Page 1: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

OFFICIAL INDUSTRY ASSOCIATION FOR MICROSOFT OFFICE PROJECT

1

Presented By:

© 2007 MPA. All rights reserved.

From Planningto

Baseline

Steve M. ClarkProject ManagerEdwards Industries, LLC.

Page 2: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

2© 2007 MPA. All rights reserved.

Typical Comments

Some interesting tidbits about “Schedules”:• It is a “buzz word”

♦ A word people like to use but do not fully understand what it is.

• It is used often during meetings but is forgotten once the meeting ends.

• Is considered by some project managers as not “real” project management work.

• It is viewed simply as an exercise that has little real value.• “We should be managing the project not the schedule.”

♦ Do you want me to manage the project or the schedule?♦ It is used to “micro-manage” the project team…

• Schedules are too much work to maintain.• The schedule does not reflect what is really happening…

…or what is really needed…

Page 3: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

3© 2007 MPA. All rights reserved.

Planning

How do you begin developing a schedule?• Are you ready to develop a schedule?

♦ What is needed?Project CharterScope StatementRequirementsWork Breakdown Structure (WBS)Stakeholders!» Determine which key stakeholders are needed for this process.» Other stakeholders are consulted as needed.

Subject Matter Experts (SME)♦ How long will it take?

That depends on the level of cooperation you get from the stakeholders and the SMEs.

Page 4: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

4© 2007 MPA. All rights reserved.

Planning

The Secret to Schedule Development…

B P PM

Page 5: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

5© 2007 MPA. All rights reserved.

Planning

What does BMPP stand for?

Big

Monster

Piece

Paperof

This is true!I affectionately refer to it as the “Wallpaper” process.

Page 6: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

6© 2007 MPA. All rights reserved.

Planning

My Definition - BMPP is a “structured” brain storming process used to develop the schedule.What is needed?• A large piece of paper

♦ Preferably from a 36” x 50’ role♦ Several smaller sheets taped together (Post-it® Easel Pad 2.5’ x 2’)

• Post-it® Notes (several colors and sizes)♦ Note - This is not a 3M endorsement

• Felt Tip Markers (makes it easier to see the task descriptions)

• Scotch Tape

• Large Empty Wall Space

Page 7: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

7© 2007 MPA. All rights reserved.

Planning

Your role in the process:• Facilitator

♦ You get the ball rollingOkay – What is the first step?

♦ Keep the ball rolling by invoking discussionKeep those light bulbs shinning bright

♦ Watch out for scope creep♦ Stop when you have squeezed all of the juice out

• Devil’s advocate♦ As the tasks are defined your job is say things like

What if…?What happens when…?What else is needed…?Are you sure…?

Page 8: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

8© 2007 MPA. All rights reserved.

Planning

BMPP Advantages• It is easier to see the “whole picture” when Post-it® Notes are taped to

the wall then it is on a computer screen.♦ Change the task order.♦ Inserting and/or deleting tasks.

• If it has not already been done the group is building the WBS. If it already exists, it is improving schedule accuracy and being refined.

• Building your resource requirements and identifying resource conflicts.• The group is identifying risks and developing ways to avoid, manage, or

mitigate the risks as the “picture” evolves.• You are creating a level of detail that everyone agrees is appropriate.• Once complete you can get “buy-in”.

♦ Why? - The Stakeholders and SMEs participated in the development process.• It can be used during proposal development which can then be built

upon to create the actual schedule.♦ You get a more accurate reading as to what it is going to take.

Page 9: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

9© 2007 MPA. All rights reserved.

Planning

BMPP Disadvantages• It can take several hours, days, or weeks to complete.

♦ However, Ask Yourself – Is it better to spend the time upfront to produce a “realistic” schedule (plan) or try to repair a “swag” later under pressure (pay me now – or pay me later…).

• If you use the wrong kind of tape you may be charged to repair the wall. ☺♦ If you use push pins make sure it is okay to do so. However,

scotch tape is better.

• Can take up a lot of wall space.How do we get started?

Page 10: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

10© 2007 MPA. All rights reserved.

Mark Your Territory!

Page 11: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

11© 2007 MPA. All rights reserved.

Identify Deliverables

Deliverables

FRD

VDD

SwDD

Page 12: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

12© 2007 MPA. All rights reserved.

Identify Recurring Tasks

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

Page 13: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

13© 2007 MPA. All rights reserved.

Identify High Level (Summary) Tasks

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

ProcurementAnalysisDesignPhase

DevelopmentPhase

TestingPhase

ProductionPhase

Page 14: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

14© 2007 MPA. All rights reserved.

Identify Next Level (Summary?) Tasks

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

ProcurementAnalysisDesignPhase

DevelopmentPhase

TestingPhase

ProductionPhase

AnalysisTask 1

AnalysisTask 2

ProcureItem # 1

ProcureItem # 2

ServerDesign

Client Design

Page 15: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

15© 2007 MPA. All rights reserved.

Define Task Relationships

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

ProcurementDesignPhase

DevelopmentPhase

TestingPhase

ProductionPhase

AnalysisTask 2

ProcureItem # 1

ProcureItem # 2

ServerDesign

Client Design

Analysis

AnalysisTask 1

Page 16: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

16© 2007 MPA. All rights reserved.

Identify Milestone Tasks

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

ProcurementDesignPhase

DevelopmentPhase

TestingPhase

ProductionPhase

AnalysisTask 2

ProcureItem # 2

ServerDesign

Client Design

Analysis

AnalysisTask 1

ProcureItem # 1

Item # 1 Received

Page 17: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

17© 2007 MPA. All rights reserved.

Define Task Parameters

Deliverables

FRD

VDD

SwDD

RecurringTasks

WeeklyStatus mtg.

WeeklyT.E.M.

ProcurementDesignPhase

DevelopmentPhase

TestingPhase

ProductionPhase

AnalysisTask 2

ProcureItem # 1

ProcureItem # 2

ServerDesign

Client Design

Analysis

AnalysisTask 1

Server Design

Start Date – 06/20/07Duration – 10 Days

Work – 80 hoursResource 1 – 80%Resource 2 – 40%

Notes – BOE, Assumptions, Dependencies, etc.

Page 18: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

18© 2007 MPA. All rights reserved.

Congratulations!Now You Are Ready for MS Project!

Transferring from “Wallpaper” to the tool (MS Project)• First - use Scotch tape to secure the Post-it® Notes to your

wallpaper before you take the wallpaper off of the wall.♦ The adhesive on the back looses its strength rather quickly.

• Data entry is much easier after this process:♦ Your structure is predefined (if you were careful)♦ The tasks contain everything you need to enter them into MS Project

Task DescriptionStart DateDurationResource Names and AllocationsPredecessors and SuccessorsNotes

Page 19: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

19© 2007 MPA. All rights reserved.

Schedule Flow Tips

Create Three Main Sections• Meetings and Major Milestones Section

♦ For Upper Management and Customer Reporting♦ Linked to Major Activities and Phases within the detailed Project

Schedule Section

• Deliverables Section♦ Listing of All Project Deliverables♦ Both Customer (contractual) and Internal (non-contractual)

• Project Section♦ Contains meat of the schedule♦ Includes Documentation Development♦ Includes Links to Meetings, Major Milestones and

Deliverables Sections♦ Contains the Documentation Section

Individual tasks for development process of each document

Page 20: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

20© 2007 MPA. All rights reserved.

Schedule Flow Tips3 Major Sections

Page 21: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

21© 2007 MPA. All rights reserved.

Schedule Flow TipsMeetings and Major Milestone Section – Major Milestones

Page 22: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

22© 2007 MPA. All rights reserved.

Schedule Flow TipsMajor Milestone Mapping

Task Grouping for Major Milestone Reporting• Server Design

♦ Server DesignServer Design - Preliminary DesignServer Design - Peer ReviewCritical Design Review (CDR) – Server Design» Server CDR with PMO

Critical Design Review (CDR) – Server Design CompleteServer Design - Develop CodeServer Design - Unit Testing

♦ Server Design Complete

Tasks in Red is linked to the Major Milestone Section task with the same names

Page 23: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

23© 2007 MPA. All rights reserved.

Schedule Flow TipsMajor Milestone Mapping

Page 24: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

24© 2007 MPA. All rights reserved.

Schedule Flow TipsMeetings and Major Milestone Section – Meetings

Task Grouping for Meeting Reporting• Meetings Reported as a Milestone

♦ Project Kick-Off Meeting – Listed in “Meetings” SectionProject Kick-Off Meeting

♦ Project Kick-Off Meeting Complete♦ Status Review Meetings with Customer – Depends Upon Frequency

In-Process Review (IPR) Complete♦ Other Review Meetings with Customer

Task in Red is linked to the Major Milestone Section task with the same name

Page 25: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

25© 2007 MPA. All rights reserved.

Schedule Flow TipsMeetings and Major Milestone Section – Meetings

Page 26: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

26© 2007 MPA. All rights reserved.

Schedule Flow TipsDeliverables Mapping – Internal (Non-Contractual)

Internal Deliverables (Non-Contractual)• This is feedback needed before a process or phase can

begin♦ In our example we need information about the Server Room

Back-up Power?Are additional power drops needed?Is room cooling capacity Sufficient?

♦ Other ItemsSigned Documentation Authorizing Asset PurchaseResource availabilityContractor Equipment Availability

♦ Internal Deliverable Task may only be a milestone task.Successor task(s) within the body of the schedule are linked to this milestone

Page 27: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

27© 2007 MPA. All rights reserved.

Schedule Flow TipsDeliverables Mapping – Internal (Non-Contractual)

Page 28: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

28© 2007 MPA. All rights reserved.

Schedule Flow TipsDeliverables Mapping – External (Contractual)

Recommended Documentation Task Flow• Functional Requirements Document (FRD)

♦ Draft FRD♦ Internal Review of Draft FRD♦ Incorporate Changes into Draft FRD and Prep for Submittal♦ Submit Draft FRD to PMO for Approval♦ Incorporate PMO Comments into Draft FRD♦ Internal Review of Final FRD and Prep for Final Submittal♦ Submit Final FRD to PMO for Approval♦ PMO Approves FRD

Tasks in Red are linked to the Deliverables Section – External (Contractual) tasks with the same names.

Page 29: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

29© 2007 MPA. All rights reserved.

Schedule Flow TipsDeliverables Mapping – External (Contractual)

Page 30: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

30© 2007 MPA. All rights reserved.

Schedule Flow TipsDeliverables Mapping – Internal (Non-Contractual) and

External (Contractual)

Page 31: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

31© 2007 MPA. All rights reserved.

Ready for Base Lining?

MS Project Data Entry Completion• Things to Double Check

♦ Calendars - Company Holidays and Vacation time (if known)♦ For each resource make sure you have the correct labor rates, other known

Non-Working times, or “Special” working hours (weekends, night or graveyard shifts, etc.).

♦ Add Material Costs and other ODC items to resource pool.• Here is what you know after base lining -

♦ The Actual Start and Dates are known♦ The Actual Project Cost (Planned Cost, BAC) is known

You have established the “Value” of each task as well as the overall project for EV.♦ Resource Requirements are defined

Hopefully a plan to deal with resource shortfalls and conflicts has been developed.

Next Steps• Stakeholder Final Review and Approval

♦ Resist those last minute attempts at scope creep

Final Step - Base Lining

Page 32: From Planning to Base Lining - MPUG - Microsoft Project ... Planning to Bas… · From Planning to Baseline ... • Is considered by some project managers as not “real” project

32© 2007 MPA. All rights reserved.

Questions!