John R. Kasich, Jerry Wray,

Ohio Governor ODOT Director

FRA-71-9.62/9.71Project Matchmaker Event

Brian Hupp, P.E., District Construction Engineer

April 18, 2017

To provide easy movement of

people and goods from place

to place, we will:__________________________________

Take care of what we have;_________________________________

Make our system work better;_________________________________

Improve safety;_________________________________

Enhance capacity.

ODOT’S M ISSION

3

• Eight Counties

• 4,921 miles of roads

• 1,557 Bridges

• 16 Garages/Outposts

• Operating Budget

approx. $52 million

• CAPITAL PROGRAM

• 83 Construction Projects

• 390 Million Dollars

District 6

John R. Kasich, Jerry Wray,

Ohio Governor ODOT Director

Steve Fellenger, P.E. ,Project Manager

Jeff Holbrook, P.E. ,Construction Area Engineer

Andrew Opsitnik, P.E. ,Construction Project Engineer

FRA-71-9.62/9.71 Project Matchmaker

5

PROJ. NO. 170393FRA-71-9.62/9.71PID 104799

Project Location

FRA-71-9.62/9.71 Project Matchmaker

6

Project Overview

• Purpose: Major Rehabilitation of Pavement. Additional Lane Along I-71 in Both Directions from Stringtown Rd. to 70/71/315 Interchange.

ESTIMATED COST$113 Million

FRA-71-9.62/9.71 Project Matchmaker

7

Project Overview

• Perform full depth pavement replacement

• Construction of additional lane in the median, in both directions

• Rehabilitate and widen Three (3) pair of mainline structures and Replace Three (3) other structures

• One (1) new Structure

• Construct two (2) noise barriers

• Floodwall work near Greenlawn Interchange

• Upgrade all highway safety features including guardrail, drainage, lighting, and signs.

WORK INCLUDES:

FRA-71-9.62/9.71 Project Matchmaker

8

Schedule

• Sale Date:06/29/17

• Award Date: 07/10/17

• Construction Start: 08/14/17

• Construction End: 06/30/20

FRA-71-9.62/9.71 Project Matchmaker

9

Construction Work Types

Construction Work TypesCode Description Code Description

1 Clearing and Grubbing 29 Structure Repairs

4 Roadway Excavation & Embankment Construction 34 Earth Retaining Structures

7 Soil Stabilization 35 Drainage (culverts, misc)

8 Temporary Soil Erosion & Sediment Control 36 Guardrail/Attenuators

9 Aggregate Bases 37 Fence

10 Flexible Paving 38 Misc Concrete

12 Rigid Paving 39 Maintenance of Traffic

13 Pavement Planing, Milling, Scarification 40 Waterproofing

15 Sawing 41 Raised Pavement Markers

16 Flexible Replacement 42 Signing

19 Structure Removal 43 Highway Lighting

20 Level 1 Bridge 44 Traffic Signals - Standard

21 Level 2 Bridge 45 Pavement Markings

23 Reinforcing Steel 46 Landscaping

24 Structural Steel Erection 51 Micro Tunneling

25 Stud Welding 53 Piling

26 Structural Steel Painting 55 & 56 Fiber Optic Cable Installation, Splicing, Termination and Testing

27 Expansion & Contraction Joints, Joint Sealers, Bearing Devices 57 Sealing of Concrete Surfaces with Epoxy or Non-Epoxy Sealers

10

Roadway & Pavement Work Type

• 304 Aggregate Base: 91,000 CY

• 302 Asphalt: 132,000 CY

• 442 Inter. Asphalt: 24,000 CY

• 442 & 806 Surface Asphalt: 20,000 CY

• 452 Concrete Pavement: 31,000 CY

Roadway & Pavement WorkEstimated Cost $39.6 M

FRA-71-9.62/9.71 Project Matchmaker

11

Structures Work Type

• Deck replacement and widening: 3 pairs of mainline bridges

• Replace 3 Structures

• WB I-270 to SB I-71 – Ramp B – New Structure

Structures WorkEstimated Cost $31 M

FRA-71-9.62/9.71 Project Matchmaker

12

Maintenance of Traffic Work Type

• 614 Work Zone and Crossover Lighting

• 615 Temporary Pavement: 130,000 SY

• 622 Port. Concrete Barrier: 273,000 LF

Maintenance of Traffic WorkEstimated Cost $12.6 M

FRA-71-9.62/9.71 Project Matchmaker

13

Drainage Work Type

• 605 Underdrains: 310,000 LF

• Misc. 8 in. to 42 in. drainage conduit: 23,000 FT

Drainage WorkEstimated Cost $9.5 M

FRA-71-9.62/9.71 Project Matchmaker

14

Retaining Walls, Noise Barriers and Floodwall Work Types

• Retaining walls

• Noise Barriers west side of I-71 near White Road and Dyer Road

• US Army Corps of Engineers 408 Floodwall

Retaining Walls, Noise Barriers and Floodwall WorkEstimated Cost $5.6 M

FRA-71-9.62/9.71 Project Matchmaker

15

Traffic Control, Lighting & Traffic Surveillance Work Types

• Misc. overhead and ground mounted signs

• LED high mast and low mast lighting

• 804 Fiber Optic cable

Traffic Control, Lighting & Traffic Surveillance Work

Estimated Cost $4.8 M

FRA-71-9.62/9.71 Project Matchmaker

16

Disadvantage Business

Enterprise (DBE)

DBE Goal 11%

• Contains the Proposal Note 013 - Disadvantaged Business Enterprise (DBE) Utilization Plan and Good Faith Efforts, updated 01/20/2017

• All bidders shall submit a DBE Utilization Plan at the time of bid, setting forth specific information demonstrating how the bidder will achieve the DBE goal.

• DBE Certified Firms: