Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April 2008 Deputy Director Martin Bech, UNI•C [email protected]

Upload: joseph-barton

Post on 27-Mar-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnettet (FSKnet) optical network upgrade

Status for the infrastructure upgrade process April 2008.

Nordunet Conference 2008 in Espoo 11th April 2008Deputy Director Martin Bech, UNI•C

[email protected]

Page 2: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 3: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 4: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

September 2005

letter to the Ministry:

We have seen the

future – and it needs

more bandwidth!

Page 5: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

January 2007:

The actual application

Page 6: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Great help from Tony

Breach, NORDUnet:

Compiling the budget

Page 7: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

April 2007:

We got t

he money –

but that’s

just w

here

the w

ork sta

rts…

Page 8: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

What do we need in Denmark?

Our own optical infrastructure10Gbps production networkλ-connections for research projects (nationally and internationally)λ-connections for separate parts of one institutionHopefully user-controlled λ-network provisioning (in a few years)

Page 9: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 10: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Wavelengths for the production service

SDU-1

SDU-2

AU-1

AU-2

AAU-1

AAU-2

DTU UNI-C

Ørestad

SDU

AU

AAU

Ørestad

DTU

Page 11: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Is there any research in Denmark requiring λ-networking at all?

Page 12: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 13: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 14: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

The User Community

University reform in 2006/07 reducing 25 institutions to 10But this left ”all” Universities with buildings in ”all” citiesOther research institutions than UniversitiesPotentially 120 addresses More than 100.000 prople have Forskningsnettet as their daily Internet supplier

Page 15: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 16: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 17: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

University of Aarhus:

23 locations

Page 18: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

First step:Call for tender for WAN connections

Framework contracts with multiple vendors for:Dark Fibre for the National Ring infrastructureDark Fibre for Access ConnectionsTransmission capacity (100Mbps, 1Gbps, 10Gbps, 40Gbps, …)

The actual procurement is done in a ”mini-competition” among suppliers qualified in the framework contracts

Page 19: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

31st August 2007: Tenders for framework contracts for WAN connections

Page 20: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Contracts with the WAN suppliersFibre for the National Ring

Fibre for access connections

Transmission capacity (100Mbps etc)

Global Connect X X X

Telia X X X

Nianet X X X

TDC

Broadcom X

SEAS-NVE (Sjælland)

X

FON (Fyn) X

Østkraft (Bornholm)

X

Page 21: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

2nd step:Mini-competition for the National Ring

Among the 3 suppliers on the framework contracts (GC, Telia, Nianet)Evaluation criteria favoring the shortest possible distanceContract entered with Global Connect A/S in December 2007

Page 22: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Page 23: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

The acquired fibre ring1154km length8 OADM sites11 ILA sitesDistance between any part of two fibre sections/spans: >5mAttenuation <0.2dB/km @1550nmPMD < 0.2 ps/√km (currently a problem)

Delivery not yet completed!Nevertheless, the fibre ring measurements are a preprequsite for the equipment tender

Page 24: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

3rd step:Pre-qualification for DWDM equipment

suppliersAnnounced 8th February 2008≥40 x 10Gbps platformEoI due 11th March 2008

Page 25: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

A lot of interest…

Page 26: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Suppliers selected for the closed call for tender for DWDM equipment

NortelAlcatel-LucentCienaNokiaSiemensConscia (Cisco)

Selected on the basis of references, technical abilities, R&D efforts and financial capacity- but not on actual prices

Page 27: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

4th step: RFQ and Tender

1200 km without regenerationExpandable and upgradable platformOption for a Metro solutionGreat help from local people as well asJanne Kanner from Funet,Afrodite Sevasti, GRNET and theTERENA community in generalIssued 28th March 2008Deadline 8th May 2008

Page 28: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

5th step: Negotiation process

In May and June 2008Reducing the number of suppliers from 5 to 2 and ultimately to 1Contract signing envisaged on 7th July 2008

Page 29: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

6th step: Delivery and commissioning

Delivery starts with some documentation in July

and ends withAcceptance test is to be passed on 15th October 2008Commissioning test to be passed in November 2008.

Page 30: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

7th step: Launch Event

At the Forskningsnet conference in Kolding on the 11th November 2008You are all invited!

Page 31: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

8th step: Operation and enjoyment

Bringing Lambdas into DenmarkParticipating in user-controlled Lambda provisioning initiativesOperations in cooperation with NORDUnet/NUNOC (hopefully)

Page 32: Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April

Forskningsnet konferencen 2007

Lessons learned (so far)

Twisting EU tendering rules to allow for a negotiation process becomes increasingly difficultYou have to do a fair bit of marketing towards the vendorsPMD values below 0.2 ps/√km are not trivial in the real world.