forth replacement crossing report on the · pdf fileforth replacement crossing . report on the...
TRANSCRIPT
FORTH REPLACEMENT CROSSING
REPORT ON THE SUSTAINED/HIGH INTENSITY RAINFALL EVENTS IN THE QUEENSFERRY AREA DURING
JUNE/JULY / AUGUST 2012 AND THE RELEVANT WORKS UNDERTAKEN BY THE FORTH REPLACEMENT CROSSING
PROJECT
INDEX
1. INTRODUCTION 2. OVERVIEW 3. CONCLUSION
ANNEX A: Scotland Rainfall (mm)Areal series Met Office Overview from hyperlink ANNEX B: Photographs
August 2012
2
1. INTRODUCTION This report has been compiled following an investigation into the flooding incident of 18 July 2012 after heavy rainfall in Queensferry and much of eastern central Scotland which occurred during a month when there was reportedly twice the monthly average rainfall for July(1) (see annex A)
2. OVERVIEW To summarise the chain of events leading up to flooding issues on roads within and adjacent to the site in the Queensferry area – see below:
(See attached photographs Annex B for locational references) HISTORICAL ISSUES TO OCTOBER – DECEMBER 2011 B924/A904/U221 Water flooding was evident on the B924 adjacent to Echline and also at the bottom of the U221 at the connection with the A904 in periods of prolonged and heavy rain. During tender City of Edinburgh Council (CEC) stated that they were aware of a historical water problem inthe area of the A904/U221/B924 junction in relation to flooding. Society Road During periods of heavy rain, water was previously seen discharging over and through the existing retaining wall adjacent to Inchgarvie Lodge. Again, local residents have stated that this is a historical problem. Transport Scotland as landowners of Echline Fields carried out investigation works in this area some years ago and repaired damage to the field drainage caused by other works. Echline Field adjacent to Springfield Ponding water gathered in the field area to the rear of properties at Springfield in periods of heavy rain. This also occurred in the summer of 2011 but to a lesser extent. The natural ground level forms a bowl and the existing field drainage did not cope during prolonged rain periods. This condition was recognised by the project and is catered for in the permanent works design though the installation of a new drain – an operation which was partially completed in spring 2012 and was stopped due to conflict with High Voltage utility diversion works and the effects of weather. This was completed shortly after the diversions during the working day of 18th of July 2012.
August 2012
3(1)http://www.metoffice.gov.uk/climate/uk/2012/july.html. See Annex A
RECENT ISSUES MAY – AUGUST 2012 May - June 2012 FCBC Temporary Works for earthworks operations were undertaken as follows: • A temporary lagoon at Echline Field was created (12/05/2012) to provide some attenuation adjacent to the area of the excavation • The recently installed permanent field drainage in Echline Fields adjacent to Springfield was connected temporarily (15/06/12) into an existing outfall pipe. 21 and 22 June 2012 On the 21 and 22 June 2012 after one of the wettest Junes on record(2), again, flooding was evident in each of the four locations noted above i.e. Society Road, Echline Fields, A904/ B924 Junction (Builyeon Road)and U221. Initial mitigation works undertaken were: • At the bottom north corner of Echline Fields adjacent to Inchgarvie Lodge, silt fencing and straw bales were installed to reduce the potential for siltation (22/06/2012) and to provide some retention • In the west field adjacent to the junction of the U221 with the A904, temporary drainage ditches channelling to a temporary sump were constructed (03/07/2012) to assist with retention. 4 July 2012 On the 4 July 2012 flooding was evident in each of the four locations below i.e. Society Road (Inchgarvie area), Echline Fields, A904/ B924 Junction (Builyeon Road) and U221. Further Works Undertaken were: • Drainage ditches and the temporary sump, as described above, were filled in because the large volume of water was running straight through rendering them ineffective. • Temporary containment measures were installed inthe north east corner of the west field adjacent to the junction of the U221 and A904 (06/07/12) 7 July 2012 During further rain FCBC assisted with combating flooding on the A904 with further temporary measures put into place after a site meeting with CEC. These additional measures were:
• A concealed chamber and outfall was discovered at the north east corner of the west field adjacent to the junction of the U221 and the A904. Water was channelled to this chamber through temporary straw bales.
August 2012
4(2)http://www.metoffice.gov.uk/climate/uk/2012/june/averages.html http://www.metoffice.gov.uk/climate/uk/datasets/Rainfall/ranked/Scotland.txt. See Annex A
Following the meeting with CEC a number of further measures were agreed to be implemented at the earliest practicable opportunity:
• An additional temporary drainage crossing under the A904. Installation -11/07/2012 – 12/07/2012
• Installation of the section of permanent outfall under Society Road on 11/07/2012 – 12/07/2012
• Improvements to the bunding in the north east corner of the west field adjacent to the junction of the U221 and the A904 on 17/07/2012
• Completion of field drain (permanent works) at the east side of Echline Fields adjacent to the properties at Springfield on 18/07/12
The following measures were also implemented:
• Debris was cleared from Society Road and the existing outlets in the vicinity of Linn Mill Burn Bridge were unblocked.
18 July 2012 Heavy rain throughout the day, the intensity of which increased in the afternoon, resulted in flooding at all of the locations noted above, including a long section of the A904 between the A90 and the B924 and throughout the wider area in Fife and West Lothian. The accumulated water in the low area of the B924 threatened some houses in Springfield and entered small number of others. Road brush and bowser units were deployed to draw water from the junction of the U221 and A904. Gullies were also cleaned at the corner of the U221/A904. FCBC utilised the plant they had available on site and this was deployed until the increasing volume of water rendered them ineffective. The soil covering was removed during the working day from the top of the recently installed permanent drain in the field adjacent to Springfield to expose the stone filter media and thus accelerate the removal of the exceptional volume of surface water which had built up in that area. It was noted in the late morning that the gullies on the B924 were ‘bubbling’ up and not coping with the volume of water. At the junction of the U221 and A904 the temporary bund was successfully guiding surface water into the previously concealed chamber and associated outfall. As the rainfall intensity increased in the afternoon, parts of Queensferry and the locality became overwhelmed by the volume of water and existing drainage systems failed to cope. As a consequence of these exceptional conditions no further water could discharge into the previously concealed chamber and the volume of water was such that water began to flow over the bund. It is important to clarify that the bund did not burst but it did leak and over-top due to the volume of water.
August 2012
5
August 2012
6
In the early evening, CEC and the emergency services attended to a low lying section of the B924 where flood waters had accumulated, the B924 being closed at its junction with Springfield Crescent. At approximately 18:45 FCBC were asked by the police to attend the site to assist in clearing the ‘muddy’ water on the A904. At about 21:40, the rain had stopped and all the gullies were coping with the surface water flows, and the council were in the process of removing their water pump and hoses from the low lying section of the B924. 6 August 2012 On the 6 August 2012 further intense rainfall occurred in the morning and early evening which caused water flows onto the A904. This provided a good test to the drainage mitigation developed and now installed. However, following the above event, the mitigation is being reviewed and further measures to improve resilience are being implemented. Although the water flows above were minor, further larger pumps are being provided for future control. Further investigation of the existing road drainage system has been undertaken and a better understanding of the drainage flows in the area has been gained.
3. CONCLUSION It is believed that the recent problems of flooding in the Queensferry area have resulted from the following key factors:
• Lengthy periods of rain throughout June and July resulting in saturated ground conditions causing any rainfall to discharge as run-off sooner than would normally occur.
• Exceptionally intense(42.8 mm)follow-on rainfall experienced on the afternoon of 18 July 2012.
• Existing road drainage system failing to cope with the exceptional water flow.
Notwithstanding the above and in the interests of helping to minimise the effects of any future similar rainfall event the project has put in place additional mitigation measures which are the subject of a separate action plan (Action Plan to Mitigate Against Flood Risk for Sustained/High Intensity Rainfall Events in the Queensferry Area.)
ANNEX A
Scotland Rainfall (mm).Areal series, starting from 1910. Values are ranked and displayed to 1 dp. Where values are equal, rankings are based in order of year descending. Data are provisional from January 2012 & Winter 2011/12. Last updated 01/08/2012. It can be seen that for June the 2012 rainfall is ranked 7th in 131 years. Average is 84mm. For July the ranking is 20th in 131 years with an average of 101mm
JUN Year JUL Year JUN Year JUL Year
Max Value 155 1938 185.6 1940 72.8 1989 88.3 1991
137.9 2002 181.4 1988 71.5 1993 88 1992
137.8 1948 170.1 1939 71.2 1976 85.4 1926
137.7 1931 165.8 2010 70.8 2009 85 1995
135 1966 162.9 1956 70.6 1967 84.8 1981
131.7 2004 159.9 1985 70.4 1955 84.4 1997
130.4 1980 158 1953 67.3 1971 83.8 1986
129.4 2012 154.6 2009 67.3 1970 83.4 1999
126.6 1928 150.9 1957 67 1968 83.3 1952
125.1 1912 150.5 1946 66.2 1933 83.1 1969
123.5 1927 149.9 1936 66 1974 81.7 1978
122.8 1990 145 1938 64.9 1977 80.8 2003
116.7 1944 144.7 1998 64.3 1996 80.6 1973
115.1 1991 144 1924 64 1939 80.5 1912
114.4 1919 143.3 1959 64 1923 77.6 1971
114 1965 143.2 1970 63.8 1953 77.2 1963
113.5 1945 141.9 1918 63.3 1984 76.3 2004
112.8 1972 139.7 1950 63.2 1975 76.3 1996
111.9 1999 134.5 2007 62.7 1951 75.2 1944
111.3 1935 133.5 1931 62.2 1978 74.6 1925
110.1 1946 127.7 2012 62 1918 74.3 1962
109.4 2007 127.2 1915 61.4 1934 71.4 1990
109.2 1947 126.8 2002 58.9 1986 71 2006
108.5 1998 125.6 1932 58.3 1942 70.9 1935
107.4 1994 121.5 1937 57 1910 67.7 1966
107.2 1954 121.1 1923 53.5 1982 67 1949
106.9 2008 120.9 1958 52.8 1936 64.6 1994
104.9 2005 118 1910 49.8 1920 63.7 1976
102.2 1913 117.2 1951 47.6 1914 59.8 1977
101.1 1943 115.4 1922 44.5 1949 55.4 1972
100.1 2011 114.3 1916 41.6 1915 54.7 1917
95.5 1952 113.9 1980 41 1995 51.7 1984
94.6 1981 113.8 1934 39.8 2010 51.5 2000
94.5 1997 113.5 1961 39.1 1992 49.4 1982
93.5 1959 112.9 1942 38.8 1940 49.2 2005
92.8 1987 110.4 1933 36.9 1932 47.8 1989
91.1 1973 110.1 1993 33.2 1921 45.8 1983
91 1950 109.1 1948 32.8 1925 39.7 1919
89.8 1917 109 1920 30.9 1941 33.7 1955
89.4 1956 108.1 1929 Min. Value 30.1 1988 32.7 1913
August 2012
7
89.2 1963 107.2 2008 Avg 83.47 101.39
88.1 2001 106.3 1954 87.9 1929 105.6 1987 87.8 1916 105.3 1947 86.9 1924 104.5 1965 86.6 1926 104.4 1941 85.5 1930 104.4 1921
Avg. YEAR 82.5 1911 102 1974 82.3 1962 101.7 1975 81.3 1964 101.5 1927 80.5 1937 100.9 1979 79.2 1985 100.2 2001 79.2 1969 99.9 2011 78.7 1958 99.2 1960 76.2 1961 99 1928 76 2003 98.9 1968 75.7 2006 98.4 1967 75.5 1960 95 1964 75.4 1957 94.8 1945 75.3 1983 93.7 1914 74.3 1922 92.2 1911 74.1 1979 90.3 1930 74 2000 90 1943
August 2012
8
August 2012
9
August 2012
10
August 2012
11
August 2012
12
August 2012
13
August 2012
14
August 2012
15
August 2012
16
ANNEX B AERIAL PHOTOGRAPHS
INDICATION OF GROUND WATER FLOW AROUND A904/U221
New U221 New A904
A904
Previously concealed chamber& outfall
U221
Temporary Drain
Crossing
B924
Route of New Connecting Road
Topographical Low Area
August 2012
17
August 2012
18
Excavation south launch
area Temp Sump
ExcavationSP8/ 9
Water removed by completion of permanent
works drain
South site compound
Temp Drain Crossing
AERIAL VIEW ECHLINE FIELD MAP SITUATION
U/G CO/H C
Detention Basins
AERIAL VIEW ECHLINE FIELD SHOWING APPROXIMATE RELATIVE POSITIONS OF ORIGINAL OVERHEAD CABLES
(O/H C), REPLACEMENT UNDERGROUND CABLES; (U/G C) AND PROPOSED DETENTION BASINS