Rev 0 – January 2016 R INSTALLATION GUIDELINES Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com January 2016 GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS INSTALLATION IMPORTANT: THIS DOCUMENT EXPLAINS THE INSTALLATION PROCEDURE OF THE GFRP EQUIPMENT SALHER BRAND. IT WILL BE NECESSARY TO MAKE A CIVIL WORK SIGNED BY A COMPETENT TECHNICIAN SUPERVISOR. THE RESPONSIBILITY OF THE INSTALLATION IS ALWAYS OF THE INSTALLATION COMPANY. SALHER COULD GIVE TECHNICAL SUPPORT TO SUPERVISE THE DIFERENT STAGES OF THE INSTALLATION. THE NONFULFILMENT OF THE NORMS PRESCRIBED MEANS THE FAILURE TO COMPLY WITH THE BASIC NORMS AND EXEMPTS SALHER FROM THE RESPONSIBILITY IN CASE OF ACCIDENTS OR DAMAGE TO THE EQUIPMENTS, AND ALSO CAUSES THE LOSS OF THE WARRANTY. ANY INSTALLATION DEFECT IS RESPONSABILITY OF THE INSTALLER. FOR INSTALLATIONS OTHER THAN THOSE CONTAINED IN THIS MANUAL, PLEASE CONSULT SALHER TECHNICAL DEPARTMENT.

Upload: duonganh

Post on 12-Mar-2018

227 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐  INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

                              

 

  

GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS INSTALLATION  

                   IMPORTANT:  

THIS DOCUMENT EXPLAINS THE INSTALLATION PROCEDURE OF THE GFRP EQUIPMENT SALHER BRAND. IT WILL BE NECESSARY TO MAKE A CIVIL WORK SIGNED BY A COMPETENT TECHNICIAN SUPERVISOR. THE RESPONSIBILITY OF THE INSTALLATION IS ALWAYS OF  THE  INSTALLATION  COMPANY.  SALHER  COULD  GIVE  TECHNICAL  SUPPORT  TO  SUPERVISE  THE  DIFERENT  STAGES  OF  THE INSTALLATION.  

THE NON‐FULFILMENT OF THE NORMS PRESCRIBED MEANS THE FAILURE TO COMPLY WITH THE BASIC NORMS AND EXEMPTS SALHER FROM THE RESPONSIBILITY  IN CASE OF ACCIDENTS OR DAMAGE TO THE EQUIPMENTS, AND ALSO CAUSES THE LOSS OF THE WARRANTY.  

ANY INSTALLATION DEFECT IS RESPONSABILITY OF THE INSTALLER.  FOR INSTALLATIONS OTHER THAN THOSE CONTAINED IN THIS MANUAL, PLEASE CONSULT SALHER TECHNICAL DEPARTMENT. 

Page 2: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

Rev 0 – January 2016

R‐ INSTALLATION GUIDELINES ‐ January 2016 

Page 1 of 21 

 

INDEX   

1. TRANSPORT............................................................................................................ 2 2. LOADING, UNLOADING AND STORAGE ................................................................... 3 3. ORDER REVIEW....................................................................................................... 4 4. WATER FILLING AND EMPTYING OF THE TANKS...................................................... 5 ANNEX I: ABOVEGROUND INSTALLATION OF GFRP VERTICAL EQUIPMENTS............... 6 ANNEX II: ABOVEGROUND INSTALLATION OF GFRP HORIZONTAL EQUIPMENTS........ 9 ANNEX III: UNDERGROUND INSTALLATION OF GFRP EQUIPMENTS .......................... 11 ANNEX III.a: STABLE GROUNDS .................................................................................. 11 ANNEX III.b: UNSTABLE GROUNDS ............................................................................. 13

ANNEX IV: UNDERGROUND GFRP EQUIPMENTS INSTALLATION PROCEDURE........... 14 ANNEX IV.a: STABLE GROUNDS OPTION 1 ................................................................ 14 ANNEX IV.b: STABLE GROUNDS OPTION 2 ................................................................. 15 ANNEX IV.c: UNESTABLE GROUNDS ........................................................................... 16 ANNEX  IV.d: PUMPING STATION IN STABLE GROUNDS ............................................ 17 ANNEX IV.e: PUMPING STATION IN UNSTABLE GROUNDS OR WITH PHREATIC LEVEL.................................................................................................................................... 18

ANNEX V: ABOVE GROUND GFRP EQUIPMENTS INSTALLATION PROCEDURE ........... 19 ANNEX V.a: VERTICAL ................................................................................................. 19 ANNEX V.b: HORIZONTAL ........................................................................................... 20

  

Page 3: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 2 of 21                              

1. TRANSPORT

  The necessary safety conditions should be taken for transport. 

 

The shipper will be responsible for any non‐fulfilment of the basic norms, as well as any 

loss, damage, alteration, deformation occurred during the shipment of the equipments, 

as well as loading and unloading.  

 

The non‐fulfilment of the prescribed norms  implies the failure to comply with the basic 

norms and exempts SALHER from any  liability  in the event of accidents or damages on 

equipments; this will also cause the loss of the warranty.  

 

Place  the  equipment  in  the middle  of  the  vehicle,  on  a  flat  base  or  a  system which 

ensures  its  stability,  avoiding  any  contact  with  other  equipments  /  materials,  and 

ensuring it will not move. If necessary, use straps to fix / tie up the equipments to avoid 

any damage / blow during the transport. 

 

Never  use metallic  straps,  only  plastic material,  to  ensure  the  equipment  safety  and 

avoid any deformation.  

 

Safety measures  should  be  taken  during  loading,  unloading  and  storage  operations, 

besides the measures required by the construction manager, safety and health Officer. 

 

During the transport, GFRP equipments must not contain water.  

 

 

 

 

 

 

 

 

 

Page 4: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 3 of 21                              

2. LOADING, UNLOADING AND STORAGE

Safety measures should be taken during loading, unloading, and storage operations. 

 

The  appropriate  resources  should  be  used  during  loading  and  unloading  operations, 

according  to  the equipment weight and dimensions, ensuring all  the  time  its  stability, a 

safe handling and avoiding any kind of sudden movement. If necessary tie up with straps. 

 

GFRP equipment  loading and unloading from the truck or  in the construction site will be 

performed only if the equipment is empty, and with non‐metallic straps, harness through 

hoisting devices available on the equipment (eyebolts). 

 

The equipments should be stored on a flat base to avoid any kind of distortion / damage / 

breaking due to external conditions. 

 

GFRP  equipments  must  be  empty  during  loading,  unloading,  and  storage  operations, 

therefore the user should take care to avoid any external water entry. 

 

 

 

Page 5: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 4 of 21                              

 

 

3. ORDER REVIEW At the reception of the order at the construction site, check the delivery note, specially 

bulks and equipments mentioned in the order. Check the GFRP equipments, accessories 

and electromechanical equipments supplied. 

At  the same  time, check externally  the equipments  to detect any blow / deformation/ 

breaking / damage, caused during the transport.  

 

Equipments have been submitted to an internal quality control, in accordance with the  

Standard ISO 9001:2008. 

 

ANY  JUSTIFIED  COMPLAINT  RECEIVED  THE  DAY  OF  DELIVERY  WILL  BE  IMMEDIATELY 

ADDRESSED. 

 

 

 

 

Page 6: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 5 of 21                              

4. WATER FILLING AND EMPTYING OF THE TANKS  

If equipments have compartments, they can be vertical or horizontal, please follow these guidelines 

during filling and emptying.   

 

To  equalise  the  hydrostatic  pressure  on  both  sides  of  the  separation  deflector  between 

chambers,  the  first  filling  of  the  equipment  and  complete  emptying  will  be  done 

simultaneously in all compartments.  

For the first filling,  it  is recommended to use a hose or a pipe  in each compartment through 

the corresponding manholes. Check visually the evolution of level in each of them, ensuring a 

balance during the whole process. 

To  empty,  use  the  hose  or  suction  pipe  in  each  compartment,  the  access  should  be  done 

through  the  corresponding manholes. Check visually  the evolution of  level  in each of  them, 

ensuring a balance during the whole process. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 7: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 6 of 21                              

ANNEX I: ABOVEGROUND INSTALLATION OF GFRP VERTICAL EQUIPMENTS  

 

The  installation will be performed on a  solid ground  (with enough  resistance  to  support  the 

equipment weight when it is full of water), flat, levelled, and must support all the base of the 

tank. 

 

If it is necessary to build a concrete slab (minimum HA25): depending on the type of ground, it 

will  be  necessary  to  calculate  a  thickness  and  a  specific  framework  according  to  the 

specifications of the construction manager, to provide a stable and levelled surface.  

 

The  surface will be  free of  rough elements  (rocks or  sharps  items) which  could damage  the 

tank base when full or empty. 

 

The appropriate safety measure should be taken to avoid any kind of alteration, deformation 

or  breaking  of  the  equipments  and  accessories,  as well  as movements  caused  by  external 

agents (wind, etc.) or unfavourable conditions on the installation site.  

 

If  necessary,  fasten  the  equipment  at  the  installation  base  with  framing  squares  or  fixing 

elements.  

 

The tank connections (inlet, outlet, overflow, etc.) to other elements of the installation can be 

performed with PVC or flexible material pipes and / or flanges. Do not make any METAL‐PVC 

rigid connections. 

 

Before making the hydraulic connections, the equipment must be filled up with water at the 

2/3 parts of  its  total  capacity. All  levelling operations will be preformed once  the hydraulic 

connections are disconnected  to avoid damages. Once  the equipment  is  full of water, check 

the correct levelling, and if necessary, level it again always without water.  

 

If equipments are  installed  in grounds with slope or hillside, the appropriate safety measures 

should  be  taken  to  avoid  any  alteration  /  deformation  /  breaking  of  the  equipments  and 

accessories,  as well  as movements  caused  by  external  agents  (wind,  etc.)  or  unfavourable 

conditions on the installation site. 

 

Page 8: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 7 of 21                              

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 9: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 8 of 21                              

The picture above shows the hoisting and aboveground installation process recommended for 

GFRP vertical tanks: 

 

Firstly, fasten with no metallic straps both sides, surrounding completely the tank.   

Secondly,  hoist  simultaneously  from  both  sides  to  a  height  which  enables  the 

straightening manoeuvres.  

Then, hoist progressively  the upper bottom of  the  tank.  It  is  important  to perform 

this operation, maintaining carefully stable the tank. 

Once the tank stands vertically, slowly lower it until  it is in contact with the support 

surface.  

It is recommended to hold the equipment until it is completely settled and fastened.   

 

The  company  in charge of  the  installation will be  liable  in  the event of non‐fulfilment of  the 

norms, as well as any other  safety norm not  taken  into account during  the  installation. The 

non‐fulfilment of the prescribed norms shall exempt SALHER from any  liability  in the event of 

accidents or equipment damage, causing also the loss of the warranty. 

                      

Page 10: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 9 of 21                              

ANNEX II: ABOVEGROUND INSTALLATION OF GFRP HORIZONTAL EQUIPMENTS   

Equipments placed on GFRP / Metallic supports SALHER brand. 

o For  tanks with diameter  ≤2.250mm,  supports will be of GFRP and will be  fixed  to  the 

equipment. 

o For tanks with diameter >2.250mm, supports will be of GFRP or metallic.  

 

The  installation will be performed on a solid surface  (with enough  resistance  to support  the 

weight  of  the  equipment  full  of water),  flat,  levelled,  the whole  base  of  the  equipment  in 

contact with ground.   

 

If it is necessary to build a concrete slab (minimum HA25): depending on the type of ground, it 

will  be  necessary  to  calculate  a  thickness  and  a  specific  framework  according  to  the 

specifications of the construction manager, to provide a stable and levelled surface.  

 

The  surface will be  free of  rough elements  (rocks or  sharps  items) which  could damage  the 

tank base when full or empty. 

 

The appropriate safety measure should be taken to avoid any kind of alteration, deformation 

or  breaking  of  the  equipments  and  accessories,  as well  as movements  caused  by  external 

agents (wind, etc.) or unfavourable conditions on the installation site.  

 

If  necessary,  fasten  the  equipment  at  the  installation  base  with  framing  squares  or  fixing 

elements.  

 

For  the  installation of equipments on metallic supports  (diameter >2500mm),  first  lower  the 

supports, aligning them on the flat base, checking its levelling, with equal separation along the 

whole length of the separator. Then a crane will lower the equipment, so that the base of the 

equipment can be  in contact with  the whole  length of  the  ferrule or cylindrical part. Finally, 

fasten the supports to the tank with the supplied straps; tighten them to avoid any movement 

of the tank. Straps should be of GFRP, nylon or similar plastic material, not metallic, for a safe 

fastening. 

 

Page 11: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 10 of 21                              

The tank connections (inlet, outlet, overflow, etc.) to other elements of the installation can be 

performed with PVC or flexible material pipes and / or flanges. Do not make any METAL‐PVC 

rigid connections. 

 

All levelling operations will be performed once the hydraulic connections are disconnected to 

avoid damages. 

 

If equipments are  installed  in grounds with slope or hillside, the appropriate safety measures 

should  be  taken  to  avoid  any  alteration  /  deformation  /  breaking  of  the  equipments  and 

accessories,  as well  as movements  caused  by  external  agents  (wind,  etc.)  or  unfavourable 

conditions on the installation site. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 12: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 11 of 21                              

ANNEX III: UNDERGROUND INSTALLATION OF GFRP EQUIPMENTS  

ANNEX III.a: STABLE GROUNDS   

 

OPTION  1:  Mechanical  compaction  equipments  and  perimetral  space  ≥1m  between 

equipments are required. 

o Base: Formed by a mechanically compacted  levelled sand bed  in  the entire excavation 

perimeter, with minimum of 95% of the normal Proctor density and thickness ≥200mm. 

o FILLING MATERIAL:  Fine,  clean,  sieved, dust‐free  and  clay‐free,  free of organic matter 

and coarse solids (ρmín.1500 Kg/m3).  

o FILLING UP: fill the perimeter up to the 2/3 parts of the equipment height with layers of 

20cm, mechanically compacted,  then  fill up with water  the ¼ parts height of  the  tank. 

Continue  to  fill  the perimeter with  layers of  30cm up  to  the pipes  level,  connect  the 

pipes and finish filling up the tank. 

 

OPTION 2:  

o BASE: Composed of fresh concrete ≥30cm and place the tank on the fresh concrete. 

o FILLING MATERIAL: Concrete HM‐20 and filling of fine sand, clean, sieved, dust‐free and 

clay‐free, free of organic matter and coarse solids (ρmín.1500 Kg/m3). 

o FILLING  UP:  Fill  up  with  vibrated  concrete  (HM‐20)  in  layers  of  30cm,  let  it  harden 

between  coats  up  to  2/3  of  the  equipment    alternating with water  up  to  the  same 

height. Upper filling with compact sand at 97%. 

 

When  performing  the  excavation,  please  consider  the  depth, material  and  diameter  of  the 

inlet collector.  

 

The ditch dimensions where  the equipment will be placed must be ≥ 1.000mm  in OPTION 1 

and ≥500mm in OPTION 2. 

 

The distance between equipments in series and parallelly must be ≥500mm.  

 

The ditch dimensions will be so that the equipment could lie on a concrete or sand slab. 

 

It is necessary to install an above ground viewfinder and a perimeter draining system to avoid 

water storage in the installation area.  

Page 13: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R ‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 12 of 21                              

 

UPPER FILLING UP LEVEL (above the upper line of equipments). 

o The upper  filling should have a minimum height of 500mm  from  the upper  line of  the 

equipment.  Equipments  are  manufactured  to  resist  to  a  maximum  filling  height  of 

1.000mm,  in  the  event  of  upper  heights  (>1.000mm)  equipment  will  be  reinforced  

(consult Salher). 

o No  machinery  will  circulate  on  and  around  the  equipments  (a  minimum  horizontal 

distance of 4 meters from the equipment). 

o In the event of road traffic, a concrete slab should be placed. This slab must not transmit 

load to the walls of the equipment, it must lay on firm ground.  

 

MANHOLE:  

o Equipment  have  upper  manholes  to  enable  the  access  inside  the  equipment.  If 

equipments are  installed at a specific depth and manhole cannot be reached, manhole 

or  access  chambers  should  be  built  to  check  the manholes  and work  inside.  Access 

chambers must be waterproof and must not transmit traffic load to from the surface to 

the tank.   

 

The  company  in charge of  the  installation will be  liable  in  the event of non‐fulfilment of  the 

norms, as well as any other  safety norm not  taken  into account during  the  installation. The 

non‐fulfilment of the prescribed norms shall exempt SALHER from any  liability  in the event of 

accidents or equipment damage, causing also the loss of the warranty. 

STABLES GROUNDS RESISTANCE TO COMPRESSION > 3700 kg/m2 

        

Page 14: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

Rev 0 – January 2016

R‐ INSTALLATION GUIDELINES ‐

Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 13 of 21                              

 

ANNEX III.b: UNSTABLE GROUNDS 

Build a skin reinforcement with a distance separation of ≥ 200mm from the tank.  

Fill up the inner part of the skin reinforcement with concrete (HM‐20). 

Fill up the exterior of skin reinforcement with sand. 

When making  a deeper excavation,  the material  and  the  inlet  collector diameter  should be 

taken into consideration. 

The  ditch  dimensions where  the  equipment  is  placed must  include  a  distance  of  ≥  500mm 

between the equipment and the wall of the ditch. 

Take into consideration the need to use timber formwork or steel  plates to ensure the walls of 

the excavation.   

Distance between equipments in series and in parallel must be ≥ 500mm. 

If equipments are  installed  in grounds with slope or hillside, the appropriate safety measures 

should  be  taken  to  avoid  any  alteration  /  deformation  /  breaking  of  the  equipments  and 

accessories,  as well  as movements  caused  by  external  agents  (wind,  etc.)  or  unfavourable 

conditions on the installation site 

 

LEVEL OF UPPER FILLING UP  

In the event of road traffic, a concrete slab should be placed. This slab must not transmit load 

to the walls of the equipment, it must lay on firm ground, not on the equipment. 

 

MANHOLE:  

Equipments have upper manholes  to enable  the access  inside  the equipment.  If equipments 

are installed at a specific depth and manhole cannot be reached, manhole or access chambers 

should be built to check the manholes and work inside. Access chambers must be waterproof 

and must not transmit traffic load to from the surface to the tank.    

 

*  UNSTABLE  GROUNDS Compression  resistance  <  3700  Kg/m2.  Marshy  or  muddy  areas,  limp  grounds expansive  clays,  or  any  ground  which would  not  support  the  equipment  weight  when  full  of  water  in resistance conditions.  

  

Page 15: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R‐  INSTALLATION GUIDELINES ‐

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 14 of 21                              

ANNEX IV: UNDERGROUND GFRP EQUIPMENTS INSTALLATION PROCEDURE   

ANNEX IV.a: STABLE GROUNDS OPTION 1

 

Page 16: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R ‐ INSTALLATION GUIDELINES ‐  

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 15 of 21                              

ANNEX IV.b: STABLE GROUNDS OPTION 2 

   

Page 17: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R‐  INSTALLATION GUIDELINES ‐

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 16 of 21                              

ANNEX IV.c: UNESTABLE GROUNDS 

 

   

Page 18: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R ‐ INSTALLATION GUIDELINES ‐  

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 17 of 21                              

ANNEX  IV.d: PUMPING STATION IN STABLE GROUNDS 

 

Page 19: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R ‐ INSTALLATION GUIDELINES ‐  

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 18 of 21                              

ANNEX IV.e: PUMPING STATION IN UNSTABLE GROUNDS OR WITH PHREATIC LEVEL 

  

Page 20: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R‐  INSTALLATION GUIDELINES ‐

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 19 of 21                              

ANNEX V: ABOVE GROUND GFRP EQUIPMENTS INSTALLATION PROCEDURE  

ANNEX V.a: VERTICAL 

 

Page 21: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R ‐ INSTALLATION GUIDELINES ‐  

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 20 of 21                              

 

ANNEX V.b: HORIZONTAL 

 

Page 22: GENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS · PDF fileGENERAL INSTRUCTIONS FOR GFRP EQUIPMENTS ... GFRP equipment loading and unloading from the truck or in the construction site will

R‐  INSTALLATION GUIDELINES ‐

Rev 0 – January 2016 Contact: Tlf: +34 918700015 / Fax: +34 918700518 Email: [email protected] / www.salher.com  

January 2016 

Page 21 of 21                              

ANNEX VI: INSTALLATION OF UNDERGROUND GFRP EQUIPMENT PROCEDURE (FRANCE)