    Chevrons Gas Production Enhancement Plan

    Inter-Ministerial Meeting

    DOC ID Chevron 2005

    ,

    Steve WilsonPresident, Chevron Bangladesh

  • 8/13/2019 Gas Production

    2/12

    Chevrons Production Capacity Enhancements

    Activity sequentially follows rig after Block 7 Kajal-1 well:

    3 wells at Moulavi Bazar to confirm new mapping & fill plant capacity

    4-6 wells at Bibiyana for Train 5

    4 Additional wells at BY for Train 6 (BY IPP)

    Back to Moulavi Bazar for 6 more wells & gas plant upgrade

    DOC ID Chevron 2005 2

    Appraisal & development drilling at Jalalabad with possible plant upgrade

    Significant investment over next 3 years to deliver these projects

    Investment justification beyond 3 MB wells depends on:

    Commitment on an additional evacuation pipelineStatus of BY IPP construction

    Delay in new pipeline will likely result in demobilization of the rig and deferral offurther activity, with postponement of further capacity enhancement

  • 8/13/2019 Gas Production

    3/12

    Moulavi Bazar Planned Activity

    Phase 1

    Construct 3 new drilling pads

    Drill 3 wells to prove up seismic interpretation:

    Evaluate BB60, BB70 and subthrust (BH10, BH20, BH40)

    Fill gas plant to 150 MMSCFD (add 100 MMSCFD)

    Phase 2

    Evaluate drilling results, validate seismic & mapping

    BB70

    Chevron 2008

    Prepare development plan to upgrade gas plant capacityand drill 6 more wells (from Phase 1 pads).

    No further land acquisition necessary

    Phase 3

    Execute Phase 2 development plan

    Add further production (circa 200 MMSCFD)

    Requires new evacuation pipeline

    3

    New BB60

    opportunity

  • 8/13/2019 Gas Production

    4/12

    Key Reservoir Performance DataBibiyana has performed better thaninitially expected.

    Reserves have increased significantly.

    3D seismic was reprocessed, showingsands are under-developed

    Bibiyana - BB60Bibiyana Planned Activity

    DOC ID Chevron 2005 4

    Multiple opportunities to increaseproduction and improve gas recovery.

    Forward plans

    Drill 8-10 additional well locations.

    Add additional 1-2 trains.

    Start pad construction in 2011.

    Commence drilling in late 2011, after 3Moulavi Bazar wells.

  • 8/13/2019 Gas Production

    5/12

    Bibiyana Gas Plant Capacity Expansion Plan

    Enhanced Liquid Recovery

    Optimize recovery of liquids

    Progressing a technical study toenhance liquid recovery

    Increase of plant gas capacitythroughput is a critical input

    DOC ID Chevron 2005 5

    Need to know future evacuationpipeline capacity & timing

    Gas Capacity Expansion (Train 5)

    Common shared utilities and systems (e.g. flare & relief system) require that gas capacityincrease and enhanced liquid recovery projects converge

    Study underway for overall debottlenecking, including flare & relief system constraints.

    Design needs clarity regarding future capacity expansions (e.g. trains 6, IPP etc).

    Should add circa 180 MMSCFD of additional capacity

  • 8/13/2019 Gas Production

    6/12

    Jalalabad Planned Activity

    Status:JB Seismic ESHIA study progressing3D seismic survey in planning stage

    Goals:Identify upside potential & well locations

    Prove up and drill additional

    resourcesJustification :

    DOC ID Chevron 2005 6

    Original Development AreaProposed Expansion

    Production data suggest the field is largerthan mapped at presentMB and BY seismic are in similar geologicsetting and both show upside potential

    Timing:Currently 90 MMSCFD of constrainedproduction, bottleneck at KT.No additional well capacity needed to fillcurrent plant capacity of 230 MMSCFDMay eventually justify plant upgrade &additional wells .Wells would be drilled after MB and BY

    Possiblenew

    pools

    Possiblereservoir

    extensions

  • 8/13/2019 Gas Production

    7/12

    Chevron Projected Production Potential

    1,250

    1,400

    1,550

    1,700

    1,850

    2,000

    i o n ( M M C F D

    )

    Chevron Projected Production Potential

    Jalalabad

    DOC ID Chevron 2005 7

    350

    500

    650

    800

    950

    1,100

    2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    G a s P r o

    d u c t

    Bibiyana

    Mou avi Bazar

    Per communication to Petrobangla on 2 nd May

  • 8/13/2019 Gas Production

    8/12

    Delivering Production Growth

    Work to enhance production capacity involves unprecedented activity in land acquisition,environmental clearance permitting & approvals, civil work, drilling engineering & designand plant construction and modification, in multiple sites at all locations.

    Will require significant investment dollars and big increase in organizational capability(e.g. drilling department and formation of Major Capital Projects group).

    Known opportunities could add around 900 MMSCFD

    DOC ID Chevron 2005 8

    - MB +100 +200- BY +180 +180- JB +80 +200Petrobanglas plans may add to this capacity

    New pipeline essential to deliver augmented production

    A discovery at Block 7 if commercially viable would add to this.

  • 8/13/2019 Gas Production

    9/12

    Plans for new Evacuation Pipeline

    JB

    BY

    Govt PipelineOption 1

    Govt PipelineFuture JB

    DOC ID Chevron 2005

    MBGovt PipelineOption 2

    In Progress

    Option 1 : Cross-country from BY direct to Dhanua about 150Km. Scope for future tie-in from JBOption 2 : Muchai to Monohordi about 105 km pipeline

  • 8/13/2019 Gas Production

    10/12

    Evaluation of Pipeline Capacity Requirement

    Additional capacity possible from Chevron circa 900 MMSCFD

    Supplied via Muchai Compressor late 2011

    Augmented by Ashugonj & Dhanua/Elenga 2012/2013

    Supplied directly to Bibiyana IPP

    DOC ID Chevron 2005 10

    =

    Additional capacity required by Petrobanglas projects = X MMSCFD

    Total pipeline capacity required = (620+ X) MMSCFD

    Ideally would like pipeline installed & commissioned by year end 2012/2013

    Physical route is less important than anticipated speed of installation, to address thecountrys medium term energy crisis in as timely a manner as possible

  • 8/13/2019 Gas Production

    11/12

    Summary

    New evacuation pipeline essential. Decision and action needed this year.

    DOC ID Chevron 2005 11

    ,clearance & various approvals.

    Information on Petrobanglas Plans for timing of projects will help (BY IPP,pipeline, compressor etc).