Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update Progress Report #54 Page 1 of 9 Kalamazoo River Study Group Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site F F o o r r m m e e r r P P l l a a i i n n w w e e l l l l I I m m p p o o u u n n d d m m e e n n t t T T i i m m e e - - C C r r i i t t i i c c a a l l R R e e m m o o v v a a l l A A c c t t i i o o n n Weekly Construction Update Work Completed: June 25-July 2, 2008 Completed removing soil and sediment from Removal Area 10B. Continued removing soil and sediment from Removal Areas 11A and 12B. Began the installation of river run rock in Removal Area 12B. Continued post-construction activities in Removal Area 10B, including placement of river run rock and general fill. Continued post-construction activities in Removal Area 11B, including placement of river run rock and topsoil. Continued soil/sediment solidification activities at Staging Areas 4N and 5S. Continued loading and transporting solidified soil/sediment material from Staging Areas 4N and 5S to Allied Waste’s C&C Landfill and Ottawa County Farms Landfill. Continued loading and transporting solidified soil/sediment TSCA material from Staging Area 3S and Removal Area 10B to EQ’s Wayne County Disposal Facility. Consumers Energy relocated an electrical utility pole in Removal Area 7. The utility pole was relocated approximately 30 feet landward from its current position near the water’s edge. Continued operation of the WCS. Estimated Weekly Volume Hauled to TSCA and Non-TSCA Landfill Facilities Date Estimated Quantity TSCA-material (cubic yards) Number of Truck Loads TSCA-material Estimated Quantity Non-TSCA material (cubic yards) Number of Truck Loads Non-TSCA material Weekly Total 1400 40 2,380 68 2008 Total 4,690 134 31,710 906 Project Total to Date 7,700 220 65,625 1,875 Note: All values are unofficial, estimated quantities, subject to revision/verification. Progress Report #54—July 7, 2008

Upload: others

Post on 20-May-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 1 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

FFoorrmmeerr PPllaaiinnwweellll IImmppoouunnddmmeenntt TTiimmee--CCrriittiiccaall RReemmoovvaall AAccttiioonn

Weekly Construction Update Work Completed: June 25-July 2, 2008

• Completed removing soil and sediment from Removal Area 10B. • Continued removing soil and sediment from Removal Areas 11A and 12B. • Began the installation of river run rock in Removal Area 12B. • Continued post-construction activities in Removal Area 10B, including placement of river run

rock and general fill. • Continued post-construction activities in Removal Area 11B, including placement of river run

rock and topsoil. • Continued soil/sediment solidification activities at Staging Areas 4N and 5S. • Continued loading and transporting solidified soil/sediment material from Staging Areas 4N

and 5S to Allied Waste’s C&C Landfill and Ottawa County Farms Landfill. • Continued loading and transporting solidified soil/sediment TSCA material from Staging Area 3S

and Removal Area 10B to EQ’s Wayne County Disposal Facility. • Consumers Energy relocated an electrical utility pole in Removal Area 7. The utility pole was

relocated approximately 30 feet landward from its current position near the water’s edge. • Continued operation of the WCS.

Estimated Weekly Volume Hauled to TSCA and Non-TSCA Landfill Facilities

Date Estimated Quantity

TSCA-material (cubic yards)

Number of Truck Loads

TSCA-material

Estimated Quantity

Non-TSCA material

(cubic yards)

Number of Truck Loads Non-TSCA

material

Weekly Total 1400 40 2,380 68 2008 Total 4,690 134 31,710 906

Project Total to Date 7,700 220 65,625 1,875

Note: All values are unofficial, estimated quantities, subject to revision/verification.

Progress Report #54—July 7, 2008

Page 2: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 2 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Work Planned: July 3-July 9, 2008

• No construction activities are planned between July 3 and July 6 in observance of the July 4 holiday weekend.

• Continue removing soil and sediment from Removal Areas 11A and 12B. • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal Area 10B and 11B, including placement of

river run rock general fill, and topsoil. • Complete the installation of river run rock in Removal Area 12B. • Continue the installation of resuspension control systems in Removal Area 11A. • Continue soil/sediment solidification activities at Staging Areas 4N and 5S. • Continue loading and transporting solidified soil/sediment material from Staging Areas 4N

and 5S to Allied Waste’s C&C Landfill and Ottawa County Farms Landfill. • Continue loading and transporting solidified soil/sediment TSCA material from Staging Area 3S

and from Removal Area 10B to EQ’s Wayne County Disposal Facility located in Belleville, Michigan.

• Continue operation of the WCS.

Page 3: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 3 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

0

10000

20000

30000

40000

50000

60000

70000

80000

90000

Cub

ic Y

ards

Week End Date

Targeted Cumulative Removal Volume

Actual Cumulative Removal Volume

Removal Progress

Notes:

Targeted volumes are neat and subject to change due to additional excavation done at request of USEPA.

Actual volumes removed are below the targeted volumes potentially due to the conservative estimation methodology used to develop targeted figures and due to the actual topographic conditions encountered at the site, which could result in smaller volumes needing to be removed than originally estimated. The targeted volumes have been increased by 10% to account for additional material that could be removed as a result of over-excavation and additional removal in response to confirmation sampling. Soil/sediment removal activities are on schedule based on the ARCADIS BBL ES 4/30/07 Plainwell TCRA Construction Schedule.

Page 4: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 4 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Cum

ulat

ive

Perc

ent C

ompl

ete

for

2008

Sea

son

PLANNED ACTUAL

COMPLETE

48%RA10A

RA12B

Mid-Channel Area C

RA10B/RA10B1

RA13B

RA9B

RA13B

RA11A

RA9A

Phase 2 Cofferdam

RA12A/UA12B1

RA13A

RA11B

Mid-Channel Area A

RA13B

RA9B

Mid-Channel Area C, RA10A

RA9A

RA11A - 35% CompleteRA12B - 75% Complete

RA12A, UA12A1, RA13A - Each 15% Complete

RA10B - UA10B1 - 100% Complete

RA11B

Mid-Channel Area B

Removal Progress

Notes:

For Areas where removal is less than 100% complete, the data point shown is an estimate based on area and volume considerations.

‘Complete’ is defined as removal of all targeted materials as detailed in the Plainwell TCRA Design Report.

Page 5: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 5 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Health & Safety Update

• 3 Loss Prevention Observations (LPOs) were completed during this period. A total of 174 LPOs have been completed for the project to date.

Weather Summary

• No weather related delays during this period.

Environmental Monitoring and Construction Quality Assurance Testing

Resuspension/Turbidity Monitoring: Testing Performed this Week? No Yes Exceedances? N/A No Yes If yes, explain:

Dewatering System Discharge Monitoring:

Discharge Flow: 0 gallons (Staging Area 4N) and 0 gallons (Staging Area 5S) Testing Performed this Week? No Yes Exceedances? N/A No Yes If yes, explain:

Excavation Verification Sampling:

Testing Performed this Week? No Yes , in Removal Area 10B and 11B Cleanup Standard Achieved? N/A Yes No If no, explain:

Issues Encountered/Solutions Advanced

• None.

Page 6: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 6 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Equipment on Site

Equipment 6/26/08 6/27/08 6/28/08 6/29/08 6/30/08 7/1/08 7/2/08

Komatsu PC-300 Excavator 4 4 4 4 4 4 4 Komatsu PC-300 HD Long Reach 2 2 2 2 2 2 2 Komatsu PC-200 Excavator 1 1 1 1 1 1 1 John Deere JD-50 Mini-Excavator 1 1 1 1 1 1 1 John Deere JD-450 Dozer 1 1 1 1 1 1 1 John Deere JD-700 Dozer - - - - - - - Komatsu D37 Dozer 1 1 1 1 1 1 1 Komatsu D61 Dozer 1 1 1 1 1 1 1 Komatsu D65 Dozer - - - - - - - Volvo P-180 Loader 1 1 1 1 1 1 1 Komatsu 380 loader 1 1 1 1 1 1 1 CAT 328 Loader (King) 1 1 1 1 1 1 1 FAVCO 40-ton Crane 1 1 1 1 1 1 1 40’ Self Propelled Work Barge 1 1 1 1 1 1 1 American 80-ton Crane (King) 1 1 1 1 1 1 1 2,000 Gallon Water Truck 1 1 1 1 1 1 1 Smooth Drum Roller 1 1 1 1 1 1 1 John Deere Skidsteer 1 1 1 1 1 1 1 Vermeer Chipper - - - - - - - Komatsu 400 Articulating Dump Truck 2 2 2 2 2 2 2

Page 7: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 7 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Personnel, Regulatory Staff, and Visitors on Site

Individual/Affiliation 6/26/08 6/27/08 6/28/08 6/29/08 6/30/08 7/1/08 7/2/08

Terra Contracting Staff 25 25 25 25 20 Jim Saric/USEPA X Michael Berkoff/USEPA Don de Blasio/USEPA X Mike Ribordy/USEPA OSC X X Tom Crosetto/USEPA OSC Patricia Birkholz/Michigan State Senator X

Tonya Schuitmaker/Michigan State Representative X

Brian Calley/Michigan State Representative X

Paul Bucholtz/MDEQ X John Bradley/MDEQ Judith Gapp/MDEQ Todd Goeks/NOAA John Lerg/MDNR X Sharon Hanshue/MDNR Lisa Williams/USFWS Weston Contractors X X X X X CDM Contractors X X X X X Chase Fortenberry/KRSG X Mark Brown/KRSG X Paul Monteny/KRSG Eric Schmidt/KRSG Suda Arakere/KRSG X Don Hunt/Lambert Edwards & Associates X

Steve Garbaciak/ARCADIS X Mike Erickson/ARCADIS X Scott Harcus/ARCADIS X X X X X Eric Hritsuk/ARCADIS Matt Bowman/ARCADIS X EJ Suardini/ARCADIS X X X X X Mike Kohagen/ARCADIS X X X X X Michelle Rumler/ARCADIS X X X X X Joe Willoughby/ARCADIS X X X X X Ben Lawrence/ARCADIS Adam Chwalibog ARCADIS H&S Audit Team Nick Harmer/ARCADIS X X X X X Other Subcontractors (Specify) King Co. JF New 4 4

Page 8: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 8 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Photos from June 26-July 2, 2008

Excavating soil and sediment from Removal Area 10B.

View of the old Plainwell Dam’s

East Channel spillway.

Backfilling and grading activities in

Removal Area 10B.

Excavating soil and sediment from

Removal Area 11A.

Page 9: Former Plainwell Impoundment Time-Critical Removal Action · • Continue removing floodplain soil from Removal Areas 12A and 13A. • Continue post-construction activities in Removal

Former Plainwell Impoundment Time-Critical Removal Action Weekly Construction Update

Progress Report #54 Page 9 of 9

Kalamazoo River Study Group

Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site

Targeted Removal Areas – Former Plainwell Impoundment

Notes:

Additional planting in ‘Removal and Replanting Complete’ areas may be necessary in 2008. All dimensions and features represented on this map are approximate. Actual locations of access roads and staging areas and final boundaries of removal areas will be determined at the time of construction.