From Feast or Famine

To Managing a Portfolio of Projects,

Estimating Capacity, and

Delivering On Time

Carolyn Caizzi, Dan Zellner, Jennifer B. Young

Northwestern University Libraries

Page 2: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Introduction

Page 3: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Northwestern University

Libraries

2

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 4: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

6.7 million volumes

3

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 5: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

24,757 linear feet of

archives & manuscripts

4

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 6: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

267TB of unique

digital content

5

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 7: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

1,969,281 visits from faculty,

students, and researchers

around the world

6

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 8: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

2,547,419 page views

on Library websites

7

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 9: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

345 staff

8

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Page 10: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

9

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

2014-

201515 new departments and new planning council

Page 11: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

10

Photo by: Gene Kannenberg, Jr.

https://flic.kr/p/HN3WFQ

Repository & Digital Curation

Department Mission Statement:

RDC creates, acquires, and archives digital objects for long-

term preservation and develops as well as deploys software

to support the discovery, access, and use of digital resources

by members of Northwestern University, scholarly

communities, and the public.

Page 12: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

11

Page 13: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

12

Page 14: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

13

Page 15: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

14

A L'Opéra by Vignola, A.

http://images.northwestern.edu/multiresimages/inu:dil-8ebd9638-64e9-48a6-9e5c-57fc5f8a92bb

Page 16: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

15

Page 17: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

16

Page 18: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Customers:

Faculty/Researchers and

Curators who represent them

17

Page 19: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

18

digital

collection

Hard Work

Page 20: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Digital Collection=Project

19

Page 21: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

The Problem/Opportunity

Page 22: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Digital Project Selection

Process and the Management

of Multiple Projects

Before Re-Structuring

21

Page 23: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

22

Digital Projects

Committee

Page 24: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Problems included:

● Few proposals

● Met sporadically

● Merit vote only

● Long timelines to go or no-go decision

● Bypassing committee

● First come first served prioritization

23

Page 25: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

24

Page 26: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Solution: The Points Process

Page 27: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

• Proactive project proposal gathering

• Determine capacity for 1 year

• Customers select projects based on

capacity

• Schedule projects for the year

Points Process Overview

26

Page 28: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Proposal Gathering

• One-on-one interview with Curators

• Coordination with other departments

• Estimate project time and follow up

27

Page 29: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

CapacityPoints = Hours

3 categories of points: Digitization, Metadata, Project Management

Capacity = The amount of hours we have to work on projects

Scheduled Projects = projects that are the result of curator

interviews. Distinctive Collections selects the projects that make

up our season.

Adhoc Projects = Unscheduled projects that come up during the

year. Work is done on these as time allows and depending on

priority.

60% of our capacity is committed to Scheduled Projects

40% of our capacity is committed to Adhoc Projects

Page 30: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

29

Formula for Staff Capacity

Capacity calculation for staff members are

based on working hours for a year

37.5 hours * 52 weeks - (15 vacation days +15

sick days +10 holidays per year) = 1650 hours

per year

Total hours at 80% efficiency = 1320 hours Source: T. Grafakos

Page 31: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

The Project Cycle

Spring Quarter

February - May

Close out projects from last cycle

Presentation to curators and staff

Plan for next season / capacity

List of projects for new cycle

Create schedule - quarterly meetings

Summer Quarter

June - August

Project work (especially high priority ones)

Fall Quarter

September -

November

Project work

Winter Quarter

December -

February

Wrap up project work and begin close out

Curator interviews in February

The Schedule: AKA Project Cycle

Page 32: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Research

31

Preservation

Department

Outside the Organization

Emory University

Inside the Organization

Page 33: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Analysis

32

● Best elements of research

● Existing frameworks

● Existing processes

Page 34: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Implementation

Page 35: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Requirements

34

● Budgeting

● Time Tracking system

● Reporting

Page 36: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Next Steps

35

● Organizational Assessment

● Process Documentation

● Roll Out

Page 37: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Assessment

36

● Customers

● Team

● Stakeholders

Page 38: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Retrospective

Page 39: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Benefits

38

More predictable workflow

Page 40: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Benefits

39

Page 41: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Benefits

40

Community of trust

Page 42: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Benefits

41

Better idea of capacity

Page 43: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

42

Benefits

Page 44: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Benefits

43

We Will

For Discovery and Creativity

Engage Locally and Globally

Page 45: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Lessons Learned

44

Be iterative

Assess regularly

Phasing multi-year projects

Page 46: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Challenges

45

Position vacancies

Adapting to change

Project management tools

Follow up follow up follow up

Page 47: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Summary

Problem: project selection done by

committee leading to unpredictable

workloads

Solution fostered by Libraries’ re-

organization: process to determine a

portfolio of projects for a yearly cycle

based on capacity

Page 48: From Feast or Famine - Northwestern University...From Feast or Famine To Managing a Portfolio of Projects, Estimating Capacity, and Delivering On Time Carolyn Caizzi, Dan Zellner,

Thank You!

Questions & Comments Welcome!