Activity Name Duration (Days) Start Date Finish
Date Project Manager7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
May 17 Jun 17 Jul 17 Aug 17
7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
Residence Halls 108.00 5/8/17 8/23/17
Residence Halls Close 11AM 0.00 5/8/17 5/8/17
Ben Franklin South 48.00 6/19/17 8/5/17CTY Staff 48.00 6/19/17 8/5/17 6/19/17 8/5/17
CTY session 1 students 21.00 6/25/17 7/15/17 6/25/17 7/15/17
CTY session 2 students 21.00 7/16/17 8/5/17 7/16/17 8/5/17
Ben Franklin North 58.00 6/9/17 8/5/17Camp / Group 4.00 6/9/17 6/12/17 6/9/17 6/12/17
CTY Staff 48.00 6/19/17 8/5/17 6/19/17 8/5/17
CTY session 1 students 21.00 6/25/17 7/15/17 6/25/17 7/15/17
CTY session 2 students 21.00 7/16/17 8/5/17 7/16/17 8/5/17
Buchanan 90.00 5/8/17 8/5/17Install new Elevator 82.00 5/8/17 7/28/17 Sheldon Wenger
Replace hallway carpet (G,1,2,3) 12.00 5/15/17 5/26/17 Sheldon Wenger
Camp / Group 7.00 6/11/17 6/17/17 6/11/17 6/17/17
Camp / Group 4.00 6/22/17 6/25/17 6/22/17 6/25/17
Camp / Group 5.00 6/28/17 7/2/17 6/28/17 7/2/17Important DatesMay 13: CommencementMay 27: All Campus Power Shut DownAugust 14: Early Arrival Begins
Camp / Group 3.00 7/10/17 7/12/17 7/10/17 7/12/17
Camp / Group 3.00 7/14/17 7/16/17 7/14/17 7/16/17
Camp / Group 14.00 7/23/17 8/5/17 7/23/17 8/5/17
Dietz 67.00 6/18/17 8/23/17 Sheldon Wenger
Wireless Network Upgrade 6.00 8/18/17 8/23/17 Alan Sutter
Camp / Group 7.00 6/18/17 6/24/17 6/18/17 6/24/17
Camp / Group 5.00 6/28/17 7/2/17 6/28/17 7/2/17
Camp / Group 28.00 7/9/17 8/5/17 7/9/17 8/5/17
Marshall 82.00 5/8/17 7/28/17 Sheldon Wenger
Install new Elevator 82.00 5/8/17 7/28/17
Wireless Network Upgrade 33.00 5/8/17 6/9/17 Alan Sutter
Camp / Group 17.88 6/11/17 6/28/17 6/11/17 6/28/17
Camp / Group 27.88 7/1/17 7/28/17 7/1/17 7/28/17
New College House 63.00 6/5/17 8/6/17Wireless Network Upgrade 5.00 6/5/17 6/9/17 Alan Sutter
Camp / Group 8.00 6/11/17 6/18/17 6/11/17 6/18/17
CTY Admin Staff 49.00 6/19/17 8/6/17 6/19/17 8/6/17
CTY Staff 45.00 6/21/17 8/4/17 6/21/17 8/4/17
Phi Kappa Psi 89.00 5/15/17 8/11/17Roof repairs 60.75 6/1/17 7/31/17 Bill Stark
Fire Alarm Upgrade 89.00 5/15/17 8/11/17 Dick Denlinger
Porch repairs 61.00 6/1/17 7/31/17 Bill Stark
Residence Halls - annual painting 58.00 6/15/17 8/11/17 Bill Stark
Schnader 84.00 5/8/17 7/30/17 Sheldon Wenger
Create 4 Gender Neutral Bathrooms 46.00 5/8/17 6/22/17
Install new Elevator 82.00 5/8/17 7/28/17
Camp / Group 8.00 6/4/17 6/11/17 6/4/17 6/11/17
Camp / Group 14.00 6/18/17 7/1/17 6/18/17 7/1/17
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Tuesday, April 18, 2017Page 1 of 4
Franklin and Marshall CollegeSummer 2017 Master Schedule of Project Work
and Residence Hall Occupation
Jonathan EnosCapital Projects Manager
Activity Name Duration (Days) Start Date Finish
Date Project Manager7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
May 17 Jun 17 Jul 17 Aug 17
7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
Camp / Group 2.88 7/16/17 7/18/17 7/16/17 7/18/17
Camp / Group 3.88 7/24/17 7/27/17 7/24/17 7/27/17
Camp / Group 4.00 7/27/17 7/30/17 7/27/17 7/30/17
Thomas 96.00 5/8/17 8/11/17 Jon Enos
complete renovation, including redesigned bathrooms, lounges and HVAC unit and infrastructure replacement
95.75 5/8/17 8/11/17
Fire Alarm Upgrade 96.00 5/8/17 8/11/17 Perry Scheid
Wireless Network Upgrade 50.00 6/12/17 7/31/17 Alan Sutter
Weis 102.00 5/8/17 8/17/17Create 3 Gender Neutral Bathrooms 46.00 5/8/17 6/22/17 Sheldon Wenger
Remove carpet/Install LVT in student rooms 46.00 5/8/17 6/22/17 Sheldon Wenger
Replace Electric cables 46.00 5/8/17 6/22/17 Pat Henry
Replace ceilings in bathrooms 46.00 5/8/17 6/22/17 Bill Stark
Shades for Great Room 18.00 5/15/17 6/1/17 Bill Stark
Wireless Network Upgrade (east) 24.00 5/8/17 5/31/17 Alan Sutter
Wireless Network Upgrade (west) 11.00 8/7/17 8/17/17 Alan Sutter
CTY Staff 48.00 6/19/17 8/5/17 6/19/17 8/5/17
CTY session 1 students 21.00 6/25/17 7/15/17 6/25/17 7/15/17
CTY session 2 students 21.00 7/16/17 8/5/17 7/16/17 8/5/17
Academic Buildings 222.00 1/3/17 8/12/17Barshinger Musical Arts 148.00 2/20/17 7/17/17 Bill Stark
Slate roof repairs 40.00 2/20/17 3/31/17
Paint lower portion of the cupola 64.00 5/15/17 7/17/17 Bill Stark
Barshinger LSP 33.00 5/15/17 6/16/17Selected rooms lighting 33.00 5/15/17 6/16/17 Pat Henry
Paint hallways, replace doorframe (basement, 1st floor)
19.00 5/15/17 6/2/17 Bill Stark
Important DatesMay 13: CommencementMay 27: All Campus Power Shut DownAugust 14: Early Arrival Begins
Hackman 61.00 5/15/17 7/14/17Upgrade classroom 131 and lighting in classroom 111
61.00 5/15/17 7/14/17 Bill Stark, Dick Denliger, Pat Henry
Joseph International Center 122.00 3/15/17 7/14/17Painting 61.00 5/15/17 7/14/17 Sheldon Wenger
Replace house trap 17.00 3/15/17 3/31/17 Don Yohe
Kauffman 54.00 5/15/17 7/7/17Selected rooms lighting, fan coil units 54.00 5/15/17 7/7/17 Don Yohe
Martin Library of the Sciences 54.00 5/15/17 7/7/17PA system 54.00 5/15/17 7/7/17
Shadek-Fackenthal Library 47.00 5/15/17 6/30/17Repair and replace glass on stair tower 19.00 5/15/17 6/2/17 Bill Stark
2nd floor classroom upgrade 46.00 5/16/17 6/30/17 John Coccia
PA system
Stager 153.00 3/13/17 8/12/17Attic Access 5.00 3/13/17 3/17/17 Bill Stark
Electrical Upgrade (new generator) 90.00 5/15/17 8/12/17 Dick Denlinger
Exterior painting 46.00 5/16/17 6/30/17 Sheldon Wenger
Classroom upgrades (215, 216, 217, 219) 46.00 5/16/17 6/30/17 Sheldon Wenger
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
Tuesday, April 18, 2017Page 2 of 4
Franklin and Marshall CollegeSummer 2017 Master Schedule of Project Work
and Residence Hall Occupation
Jonathan EnosCapital Projects Manager
Activity Name Duration (Days) Start Date Finish
Date Project Manager7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
May 17 Jun 17 Jul 17 Aug 17
7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
TV Studio conversion (Lightboard Studio) 40.88 3/22/17 5/1/17 Bill Stark
Film Media Service / Classroom
Writer's House 172.00 1/3/17 6/23/17Interior painting - phase 1 25.00 1/3/17 1/27/17 Sheldon Wenger
Interior painting - phase 2 40.00 5/15/17 6/23/17 Sheldon Wenger
Athletics 186.75 2/6/17 8/11/17ASFC 55.88 6/6/17 7/31/17
Tile around pool 55.88 6/6/17 7/31/17 Don Yohe
Mayser 186.75 2/6/17 8/11/17HVAC Roof Unit replacement 40.00 2/6/17 3/17/17 Don Yohe
Replace Roof G 9.00 7/24/17 8/1/17 Bill Stark
Replace Roof H 9.88 7/18/17 7/27/17 Bill Stark
Replace Roof K & L 68.00 5/15/17 7/21/17
Replace exit doors at dance studio 57.75 6/15/17 8/11/17 Bill Stark
Core Campus 852.00 5/3/15 8/31/17Central Services 16.88 5/15/17 6/1/17
Commercial washer & dryer 16.88 5/15/17 6/1/17 Don Yohe
Ben's Dining 47.00 5/15/17 6/30/17 Bill Stark
E-Temp 46.00 5/15/17 6/29/17 Nic Auwaerter Important DatesMay 13: CommencementMay 27: All Campus Power Shut DownAugust 14: Early Arrival Begins
Equipment Upgrades 47.00 5/15/17 6/30/17 Perry Schied
Grease Trap replacement 14.88 5/17/17 5/31/17 Don Yohe
Distler - Zime 772.00 5/3/15 6/12/17
Brick repairs 29.00 5/15/17 6/12/17 Bill Stark
Window repairs 15.00 5/15/17 5/29/17 Bill Stark
Replace Trash enclosure 1.00 5/3/15 5/3/15
Business Office 93.00 5/15/17 8/15/17Replace back doors 93.00 5/15/17 8/15/17 Bill Stark
College Square 224.88 12/5/16 7/17/17Lighting replacement hallways, offices 63.88 5/15/17 7/17/17 Pat Henry
Heat Pump replacement 57.00 5/15/17 7/10/17 Don Yohe
Advancement phase 2 75.00 12/5/16 2/17/17 Sheldon Wenger
Disability Services 71.00 3/6/17 5/15/17 Sheldon Wenger
Old Main 96.00 5/15/17 8/18/17President's Office 96.00 5/15/17 8/18/17 Sheldon Wenger
Steinman College Center 839.00 5/3/15 8/18/17Gender Neutral Bathrooms 96.00 5/15/17 8/18/17 Sheldon Wenger
Mail Room access window 29.00 5/17/17 6/14/17 Bill Stark
Replace floor of freight elevator 1.00 5/3/15 5/3/15 Bill Stark
LED lighting 47.00 6/6/17 7/22/17Campus-wide conversion schedule 47.00 6/6/17 7/22/17 Dick Denlinger
Window Cleaning 151.00 4/3/17 8/31/17across campus 151.00 4/3/17 8/31/17 Bill Stark
Grounds 56.00 6/5/17 7/30/17Trash enclosures 30.00 6/5/17 7/4/17
Distler, TBD 30.00 6/5/17 7/4/17 Bill Stark
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
Tuesday, April 18, 2017Page 3 of 4
Franklin and Marshall CollegeSummer 2017 Master Schedule of Project Work
and Residence Hall Occupation
Jonathan EnosCapital Projects Manager
Activity Name Duration (Days) Start Date Finish
Date Project Manager7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
May 17 Jun 17 Jul 17 Aug 17
7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
Parking Lots 30.00 7/1/17 7/30/17TBD lots and sidewalks 30.00 7/1/17 7/30/17 Ted Schmid
Rental Properties 424.88 5/2/16 6/30/17758 Pine St 29.88 6/1/17 6/30/17
Replace boiler 29.88 6/1/17 6/30/17 Don Yohe
College Ave Admin Office 95.88 5/2/16 8/5/16upgrade oil units to gas 95.88 5/2/16 8/5/16 Don Yohe
Other Properties 123.88 4/30/17 8/31/17President's Residence 123.88 4/30/17 8/31/17 Don Yohe
Replace boiler and building-wide AC system 123.88 4/30/17 8/31/17
Provost's Residence 29.88 6/1/17 6/30/17 Don Yohe
Replace boiler and hot water heater 29.88 6/1/17 6/30/17
Harbaugh House 88.88 5/15/17 8/11/17 Dick Denlinger
Replace Fire Alarm system 88.88 5/15/17 8/11/17
134
135
136
137
138
139
140
141
142
143
144
145
146
147
Tuesday, April 18, 2017Page 4 of 4
Franklin and Marshall CollegeSummer 2017 Master Schedule of Project Work
and Residence Hall Occupation
Jonathan EnosCapital Projects Manager