging facility
The charges are assumed at Rs 400/MT. It is also assumed that only 40% of peak
arrival will go through these processes.
8.6.8 Warehouse
The rental assumed for storage of grains and other suitable commodities is Rs 100/
MT/Month.
8.6.9 Non Marketing Activities
Area of 3200 sq mt has been proposed for non marketing infrastructure. Guest
house, motel, auto parts shop, restaurants etc. have been planned for the facility. The
rental for space is taken as Rs 300/ sqm/month.
8.6.10 Capacity Utilization
The project has assumed 40% capacity utilization in the first year, which may be
regarded as conservative considering the established road network, production in the
area and vicinity to major consumption market of the state. Capacity utilization may
be higher than the projected one.
Table 32: Estimated Capacity Utilization
Year Capacity Utilization
Year I 40%
Year II 55%
Year III 70%
Year IV onwards 80%
Project Information Memorandum, TMC, Sambalpur, Odisha 67
8.7 Projected Financial Performance
The projected profitability statement, cash flows and balance sheet of Modern
Terminal Market are given below.
Table 33: Projected Profitability Statement (Rs. Lakh)
Amount in Rs. Lakh (Land Cost as 2 Lakh per acre)
Year 1 2 3 4 5 6 7
Revenues 926.29 1273.65 1621.00 2172.58 2172.58 2172.58 2172.58
Total Expenditure 389.12 450.92 513.81 557.75 552.83 548.29 541.18
EBIDTA 537.16 822.72 1107.19 1614.83 1619.75 1624.28 1631.40
Total Interest Cost 417.06 417.55 382.23 339.54 291.74 243.95 196.14
Depreciation 323.63 323.63 323.63 323.63 323.63 323.63 323.63
PBT -203.53 81.54 401.33 951.66 1004.38 1056.70 1111.63
Tax 0.00 0.00 0.00 282.38 320.83 356.02 389.41
Net Profit (PAT) -203.53 81.54 401.33 669.28 683.55 700.68 722.22
PAT Margin -21.97% 6.40% 24.76% 30.81% 31.46% 32.25% 33.24%
The detailed projected income statement is attached as Annexure-1
The above table indicates that the project will be able to generate profit from 2nd
year of operation at Rs. 2 lakh as land cost. The net profit is showing increasing
trend, which indicates commercial sustainability of the proposed project. Though,
there is loss (which is just an accounting number) in 1st year of operation, but the
project will generate positive cash from 1st year of operations.
Table 34: Financial Performance indicators
Amount in Rs. Lakh (Land Cost as 2 Lakh per acre)
Year 1 2 3 4 5 6 7
EBITDA Margin 57.99% 64.60% 68.30% 74.33% 74.55% 74.76% 75.09%
PAT margin -21.97% 6.40% 24.76% 30.81% 31.46% 32.25% 33.24%
Debt-Equity Ratio 0.77 0.71 0.57 0.42 0.31 0.22 0.15
Debt to EBITDA ratio 5.96 3.70 2.44 1.47 1.24 1.01 0.78
Interest Coverage Ratio 1.29 1.97 2.90 4.76 5.55 6.66 8.32
DSCR 1.29 1.37 1.48 2.29 2.47 2.67 2.91
Average DSCR 2.09
Project IRR 15.24%
The DSCR for the proposed project is more than 1.50 throughout the term of loan
and is regarded as at respectable level. It indicated the ability of project to re-pay its
Project Information Memorandum, TMC, Sambalpur, Odisha 68
debt liabilities. Moreover, the time series analysis of debt-equity ratio shows that
project will be easily able to reduce debt burden from its capital structure. The IRR
of project is estimated at 15.24 at Rs.2 lakh as land cost (Considering the grant
component @ 40% of eligible cost of project for calculation of grant. As, all the
project cost components are not eligible for grant, the effectively the grant
component is 37% of project cost) and makes the project attractive to the investors.
Table 35: Projected Cash Flow Statement (Rs. Lakh)
Amount in Rs. Lakh (Land Cost as 2 Lakh per acre)
Year 0 1 2 3 4 5 6 7
Sources
Total Cash inflow 7321.21 227.69 430.72 748.37 1027.46 1003.93 1021.09 1042.46
Uses
Total Uses 7285.34 143.45 216.21 395.50 410.35 359.95 359.98 359.77
Opening Cash Balance 0.00 35.86 120.10 334.62 687.49 1304.59 1948.57 2609.67
Surplus/ Deficit 35.86 84.24 214.51 352.87 617.10 643.98 661.10 682.69
Closing Cash Balance 35.86 120.10 334.62 687.49 1304.59 1948.57 2609.67 3292.36
The closing cash balance is always positive for the project and showing steady
increasing trend. The detailed cash flow statement is attached as annexure-2.
The sensitivity analysis of major financial performance indicators IRR and DSCR is
performed w. r. t. Grant component due to the fact that bidders will be submitting
their proposals for various level of grants. The range for grant component is 25% to
40% of eligible cost of project. The table below shows the variation in IRR and
DSCR with change in Grant component.
Table 36: Sensitivity Analysis
Land Cost Grant (%) 25% 30% 35% 40%
Rs. 2 Lakh
Land Cost
Rs. 20 Lakh
Land Cost
IRR (%) 8.70% 11.01% 12.75% 15.24%
DSCR 1.5 1.7 1.9 2.1
The analysis shows that even if the grant component is at lower end (25%) the IRR
and DSCR seems attractive from investor and lender‟s point of view if land cost is
Rs 2 lakh per acre.
Project Information Memorandum, TMC, Sambalpur, Odisha 69
Annexure
Annexure 1: Projected Income Statement (Amount in Lakh Rs)
Amount in Rs. Lakh
Year 1 2 3 4 5 6 7 8 9 10
Capacity Utilization 40% 55% 70% 80% 80% 80% 80% 80% 80% 80%
User Charges (Market fees) 160.00 220.00 280.00 640.00 640.00 640.00 640.00 640.00 640.00 640.00
Rental of Traders Shop 36.00 49.50 63.00 72.00 72.00 72.00 72.00 72.00 72.00 72.00
Income from agri mall, parking testing lab etc. 115.20 158.40 201.60 230.40 230.40 230.40 230.40 230.40 230.40 230.40
Crates User Charges 134.40 184.80 235.20 268.80 268.80 268.80 268.80 268.80 268.80 268.80
Revenue from Cold Store 154.00 211.75 269.50 308.00 308.00 308.00 308.00 308.00 308.00 308.00
Rental- Ripening Chambers 36.96 50.82 64.68 73.92 73.92 73.92 73.92 73.92 73.92 73.92
Sorting/ Grading Packaging facility 219.65 302.02 384.38 439.30 439.30 439.30 439.30 439.30 439.30 439.30
Rental-Warehouse 24.00 33.00 42.00 48.00 48.00 48.00 48.00 48.00 48.00 48.00
Non Marketing Income 46.08 63.36 80.64 92.16 92.16 92.16 92.16 92.16 92.16 92.16
Total Revenue 926.29 1273.65 1621.00 2172.58 2172.58 2172.58 2172.58 2172.58 2172.58 2172.58
Total Expenses 389.12 450.92 513.81 557.75 552.83 548.29 541.18 534.16 527.15 522.15
EBITDA 537.16 822.72 1107.19 1614.83 1619.75 1624.28 1631.40 1638.42 1645.43 1650.43
Interest on term loan 402.54 399.58 361.10 313.74 266.38 219.03 171.67 124.31 76.96 29.60
Interest on working capital borrowings 14.52 17.97 21.13 25.80 25.36 24.92 24.47 24.01 23.55 23.12
Depreciation 323.63 323.63 323.63 323.63 323.63 323.63 323.63 323.63 323.63 241.40
PBT -203.53 81.54 401.33 951.66 1004.38 1056.70 1111.63 1166.47 1221.29 1356.32
Tax 0.00 0.00 0.00 282.38 320.83 356.02 389.41 420.51 449.69 476.56
Net Profit (PAT) -203.53 81.54 401.33 669.28 683.55 700.68 722.22 745.95 771.60 879.76
Project Information Memorandum, TMC, Sambalpur, Odisha 70
Annexure 2: Projected Cash Flow Statement (Amount in Lakh Rs.)
Amount in Rs. Lakh
Year 0 1 2 3 4 5 6 7 8 9 10
Sources
Cash from Operations
PAT -203.53 81.54 401.33 669.28 683.55 700.68 722.22 745.95 771.60 879.76
Add Depreciation 323.63 323.63 323.63 323.63 323.63 323.63 323.63 323.63 323.63 241.40
Net Cash from Operations 120.10 405.17 724.96 992.91 1007.18 1024.31 1045.85 1069.58 1095.23 1121.15
Cash From Financing
Equity 1464.24
Grant 2760.54
Term Loan 3096.43
Increase in Working Capital
Borrowing
0.00 107.59 25.55 23.41 34.55 -3.25 -3.23 -3.39 -3.38 -3.38 -3.25
Total Cash inflow 7321.21 227.69 430.72 748.37 1027.46 1003.93 1021.09 1042.46 1066.20 1091.85 1117.90
Uses
Capital expenditure 7285.34
Increase in Working capital 0.00 143.45 34.07 31.21 46.07 -4.33 -4.30 -4.51 -4.51 -4.51 -4.34
Repayment of principal 0.00 0.00 182.14 364.29 364.29 364.29 364.29 364.29 364.29 364.29 364.29
Total Uses 7285.34 143.45 216.21 395.50 410.35 359.95 359.98 359.77 359.78 359.78 359.95
Opening Cash Balance 0.00 35.86 120.10 334.62 687.49 1304.59 1948.57 2609.67 3292.36 3998.79 4730.86
Surplus/ Deficit 35.86 84.24 214.51 352.87 617.10 643.98 661.10 682.69 706.42 732.07 757.95
Closing Cash Balance 35.86 120.10 334.62 687.49 1304.59 1948.57 2609.67 3292.36 3998.79 4730.86 5488.81
Project Information Memorandum, TMC, Sambalpur, Odisha 71
Annexure 3: Projected Balance Sheet (Amount in Lakh Rs)
Amount in Rs. Lakh
Years 0 1 2 3 4 5 6 7 8 9 10
Liabilities
Equity Capital 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24 1,464.24
Reserve & Surplus 0.00 -203.53 -121.98 279.35 948.62 1,632.17 2,332.85 3,055.07 3,801.02 4,572.62 5,452.38
Grant/ Subsidy 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54 2,760.54
Net Worth 4,224.78 4,021.25 4,102.80 4,504.12 5,173.40 5,856.95 6,557.63 7,279.85 8,025.80 8,797.40 9,677.16
Term Loan 3,096.43 3,096.43 2,914.29 2,550.00 2,185.71 1,821.43 1,457.14 1,092.86 728.57 364.29 0.00
Working Capital
Loan
0.00 107.59 133.14 156.55 191.10 187.85 184.62 181.24 177.86 174.48 171.22
Total Liabilities 7,321.21 7,225.27 7,150.22 7,210.67 7,550.21 7,866.23 8,199.40 8,553.95 8,932.23 9,336.16 9,848.38
Assets
Gross Fixed Assets 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34 7,285.34
Less Accumulated
Dep. 0.00 323.63 647.26 970.89 1,294.52 1,618.15 1,941.78 2,265.41 2,589.04 2,912.67 3,154.07
Net Fixed Assets 7,285.34 6,961.71 6,638.08 6,314.45 5,990.82 5,667.19 5,343.56 5,019.93 4,696.30 4,372.67 4,131.28
Working Capital 0.00 143.45 177.52 208.73 254.80 250.46 246.16 241.65 237.14 232.64 228.30
Cash Bal 35.86 120.10 334.62 687.49 1,304.59 1,948.57 2,609.67 3,292.36 3,998.79 4,730.86 5,488.81
Total Assets 7,321.21 7,225.27 7,150.22 7,210.67 7,550.21 7,866.23 8,199.40 8,553.95 8,932.23 9,336.16 9,848.38
i
Request for Qualification
(Bid document)
Design, Engineering, Financing, Procurement, Construction,
Operation and Maintenance of the Terminal Market Project
Complex (TMC) located at Nildunguri, Sambalpur in the
State of Odisha
Date: ------
Government of Odisha
1
Awarder As defined in Page No.2
Amendment As defined in Clause 2.11
Bid As defined in Clause 2.1
Bidders As defined in Clause 1.2.1
Bidding Process As defined in Clause 1.2.0
Clarification As defined in Clause 2.24
Commodity As defined in Clause 1.1.2
Corrupt Practices As defined in Page No. 42
Currencies As defined in Clause 2.13
Equity As defined in Clause 3.5
Estimated Project Cost As defined in Clause 3.1(B)
Evaluation As defined in Clause 3.1
Opening As defined in Clause 2.21
Parameters As defined in Clause 3.1(A)
Proposal Stage As defined in Clause 1.3
Qualification Stage As defined in Clause 1.3
Re. or Rs. or INR (Indian Rupee) As defined in Clause 2.13
Reject Application As defined in Clause 2.6
RFQ Documents As defined in Clause 2.8
Scoring Model As defined in Clause 3.2
Terminal Market Complex As defined in Clause 1.1.1
Validity Period As defined in Clause 2.14
The words and expressions beginning with capital letters and defined in this document shall,
unless the context otherwise requires, have the meaning ascribed thereto herein. The words and
expressions beginning with capital letters and not defined herein, but defined in the RFQ, shall,
unless the context otherwise requires, have the meaning ascribed thereto therein.
2
DISCLAIMER The information contained in this Request for Qualification document (the “RFQ”) or
subsequently provided to Applicant(s), whether verbally or in documentary or any other
form, by or on behalf of the Government of Odisha (referred hereinafter as “AWARDER”)
or any of its employees or advisors, is provided to Applicant(s) on the terms and conditions
set out in this RFQ and such other terms and conditions subject to which such information
is provided.
This RFQ is not an agreement and is neither an offer nor invitation by the
Awarder to the prospective Applicants or any other person. The purpose of this RFQ is to
provide interested parties with information that may be useful to them in the formulation
of their application for qualification pursuant to this RFQ (the “Application”).
This RFQ includes statements, which reflect various assumptions and assessments arrived at
by the Awarder in relation to the Project. Such assumptions, assessments and statements do
not purport to contain all the information that each Applicant may require. This RFQ may
not be appropriate for all persons, and it is not possible for the awarder, its employees or
advisors to consider the investment objectives, financial situation and particular needs of
each party who reads or uses this RFQ. The assumptions, assessments and statements
contained in this RFQ may not be complete, accurate, adequate or correct. Each Applicant
should therefore, conduct its own investigations and analysis and should check the
accuracy, adequacy, correctness, reliability and completeness of the assumptions,
assessments, statements and information contained in this RFQ and obtain independent
3
advice from appropriate sources. Information provided in this RFQ to the Applicant(s) is on
a wide range of matters, some of which may depend upon interpretation of law. The
information given is not intended to be an exhaustive account of statutory requirements and
should not be regarded as a complete or authoritative statement of law. The awarder accepts
no responsibility for the accuracy or otherwise for any interpretation or opinion on law
expressed herein.
4
The awarder, its employees and advisors make no representation or warranty and shall have
no liability to any person, including any Applicant or Bidder, under any law, statute, rules
or regulations or tort, principles of restitution or unjust enrichment or otherwise for any
loss, damages, cost or expense which may arise from or be incurred or suffered on account
of anything contained in this RFQ or otherwise, including the accuracy, adequacy,
correctness, completeness or reliability of the RFQ and any assessment, assumption,
statement or information contained therein or deemed to form part of this RFQ or arising in
any way with pre-qualification of Applicants for participation in the Bidding Process. The
awarder also accepts no liability of any nature whether resulting from negligence or
otherwise howsoever caused arising from reliance of any Applicant upon the statements
contained in this RFQ.
The awarder may, in its absolute discretion but without being under any obligation to do so,
update, amend or supplement the information, assessment or assumptions contained in this
RFQ. The issue of this RFQ does not imply that the awarder is bound to select and shortlist
pre-qualified Applications for Bid Stage or to appoint the selected Bidder or
Concessionaire, as the case may be, for the Project and the awarder reserves the right to
reject all or any of the Applications or Bids without assigning any reasons whatsoever. The
Applicant shall bear all its costs associated with or relating to the preparation and
submission of its Application including but not limited to preparation, copying, postage,
delivery fees, expenses associated with any demonstrations or presentations which may be
required by the awarder or any other costs incurred in connection with or relating to its
5
Application. All such costs and expenses will remain with the Applicant and the awarder
shall not be liable in any manner whatsoever for the same or for any other costs or other
expenses incurred by an Applicant in preparation or submission of the Application,
regardless of the conduct or outcome of the Bidding Process.
6
TABLE OF CONTENTS
S.
No.
Contents Page no.
1 Introduction 10
1.1 Background 11
1.2 Brief description of Bidding Process 13
1.3 Schedule of Bidding Process 16
2 Instructions to Applicants
2A General 18
2.1 Scope of Bid 18
2.2 Eligible Applicants 18 2.3 Change in Consortium composition 20 2.4 Project Inspection and site visit 20 2.5 Application preparation cost 21 2.6 Right to accept or reject any Application/Bids 21 2.7 Acknowledgement by applicant 21
2B Documents
2.8 Contents of the RFQ 22
2.9 Updating pre-qualification information 22 2.10 Pre-application conference and clarification 22
2C
2.11 Amendment of RFQ Document 23 Preparation and Submission of Application
2.12 Language of the application 24
2.13 Currencies of application & payment 24 2.14 Application validity period 24 2.15 Extension of application validity period 24 2.16 Format and signing of Application 24 2.17 Sealing and marking of Applications 25 2.18 Application Due Date 25
2.19 Late Applications 26
2D
2.20
Modification/substitution/withdrawal of applications
Evaluation of Application 26 2.21 Opening and Evaluation of Applications 26
2.22 Confidentiality 26 2.23 Tests of responsiveness 27 2.24 Clarifications 27
2E Qualification and Bidding
2.25 Short-listing and notification 28
2.26 Submission of Bids 28 2.27 Proprietary data 28 2.28 Correspondence with the Applicant 28
7
3 3.1
Criteria for Evaluation 29
Technical Evaluation of applicants 30
3.2 Scoring Model 33 3.3 General Information 34 3.4 RFQ Application For the purpose of RFQ 34
3.5 Minimum Equity Holding 35
3.6 Minimum Equity Holding for a sole applicant 35
4 Fraud and Corrupt Practices 35
5 Miscellaneous 37
Appendix
1 Contract outline
2 Format for power of attorney for signing of application
3 Letter of application
3A Bids response Sheet No. 1
3B Bids response Sheet No. 2
4 Eligible Project details
5 Guidelines for providing information related to Project cost
Schedule 1
Schedule 2
Schedule 3
8
Request for Qualification
For
Design, Engineering, Financing, Procurement, Construction,
Operation and Maintenance of the Terminal Market Project
Complex (TMC) located at Nildunguri, Sambalpur in the State of
Odisha
(Bid Document for Preparing, Request for Qualification Proposal
for Terminal Market Complex, Nildunguri, Sambalpur,
Odisha)
9
Contents
Section I: Introduction to the Project
Section II: Instructions to Applicants
Section III: Criteria for Evaluation
11
INTRODUCTION
1.1 Project Background
The Terminal Market Project Complex (TMC) would endeavor to integrate farm production with
buyers by offering multiple choices to farmers for sale of produce such as electronic auctioning
and facility for direct sale to exporter, processor and retail chain network under a single roof. In
addition, the market would provide storage infrastructure thus offering the choice to trade at a
future date to the participants. This is to facilitate alternate marketing channel to farmers to ensure
for them better and fair share in consumer price, while providing better quality and hygienic
products to consumers at reasonable price. It is envisaged to offer a one stop solution that
provides logistics support including transport services & cool chain support, storage facilities
including warehouse, cold storage, ripening chamber, storage shed, facilities for cleaning,
grading, sorting, packaging and palletisation of produce along with extension support and
advisory services to farmers. Each of these services would be provided in lieu of a user charge.
The TMC would be built, owned and operated by a Special Purpose Vehicle which shall be
constituted under Companies Act, 1956 by the successful Bidder (hereinafter called as
“Private Enterprise” or “PE”). The Private Enterprise may be an individual enterprise or a
consortium of enterprises in the field of Agri-Business and Infrastructure Development.
1.1.1 Salient features of Terminal Market Complex project
I. TMC will operate on a Hub-and-Spoke format wherein Terminal Market
Complex (hub) would be linked to a minimum number of Collection Centres/spokes
(5 in case of TMC near Sambalpur to be conveniently located at key production
centres to allow easy farmer access and which are essentially required to support the
Terminal market Complex project.
II. TMC will establish backward linkages with farmers through collection centres and
also have effective forward linkages with wholesalers, exporters, organized retail
chains, distribution centres, retail cash and carry stores, food processing units,
retailers and exporters etc. thus providing better farm to market and customer linkages.
III. Electronic auction system will be established to ensure transparency in price fixation and
12
competition.
IV. Producers, farmers and their associations and other market functionaries from any
part of the country may use infrastructure and facilities of TMC, directly or through
collection centres.
1.1.2 Commodities
The commodities to be marketed by the TMC will include all perishables, inter-alia, fruits,
vegetables, flowers, spices, aromatics, herbs, medicinal plants, meat products, poultry
products, dairy products, fish and marine products etc. Non-perishables can also be handled
in the TMC. However, the annual throughput for perishable horticultural produce such as fruits,
vegetables, flowers, medicinal plants, aromatics, herbs etc handled by each TMC should not be
less than 70% of the throughput capacity of the TMC. In addition to this, each TMC shall be
allowed to handle other perishable produce (other than horticultural produce such as milk, dairy,
poultry, meat, fish and marine products etc) and Non- Perishables produces1. Volume of other
perishable produces (other than horticultural produce) and Non Perishable produce shall not
exceed 30% of throughput capacity of TMC.
In view of the above, AWARDER proposes to facilitate setting up a Terminal Market Project
Complex in Sambalpur, Odisha on Build-Own-Operate (BOO) basis. The AWARDER has
identified around 60 acres of land for this purpose at Village Nildunguri; District Sambalpur .and
proposes to provide this land for development of TMC to PE. The cost of this land has been
indicated as Rs. 2 lakh per acre.
The Successful Applicant at the end of the bidding process may be awarded a Contract by
AWARDER to implement the Project on BOO basis. The successful bidder would constitute a
Company (hereinafter referred to as “Private Enterprise” or “PE”) under the Companies Act,
1956 for the purpose of implementation and operation of TMC before the award of bid
1 May include all food-grains, oilseeds, pulses, cereals, condiments & spices and other agricultural commodities not
included under the perishable commodities; Permitted agro-forestry products may be included under this category for
the states of Himachal Pradesh, J&K, Uttarakhand and North Eastern States which are eligible under the scheme (strike
out whichever is not applicable).
13
.Private Enterprise would ensure equity participation by Producers’ Association2 as
prescribed.
1.2 Brief Description of Bidding Process
1.2.1 1.2.1 AWARDER intends to follow a two-stage process for selection of the preferred
Bidder for the Project comprising Qualification followed by a Proposal stage.
1.2.2 The first stage of the process involves Qualification of interested parties (Applicants). This
RFQ Document deals with the first stage (Qualification stage) wherein, Applicants would
be required to furnish the information specified in this RFQ Document. At the end of the
Qualification stage, AWARDER shall announce a shortlist of Qualified Applicants for the
second stage (Proposal stage)
1.2.3 In the Proposal stage, the Qualified Applicants will be invited to bid by submitting Detailed
Project Reports (Proposal/DPRs) in respect of the Project in accordance with a Request for
Proposal (RFP) Document. During the Proposal stage, Qualified Applicants would be
expected to examine the Project in further details, and to carry out such studies as may be
required to submit Detailed Proposals for the implementation of the Project. The Qualified
Applicants bidding (Bidders) in the Proposal stage shall be evaluated on the basis of
technical and other submissions relating to the project and the financial bids as detailed in
the RFP document. The Project would be awarded to the successful bidder quoting the
lowest total subsidy support3 amount (in INR) to be required from AWARDER for the
implementation of the viable Project subject to the Bidder fulfilling all other requirements
of the selection process. The subsidy shall be released by the National Horticulture Mission
2 A Producers Association will consist of farmer societies, farmers cooperative societies registered in India engaged in
Agricultural and allied activities, Producer Company, registered NGO‟s empanelled with GOI/State Govt./Planning
Commission and SHGs recognized under schemes of Government of India or State Governments and working in
agricultural production, Independent Commodity Boards and other registered organizations such as APMCs etc
engaged in production, procurement and trading of agricultural commodities. The producer association should be
separate from the Lead Technical and Lead Financial Member 3 Total Subsidy support shall be sum of fixed subsidy and additional subsidy. The subsidy shall be provided by GOS
through NHM
14
upon request by the State Horticulture Mission. The details of the subsidy are provided as
under:
A floor subsidy of 25%for a project cost is offered to private entrepreneurs to bid for setting
up terminal market complex.
In the competitive bidding, all bidders will be eligible to quote additional bid subsidy from
25% up to 40% of their respective project cost. Maximum subsidy will be INR 50 Cores.
For the purpose of calculation of subsidy, the unit cost ceiling shall be Rs 150.00 crore.
The Project will be awarded to the successful bidder quoting least subsidy amount in INR.
The amount of subsidy quoted by the successful bidder at the RFP stage shall be the
maximum subsidy to be provided to the bidder.
In case of downward revision of project cost during the construction phase of the TMC due
to downward movement of cost indices, the State Government will reduce the subsidy
amount proportionately.
Subsidy of NHM for Terminal Market Complex Project will be released in following five
installments.
Installment on completion of 25% of project ---- 15% of the approved subsidy
Installment on completion of 50% of project ---- 20% of the approved subsidy
Installment on completion of 75% of project ---- 25% of the approved subsidy
Installment on completion of 100% of project ---- 30% of the approved subsidy
Installment on completion of one year of operation of project ---- 10% of the
approved subsidy
The release of subsidy shall be subject to Utilization of previous subsidies for this project
and Inspection certificate /Utilization issued by Joint inspection team comprising of Nodal
officer, Independent Consultant (IC) and a representative of marketing division of
15
DAC, Ministry of Agriculture for satisfactory completion of prescribed mandatory capital
project.
The release of subsidy shall also consider the equity participation of Producer Association,
as promised by the PE. In case the % of equity participation from Producers Association, at
the time of release of fourth installment of subsidy, is less than the % mentioned at the time
of submission of technical bid, the SHM/GOS shall have the right to withhold the release of
subsequent installments (fourth and fifth) of subsidy to the PE, till the PE fulfils the
required equity participation from the producers association
Provided that if the percentage of equity participation by producer association
remains below the percentage of equity of the project as promised /quoted, by the
PE at the time of bidding and considered at the time of evaluation of the bid, within
two years of signing of OMDA or transfer of land to PE whichever is later, despite
reasonable efforts4 made by PE, no restrictions shall be imposed on the PE in this
regard and the eligible subsidy shall be released to him as due.
However this stipulation will not be applicable to successful bidder/PE who has not
committed any equity to Producers’ Association in his bid.
1.2.4 Further details of the process to be followed at the Proposal Stage would be spelt out in the
RFP Document (to be provided to Qualified Applicants).
4 Reasonable effort would include all individual efforts to formally invite Producers Association for equity
participation, including that of invitation by publicity through Mass Media
16
1.3 Schedule of Bidding Process
The Awarder and Applicants shall endeavor to adhere to the following schedule:
Event Description Date
Qualification Stage:
Note: The timelines given are as per the Operational Guidelines for Setting up a Terminal Market
Complex 2009, Government of India. The final dates will be decided by the Directorate of
Horticulture, Odisha.
1. Last date for receiving queries [15 days from date of release of Global Tender Notice- Date
To be decided by the Directorate of Horticulture, Odisha]
2. Pre-Application Conference [25 days from date of release of Global Tender Notice- Date
To be decided by the Directorate of Horticulture, Odisha]
3. Awarder’s response to queries latest by [30 days from date of release of Global Tender
Notice- Date To be decided by the Directorate of Horticulture, Odisha]
4. Last date for sale of RFQ documents [35 days from the date of release of Global Tender-
Date To be decided by the Directorate of Horticulture, Odisha]
5. Application Due Date/Last date of receipt [1400 hours of 50th day from date of Application
Release of Global Tender Notice- Date To be decided by the Directorate of Horticulture,
Odisha]
6. Announcement of qualified applicants [70 days from date of release of Global Tender
Notice- Date To be decided by the Directorate of Horticulture, Odisha]
18
INSTRUCTIONS TO APPLICANTS
A. General
2.1 Scope of Bid
2.1.1 During this RFQ stage, AWARDER invites Applications for Qualification from
Applicants in order to qualify experienced and capable Applicants for the RFP
stage.
2.1.2 Throughout these bidding documents, the terms “bid” and “tender” and their
derivatives (bidder, bid/tender, bidding/tendering etc.) are synonymous, and “day”
means calendar day.
2.2 Eligible Applicants
2.2.1 The Applicant may be a single entity/ individual or a group
of entities (hereinafter referred as Consortium) such as Group of Farmers/ Growers/
Consumers/ Producer Organizations/ Producer Company, Partnership/ Proprietary
firms, Companies, Marketing Boards, Public Sector Undertaking, Co-operatives,
registered NGOs empanelled with GOI/State Govt./Planning Commission,
recognized Self Help Groups under the schemes of GOI/State Governments,
And other registered bodies engaged in production and trading of agricultural
produce and coming together to implement the project. The term Applicant used
hereinafter would therefore apply to both a single entity and a Consortium as the
case may be.
2.2.2 The Consortium shall comprise of a maximum of five members with at least one
member from the field of Agribusiness. The other members of the consortium can
be from amongst Infrastructure Development Organizations, Financial Institutions
etc.
2.2.3 The eligible candidates for applying in the category of Individual applicants should
have relevant experience in the following fields:
A. Agribusiness
B. Project execution of Agribusiness and related supply chain projects / Infrastructure
projects /Cold chain and warehousing and logistics or any other similar project
2.2.4 Investment from the Lead Member of the Private Enterprise in the complex should
be more than 26% of the project equity for the five years of operation of TMC. The
lead member of the PE is the member who holds the largest share in PE and is
primarily responsible for overall management of the TMC project.
19
2.2.5 The Applicant should submit a Power of Attorney as per the format enclosed at
Appendix 2 authorizing the signatory of the application to commit the Applicant.
2.2.6 An individual Applicant cannot at the same time be a member of a
Consortium applying for the project. Further, a lead member of a particular
Consortium including its lead technical member and lead financial member cannot
be a member of any other Consortium applying for this project. However, this does
not limit the inclusion of the same subcontractor in more than one tender.
2.2.7 Any Applicant who submits or participates in more than one application will
be disqualified and will also lead to the disqualification of the Consortia of which it
is a member.
2.2.8 Any entity which has been barred by AWARDER from participating in
AWARDER projects (BOO or otherwise) and the bar subsists as on the
Application Due Date, would not be eligible to submit an application, either
individually or as a member of a Consortium
2.2.9 The Members of the consortium shall be required to meet the criteria
specified in this RFQ Document. (already mentioned above)
2.2.10 Members of the Consortium (Indian or Foreign5) shall enter into a Legal agreement
(LA) for the purpose of making the application and submitting the Proposal in the
event of being short-listed. The Legal Agreement shall be governed by the Indian
laws and in the event of Arbitration, Arbitration & Conciliation Act, 1996 shall
apply and would be subject to jurisdiction of Indian Courts only.
The LA shall inter alia
1. Convey the intent to form a joint venture company, with Shareholding
commitment(s) which would enter into the Contract Agreement and subsequently
carry out all the responsibilities as Successful Bidder in terms of the Contract
Agreement, in case the Contract to undertake the project is awarded to the
Consortium
2. Include a statement to the effect that all members of the Consortium shall be liable
jointly and severally for the execution of the project in accordance with the terms of
the Contract Agreement.
5 Subject to the condition that the consortium that has Foreign member as one of its constituent members will
not enter into retail business anywhere in India as per Government regulations
20
3. Provide for allocation up to 26% of equity share to Producers Association6.
2.2.11 Copy of the LA should be submitted with the application. The LA entered into
between the members of the Consortium should be specific to this project and
should contain the above requirements failing which the application shall be
considered non-responsive under the provision of Clause 2.25 of this RFQ
Document.
2.2.12 The purchaser of the RFQ document must be the Applicant itself or a member of
the consortium submitting the application.
2.3 Change in Consortium Composition
2.3.1 Change in the composition of a Consortium may not be permitted by AWARDER
after the due date/last date of receipt of RFQ application.
2.4 Project Inspection and Site Visits
2.4.1 The Applicant, at the Applicant's own responsibility and risk and cost is
encouraged to visit the location of the Land/Site and its surroundings and obtain all
information that may be necessary for preparing the application of Qualification
and Proposal. The costs of visiting the site shall be borne by the Applicant.
AWARDER shall not be liable for such costs, regardless of the outcome of the
selection process.
2.4.2 It would be deemed that by submitting the application, Applicant has:
Made a complete and careful examination of the RFQ.
Received all relevant information requested from AWARDER.
2.4.3 AWARDER shall not be liable for any mistake or error on the part of the
Applicant in respect of the above.
6 A producers Association will consist of farmer societies, farmers cooperative societies registered in India
engaged in Agricultural and allied activities, Producer Company, registered NGO‟s empanelled with
GOI/State
Govt./Planning Commission and SHGs recognized under schemes of Government of India or State
Governments and working in agricultural production, Independent Commodity Boards and other registered
organizations such as APMCs etc engaged in production, procurement and trading of agricultural
commodities. The producer association should be separate from the Lead Technical and Lead Financial
Member
21
2.5 Application preparation cost
2.5.1 The Applicant shall be responsible for all costs associated with the preparation of
its application and its participation in the Qualification process. AWARDER will
not be responsible nor in any way liable for such costs, regardless of the conduct or
outcome of the Qualification process.
2.6 Right to accept or Reject any application and to reject any or all Applications or Bids
during the Selection Process
2.6.1 Notwithstanding anything contained in this RFQ, AWARDER reserves the right
to accept or reject any application and to annul the selection process and reject all
applications/proposals at any time without any liability or any obligation for such
acceptance, rejection or annulment, without assigning any reasons therefore.
2.6.2 AWARDER reserves the right to reject any application If-
I. At any time a material misrepresentation is made or Uncovered or
II. The Applicant does not respond promptly and thoroughly to
requests for supplemental information required for the evaluation of the application.
This would lead to the disqualification of the Applicant. If the Applicant were part
of Consortium then the entire Consortium would be disqualified or rejected.
2.6.3 If such disqualification/rejection occurs during the Proposal stage, after the price
proposals have been opened and the lowest bidder gets disqualified/ rejected, then
AWARDER reserves the right to:
I. Either invites the next lowest bidder
II. Take any such measures as may be deemed fit in the sole discretion of
AWARDER, including annulment of the bidding process.
2.7 Acknowledgement by Applicant
2.7.1 It shall be deemed that by submitting the Application, the Applicant has:
Made a complete and careful examination of the RFQ;
Received all relevant information requested from the Awarder;
22
Accepted the risk of inadequacy, error or mistake in the information provided in the
RFQ or furnished by or on behalf of the Awarder relating to any of the
matters referred to in the RFQ.
Agreed to be bound by the undertakings provided by it under and in terms
hereof.
2.7.2 The Awarder shall not be liable for any omission, mistake or error in respect of
any of the above or on account of any matter or thing arising out of or concerning
or relating to the RFQ or the Bidding Process, including any error or mistake
therein or in any information or data given by the Awarder.
B. Documents
2.8 Contents of RFQ
The RFQ document comprises the contents as listed below and would additionally
include any addenda in accordance with clause 2.10.
I. Contract Outline
II. Format for Power of Attorney for signing
of Application
III. Format of Application.
IV. Details of Eligible projects
V. Guidelines for providing information
related to experience
Detailed format for each of the above are provided at Appendix II to Appendix VI. A
copy of Project Information Memorandum is also being given along with this RFQ.
2.9 Updating Pre-Qualification Information
2.9.1 Successful Applicants shall be required to update the financial and other
information used for pre-qualification at the time of submitting their bids, to
confirm their continued compliance with the Qualification criteria and verification
of the information provided. A bid shall be rejected if the Applicant's Qualification
for the threshold levels is no longer valid at the time of the bidding process.
2.10 Pre-Application Conference and Clarifications
2.10.1 Pre-Application conference of the interested parties shall be convened at the
designated date, time and place. Only those persons/entities that have purchased the
RFQ document shall be allowed to participate in the Pre-Application conference.
23
2.10.2 Applicants who have downloaded the RFQ document from the Awarder’s website
[www.Odisha.gov.in, www.Odisha.gov.in/dhc/Index.html, www.orihort.in,
www.nhm.nic.in, www.ilfsclusters.com] should submit a Demand Draft of [Rs
5000] towards the cost of document, through their representative attending the
conference. A maximum of three representatives of each Applicant shall be allowed
to participate on production of Awarder letter from the Applicant.
2.10.3 During the course of Pre-Application conference, the Applicants will be free to
seek clarifications and make suggestions for consideration of the Awarder. The
Awarder shall endeavor to provide clarifications and such further information as it
may, at its sole discretion, consider appropriate for facilitating a fair, transparent
and competitive Bidding Process.
2.10.4 A prospective Applicant requiring any clarification on the RFQ documents may
notify the AWARDER in writing or facsimile. The Applicant should send in their
queries latest by the Last Date for Receiving Queries as given in the 'Schedule of
Bidding Process'.
2.10.5 Copies of the AWARDER response will be available to all purchasers of the RFQ
documents, including a description of the enquiry but without identifying its source
through the email. The same will also be communicated to those who have
downloaded the RFQ document from the AWARDER website and have duly
intimated to AWARDER, their particulars including email address for
communication (Registered Applicants).
2.11 Amendment of RFQ Documents
2.11.1 Before the deadline for submission of applications, AWARDER may modify the
RFQ Documents by issuing an addendum/corrigendum.
2.11.2 Any addendum/corrigendum thus issued shall be part of the RFQ Documents and
shall be communicated in writing/email to all the purchasers of the RFQ
Documents. Applicants shall acknowledge receipt of each addendum in
writing/email to AWARDER. AWARDER will assume no responsibility for postal
delays. The same will also be communicated to the Registered Applicants.
2.11.3 To give prospective Applicants reasonable time in which to take addendum into
account in preparing their bids, AWARDER may, at its sole discretion, extend the
Application Due Date.
24
C. Preparation and submission of Application
2.12 Language of the Application
The Application and related documents and correspondence shall be in the English
language. Supporting documents and printed literature furnished by Applicant with the
application may be in any other language provided that they are accompanied by
translations in the English language. Supporting materials, which are not translated into
English, may not be considered. For the purpose of interpretation and evaluation of the
application, the English language translation shall prevail.
2.13 Currencies of Application and Payment
The currency for the purpose of this RFQ shall be the Indian Rupees (INR).
2.14 Application Validity period
Application shall remain valid for a period of 36 weeks from the Application Due Date
(Application Validity Period). AWARDER reserves the right to reject any Application
which does not meet the requirement.
2.15 Extension of Application Validity period
In exceptional circumstances, prior to expiry of the original Application Validity Period,
AWARDER may request that the Applicants extend the period of validity for a specified
additional period. The request and the Applicants‟ responses shall be made in writing.
2.16 Format and Signing of Application
2.16.1 The Applicant would provide all the information as per this RFQ. AWARDER
would evaluate only those applications that are received in the required format and
complete in all respects.
2.16.2 The Applicant shall prepare one original of the document comprising the
application and clearly marked “ORIGINAL”. In addition the Applicant shall make
one (1) copy of the application clearly marked “COPY” as appropriate. In the event
of discrepancy between original and the copy, the original shall prevail.
2.16.3 The original and the copy of the application shall be typed or written in indelible
ink. Each page of the application shall be signed by a person or persons duly
authorized to sign on behalf of the Applicant holding the Power of Attorney as per
the format provided in Appendix 2A.
25
2.16.4 The application shall contain no alterations or additions, except those to comply
with instructions issued by AWARDER, or as necessary to correct errors made by
the Applicant, in which case such corrections shall be initiated by the person or
persons signing the application.
2.17 Sealing and Marking of Application 2.17.1 The Applicant shall seal the original and copy of the application in
separate envelopes, duly marking the envelopes as “ORIGINAL” and
“COPY”. These two envelopes (called as inner envelopes) shall then be put inside
one outer envelope. 2.17.2 Each envelope shall contain:
Covering letter stating clearly the validity of the application. Application in the prescribed format (Appendix 3) along with
supporting documents. Power of Attorney as per the format in Appendix 2. Copy of LA in case of a Consortium Documentary proof of Annual peak volumes handled.
The envelopes shall clearly bear the following identification, Application for
Qualification for Designing, Engineering, Financing, Procurement, Constructing,
Operating and Maintaining of the Terminal Market Project Complex located near
Sambalpur in the State Odisha 2.17.3 In addition to the identification required in Sub-clauses 2.16.2, each of the
envelopes shall indicate the name and address of the Applicant to enable the
application to be returned unopened in case it is declared late, pursuant to Clause
2.18.1 or AWARDER declares the application as non responsive pursuant to
Clause 2.25.
2.17.4 If the outer envelope is not sealed and marked as above, AWARDER will
assume no responsibility for the misplacement or premature opening of the
application.
2.18 Application Due Date
2.18.1 Application should be received before 1400 hours Indian Standard Time (IST),
on the Application Due Date(Last date of receipt of application), as stated
in the 'Schedule of Bidding Process', at the under noted address, in the manner
and form as detailed in the RFQ. Applications submitted by either facsimile
transmission or telex will not be accepted.
26
Nodal Officer for MTM-cum-
Director Horticulture, Directorate of
Horticulture, Udyan Bhawan,
Bhubaneshwar- 751015
2.18.2 AWARDER may, in exceptional circumstances and at its sole discretion, extend
the Application Due Date by issuing an Addendum in accordance with Clause
2.10 uniformly for all Applicants.
2.19 Late Applications
Any Application received by AWARDER after 1400hrs IST on the Application Due
Date will be returned unopened to the Applicant. 2.20 Modifications / Substitution / Withdrawal of Applications
2.20.1 The Applicant may modify, substitute, or withdraw its application after
submission, provided that written notice of the modification, substitution, or
withdrawal is received by AWARDER by the Application Due Date. No
application shall be modified, substituted, or withdrawn by the Applicant after the
Application Due Date. 2.20.2 The modification, substitution, or withdrawal notice shall be prepared
sealed, marked, and delivered in accordance with Clause 2.16, with the
enveloped being additionally marked “MODIFICATION”, "SUBSTITUTION”
OR “WITHDRAWAL”, as appropriate. 2D. Evaluation of Application
2.21 Opening and Evaluation
2.21.1 AWARDER would open the applications on the due date at 1600 hours for the
purpose of evaluation.
2.21.2 Applications for which an acceptable notice of withdrawal has been submitted in
accordance with Clause 2.19 shall not be opened.
2.21.3 AWARDER would subsequently examine and evaluate applications in
accordance with the criteria set out in Section 3.
2.22Confidentiality
27
Information relating to the examination, clarification, evaluation, and
recommendation for the Qualified Applicants shall not be disclosed to any person not
officially concerned with the process. AWARDER will treat all information submitted
as part of application in confidence and would require all those who have access to such
material to treat the same in confidence. AWARDER will not divulge any such
information unless it is ordered to do so by any Awarder that has the power under law to
require its disclosure.
2.23 Tests of responsiveness
2.23.1 Prior to evaluation of applications, AWARDER will determine whether
each application is responsive to the requirements of the RFQ. An application
shall be considered responsive if the application:
(i) Is received by the Application Due Date including any extension
thereof pursuant to Clause 2.17.2
(ii) Is signed, sealed and marked as stipulated in Clause 2.15 and 2.16
(iii) Is accompanied by the Power (s) of Attorney as specified in Clause
2.2.3. (iv) Contains all information as requested in the RFQ.
(v) Contains information in formats same as those specified in this
RFQ. (vi) Mentions the validity period as set out in Clause 2.13
(vii) Is accompanied by the LA (for Consortium) as stipulated in Clause 2.2.8
and
Power of Attorney as stipulated in Clause 2.2.7.
(viii) Is accompanied by payment towards cost of the RFQ Document in case
the same has not been paid while procuring the RFQ Document.
(ix) Is accompanied by the valid documentary proof of Annual peak
volumes handled , projects executed and certified copies of the last three
years audited financial statements and certified net worth statements in
respect of Applicant.
2.23.2 AWARDER reserves the right to reject any application which is non-responsive
and no request for alteration, modification, substitution or withdrawal shall be
entertained by AWARDER in respect of such applications.
2.24 Clarifications
To facilitate evaluation of Applications, AWARDER may, as its sole discretion, seek
clarifications in writing from any Applicant regarding its application. Notwithstanding
anything contained in the RFQ, AWARDER reserves the right to not take into
28
consideration any such clarifications sought by it for evaluation of the application.
2E Qualification and Notification 2.25 Short-listing and notification
After the evaluation of applications, AWARDER would announce a short list of
Qualified Applicants (Bidders). The Qualified Applicants would be notified in writing
by AWARDER and issued a set of Request for Proposal (RFP) Documents. At the same
time, AWARDER would notify the other Applicants that their applications have been
unsuccessful. 2.26 Submission of Bids
The Bidders will be requested to submit a Bid in the form and manner to be set out in the
RFP including the Detailed Project Report. Only pre-qualified Applicants shall be
invited by the Awarder to submit their Bids for the Project. The Awarder may provide a
limited time span for submission of the Bids for the Project. The Applicants are therefore
advised to visit the site and fully familiarize themselves with the Project by the time of
submission of the Application. No extension of time is likely to be considered for
submission of Bids pursuant to invitation that may be issued by the Awarder. 2.27 Proprietary data
All documents and other information supplied by the Awarder or submitted by an
Applicant to the Awarder shall remain or become the property of the Awarder.
Applicants are to treat all information as strictly confidential and shall not use it for any
purpose other than for preparation and submission of their Application. The Awarder
will not return any Application or any information provided along therewith. 2.28 Correspondence with the Applicant
Save and except as provided in this RFQ, the Awarder shall not entertain any
correspondence with any Applicant in relation to the acceptance or rejection of any
Application.
30
CRITERIA FOR EVALUATION 3. Criteria for Evaluation
3.1 Technical Evaluation of Applicants
1) Categorization of Applicants: would be done on the basis of multiple criteria in
order to arrive at an objective result.
a) Individual/Consortium Basis:
i) Individual Applicants: Those applicants who apply as an individual business
entity7. Only applicants who qualify the minimum eligible score requirement of volume and project cost will be qualified to apply individually.
ii) Consortium Applicants: Applicants who apply in consortium where at
least one of the members necessarily belongs to the Agribusiness category.
b) Core Competency Basis:
i) Agribusiness: This category would include applicants with a core competency in the field of Agribusiness. The applicants in this category would be further classified as : (1) Class “AB” : This category includes applicants involved in the business of
Agri-Inputs or Agri- Logistics or Trading of Agri-Commodities or Agri-Processing or Marketing/Whole selling of Agri-Commodities or Storage and Warehousing of Agri-Commodities & Food Retailing or agri services or agri infrastructure development8 or commodity exchanges are included in this category
ii) Infrastructure Developers (ID): This category would include applicants with a
core competency in the field of Infrastructure Development9.
iii) Others: This category would include applicant with competencies in other areas other than agribusiness and Infrastructure Developers.
c) Commodity categories : The agricultural commodities are divided into the
following categories :
1) Fruits, Vegetables & Flowers 2) Grains: Wheat/Paddy 3) Milk and Milk products
7 Business entity may be Private companies/Public Ltd Companies/ Partnership Firms/Producers Association
,Co-operatives,registered NGO‟ s empanelled with GOI/State Govt./Planning Commission and SHGs recognized
under schemes of Government of India or State Governments and working in agricultural production, Agriculture
Commodity Boards, Agriculture Marketing Boards, and other registered organizations such as APMCs etc(or similar
organisation constituted under state law) engaged in production, procurement and trading of agricultural commodities. 8
Agri infrastructure will include infrastructure used for production and storage of agri input, infrastructure used
for production & harvesting of agri commodities, infrastructure used for processing of agri produce, infrastructure
used for distribution, retailing and export of agri commodities 9
For Infrastructure development other than agri infrastructure development.
31
4) Meat & Meat Products 5) Condiments and spices 6) Others
A. Parameters followed: The following parameters have been followed for calculation of
scores for screening of the prospective applicants:
a) Volume (P1): The first parameter that will be considered is the annual highest volumes
handled (in MT) of different commodity categories by the applicant over the last three years.
Each commodity is divided into three bands Low, medium and high based as shown in the
table below:
Categories Low Medium High
F & V & flowers 5000-40000 40000-80000 >80000
Grains 5000-50000 50000-200000 >200000
Milk(in liters) & Milk Products (Kgs) 5000-25000 25000-70000 >70000
Meat & Meat Product 5000-40000 40000-150000 >150000
Condiments & Spices 50-2000 2000-10000 >10000
others 1000-50000 50000-200000 >200000
Volume Factor: It is the weightage assigned to Volumes of different commodity categories
of applicants. The volume factors that would be followed for screening process are given
below:
PARAMETER
Commodity categories
Annual Peak volume handled
(in MT)
Low
Medium
High
VOLUME
FACTOR
(P1)
F & V & Flowers 3 6 9
Grains
3
5
8
Milk & Milk Products
3
4
7
Meat & Meat Product
3
4
6
Condiments & Spices 2 3 6
Others 2 3 6
32
b) Project Cost (P2): The Project Cost is the cost of the largest project completed over last
ten years10. Based on the value of project (in INR Crores) the different projects will
be divided into low medium and high categories as per the table given below:
Categories Agri Infrastructure
Development
Infrastructure Development (other
than Agri) Low 25-50 100--250
Medium 50-100 250-500
High >100 >500
Project Cost Factor: It is the weightage assigned to individual Project Cost. The
Project Cost Factors for different categories are given below:
Parameter Infrastructure Categories Cost of Projects Handled
(Rs. Crores) Low Medium High
Project Cost Agri Infrastructure Development 4 6 8
Infrastructure Development
(Other than Agri)
3 4 7
Net worth (P3): The Net worth would be aggregate net worth of an Applicant. The Net
worth of an applicant includes the share holder capital and Reserves and Surplus as calculated
from the latest financial statements of the year as specified in RFQ. Minimum net worth of
individual applicant/bidder or that of Lead Financial Member/promoter in case of consortium
specified in the RFQ must be Rs 30 crore. Based on the net worth value of Applicant (in INR
Crores), they will be divided into low medium and high categories as per the table given
below:
(In Rs. Crores)
Categories Low Medium High Net worth of Applicant
30 -50 50- 150 > 150
Net worth Factor: It is the weightage assigned to aggregate net worth of Applicants. The
net worth factors for different categories are given below:
10 The financial year would be the same as followed by the Applicant for its annual report. Year I will be the financial
[insert the most recent financial year]. Year 2 shall be the year immediately preceding Year 1 and Year shall be the year
immediately preceding Year 2.
33
Parameter
Networth of Applicant
(in Rs crore)
Low Medium High
Networth factor
(P3)
3
6
9
3.2 Scoring Model
1. Scoring: Depending on the feeder value for an applicant, the feeder sheet would
calculate the corresponding value of Volume Factor, Project Cost Factor and Net
worth Factor for each Applicant. This value may be regarded as the score of the
Applicant on the parameters P1, P2 and P3.
2. Interpretation o f the Score:
A) For Individual Applicants : For individual applicants, the corresponding score for
each of the parameter P1 , P2 and P3 will be taken as the score for screening at the
RFQ stage. The range of scores for P1, P2 and P3 would vary from 0- 9. B) For Consortium: Each member of consortium will get an individual score on
P1 and P2. For the screening purpose of consortium the highest value of P1 and P2
among the individual values of all the members of the consortium will be regarded as
the score of the consortium.
3. Minimum Qualifying Score
There would be a minimum qualifying value for each of P1, P2 and P3 for Individual
applicants as well as for the consortium. The minimum qualifying values for each
of P1, P2 and P3 would be as follows: a) Individual:
Parameter Minimum Eligibility
Volume Factor (P1) 3
Project Factor (P2) 3
Networth Factor (P3) 3
The total of the score secured against P1, P2 and P3 for the individual category
should be minimum of 12.
b) Consortium:
Parameter Minimum Eligibility
Volume Factor (P1) 3
Project Factor (P2) 3
Networth Factor (P3) 3
The total of the score secured against P1, P2 and P3 for the consortium category
should be minimum of 12.
34
3.3 General Information Regarding Evaluation of RFQ application: Applicant shall
quote experience in respect of a particular eligible project for Project Cost factor
under any one category only. 3.3.1 In the event that two or more members of a Consortium have participated in the
same project, only one member should mention the project. In case more than one
member mentions the same project, the project cost factor of the member with the
highest project cost Factor, as defined in Clause 3.2.(C)6, for that project shall be
considered and the project cost factor of the other members shall not be considered
for the purpose of evaluation of the RFQ.
However in case two or more members intending to quote project cost have
participated in the same project, then these members may quote the same project
provided that their scope(s) of work were independent. The scope of work shall not
be considered to be independent in case of any project if:
i) Any member/s is/are sub-contractor/s of another member/s.
ii) Payment to any member/s has been made out of project fees of the
other member/s
iii) Payments of project fees have been made jointly to the members as a
consequence of a joint contract with the party making the payment
specifically providing for such joint payment.
3.4 For the purpose of RFQ
3.4.1 The Applicant should furnish the details of Eligible volume factor, Project Cost and
Net worth Statements as on date of submission of RFQ 3.4.2 The Entity claiming Project execution under the Project Cost Factor should have
held minimum of 26% of the equity including management control in the project as
on date of commissioning. 3.4.3 The Applicant should furnish adequate evidence to support its claim as per
Appendix 4. 3.4.4 The Applicant should provide the necessary information as per Appendix 3, Bid
Response Sheet 2. 3.4.5 The application should be accompanied by the audited annual reports of the
Applicant (of each Member in case of a Consortium) for the last three financial
years. 3.4.6 A certificate from the Applicant's statutory auditor must support the response sheet
35
3.4.7 The audited annual accounts for last three financial years have to be provided. In case
the audited annual accounts for the last financial years is not audited and therefore
the Applicant could not make it available, the Applicant shall give an undertaking to
the same effect and the statutory auditor shall certify the same while providing for
the audited account of previous three years prior to last financial year. The audited
annual reports for three financial years preceding the latest financial year have to be
provided. In case the annual report for last financial year is not yet ready, the annual
reports of last three years prior to last financial year is to be submitted failing which
the application shall be rejected as non-responsive. 3.5 Minimum Equity Holding
The Applicant will be required to incorporate a Special Purpose Vehicle (SPV) to domicile
the Project prior to the start of implementation of the Project. The members of the
Consortium shall be required to commit to a minimum equity holding in the SPV as:
1 All the members of the Consortium would be required to hold their
initial equity stakes in the SPV at all times for a period of 3 years from the
date of commencement of commercial operations.
2 In case of the Lead Member of a Consortium, it would be required to h o l d its initial equity stake in the SPV for a period of at least 5 years from the date of commencement of commercial operations. In any case, Lead Member would be required to hold equity stake of more than 26% in SPV at all times during the project period
3 The PE may provide up to 26% of equity stake to Producer Associations.
3.6 Minimum Equity Holding for a Sole Applicant
The sole Applicant will be required to incorporate a Special Purpose Vehicle (SPV) to
domicile the Project prior to the start of implementation of the Project. The Applicant would
be required to commit to hold a minimum equity stake equal to 51% of the aggregate
shareholding of the SPV at all times during a period which shall not be less than 5 years
from the date of commencement of commercial operations
3.6.1 AWARDER may, at its sole discretion and prior to the conclusion of the
bidding process, provide for the Bidder to induct institutional investors into the SPV
to an extent to be specified by AWARDER. 4. FRAUD AND CORRUPT PRACTICES
4.1 The Applicants and their respective officers, employees, agents and advisers shall
observe the highest standard of ethics during the Bidding Process. Notwithstanding
anything to the contrary contained herein, the Awarder may reject an Application without
being liable in any manner whatsoever to the Applicant if it determines that the Applicant
has, directly or indirectly or through an agent, engaged in corrupt practice, fraudulent
36
practice, coercive practice, undesirable practice or restrictive practice in the Bidding
Process. 4.2 Without prejudice to the rights of the Awarder under Clause 4.1 hereinabove, if an
Applicant is found by the Awarder to have directly or indirectly or through an agent,
engaged or indulged in any corrupt practice, fraudulent practice, coercive practice,
undesirable practice or restrictive practice during the Bidding Process, such Applicant shall
not be eligible to participate in any tender or RFQ issued by the Awarder during a period of
2 (two) years from the date such Applicant is found by the Awarder to have directly or
indirectly or through an agent, engaged or indulged in any corrupt practice, fraudulent
practice, coercive practice, undesirable practice or restrictive practice, as the case may be. 4.3 For the purposes of this Clause 4, the following terms shall have the meaning
ereinafter respectively assigned to them:
(a) “Corrupt practice” means (i) the offering, giving, receiving, or soliciting, directly or
indirectly, of anything of value to influence the actions of any person connected with the
Bidding Process (for avoidance of doubt, offering of employment to, or employing, or
engaging in any manner whatsoever, directly or indirectly, any official of the Awarder who
is or has been associated in any manner, directly or indirectly, with the Bidding Process or
the LOA or has dealt with matters concerning the Concession Agreement or arising there
from, before or after the execution thereof, at any time prior to the expiry of one year
from the date such official resigns or retires from or otherwise ceases to be in the service of
the Awarder, shall be deemed to constitute influencing the actions of a person connected
with the Bidding Process); or (ii) save and except as permitted under sub clause (d) of
Clause
2.2.1, engaging in any manner whatsoever, whether during the Bidding Process or after the
issue of the LOA or after the execution of the Concession Agreement, as the case may be,
any person in respect of any matter relating to the Project or the LOA or the Concession
Agreement, who at any time has been or is a legal, financial or technical adviser of the
Awarder in relation to any matter concerning the Project;
(b) “Fraudulent practice” means a misrepresentation or omission of facts or suppression
of facts or disclosure of incomplete facts, in order to influence the Bidding Process; (c) “Coercive practice” means impairing or harming or threatening to impair or harm, directly or indirectly, any person or property to influence any person‟ s participation or action
in the Bidding Process; (d) “Undesirable practice” means (i) establishing contact with any person connected with
or employed or engaged by the Awarder with the objective of canvassing, lobbying or in any
manner influencing or attempting to influence the Bidding Process; or (ii) having a Conflict
38
(e) “Restrictive practice” means forming a cartel or arriving at any understanding or
arrangement among Applicants with the objective of restricting or manipulating a full and
fair competition in the Bidding Process.
5. MISCELLANEOUS 5.1 The Bidding Process shall be governed by, and construed in accordance with, the laws
of India and the Courts at Sambalpur shall have exclusive jurisdiction over all disputes
arising under, pursuant to and/ or in connection with the Bidding Process. 5.2 The Awarder, at its sole discretion and without incurring any obligation or liability,
reserves the right, at any time, to; a. Suspend and/ or cancel the Bidding Process and/ or amend and/ or supplement the
Bidding Process or modify the dates or other terms and conditions relating thereto; b. Consult with any Applicant in order to receive clarification or further information;
c. Pre-qualify or not to pre-qualify any Applicant and/ or to consult with any applicant
in order to receive clarification or further information; d. Retain any information and/ or evidence submitted to the Awarder by, on behalf of, and/
or in relation to any Applicant; and/ or e. Independently verify, disqualify, reject and/ or accept any and all submissions or other
information and/ or evidence submitted by or on behalf of any Applicant. 5.3 It shall be deemed that by submitting the Application, the Applicant agrees and releases
the Awarder, its employees, agents and advisers, irrevocably, unconditionally, fully and
finally from any and all liability for claims, losses, damages, costs, expenses or liabilities in
any way related to or arising from the exercise of any rights and/ or performance of any
obligations hereunder and them Bidding Documents, pursuant hereto, and/ or in connection
with the Bidding Process, to the fullest extent permitted by applicable law, and waives any
and all rights and/ or claims it may have in this respect, whether actual or contingent, whether
present or in future.
40
APPENDIX 1
CONTRACT OUTLINE The following is an outline of the proposed contract terms for the Project and is
indicative in nature. The proposed OMDA Agreement would form part of the Request for
Proposal (RFP) and would be provided to bidders at the Proposal Stage. 1. Contract Period
The Contract Period would be 15 years from the Effective date extendable further by 10
years. 2. Grant
The GOS will authorize/ permit the PE to operate the Terminal Market Complex through a
single license in the state, source Agriculture Produce directly from farmers and sell directly
the produce to the end users. 3. Rights to collect User Charges
The PE will be entitled to levy User charges on Market services and Non Market Services
and essential services (as per the relevant Operational guidelines /agreements) from the users
of TMC .
4. Initial Development Plan and Master Plan: The qualified bidders who are invited to participate in the RFP stage are required to submit
an Initial Development Plan (along with the other Documents required along with RFP) that
includes business plans for achieving the required business volumes in the proposed TMC
and for providing the specified services to the users of TMC and technical & architectural
plans for required for developing the necessary infrastructure for the proposed TMC.
The Master Plan, to be provided by PE, will cover the details of the development of entire
TMC over a time frame of 15 years and will specify the volume forecast and the overall
development of TMC in consistency with the time frame and the level of service quality,
development and product standards (as specified in OMDA). The development of individual
facilities will be time bound activities with specified target dates for each facility. The
proposed Master Plan including the target dates shall be approved by the Nodal Officer and
the Independent Consultant.
5. Conditions Precedent to be satisfied by PE The PE needs to fulfill these conditions over and above the bidding criteria in order to
qualify to avail the TMC project. These conditions include furnishing the Performance bond
41
(in form of Bank Guarantee) of the specified amount, manage and develop the TMC and
execution of necessary agreements such as lease deed, TRA agreement ,Share holders
agreement and the Master Plan.
6. Mandatory Capital Projects
The PE is obliged to complete the capital projects within a specified time frame as specified
in OMDA. Also, in case of non fulfillment of this condition, the PE shall be levied damages
(more specifically as specified in OMDA)
7. Service Quality, Development and Product Standards
In order to render the TMC comparable to the major International Markets, a high level of
quality standard will be required at the TMC. The quality standards are fixed for Service
Quality, Development and Products that will be handled by TMC. The quality standards
include NBC (National Building Code), Indian standard code and other specified standards
for Development Quality and AGMARK, EuroGAP, ISO17025 and other standards
for Product Quality. Specific service quality standards for each service need to be attained.
These quality standards need to be provided in the TMC within a specified time frame. The PE is liable to specified default norms in the event of not meeting the service quality
requirement. 8. Monitoring and Evaluation
Nodal Officer will monitor progress of implementation of project and operation including
progress with respect to timeliness and quality. State Horticulture Mission will submit
Quarterly reports on progress of implementation of TMC to AMA and also to Mission
Director, National Horticulture Mission. For this, if required by GoS, an Independent
Consultant (IC) may be appointed by GoS for the purpose of determining and ensuring
compliance with technical standards, specifications, costs and time schedules during any
operation, development, design, repair, maintenance, replacement or construction at the
Terminal Market Complex Site. The duties of IC include review of designs, drawings and
procurement documents, Monitoring of the construction, operation and management of the
TMC, monitoring the progress of mandatory and capital projects and other components of
project to be undertaken by the PE, approval and review of Master Plan submitted by PE,
audit of fund utilization by the PE and other relevant duties. The PE will provide all relevant
information promptly for the purpose.
42
9. Defaults
Each of the following events or circumstances, to the extent not caused by a Force
Majeure, shall be considered for the purposes of this Agreement as events of default of
which, if not cured within the time period permitted, shall provide the GOS the right
to terminate this Agreement in accordance OMDA. The conditions that will be classified as events of default on part of PE include: breach of
terms of agreement, material breach, non achievement of ISO standards, breach of
obligations under Objective Service Quality Requirements, Product Standards, or
Development Standards and Requirements for a period, non completion of the Project in
the given period and setting up of lower capacities/ incurring lower investments than what is
prescribed.
10. Force Majeure The PE shall be entitled to suspend or excuse performance of its respective obligations under
this Agreement to the extent that the PE is unable to render such performance by an event of
Force Majeure (a "Force Majeure"). The conditions that may qualify for the execution of
Force Majeure include but not restricted to war, revolution, riot, nuclear explosion, strike,
epidemic and other conditions. The Force Majeure will be executed as per the specified
procedure.
43
APPENDIX 2
FORMAT FOR POWER OF ATTORNEY FOR SIGNING OF
APPLICATION POWER OF ATTORNEY
Know all men by these presents, we (name and address of the registered office)
do hereby constitute, appoint and authorize Mr. / Ms. (name and address of
residence) who is presently employed with us and holding the position of as our
attorney, to do in our name and on our behalf, all such acts, deeds and things necessary in
connection with or incidental to our bid for the project envisaging Designing,
Engineering Financing, Procurement, Constructing, Operating and Maintaining the
Terminal Market Project Complex located at [ ] in the State of [ ] ,
including signing and submission of all documents and providing information /
responses to (AWARDER), representing us in all matters before AWARDER, and
generally dealing with AWARDER in all matters in connection with our bid for the
said Project.
We hereby agree to ratify all acts, deeds and things lawfully done by our said attorney
pursuant to this Power of Attorney and that all acts, deeds and things done by our
aforesaid attorney shall and shall always be deemed to have been done by us.
For
(Signature)
(Name, Title and Address)
Accept
…….. .............................. (Signature) (Name, Title and Address of the Attorney)
Notes:
To be executed by the sole Applicant and/ or the Lead Member, as the case
may be, in case of a Consortium.
The mode of execution of the Power of Attorney should be in accordance
with the procedure, if any, laid down by the applicable law and the charter
documents of the executants (s) and when it is so required the same should be
under common seal affixed in accordance with the required procedure.
44
Also, wherever required, the executants(s) should submit for verification the
extract of the charter documents and documents such as a resolution / power of
attorney in favour of the Person executing this Power of Attorney for the
delegation of power hereunder on behalf of the executants(s).
45
APPENDIX 3
LETTER OF
APPLICATION
(On the Letter head of the Applicant (in case of Single Applicant) or Lead Member
responsible (in case of a Consortium / Joint Venture)
Date:
To
Mr. [Name of the official]
[Designation] GOS
[state name]
[Address 1],
[Address 2]
[City] [State] – [Pin]
Ref : Designing, Engineering, Financing, Procurement, Constructing, Operating and
Maintaining the Terminal Market Project Complex located at [ ] in the state of
[ ] (“the Project”) Sir,
Being duly authorized to represent and act on behalf of (hereinafter referred to as
“the Applicant”), and having reviewed and fully understood all of the pre-qualification
requirements and information provided, the undersigned hereby apply for qualification for
the project referred above. We are enclosing our Application for Qualification in One original plus one copy, with
the details as per the requirements of the RFQ, for your evaluation.
(Authorized Signatory)
46
APPENDIX 3A
Bid Response Sheet No.1
Details of Applicant
1. (a) Name
(a) Country of Incorporation
(b) Address of the corporate
headquarters and its branch
office (s), if any, in India
(c) Date of incorporation and / or commencement of business
2. Brief description of the business entity including details of its main lines of business and
proposed roles and responsibilities in this Project. 3. Details of individual (s) who will serve as the point of contract / communication for
AWARDER within the Company
a) Name:
b) Designation:
c) Business Entity:
d) Address:
e) Telephone No:
f) E-mail Address:
g) Fax No: 4. Name, Designation, Address and Phone Nos. of Authorized Signatory of the Applicant:
a) Name:
b) Designation:
c) Address:
d) Telephone No:
e) E-mail address:
f) Fax No:
5. In case of a Consortium:
The information above (1-4) should be provided for all the Members of the Consortium
47
APPENDIX 3B
Bid Response Sheet No. 2
Experience of the applicant # Applicant
type # #
Member
code *
Core
competencies
* *
Categorization
of applicant
***
Volume
factor
# # #
Project
cost
factors
****
Networth
factors
Single
Entity
Applicant
Consortium
Member 1
Consortium
Member 2
Consortium
Member 3
Maximum Volume Score =
Maximum Project Cost Score =
Maximum Net Worth Score =
# The Applicant should provide details of only those projects undertaken by it under its
own name. Project experience of the Applicant‟ s parent company or its subsidiary or any
Associate company (who is not a member of the Consortium) will not be considered for
computation of the volume score
## Any Applicant consisting of a single entity should fill in details as per the row
titled Single Entity Applicant and ignore the other rows mentioned below. In case of a
Consortium, the details need to be provided as per the lower rows depending upon the
number of Consortium Members and the row titled Single Entity Applicant may be ignored.
48
### Refer to clause 3 B (a, b) also in the event that two or more members of a Consortium
had participated in the same project, only one member should mention the project. In case
more than one member mentions the project, the Project cost score of the member with
the highest project cost score for that project shall be considered and the experience of the
other members shall not be considered for the purpose of evaluation of the RFQ. * Member codes
NA = Not Applicable in case of a single entity
Applicant. M = Member.
**Refer to clause 3 A (b): Eligible project details. Add more rows if
necessary. ***Refer Clause 3.2.
(a) ****Refer to Clause 3.2.B
(c).
49
APPENDIX 4
ELIGIBLE PROJECT DETAILS
Project Code: Member Code: Refer Instruction Applicant To Fill Up The
Details Here
Category 5
Year code 6
Title & nature of the project
Entity for which project was
constructed / developed
7
Location
Project cost 8
Date of commencement of
project
Date of completion /
commissioning
9
Equity shareholding 10
Instructions
1. Applicants are expected to provide information in respect of Eligible Projects in this
section. The Projects cited must comply with the eligibility criteria specified in
Clause
3.(C).4. Information provided in this section is intended to serve as a back up for
information provided in accordance with Bid Response Sheet 2. Applicants are also
required to refer to Appendix 4for Guidelines for providing related to experience.
For a single entity Applicant, or individual member of consortium: Core Competencies
would include .1. Agribusiness: (Class “AB”) and 2. Infrastructure Developers: (Class
“ID”)
This category would include applicants with a core competency in the field of Infrastructure
Development.
2. A separate sheet should be filled for each of the Eligible Projects.
3. Member codes shall be
NA = Not Applicable in case of a Single entity
Applicant, LTM = Lead Technical Member
LFM = Lead Financial Member
M = Member.
LM = Lead Member
50
4. Refer Clause 3.(A).1 for Category 5. Figures may be provided for the past three years. The financial year would be the
same as the one normally followed by the Applicant for its Annual Report. Year 1 refers to
the latest financial year [insert the most recent financial year]; Year 2 refers to the financial
year before Year 1, Year 3 refers to the financial year before Year 2,
6. For applicant in in Agribusiness or Infrastructure Development, largest value Project
Cost should be provided till the most recent year. 7. For applicant in infrastructure development in Agribusiness or Infrastructure
Development, date of commissioning should be provided and the date of completion should
be provided.
8. For applicants, the equity shareholding of the Applicant in the project as on date of
commissioning needs to be given. 9. Certificate from the client or a certificate from the Applicant‟ s statutory auditor must be
furnished stating the following details (as provided in Appendix 5):
a. Date of completion/ date of commissioning of the project
b. Cost of project
c. Equity shareholding as on date of commissioning (only in case of relevant categories) It may be noted that in the absence of any one of the above (including the certificate from
the client), the information would be considered inadequate and could Lead to exclusion of
the relevant project in computation of project cost Score.
51
Appendix 5
Guidelines for Providing Information related to Project cost If the Applicant is claiming experience under relevant Category, the Applicant should
provide certificate from the client, which should contain the following minimum
details:
1. Title & Nature of the Project
2. Entity for which the Project was constructed. (in the event not constructed for itself)
3. Work executed by the Applicant.
4. Names of all the Consortium Members (in case of jobs/ contracts which have been
executed as part of a Consortium).
5. Value of the job/ contract/ certified billing
6. Date of completion/ certified billing.
a. It may be noted that in the absence of any one of the above, the information would
be considered inadequate and could lead to exclusion of the relevant project in
computation of Experience Score
b. In case of a particular job/ contract has been jointly executed by the Applicant (as
part of a Consortium), he should further support his claim for the share in work done for
that particular job / contract by producing a certificate from his statutory auditor or the
client/ employer in the format given below. This certificate would be in addition to
the
above-mentioned certificate from the client.
Certificate from the Statutory Auditor / Client
This is to certify that (Name and Registered office of the Applicant)
has constructed (Title of the Project).
We further certify that (Name and Registered office of the Applicant)
has executed /earned an income from executing this project of (Amount).
Signature of the Name Place Date
Authorized Signatory
52
It may be noted that in the absence of any detail from the above certificate, the information
would be considered inadequate and could Lead to an exclusion of the relevant project in
computation of Experience Score.
2. If the Applicant is claiming experience under relevant Category the Applicant should provide a
certificate from his statutory auditor in the format given below
Certificate from the Statutory Auditor
This is to certify that (Name and Registered office of the Applicant) has promoted
(Title & Nature of the Project). This Project was commissioned
on (Date of commissioning of the Project) and
(Name and Registered office of the Applicant) held % of the equity capital in
the Project as on the date of commissioning.
We further certify that total cost of the Project as on the date of commissioning was
Signature of the Name Place Date
It may be noted that in the absence of any detail from the above certificate, the information
would be considered inadequate and could lead to exclusion of the relevant project in
computation of experience score.
53
SCHEDULE 1 “Market Services” means the provision of following User facilities and services at the TMC
eligible for subsidy (Indicative only; State Govt to finalise on need based) a. TMC: Facilities and services to be provided at the central terminal market complex for
Perishable Agricultural Produce handled by the PE
i. Auction platform/Automatic weighing platform/ electronic auction facility
ii. Loading/unloading/dispatch facilities
iii. Drying yards iv. Cold storage facility & temperature controlled warehouse
v. Ripening chamber
vi. Sorting, grading, washing and packing lines Labelling of produce
vii. Quality testing facility
viii. Material handling equipment (palletisation and plastic crates ) ix. Movement and parking facility for vehicles
x. Futures trading facility
xi. Transport services (including climate controlled transport) xii. Banking services including settlement of transactions
xiii. Vehicle fuelling services
xiv. Waste and refuse treatment and disposal
xv. Basic lodging services for farmers
xvi. Storage area of plastic crates
xvii. Standards for the produce arriving at the market
xviii. Bulk Weightment etc
xix. Price displays / bulletin service xx. Advisory on inputs, prices, quality for Perishable Agricultural Produce &
Farmers training
b. Facilities and services to be provided at the collection centre for Perishable
Agricultural Produce handled by the PE
54
i. Washing, grading, sorting, weightment services
ii. Multi-modal transport services including to central tmc
iii. Plastic crates
iv. Facility for collection and aggregation of produce
v. Services for settlement of transaction NOTE: The marketing services to be provided free if any to farmers is mentioned in OMDA.
55
SCHEDULE 2
Essential Services “Essential Services” means the provision of the following User facilities and
services (indicative list) at the TMC and eligible for subsidy: These are:
1. Toilets and nursing mothers rooms;
2. Waiting rooms;
3. Drinking water
4. Cleaning, heating, lighting and air conditioning public areas
5. Facilities for the disabled and other special needs people
6. Information desks
7. Policing and general security
8. Fire fighting services
9. Emergency services including emergency medical care room
10. Any other services deemed to be necessary for the safe and efficient operation of the
Terminal Market Complex. In addition to the above which are non chargeable, the TMC will provide the following
User facilities and services at nominal rates to the TMC Users:
11. Canteen/ Food items
12. Required Infrastructure/ Facilities for Post Offices
13. Infrastructure/ Facilities for Public telephones
14. Infrastructure/ Facilities for access to internet
15. Vehicle parking
56
SCHEDULE 3
Non Market Services “Non Market Services” means the provision of the following indicative User facilities and
services at the TMC but which are not eligible for subsidy including its land portion
(Indicative only) : a) Business Centre services
b) Catering services
c) Freight consolidators/forwarders or agent services
d) General retail shops
e) Hotels and Motels services including reservation services
f) Locker rental
g) Logistic Centres
h) Messenger services
i) Porter service
j) Restaurants, and other refreshment services
k) Vehicle rental services
l) Vending services
m) Leisure service Facilities and entertainment
n) Shopping Complex
o) Secondary and Tertiary processing
The PE is entitled to collect user charges for these services in line with prevailing market
conditions.
Negative list of activities: Indicative List of businesses or operations which cannot be
established / performed in the Terminal Market complex:
a) Arm Shop
b) Gambling
c) Contraband items
GOS can further add the items in the negative list as per specific requirements.