form-1, pre- feasibility reportenvironmentclearance.nic.in/writereaddata/formb/ec/...form-1, pre-...

23
FORM-1, pRE- FEASIBILITY REpORT FOR pROpOSEd RIVER BEd SAnd MInE pROjECT OF SHREE RAJUBHAI HAMIRBHAI SOLANKI -:Address:- Survey no. River Bed Of “Raval” River, Vill.Umej, Tal.Una, Dis.Gir Somnath, Gujarat. AREA – 2.00.00 HECTOR pROpOSEd CApACITY: - 48,000 TpA.

Upload: dobao

Post on 08-May-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

FORM-1,

pRE- FEASIBILITY REpORT

FOR

pROpOSEd RIVER BEd SAnd MInE

pROjECT

OF

SHREE RAJUBHAI HAMIRBHAI SOLANKI

-:Address:-

Survey no. River Bed Of “Raval” River,

Vill.Umej, Tal.Una,

Dis.Gir Somnath,

Gujarat.

AREA – 2.00.00 HECTOR

pROpOSEd CApACITY: - 48,000 TpA.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

Sand Mine of Rajubhai Hamirbhai Solanki Surveyno .River Bed Of “Raval” River, Vill. Umej, Tal.Una , Dis.Gir Somnath. Date:-28/02/2016.

To,

Respected ,

District Level Environment Impact Assesment Authority

District Magistrate,

Collector Office,

Gir Somnath

Sub:- For grant of the Environmental Clearance Certificate for minor mineral “River Bed Sand”

mining project as per the DEIAA notification of 15- Jan.-2016.

Sir,

I,The lease of Rajubhai Hamirbhai Solanki has been proposed a Mining Lease of minor

mineral “River Bed Sand Mine ”by the Collector, Gir Somnath,(Gujarat)Opp Gamtal Sr.No River Bed

Of “Raval” River,, Vill : Umej Tal :Una ,Dist. Gir Somnath, State : Gujarat for the lease area of 2.00.00

Ha.Accordance to the Notification No. of 141(E),dated 15th Jan 2016 issued by ministry of

Environment and Forest. Our lease area having less than 05.00 Ha. Are compulsorily eligible for

environmental clearance. In consideration of above, we humbly request you to accept our

application to accord environmental clearance at the earliest.

Annexures:-

(1)Form No.1.

(2)Pre-feasibility Report.

(3)Environment Management Plan.

Your Thanking

(Rajubhai Hamirbhai Solanki)

Project Details-Riverbed sand Mining Project

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

Sr.

No. Details Particulars

About The Proposal

1. Name of Lease Holder RAJUBHAI HAMIRBHAI SOLANKI

2. Location Address Survey no. River Bed Of “Raval” River, Vill.Umej,

Tal.Una, Dis.Gir Somnath.

3. Applicability of the CRZ Notification

2011

Not Applicable

4. Lease Area (Hectares) 2.00.00 Hectare

5. Co-ordinates of the lease area . 20°52'11.19"N & 71° 7'1.92"E

6. Ownership of the land (Govt. /

Private land)

Government lease land area

7. Status of Operation

(New project or Existing Project

operating Since.

Existing

8. Status of Lease (Lease No., Date of

issue, lease Period, Date Of

application for lease renewal etc

Lease No-GJ/QL/5625/699 Date Of Issue:4/2/2009. Lease Period:10 Years.

9. Sand reserve (MT) 48,000 MT

10. Rate of Mining of Sand (MT/Month) 4000 MT/M

ENVIRONMENT SETTING

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

11 If located within 15 Km, aerial

Distance of the lease area from

nearest.

Name Distance (Km)

i. National Park/Wildlife Sanctuary/Biosphere Reserve

Gir Forest 37.10 Km.

ii. Reserve Forest/ Protected Forest:

Gir Forest 37.10 Km.

iii Human Habitation Umej 860 Mtr.

Iv. Railway Line Una Railway 9.70 Km.

V. Road NH-6 1.26 Km.

vi. Notified/Protected

Archaeological Sites:

Gir Somnath 74.99 Km.

Vii Social Infrastructure

e.g.school,hospital,historic

cultural/religious places,defence

establishment etc.

Una 10 Km.

12. Width of riverbed (meters) 190 meter width of riverbed

13. Average depth of water at lease area

(meters)

This is mansoon river so in mansoon

season 06 meter depths

14. Average thickness of sand deposit at

lease area (meters)

Avarage thinkness of sand 3 meter

15. Details on Riparian vegetation,

including endemic and endangered

species of fauna, if any

Raval river belt side most of is found

grass and local flora spices found.

No one found endangered species of

fauna

16. Geo- hydrology of the river, flow

(perennial, seasonal. Etc.), sediment

transport

characteristics/replenishment

This is seasonal river so mason season

river flow eastern to western direction.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

potential etc.

17. Width and condition of access road

(kutcha/pucca) to the lease area.

4 meter wide metal road access to the

lease area.

DETAILS ON MINING/EXCAVATION ACTIVITIES

18 Type of mining (Manual/Semi

mechanized/mechanized)

Open cast mining by manually

19 Equipment’s to be used

(buylldozers,hydraulic

excavators,JCB,Scrapers,Loader Diesel pump

Etc.

By manually without Equipment

and machinery.

20 Minimum setback distance from river bank

(meters)

1441 meter

21 Minimum buffer distance from bridge

piers/water intake we;;s/irrigation structures

2.76 Kilo meter

22 Minimum distance of stockpiles/vehicle

loading place from the river bank

300 meter

23 Maximum depth of sand removal (3 m or

water depth whichever is less)

Maximum depth of sand removal 3

meter

24 Man power requirement 07 person

25 No. of working days in a year 240 Days

26 Time of working hours in a day 8 Hours

ENVIRONMENTAL MANAGEMENT PLAN

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

27 Measures proposed for protection of

environmental attributes like riverbed,

riverbed vegetation, water, air human health,

etc.

We have excavation on maximum 2

meter. We have plantation trees on

upper level on river bed. Human

health provide noise mask, safety

shoes and regularly doing health

check up by local doctor.

28 Details on transportation route & measures

proposed for control of fugitive emission

during transportation.

This lease area to main road route

is metal road. When transport sand

that time cover by plastic sheet for

prevent fugitive emission during

transportation.

29 Details on transportation route area /road

sides in at least 20 % of lease area, numbers &

types of species and budgetary outlay for the

same

We have reserve budget for

restoration of metal road and

developed local flora species by

under CSR.

30 Plan for restoration / reclamation Here is not required plan for

restoration and reclamation

because of each year rain water

carry with sand so gradually pit fill

up by sand.

Date: Signature and Stamp of

Place: Gir Somnath Mining and Geological Department

APPENDIX VIII

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

FORM- 1 M

APPLICATION FOR MINING OF MINERALS UNDER CATEGORY’B2’ FOR LESS THAN AND EQUAL

TO FIVE HECTORE

(Accordance to the Notification No. of 141(E),dated 15th Jan 2016 issued by MoEF & CC)

(II) Basic Information

(VIII) Name of the Mining Lease site : Rajubhai Hamirbhai Solanki.

(IX) Location/site(GPS Co-ordinates):

(X) Size of the Mining Lease(Hectare): 2.00.00 Ha

(XI) Capacity of Mining Lease(TPA): 48000 TPA

(XII) Period of Mining Lease: 10 Years

(XIII) Expected cost of the Project: 15 lakhs

(XIV) Contact Information: 9408209999.

Environmental Sensitivity Sr.NO. Areas Distance in

Kilometer/Details 1. Distance of project site from nearest rail or road

bridge over the concerned River,Rivulet,Nallah etc.

Road Bridge on Raval River-1.25 Km.

2. Distance of infrastructural facilities 1 Railway Line Una railway station

9.70 Km. 2 State Highway Khambha-Samter-Hwy-

1.45 Km. 3 Major District Road Khambha-Samter-Hwy-

1.45 Km.

20°51'52.08"N 71° 7'3.87"E

20°51'51.30"N 71° 7'6.43"E

20°51'44.16"N 71° 7'2.32"E

20°51'44.71"N 71° 7'0.67"E

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

4 Any Other Road NH-6 1.26 Km. 5 Electric transmission line pole or tower 860 Mtr. 6 Canal Or check dam or reservoirs or lake or

ponds Raval Dam-20.41 Km.

7 In-take for drinking water pump house Umej 860 Mtr. 8 Intake for Irrigation canal pumps NA

3. Areas protected under international conventions, national or local legislation for their ecological,landscape,cultural or other related value

No, this area do not come under protected international conventions, national or local legislation for their ecological,landscape,cultural or other related value

4. Area which are important or sensitive for ecological reasons –Wetlands,watercourses or other water bodies,coastal zone,biospheres,mountains,forests.

Raval Dam-20.41 Km.

5. Areas used by protected, important or sensitive for ecological reasons – Wetlands,watercourses or other water bodies,coastal zone,biospheres,mountains,forests

No,

6. Inland,costal,marine or underground water No, 7. State, National boundaries No, 8. Routes or facilities used by the public for access

to recreation or other tourist,pilgrim areas No,

9. Defence installations No, 10. Densely populated or built-up area, distance

from nearest human habitation Vill. Patapur -2.43 km

11. Areas occupied by sensitive man-made land uses. 1 Hospital (Una Gov.Hospital) 10.00 Km. 2 Schools (Una Primary and High school 10.00 Km. 3 Place of work ship (Una ) 10.00 Km. 4 Community facility 10.00 Km.

12. Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

Ground water available 40 mt. Surface resource is Raval Dam-20.41 Km.

Agriculture crop taking Banana,cotton, ground nuts. Fisheries ,tourism activity in nil. Mineral available is black

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

trap, river sand, betoniet other minor category mineral.

13. Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

No, Because Industrial is very less.

14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

This come under seismic zone III. (this area is not come under subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

15. Is proposed mining site located over or near fissure / fracture for ground water recharge

Raval Dam-20.41 Km.

16. Whether the proposal involves approval or clearance under the following Regulations or Acts, namely:-

1 (a) The Forest (Conservation) Act, 1980; No 2 (b) The Wildlife (Protection) Act, 1972 No 3 (c) The Coastal Regulation Zone

Notification, 2011 No

If yes, details of the same and their status to be given.

17. Forest land involved (hectares) 0.00.00 Ha 18. Whether there is any litigation pending against

the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Orders or directions of the Court, if any, and its relevance with the proposed project.

NA

(Signature of Project Proponent

Along with name and address)

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

pRE FEASIBILITY FOR SAnd MInE

CHAPTER – 1

1. EXECUTIVE SUMMARY :

The Government of Gujarat is considering to grant the mining lease to Mr.

RAJUBHAI HAMIRBHAI SOLANKI Sand Mine in area admeasuring 2.00.00

hector located at Survey no.Raval River Bed Vill.Umej, Tal.Una,Dis.Gir Somnath,

Gujarat.

With following references, the application dated 28/02/2016 by applicant

RAJUBHAI HAMIRBHAI SOLANKI for is under process and the mining lease

may be granted subject to several conditions, one of which is getting prior

Environmental clearance from state Environment impact Assessment Authoriy.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 2

INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION

1.1 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT

This is an existing project of Sand Stone mining.

The project name is M/s. Sand Stone Mine of shree RAJUBHAI HAMIRBHAI SOLANKI,which is located at Survey no. Raval River Bed Vill.Umej, Tal.Una, Dis.Gir Somnath.

Category of project – B Sr. No. In the schedule – 1(a) The existing Lease area 2.00.00 hectare The applicant M/s. shree RAJUBHAI HAMIRBHAI SOLANKI is

Proprietor in this proprietorship firm. The Lease copy is attached as per Annexure – 1 of Form – I application.

1.2 BRIEF DESCRIPTION OF NATURE OF PROJECT.

Sand Stone mining is a practice to extract building material, mainly through

excavation by in an open pit mining. Sand stone is a main material for building

construction material. In the construction business building sand plays an

important role in the saurashtra region.

sand is mineral present as sand stone benches. The height and thickness of

bench is vary with place to place. The average thickness of the is around 2.00

meters. Sand is excavation by earth mover vehicle like JCB etc..The average

annual production of sand stone @ 4000 MT/Month.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

1.3 NEED FOR THE PROJECT AND IMPORTANCE TO THE COUNTRY The Mining project falls in the area of the Gir Somnath district, Gujarat. As

industrial growth and infrastructure growth is going on day by day in Gujarat,

there is huge requirement of sand stone that plays a very crucial role in any

developing countries .These product should be cleaning as per market demand

and transferred construction site.

1.4 DEMAND AND SUPPLY GAP As infrastructure growth is on peak in Gujarat, there is a huge demand of sand

as a secondary material so there is a marginal gap between demand and supply.

1.5 EXPORT POSSIBILITY

Currently, sand is not export in any country so ‘0’ possibility.

1.6 DOMESTIC/EXPORT MARKET sand mineral use in local market building construction industry. It is not seen

demand outside region area and country because of it is available through nation

and not possibility also export is proposed.

1.7 EMPLOYEMENT GENERATION (DIRECT & INDIRECT) DUE TO THE

PROJECT. About 07 staff members including labors directly and approximately 5 persons

will be engaged indirectly in this proposed sand mining project. Thus total 13

person will get employment including directly or indirectly. Considering 5 people

in a family, total 13 x 5 = 65 person will be benefited and shall depend on the

mining activities of this mining lease area.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 3

PROJECT DESCRIPTION 2.1 TYPE OF PROJECT (INCLUDING INTERLINKED AND INTERDEPENDENT

PROJECTS, IF ANY) This is an existing Mining project for production of mineral sand stone from the

lease, having an area of 2.00.00hectare.

2.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION

AND PROJECT BOUNDARY & PROJECT SITE LAYOUT) WITH

COORDINATES. The entire project area is 2.00.00 hectare. The area break up in the following table:

Lease area Agricultural Grazing land Forest land Total (Ha) land (Ha) (Ha) (Ha) (Ha)

2.18.53 Nil Nil Nil 2.00.00

The Project is located at Survey no. Raval River Bed Vill.Umej, Tal.Una, Dis.Gir

Somnath, Gujarat. Key plan of the project is attached as per Annexure –4 of Form- I.

Layout plan and short view is attached as per Annexure – 6 & 7 of Form –I

application.

· The lease area is located between the

2.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF

SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL

CONSIDERATION GONE INTO SHOULD BE HIGHLIGHTED.

Since it is an existing sand stone mining and hence site specific, no alternative

site considered. The existing mining is in the lease area only for excavation of mineral sand stone

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

2.4 SIZE AND MAGNITUDE OF OPERATION This is an existing sand quarry project in a lease area of 2.00.00hectare which has

capacity to produce river Sand @ 2000 MT/Month by opencast mining.

2.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC

DIAGRAM/FLOW CHART SHOWING THE PROJECT LAYOUT,

COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN) At present the manual opencast mining will be carried out. There is no

overburden in the area. Mining in general will be carried out by manual open cast

method by forming benches up to 2.0 meter height. The Sand excavation in

lease area and after cleaning manually by workers.. This preferred Sand will be

loaded Tractor and trucks manually and dispatched to the building construction

site. Manufacturing process detail is attached as per Annexure – 8 of Form – I

application. sand stone excavation limits of all workings are planned with a 4 meters statutory

barrier against the lease boundary or roads existing in the lease hold. All haulage

roads, the alignment of which keeps on changing depending upon the working in

the pit, joins the existing surface roads of the lease hold. Four Wheeled Trolley

attached to tractor will be generally used for movement of mineral. The mineral

transported out of the lease hold will be with the help of tippers and trucks. All pit working will be securely fenced as per the standards prescribed by DGMS.

Approach roads to pit faces shall be maintained as required. Mining will be carried out for sand stone only. In the available thickness of

2.18.53m of deposit, single benches are proposed to be developed. Width of

bench is proposed to at 2 m.

BLASTING The sand stone mining activity in not required any type of blasting. because of this

by machine. BLASTING PATTERN As above mention mining activity in not applicable blasting so does not required

adopt any blasting pattern at here.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

2.6 REGIONAL GEOLOGY Umej town is falls Una Taluka in Gir Somnath district of Gujarat State. Nearby

town are Keshod, Una, Gir Somnath other nearest village etc.

2.7 RAW MATERIAL REQUIRED ALONG ESTIMATED QUANTITY, LIKELY

SOURCE, AND MARKETING AREA OF FINAL PRODUCTS MODE OF

TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT. This is an existing project for mining of sand stone are being done by excavation

vehicle So here Explosive Material is not used as Raw Material for blasting

Purpose. No another major Raw Material is required. Final product is marketed in Keshod, Umej, Gir Somnath other nearest village

etc. The Product is sand Stone which are transported directly by road through Tractor

or Truck to by the located in the nearby Area.

2.8 RESOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE

PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED. No optimization/recycling and reuse envisaged in the project.

2.9 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER REQUIREMENT

AND SOURCE SHOULD BE GIVEN.

Water consumption is 0.0000 KL/Day. Out of this, 0.00.00 KL/Day is used for

Domestic purpose. Electricity power is not applicable any operation activity. No another power is

required for the project.

2.10 QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND

SCHEME FOR THEIR MANAGEMENT/DISPOSAL.

· There is not a such waste or hazardous waste (Liquid and Solid) is generated

from sand mining activities.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 4

SITE ANALYSIS 3.1 CONNECTIVITY The existing project site is well connected with all the infrastructure i.e.

telephone, fax, road, railway, airport, etc. The nearest railway station of Una Railway station 9.70 km From exciting site.

The nearest airport is Diu 25.98 Km, from exciting site.

The nearest town is Una 10 km, Gir Somnath 76.25 km from Umej in direction

from existing site. Also the school, collages, hospital, etc are available within the 10 km radius from

the existing site.

3.2 LAND FORM, LAND USE AND LAND OWNERSHIP. The entire lease area is 2.00.00 Hector.

The total lease area is used for the sand Stone mining.

Mr. RAJUBHAI HAMIRBHAI SOLANKI Proprietor of this existing mining area.

A copy of 7-12 documents and NA is attached as per Annexure –9 of Form -I

application.

3.3 TOPOGRAPHY (ALONG WITH MAP) The mine lease area at present exhibits almost plain topography which will

marginally change during running of mine and on its abandonment at the end of

the proposed mining, due to digging of shallow pits up to 2.0 m depth. Key plan is attached as per Annexure – 4 of Form – I.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 5

PLANNING BRIEF

4.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES,

TRANSPORTATION ETC) TOWN AND COUNTRY

PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION. It is a mine project hence mining of sand stone is carried out. The production of

river sand is around 4000 MT/Month. Transportation of sand is done through

road by Tractors and trucks. Other facilities such as power, transportation and communication, social

infrastructure facilities are locally available near project site.

4.2 POPULATION PROJECTION The project is small in magnitude. No influx of population is expected as labor

shall be hired from nearby area and/or local villages. About 10 staff members including labors directly and approximately 5 persons

will be engaged indirectly in this proposed mining project.

Heads Census 2001 Census 2011

Total population of Gir Somnath 24,48,173 27,43,082

Total Male Population 12,52,350 14,04,356

Total Female population 11,95,823 13,38,726

Percentage of decadal growth 0.13

Total Literacy in % 67.78 75.80

Total Area (Sq Km) 8,831 Sq Meter

(Note: Here consider above mention Data with gir somnath district )

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

4.3 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.) The sand Stone mining is covered 2.18.53hectare area.

SR. ITEMS EXISTING GREEN BELT

NO.

1. Total Mining

2.00.00 hectare

area Green belt are

Depth of

Mining are done as per developed along

2. guidance of Geology and periphery of lease area.

mining

Mining Department

4.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL)

4.4.1 PHYSICAL INFRASTRUCTURE The road facility is already available which are being used and maintained. The labor

requirement is drawn from the nearest villages, which are also being trained as per

requirement. Other request infrastructure as transport of mine labors is available by

way of jeep; two-wheeler. Medical facility is available for fist aid at project site. Govt.

Dispensary is available nearest to 7 Km area in villages.

4.4.2 SOCIAL INFRASTRUCTURE About 10 staff members including labors directly and approximately 5 persons

will be engaged indirectly in this mining project. Primary infrastructure like road,

water, phone, schools is available in nearby area.

4.5 AMENITIES/FACILITIES The mine working is not proposed to be semi mechanized, hence there will be no

need for separate workshop. However Tractor or pump will continue to be

serviced. It is proposed that few spanners & wrenches at kept at the mine site to

attend an emergency. Rest shelter along with first-aid station complying with all the provisions of Mines

Rules will be constructed in the lease area itself. A portable blasting shelter will not be required

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

Water is required for drinking purpose carry with home because of it is possible

holding there. The mine is proposed to be worked in one shift (general shift) only. So no electric

power connection is required at mine for lighting. Employee will report to the duty on own means. The material from the mine will

be transported by trucks / Tractor. Fire extinguishers shall be provided in accordance with legal requirements.

Appropriate security arrangement shall be made.

First aid box with all necessary materials will kept all time in the office building for

minor injury.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 6

EXISTING INFRASTRUCTURE 5.1 INDUSTRIAL AREA (PROCESSING AREA) At the side is not required any office cum labor room has been constructed at mine area for primary necessities.

5.2 RESIDENT AREA (NON PROCESSING AREA) No residential area is existing. Workers are available in nearby area.

5.3 GREEN BELT To improve the environment of the area there has been trees are planted along

periphery of the mine.

5.4 SOCIAL INFRASTRUCTURE This project has providing employment opportunity for about 15 people directly

and indirectly, employment shall be generated for providing about 10 persons

which are Supervisor, excavation machine operator, drivers, transporters etc.

The project is responsible for social benefits like water, health care measures,

educational benefits, promotion of culture & religious activities.

5.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO /

WATER WAYS ETC) The existing project site is well connected with all the infrastructure i.e.

telephone, fax, road, railway, airport, etc. The nearest railway station is of Una Railway station 9.70 km From exciting site.

The nearest airport is Diu Airport 25.98 km from exciting site.

The nearest town is Una 10 km, Gir Somnath 76.25 km from from existing site

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

Also the school, collages, hospital, etc are available within the 10 km radius from

the existing site.

5.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER)

· Water consumption is 0.0000 KL/Day. Out of this, 0.0000 KL/Day is used for

Domestic purpose

5.7 SEWAGE SYSTEM Here Sewage System is not setup in premises because of mine come belt of

river.

5.8 INDUSTRIAL WASTE MANAGEMENT No Industrial waste will be generated from the existing as well as proposed

activity.

· The mining activity will not be generating any waste water. 5.9 SOLID WASTE MANAGEMENT This activity in not generate any type Solid Waste materials. So not required set

Solid Waste Management Plan.

5.10 POWER REQUIREMENT No Electricity Power required and other engery source required.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 7

REHABILITATION AND RESETTLEMENT(R&R PLAN)

No R&R plan is required as no displacement of people is proposed for the mining

project.

CHAPTER – 8

PROJECT SCHEDULE AND COST ESTIMATES

7.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF

COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BEGIVEN) This is an existing sand stone mining project. There is no such construction activity is

required for this project. Since this is an existing project the \

existing at the site.

Project Report River Bed sand mine of Rajubhai Hamirbhai Solanki

CHAPTER – 9

ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION) 8.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT

TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE

AREA The project is expected to provide employment to local people in different activities

such as Cleaning, Handling, transportation and plantation activities. The project activity

will not have any major impact on the environment. At Post mining stage of proposed

project, the existing waste land shall be converted to water harvesting bodies and

green belts. The company provides the helping hand in the development of the nearby villages by

following ways:

a. Development of facilities within the villages like roads etc.

b. Supply of drinking water in the period of scarcity to the nearby villages.

c. Up gradation of primary school in nearby villages.

In the interest of mineral development infrastructure boom and improving the social

conditions of the local habitants, this proposed project should be allowed after

considering all the environmental aspects.