FORM 1 & 1A ‘
For
PROPOSEDREDEVELOPMENTOFSUBHASHNAGARUNDERSRASCHEME
At
LandBearingS.No.509&510(pt),Village‐Panchpakhadi,
Tal.&Dist.–Thane,Maharashtra.
Proposed By
JaykaliDevelopersPvt.Ltd.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 1
APPENDIX‐I(Seeparagraph–6)
FORM1(I) BasicInformation
Sr.No.
Item Details
1 Nameoftheproject/s ProposedRedevelopmentofSubhashNagar,Thane(W),Maharashtra
2 S.No.intheSchedule 8(a)
3 Proposedcapacity/area/length/tonnagetobehandled/commandarea/leasearea/numberofwellstobedrilled.
TotalPlotArea 37,370.00 m2
Built‐upArea
FSIArea 1,38,493.24 m2
NonFSIArea 1,72,676.61 m2
TotalConstructionBuiltUpArea
3,11,169.85 m2
4 New/Expansion/Modernization RedevelopmentProjectunderSRAScheme
5 ExistingCapacity/Areaetc. ExistingSlums
6 Categoryofprojecti.e.AorB Acategory
7 Does it attract the generalcondition?ifyes,pleasespecify No
8 Does it attract the specificcondition?Ifyes,pleasespecify No
9 Location
Plot/Survey/KhasraNo. OnlandBearingS.No509&S.No.510(pt)
Village Panchpakhadi
Tehsil Thane
District Thane
State Maharashtra
10 Nearest railway station/portalongwithdistanceinkms.
ThaneRailwaystation:Approx.:4.0km
11 NearestTown,city,DistrictHeadquartersalongwithdistanceinkms.
Thanecity
12 VillagePanchayat,ZillaParishad,MunicipalCorporation,Localbody(completepostaladdresseswithtelephonenos.tobegiven)
ThaneMunicipalCorporation
13 Nameoftheapplicant JaykaliDevelopersPvt.Ltd.,
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 2
14 Registeredaddress SPCentre,41/44,MinooDesaiMarg,Colaba,Mumbai–400005.
15 Addressforcorrespondence: SPCentre,41/44,MinooDesaiMarg,Colaba,
Mumbai–400005.
Name Shri.SubodhPagnis
Designation(Owner/ Partner/CEO) Sr.VicePresident–RegulatoryApprovals
Address SPCentre,41/44,MinooDesaiMarg,Colaba,Mumbai–400005.
Pincode Mumbai–400005.
E‐mail [email protected]
TelephoneNo. 022–67490346
FaxNo. ‐
16 Details of alternative sitesexamined, if any. Location ofthesesitesshouldbeshownonatoposheet.
Village‐District‐State
1.
2.
3.
RedevelopmentofExistingslums/Structures
17 Interlinedprojects NotApplicable
18 Whetherseparateapplicationofinterlinked project has beensubmitted?
No
19 Ifyes,dateofsubmission
20 IfNo,Reason Standaloneconstructionproject
21 Whethertheproposalinvolvesapproval/clearanceunder:if,yesdetailsofthesameandtheirstatustobegiven
a) TheForest(Conservation)Act,1980?
b) Thewildlife(protection)Act,1972?
c) The CRZ Notification,1991?
NA.
As per MoEF&CC ESZ Notification No. S.O. 3645(E)dated 05.12.2016 our site is outside eco sensitivezonei.e.(100m)&atadistanceabout1.8km.Hencetheclearance fromthestandingcommitteeofNBWLisnotrequired.
22 WhetherthereisanyGovernmentOrder/policyrelevant/relatingtothesite?
No
23 Forestlandinvolved(hectares) No
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 3
24 Whether there is any litigationpending against the projectand/orlandinwhichtheprojectisproposetobesetup?
a) Nameofthecourtb) CaseNo.c) Orders/Directionsofthe
courtifanyanditsrelevancewiththeproposedproject.
No
Capacity corresponding to sectoral activity (such as production capacity for manufacturing,miningleaseareaandproductioncapacityformineralproduction,areaformineralexploration,lengthforlineartransportinfrastructure,generationcapacityforpowergenerationetc.,)
(II)ACTIVITY1. Construction, operation or decommissioning of the Project involving actions,
whichwillcausephysicalchangesinthelocality(topography,landuse,changesinwaterbodies,etc.)
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
1.1 Permanentortemporarychangeinlanduse,landcoverortopographyincludingincreaseinintensityoflanduse(withrespecttolocallanduseplan)
No LandisreservedforResidentialDevelopmentaspertheDPofTMC.Existingslum/structureswillbedemolishedandthedemolitionquantitywillbedisposedasperDistrictcollectorguidelines.
1.2 Clearance of existing land,vegetationandbuildings?
No Notreesonsite
1.3 Creationofnewlanduses?
No Theplotofprojectsiteisalreadyapprovedforresidentialdevelopmentasperlocaldevelopmentplanandwillbedevelopedasperthelocalbuildingby‐laws.Hence,nonewlandusewillbecreated.
1.4 Pre‐constructioninvestigationse.g.borehouses,soiltesting?
Yes HydrogeologicalassessmentandGeophysicalinvestigationwillbecarriedout.
1.5 Constructionworks?
Yes ProposedRedevelopmentofslums/structures
1.6 Demolitionworks?
Yes Existingslums/structureswillbedemolishedandabout40,273m3ofdemolitionquantitywillbedisposedatdesignateddisposalsiteasapprovedbytheDistrictCollector/TMC.
1.7 TemporarysitesusedforconstructionworksorHousingofconstructionworkers?
Yes Temporaryshedswillbeprovidedforworkers
1.8 Abovegroundbuildings,structuresorearthworksincludinglinearstructures,cutandfillorexcavations
Yes
ExcavationwillbecarriedoutforBasementandfoundationpurposes.Mostoftheexcavatedsoilwillbeusedforbackfillingatprojectsiteonly.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 4
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
1.9 Underground works includingminingortunnelling?
No
1.10 Reclamationworks? No 1.11 Dredging? No
1.12 Offshorestructures? No
1.13 Productionandmanufacturingprocesses?
No Constructionproject
1.14 Facilities for storage of goodsormaterials?
Yes Onlyconstructionmaterialwillbestoredintemporarystoragesite
1.15 Facilitiesfortreatmentordisposalofsolidwasteorliquideffluents?
Yes ExistingFacilities:NoSewage&Solidwastetreatmentfacilitiesareavailableonsite.ProposedFacilities:Solidwastewillbetreatedbymechanicalcompostingmethod(Ecobio‐compack).SewagegeneratedfromtheproposedcomplexwillbetreatedinSewagetreatmentPlant.TheexcesstreatedwaterwillbedirectlydisposedinMunicipalSewerLines(Existing)ThetreatedwaterwillbeusedforflushingandGardening.Thedriedsludgeandcompostwillbeusedasmanureforlandscaping.
1.16 Facilitiesforlongtermhousingofoperationalworkers?
No
1.17 Newroad,railorseatrafficduringconstructionoroperation?
Yes Existingroadnetworkwillbeusedduringconstructionandoperationphaseofproject.
1.18 Newroad,rail,airwaterborneorothertransportinfrastructureincludingneworalteredroutesandstations,ports,airportsetc?
No Existingroadwillbeusedforthetransportpurpose.
1.19 Closureordiversionofexistingtransportroutesorinfrastructureleadingtochangesintrafficmovements?
No
1.20 New or diverted transmissionlinesorpipelines?
No
1.21 Impoundment, damming,culverting, realignment orotherchangestothehydrologyofwatercoursesoraquifers?
No
1.22 Streamcrossings? No
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 5
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
1.23 Abstraction or transfers ofwater form ground or surfacewaters?
No
1.24 Changesinwaterbodiesorthelandsurfaceaffectingdrainageorrun‐off?
No Thereisnowaterbodywithinprojectsite.Theexistingdrainagesystemwillbeupgradedbyprovidingproperstormwaterandsewernetwork.
1.25 Transportofpersonnelormaterialsforconstruction,operationordecommissioning?
Yes Constructionworkersandconstructionmaterial
1.26 Long‐termdismantlingordecommissioningorrestorationworks?
No
1.27 Ongoingactivityduringdecommissioningwhichcouldhaveanimpactontheenvironment?
Yes DustgenerationandincreaseinNoiselevelsduringdemolitionsofexistingslums/structures.
1.28 Influxofpeopletoanareaineithertemporarilyorpermanently?
Yes Constructionworkersduringconstructionphaseandresidentsduringoperationphase
1.29 Introductionofalienspecies? No Nointroductionofalienspecieswilloccurasthisispurelyresidentialproject
1.30 Lossofnativespeciesorgeneticdiversity?
No Nothreatofspecieslosswilloccur.
1.31 Anyotheractions?
No No
2. Use ofNatural resources for construction or operation of the Project (such asland, water, materials or energy, especially any resources which are non‐renewableorinshortsupply):
Sr.No. Information/checklistconfirmation
Yes/No Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
2.1 Landespeciallyundevelopedoragriculturalland(ha)
No LandisreservedforResidentialDevelopmentaspertheDPofTMC
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 6
Sr.No. Information/checklistconfirmation
Yes/No Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
2.2 Water(expectedsource&competingusers)unit:CMD
Yes OperationPhase:TotalWaterdemand‐2,414KLDSource:TMC(BasisforWatersupplyistakenfromBIS:NationalBuildingCodeofIndia2005:Part9pg19)ThedetailedwaterbalanceforoperationphaseofprojectisattachedasAnnexureVI
2.3 Minerals(MT) No 2.4 Constructionmaterial–stone,
aggregates,sand/soil(expectedsource–MT)
Yes Constructionmaterialwillbesourcedfromnearbylocalvendors
2.5 Forestsandtimber(source–MT)
Yes Onlydoorframes(ifsoplanned)
2.6 Energyincludingelectricityandfuels(source,competingusers)Unit:fuel(MT),energy(MW)
Yes Connectedload26.8MW
Sourceofelectricity:MSEDCL
2.7 Anyothernaturalresources(useappropriatestandardunits)
Yes Wewillprovidesolarlighting(twolightsandonefan)ineachflatbyconnectingsolargenerationtothegrid.
3. Use,storage,transport,handlingorproductionofsubstancesormaterials,whichcouldbeharmful tohumanhealthor the environmentor raise concerns aboutactualorperceivedriskstohumanhealth.
Sr.No
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
3.1 Useofsubstancesormaterials,whicharehazardous(asperMSIHCrules)tohumanhealthortheenvironment(flora,fauna,andwatersupplies)
Yes Thisbeingaresidential,nouseandstorageofhazardouschemicals(asperMSIHCrules)duringoperationphaseisanticipated.Howevertheremaybesomehandlingofspentoil,frombackupDGsets.UsedlubricantoilfromDGsetswillbegiventoauthorisedrecyclers
3.2 Changes in occurrence ofdisease or affect diseasevectors (e.g. insect or waterbornediseases)
No
NotApplicable
3.3 Affectthewelfareofpeoplee.g.bychanginglivingconditions?
Yes
Proposedprojectwillpositivelyaffectthewelfareofpeoplebyprovidingstateofartinfrastructure.Theprojectwillgenerateemployment(Labouremploymentofhouseholdactivity)duringoperational
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 7
phasewhichwillbenefitthelocalpopulationingettingworkopportunities.Itwillcreatelongtermemploymentinactivitiessuchasmaintenanceofthebuildingsandancillaryservices.
3.4 Vulnerable groups of peoplewho could be affected by theproject e.g. hospital patients,children,theelderlyetc.,
No Proposedprojectwillnotaffecthospitalpatients,childrenetc.asthesearelocatedawayfromtheprojectsite
3.5 Anyothercauses No 4. Productionofsolidwastesduringconstructionoroperationordecommissioning(MT/month)
Sr.No.
Information/Checklistconfirmation
Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
4.1 Spoil,overburdenorminewastes
Yes Soilduringexcavation
4.2 Municipalwaste(domesticandorcommercialwastes)
Yes MunicipalSolidWasteTotal 9,214 kg/day
4.3 Hazardouswastes(asperHazardousWasteManagementRules)
Yes UsedoilfromDGsetwillbegiventoauthorisedrecyclers
4.4 Otherindustrialprocesswastes No ThisisResidentialproject
4.5 Surplusproduct No NotApplicable
4.6 Sewagesludgeorothersludgefromeffluenttreatment
Yes 22m3/dUsedasmanureafterdrying.
4.7 Constructionordemolitionwastes
Yes Demolitionquantity& constructiondebriswillbedisposedaspertheapprovalofDistrictcollector/TMC.
4.8 Redundantmachineryorequipment
No NotApplicable
4.9 Contaminatedsoilsorothermaterials
No NotApplicable
4.10 Agriculturalwastes No NotApplicable4.11 Othersolidwastes No NotApplicable
5. Releaseofpollutantsoranyhazardous,toxicornoxioussubstancestoair(kg/hr)
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
5.1 Emissions from combustion offossil fuels from stationary ormobilesources
Yes EmissionfromDGsetsduringpowerfailureandmovementofvehicleduringoperationphaseoftheproject
5.2 Emissions from productionprocesses
No NotApplicable
5.3 Emissions from materialshandling including storage ortransport
Yes Fugitiveemissionfromhandlingsand,aggregates,cementetc.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 8
5.4 Emissions from constructionactivities including plant andequipment
Yes Transportationofconstructionmaterial&handlingofsand,aggregates,cement,DGsetsetc.Theemissionsfromconstructionmachinerywouldcontainparticulates,SOx,NOxandCO
5.5 Dustorodourfromhandlingofmaterialsincludingconstructionmaterials,sewageandwaste
Yes Transportation,loadingandunloadingofmaterialwillgeneratedustOdourfromSolidwasteManagementandSTPareaifnothandledproperly
5.6 Emissionsfromincinerationofwaste
No NotApplicable
5.7 Emissionsfromburningofwasteinopenair(e.g.slashmaterials,constructiondebris)
No NotApplicable
5.8 Emissions from any othersources
No NotApplicable
6. GenerationofNoiseandVibration,andEmissionsofLightandHeat:
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdatawithsourceofinformationdata
6.1 Fromoperationofequipmente.g.engines,ventilationplant,crushers
Yes Increaseinnoiselevelsduetooperationsofconstructionequipment’s&vehicularmovement.
6.2 From industrial or similarprocesses
No NotApplicable
6.3 Fromconstructionordemolition
Yes Increaseinnoiselevelsduetooperationofconstructionequipments&vehicularmovementemissionsfromvehicles&DGsets
6.4 Fromblastingorpiling No OpenFoundation6.5 Fromconstructionor
operationaltrafficYes Trafficduringconstructionphaseisnegligible
andduringoperationphasewillbemore6.6 From lighting or cooling
systemsNo
6.7 Fromanyothersources No NotApplicable
(II) Risksof contaminationof landorwater from releasesofpollutants into thegroundorintosewers,surfacewaters,groundwater,coastalwatersorthesea:
Sr.No.
Information/Checklistconfirmation Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
7.1 Fromhandling,storage,useorspillageofhazardousmaterials
Yes DuetospillageofusedoilfromDGset
7.2 From discharge of sewage orother effluents towater or theland(expectedmodeandplaceofdischarge)
No STPwillbeusedforsewagetreatment.Treatedsewagewillbeusedforgardeningandflushingpurpose.SurplusTreatedWaterwillbedischargedinMunicipalSewerLines(Existing)
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 9
7.3 By deposition of pollutantsemitted to air into the land orintowater
No NotApplicable
7.4 Fromanyothersources No NotApplicable
7.5 Is there a risk of long termbuild up of pollutants in theenvironment from thesesources?
No NotApplicable
(III) RiskofaccidentsduringconstructionoroperationoftheProject,
whichcouldaffecthumanhealthortheenvironment
Sr.No.
Information/Checklistconfirmation
Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
8.1 Fromexplosions,spillages,firesetcfromstorage,handling,useorproductionofhazardoussubstances
Yes SpillageofusedoilfromDGsetsandexplosioninDieselStoragearea.AdequatefireprotectionmeasureswillbetakenupaspertheFireNOC
8.2 Fromanyothercauses
Yes Accidentsduringconstructionphase(Slips,fallfromheight,fallingofobjects/materialonworkers,fire,cutandburns,electricshockandcollapseofshuttering
Fireduetoshortcircuiting Terrorism Breakdownofelevator
8.3 Couldtheprojectbeaffectedbynaturaldisasterscausingenvironmentaldamage(e.g.Floods,earthquakes,landslides,cloudburstetc)?
No TheproposedstructureisdesignedasperSeismicZoneIIIstandards.
9. Factorswhichshouldbeconsidered(suchasconsequentialdevelopment)which
could leadtoenvironmentaleffectsorthepotential forcumulative impactswithotherexistingorplannedactivitiesinthelocality
Sr.No.
Information/Checklistconfirmation
Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 10
Sr.No.
Information/Checklistconfirmation
Yes/No
Detailsthereof(withapproximatequantities/rates,whereverpossible)withsourceofinformationdata
9.1
Leadtodevelopmentofsupporting. Facilities,ancillarydevelopmentordevelopmentstimulatedbytheprojectwhichcouldhaveimpactontheenvironmente.g.:
•Supportinginfrastructure(roads,powersupply,wasteorwastewatertreatment,etc.)•housingdevelopment•extractiveindustries•supplyindustries•other
No
SupportinginfrastructureisalreadyinexistenceanditwillbefurtherdevelopedTheareaisplannedforurbandevelopment.ThedevelopmentsrelatedtourbanizationareenvisagedandTownPlanningAuthorityhasdeclaredthelocationforthesame,consideringtheenvironmentalfactors.
9.2 Lead to after‐use of the site,whichcouldhaveanimpactontheenvironment
No NotApplicable
9.3 Set a precedent for laterdevelopments
No NotApplicable
9.4 Havecumulativeeffectsduetoproximitytootherexistingorplannedprojectswithsimilareffects
No NotApplicable
(IV) EnvironmentalSensitivity
Sr.No. Areas
Name/Identity
Aerialdistance(within15km.)Proposedprojectlocationboundary
1 Areasprotectedunderinternationalconventions,nationalorlocallegislationfortheirecological,landscape,culturalorotherrelatedvalue
Yes SanjayGandhiNationalPark‐Approx.1.8kmfromtheProposedProjectSiteTungareshwarWildlifeSanctuary(12.5km)
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 11
Sr.No. Areas Name/
IdentityAerialdistance(within15km.)Proposedprojectlocationboundary
2 Areas which are important orsensitive for ecological reasons– Wetlands, watercourses orother water bodies, coastalzone, biospheres, mountains,forests
Yes ThaneCreek:2.3kmUlhasRiver:3.2kmUpvanLake:1.7kmMasundaLake:3.8kmRailaDeviLake:4.7kmKacharliLake:2.6kmTulsilake:8.4kmViharLake:9.1kmPowaiLake:12.2kmSanjayGandhiNationalParkApprox.1.8kmfromtheProposedProjectSiteTungareshwarWildlifeSanctuary(12.5km)
3 Areas used by protected,important or sensitive speciesof flora or fauna for breeding,nesting, foraging, resting, overwintering,migration
No
4 Inland, coastal, marine orundergroundwaters
No ThaneCreek:2.9kmUlhasRiver:3.2kmUpvanLake:1.7kmMasundaLake:3.8kmRailaDeviLake:4.7kmKacharliLake:2.6kmTulsilake:8.4kmViharLake:9.1kmPowaiLake:12.2km
5 State,Nationalboundaries No 6 Routesorfacilitiesusedbythe
publicforaccesstorecreationorothertourist,pilgrimareas
No
7 Defenceinstallations No
8 Densely populated or built‐uparea
Yes Fullyurbanisedarea
9 Areasoccupiedbysensitiveman‐madelanduses(hospitals,schools,placesofworship,communityfacilities)
Yes Hospitals,schools,communityfacilities,&placesofworshiparepresentaroundprojectsite.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 12
Sr.No. Areas Name/
IdentityAerialdistance(within15km.)Proposedprojectlocationboundary
10 Areascontainingimportant,highqualityorscarceresources(groundwaterresources,surfaceresources,forestry,agriculture,fisheries,tourism,minerals)
No ThaneCreek:2.3kmUlhasRiver:3.2kmUpvanLake:1.7kmMasundaLake:3.8kmRailaDeviLake:4.7kmKacharliLake:2.6kmTulsilake:8.4kmViharLake:9.1kmPowaiLake:12.2kmSanjayGandhiNationalParkApprox.1.8kmfromtheProposedProjectSiteTungareshwarWildlifeSanctuary(12.5km)
11 Areasalreadysubjectedtopollutionorenvironmentaldamage.(thosewhereexistinglegalenvironmentalstandardsareexceeded)
No
12 Areas susceptible to naturalhazard which could cause theproject to presentenvironmentalproblems(earthquakes, subsidence,landslides, erosion, flooding orextreme or adverse climaticconditions)
No
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 13
(IV). ProposedTermsofReferenceforEIAstudies
Applicable
Iherebygivenundertaking that thedata& informationgiven in theapplication&enclosuresare true to thebest ofmyknowledge&belief& I amaware that if anypartof thedata andinformation submitted is found to be false or misleading at any stage, the project will berejectedandclearancegive,ifanytotheprojectwillberevokedatourriskandcost.Date:16.03.2017Place:Mumbai
Sr.VicePresident–RegulatoryApprovals
JaykaliDevelopersPvt.Ltd., SPCentre,41/44,MinooDesaiMarg,Colaba,
Mumbai–400005.
Signatureoftheapplicant Withname&fulladdress (Projectproponent/Authorisedsignatory)NOTE:
1) The projects involving clearance under Coastal Regulation Zone Notification, 1991shall submit with the application a C.R.Z map duly demarcated by one of theauthorizedagencies,showingtheprojectactivities,w.r.tC.R.Z(atthestageofTOR)andtherecommendationsoftheStateCoastalZonemanagementAuthority(atthestageofEC).SimultaneousactionshallalsobetakentoobtaintherequisiteclearanceundertheprovisionsoftheC.R.ZNotification,1991fortheactivitiestobelocatedintheCRZ.
2) Theprojectstobelocatedwithin10kmofthenationalParks,Sanctuaries,Biosphere
Reserves,MigratoryCorridorsofWildAnimals,theprojectproponentshallsubmitthemapdulyauthenticatedbyChiefWildlifeWardenshowingthesefeaturesvis‐avistheproject location and the recommendations or comments of the chief Wildlifethereon.(atthestageofEC)
3) AllcorrespondencewiththeministryofEnvironment&ForestsincludingsubmissionofapplicationforTOR/EnvironmentalClearance,subsequentclarificationsasmayberequiredfromtimetotime,participationintheEACmeetingonbehalfoftheprojectproponentshallbemadeby theauthorisedsignatoryonly.Theauthorisedsignatoryshouldalsosubmitadocumentinsupportofhisclaimofbeinganauthorisedsignatoryforthespecificproject.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 14
APPENDIX‐II(Seeparagraph6)
FORM‐1A(onlyforconstructionprojectslistedunderitem8oftheSchedule)
CHECKLISTOFENVIRONMENTALIMPACTS
(ProjectproponentsarerequiredtoprovidefullinformationandwherevernecessaryattachexplanatorynoteswiththeFormand
submitalongwithproposedenvironmentalmanagementplan&monitoringprogramme)
1. LANDENVIRONMENT
(Attachpanoramicviewoftheprojectsiteandthevicinity)
1.1 Willtheexistinglandusegetsignificantlyalteredfromtheprojectthatisnotconsistentwiththesurroundings?(ProposedlandusemustconformtotheapprovedMasterPlan/DevelopmentPlanofthearea.Changeoflanduseifanyandthestatutoryapprovalfromthecompetentauthoritybesubmitted).AttachMapsof(i)sitelocation,(ii)surroundingfeaturesoftheproposedsite(within500meters)and(iii)thesite(indicatinglevels&contours)toappropriatescales.Ifnotavailableattachonlyconceptualplans.
Theexistinglandusewillnotgetalteredfromtheproject.
ProposeddevelopmentisinlinewithD.PofTMC&itisreservedforresidentialpurpose.Followingdocumentsareattachedassupportingdocuments.
ToposheetasANNEXUREII
LocationplanasANNEXUREIII
SuperimposedofProposedLayoutonExistingGoogleImageisattachedasANNEXUREIV
ProposedConceptualPlanisattachedasANNEXUREV
1.2 Listoutallthemajorprojectrequirementsintermsofthelandarea,builtuparea,waterconsumption,powerrequirement,connectivity,communityfacilities,parkingneeds,etc.
TotalPlotArea 37,370.00 m2
FSIArea 1,38,493.24 m2
NONFSIArea 1,72,676.61 m2
TOTALCONSTRUCTIONBUILTUPAREA
3,11,169.85 m2
TOTALWATERDEMAND 2,408 KLD
EnergyConsumption
Totalconnectedload:26.8MW
ParkingProvided
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 15
Parkingprovided(Nos)
4wheeler 1,866
2wheeler 3,553
Connectivity ProjectSiteisaccessibleby40mwidePokhranRoadNo.1&20mwideDPRoad.LocationPlanisattachedasANNEXUREIII
1.3 Whatarethelikelyimpactsoftheproposedactivityontheexistingfacilitiesadjacenttotheproposedsite?(Suchasopenspaces,communityfacilities,detailsoftheexistinglanduse,disturbancetothelocalecology).
Theprojectbeingawellplannedactivitywillresultinorganizedopenspacesandgreenareas.Thebiodiversityintheareawillincreaseduetoproposedgreenareas.Communitycumrecreationalfacilitieswillbedevelopedhencenostressontheexistingfacilityisanticipated.
1.4. Willtherebeanysignificantlanddisturbanceresultinginerosion,subsidence&instability?(Detailsofsoiltype,slopeanalysis,vulnerabilitytosubsidence,seismicityetcmaybegiven).
Themainreasonsforerosionareoverexploitationofgroundwater,instableslopes,landslidesetc.Theproposedconstructionwillinvolvecuttingandfillingoperations.Theprojectwillinvolveconstructionofroadsanddevelopmentofgreenareas,whichwouldreducethechancesoferosionandsubsidence.Subsidenceisnotanticipatedasgroundwaterwouldnotbeusedasasourceofwatersupply.Asperseismic‐zoningmapofIndia,theprojectsitefallsunderzoneIII.StructuraldesignrequirementswillbeasperzoneIII.
1.5 Willtheproposalinvolvealterationofnaturaldrainagesystems?(Givedetailsonacontourmapshowingthenaturaldrainageneartheproposedprojectsite)
Theproposeddevelopmentisplannedinsuchamannerthatitwillnotaltertheexistingdrainagepatternofthearea.
1.6 Whatarethequantitiesofearthworkinvolvedintheconstructionactivity‐cutting,filling,reclamationetc.(Givedetailsofthequantitiesofearthworkinvolved,transportoffillmaterialsfromoutsidethesite,etc.)
Excavatedsoil/materialwillbeusedforbackfillingatprojectsiteonlyTherewillnotbeanytransportoffillmaterialsfromoutside.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 16
1.7 Givedetailsregardingwatersupply,wastehandlingetcduringtheconstructionperiod.
Temporarywaterstoragetankswillbeprovidedfordrinkingandconstructionpurpose.DrinkingwaterwillbemadeavailablefromMunicipalWaterSupplyLineandotherwaterwillbetakenfromtankerwater.TemporarySepticTanksfortheconstructionworkerswillbeprovided.
1.8 Willthelowlyingareas&wetlandsgetaltered?(Providedetailsofhowlowlyingandwetlandsaregettingmodifiedfromtheproposedactivity)
Nowetlandsandlow‐lyingareasonthesite.
1.9 Whetherconstructiondebris&wasteduringconstructioncausehealthhazard?(Givequantitiesofvarioustypesofwastesgeneratedduringconstructionincludingtheconstructionlabourandthemeansofdisposal)
Nohealthhazardisanticipated.Minorquantityofconstructiondebriswillbegenerated.TheconstructiondebrisandexcavatedsoilwillbedisposedaspertheDistrictCollectorsapproval
2. WATERENVIRONMENT
2.1 Givethetotalquantityofwaterrequirementfortheproposedprojectwiththebreak‐upofrequirementsforvarioususes.Howwillthewaterrequirementmet?Statethesources&quantitiesandfurnishawaterbalancestatement.
WaterRequirement:2,414KLD.TheproposedwaterdemandwillbemetfromTMCEnclosedasANNEXUREVII
2.2 Whatisthecapacity(dependablefloworyield)oftheproposedsourceofwater?
BeingaredevelopmentprojectwatersourceisavailablefromTMC.
2.3 Whatisthequalityofwaterrequired,incase,thesupplyisnotfromamunicipalsource?(Providephysical,chemical,biologicalcharacteristicswithclassofwaterquality)
Being a redevelopment project water source isavailablefromTMC.
2.4 Howmuchofthewaterrequirementcanbemetfromtherecyclingoftreatedwastewater?(Givethedetailsofquantities,sourcesandusage)
TreatedwaterfromSTPwillbeusedforflushingintoilets,gardenarea
TotalSewagegenerated 2,249 KLD
TotalSTPCapacity 2,400 KLD
Treatedwaterrecycledforflushing
824 KLD
Treatedwaterforgardening 16 KLD
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 17
TreatedwatertoMunicipalDrain
1,387 KLD
2.5 Willtherebediversionofwaterfromotherusers?(Pleaseassesstheimpactsoftheprojectonotherexistingusesandquantitiesofconsumption)
Nodiversionisanticipated
2.6 Whatistheincrementalpollutionloadfromwastewatergeneratedfromtheproposedactivity?(Givedetailsofthequantitiesandcompositionofwastewatergeneratedfromtheproposedactivity)
The total sewage of about 2,249 KLD will begenerated from the complex. The composition ofwaterisgiveninthetableindicatingthequalityofrawwastewaterbeforetreatment
Parameters Values Units
pH 7‐8 mg/l
BOD 250‐300 mg/l
COD 450‐600 mg/l
O&G/ABS 10‐20 mg/l
TSS 100‐200 mg/l
Mitigation measures: Domestic Effluent will betreated in the Sewage Treatment plant of totalcapacity 2400 KLD. (Sale STP: 850 KLD & RehabSTP:1,550KLD)Thetreatedsewagewaterwillbereusedforflushingandgardening.
2.7 Givedetailsofthewaterrequirementsmetfromwaterharvesting?Furnishdetailsofthefacilitiescreated.
Rainwater from project area will be harvestedthroughrechargepits.
2.8. Whatwouldbetheimpactofthelandusechangesoccurringduetotheproposedprojectontherunoffcharacteristics(quantitativeaswellasqualitative)oftheareainthepostconstructionphaseonalongtermbasis?Woulditaggravatetheproblemsoffloodingorwaterlogginginanyway?
ProposeddevelopmentisintunewithD.PofTMC.
Theprojectwillhaveproperstormwaterdrainagefacility as per Storm Water Drain Remarks byconcernedauthority.Sotherewillbenoproblemofwaterloggingduetothisproject.
2.9 Whataretheimpactsoftheproposalonthegroundwater?(Willtherebetappingofgroundwater;givethedetailsofgroundwatertable,rechargingcapacity,andapprovalsobtainedfromcompetentauthority,ifany)
In the proposed development there will be notapping of groundwater. Water demand for theoperationalphasewillbemetfromsourcessuchasTMC.Thegroundwatertableisat3‐4m.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 18
2.10 Whatprecautions/measuresaretakentopreventtherun‐offfromconstructionactivitiespollutingland&aquifers?(Givedetailsofquantitiesandthemeasurestakentoavoidtheadverseimpacts)
Topreventdegradationandmaintainthequalityofwater source, adequate control measures havebeenproposedtocheckthesurfacerun‐off,aswellasuncontrolledflowofwaterintoanywaterbody.
Avoidexcavationduringmonsoonseason.
Rainwater harvesting can serve as a solution towaterprobleminworstcasescenario.
Following methods can increase efficiency ofrainwaterharvestingandrecharginggroundwater.
Catchdrainageallalong theperipheryofplot topreventsurfacerunoff.
Reduceandfiltersurfacerunoff.
Usevegetatedswalesanddepressions toreducerunoff.
2.11 Howisthestormwaterfromwithinthesitemanaged?(Statetheprovisionsmadetoavoidfloodingofthearea,detailsofthedrainagefacilitiesprovidedalongwithasitelayoutindicationcontourlevels)
Duringrainyseason,aftertherainfallsomepartoftherainwaterpercolates intothegroundand joinsground water table, a part is retained as soilmoisture, some part is lost in evapotranspirationand the remaining part overflows as stormwaterrun‐off.Thequantityofrunoffreachingthesewersordrainsisconsiderableascomparedwithsanitarysewage.
Theprojectwillhaveproperstormwaterdrainagefacility as per Storm Water Drain Remarks byconcerned authority. So therewill not beproblemofwaterloggingduetothisproject.
2.12 Willthedeploymentofconstructionlabourersparticularlyinthepeakperiodleadtounsanitaryconditionsaroundtheprojectsite(Justifywithproperexplanation)
No, the deployment of construction labourerswillnot lead to any unsanitary condition. Theconstruction labourers will be provided withtemporary shelter shades within the projectpremises. The unsanitary condition will beremovedbymeans of providing readymade septictanks&soakpits.Solidwastewillbedisposedoffinmunicipalwastedisposalsystem.
2.13 Whaton‐sitefacilitiesareprovidedforthecollection,treatment&safedisposalofsewage?(Givedetailsofthequantitiesofwastewatergeneration,treatmentcapacitieswithtechnology&facilitiesforrecyclinganddisposal)
The Sewage Treatment plant (STP) is designed totreattherawwastewatergeneratedfromproposedResidentialProject.
2.14 Givedetailsofdualplumbingsystemiftreatedwasteusedisusedforflushingoftoiletsoranyotheruse.
Yes,Theproposeddevelopmentwillhavethedualplumbingsystemasthetreatedsewagewillbeusedforrecycling.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 19
3. VEGETATION
3.1 Isthereanythreatoftheprojecttothebiodiversity?(Giveadescriptionofthelocalecosystemwithit’suniquefeatures,ifany)
Thereisnosensitiveecosystempresentatsitethatwill be disturbed by the project, as existing landuse in surrounding area is residential andcommercial
3.2 Willtheconstructioninvolveextensiveclearingormodificationofvegetation?(Provideadetailedaccountofthetrees&vegetationaffectedbytheproject)
Notreesonsite
3.3 Whatarethemeasuresproposedtobetakentominimizethelikelyimpactsonimportantsitefeatures(Givedetailsofproposalfortreeplantation,landscaping,creationofwaterbodiesetcalongwithalayoutplantoanappropriatescale)
About 3,192.47m2 (RG area on Ground: 1,164.94m2 RG area on Podium: 2,027.53 m2) areas areprovided for thedevelopmentofGreenbelt in thepremises. The green belt will be developed forcontrol of pollution and aesthetic view of thecomplex.
4. FAUNA
4.1 Istherelikelytobeanydisplacementoffauna‐bothterrestrialandaquaticorcreationofbarriersfortheirmovement?Providethedetails.
No.Theproposedsiteanditssurroundingsdonotsupportanyhabitatforanygroupofwildanimals.
4.2 Anydirectorindirectimpactsontheavifaunaofthearea?Providedetails.
No.Therewillbenodirectorindirectimpactontheavifaunaofthearea.
4.3 Prescribemeasuressuchascorridors,fishladdersetctomitigateadverseimpactsonfauna
Sincetheproposedprojectwouldnothaveanyadverseimpactonfaunahencemitigationmeasurenotrelevant.
5. AIRENVIRONMENT
5.1 Willtheprojectincreaseatmosphericconcentrationofgases&resultinheatislands?(Givedetailsofbackgroundairqualitylevelswithpredictedvaluesbasedondispersionmodelstakingintoaccounttheincreasedtrafficgenerationasaresultoftheproposedconstructions)
Theprojectwill result innegligible increase in theatmospheric concentrations of gases due to D.G.operations(backuppoweronly)andtheincreasedtraffic. Theproposed activitywill not result in theformationofanyheatislands,asitdoesnotinvolveanysignificantchangeinthelandusepatternortheconcretingofareas.
5.2 Whataretheimpactsongenerationofdust,smoke,odorousfumesorotherhazardousgases?Givedetailsinrelationtoallthemeteorologicalparameters.
Diesel generator sets operated for back‐up powersupply are identified as the onlymajor sources ofgaseous and particulate emission. Impact ofvehicular is not significant. SO2, SPM, NOX and COemissions are expected due to fuel combustion ingeneratorsets.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 20
5.3 Willtheproposalcreateshortageofparkingspaceforvehicles?Furnishdetailsofthepresentleveloftransportinfrastructureandmeasuresproposedforimprovementincludingthetrafficmanagementattheentry&exittotheprojectsite.
Theproposedprojectislocatedinwell‐developedurbanisedarea.Theprojectwillhaveproperentryandexitforthevehicles.Therewillnotanysignificanttrafficcongestionduetoprojectsite.
ParkingProvided
Parkingprovided(Nos)
FourWheeler 1,866
Twowheeler 3,553
5.4 Providedetailsofthemovementpatternswithinternalroads,bicycletracks,pedestrianpathways,footpathsetc.,withareasundereachcategory.
Internalroads,footpaths/pedestrianpathwayshavebeenplannedwithintheproposedcomplex.
5.5 Willtherebesignificantincreaseintrafficnoise&vibrations?Givedetailsofthesourcesandthemeasuresproposedformitigationoftheabove.
Considering the addition of vehicles due to theproposed project with the existing roads andvehicles plying on them, there will be marginalincreaseinthenoiselevelsbutwillnotresultinanimpact.
5.6 WhatwillbetheimpactofDGsets&otherequipmentonnoiselevels&vibrationin&ambientairqualityaroundtheprojectsite?Providedetails.
DGsetwillbeusedinconstructionandoperationphaseonlyincaseofpowerfailure.The DG Sets shall be as per the guide lines laiddownbyEPRforspecificnoiseemissionstandards.Measures shall be taken for reduction of noise byusingacousticenclosures.Increase innoise levels are expected fromvariousconstructionequipmentandmachinery.
6. AESTHETICS
6.1 Willtheproposedconstructionsinanywayresultintheobstructionofaview,scenicamenityorlandscapes?Aretheseconsiderationstakenintoaccountbytheproponents?
TheproposedlanduseofthesitewouldbemainlyResidential Building and will not result inobstruction of view, scenic amenity or landscape.However, the buildings will be planned in such awaythattheorganisedopenareasandlandscapedareas are at the centre so that all can enjoy thegreenareas.
6.2 Willtherebeanyadverseimpactsfromnewconstructionsontheexistingstructures?Whataretheconsiderationstakenintoaccount?
Internal roads, footpaths/ pedestrian pathwayshavebeenplannedwithintheproposedcomplex
6.3 Whetherthereareanylocalconsiderationsofurbanform&urbandesigninfluencingthedesigncriteria?Theymaybeexplicitlyspeltout.
The project has been designed as per thedevelopmentcontrolRegulationofTMC
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 21
6.4 Arethereanyanthropologicalorarchaeologicalsitesorartefactsnearby?Stateifanyothersignificantfeaturesinthevicinityoftheproposedsitehavebeenconsidered.
No anthropological or archaeological sites orartefactsarefoundnearthesitearea.
7. SOCIO‐ECONOMICASPECTS
7.1 Willtheproposalresultinanychangestothedemographicstructureoflocalpopulation?Providethedetails.
No.Majorityof the labourwillbe recruited locallyand only minimal skilled workers would be fromoutside,which is anticipated to be very small andwill not alter the existing demographic profile ofthearea.
7.2 Givedetailsoftheexistingsocialinfrastructurearoundtheproposedproject.
The project comes in residential area and has allbasic infrastructural facilities as schools, medicalestablishments,shops,etc.
7.3 Willtheprojectcauseadverseeffectsonlocalcommunities,disturbancetosacredsitesorotherculturalvalues?Whatarethesafeguardsproposed?
No. The projectwill have positive impact on localcommunities.
8. BUILDINGMATERIALS
8.1 Mayinvolvetheuseofbuildingmaterialswithhigh‐embodiedenergy.Aretheconstructionmaterialsproducedwithenergyefficientprocesses?(Givedetailsofenergyconservationmeasuresintheselectionofbuildingmaterialsandtheirenergyefficiency)
Yesbuildingmaterialssuchascoalash,lightweightconcrete, composite or engineered marble,aluminium, recycled glass or compositewoodwillbeused.
8.2 Transportandhandlingofmaterialsduringconstructionmayresultinpollution,noise&publicnuisance.Whatmeasuresaretakentominimizetheimpacts?
Adequate mitigative measures will be adopted.Construction equipment with idling controltechnologieswill be used. Regularmaintenance ofthe equipments will be carried out. Theconstruction activities will be carried out duringthe daytime only. The workers exposed to highnoisegeneratingwouldbeprovidedwithearplugsearmuffs.AsperEnvironmentalManagementPlan.
8.3 Arerecycledmaterialsusedinroadsandstructures?Statetheextentofsavingsachieved?
Flyash incementconcrete.Typically20 ‐25%offlyashissubstitutedincement
8.4 Givedetailsofthemethodsofcollection,segregation&disposalofthegarbagegeneratedduringtheoperationphasesoftheproject.
Thebio‐degradableandnon‐biodegradablewastewillbesegregatedatsourceofwastegeneration.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 22
Proposed UnitSolidwastegenerated
9,214 kg/day
Thebiodegradablewaste5,529kg/daywillbetreatedbymechanicalcompostingmethod
Thenon‐biodegradablewaste3,686kg/daywillbedisposedoffthroughrecyclers.
9. ENERGYCONSERVATION
9.1 Givedetailsofthepowerrequirements,sourceofsupply,backupsourceetc.Whatistheenergyconsumptionassumedpersquarefootofbuilt‐uparea?Howhaveyoutriedtominimizeenergyconsumption?
Sourceofpowersupply:MSEDCLDGSetwillbeprovidedasemergencybackup.
ConnectedLoad:26.8MW
9.2 Whattypeof,andcapacityof,powerback‐updoyouplantoprovide?
DGSetwillbeprovidedfor100%emergencybackupforResidentialbuildingsmainlyforcommonareas,lift,pathwaysetc.DGSet:Total:6,500kVA(D.G.SetprovisionismadeforemergencybackupofLift,STP,waterandFirePumps)Sourceofpowersupply:MSEDCL
9.3 Whatarethecharacteristicsoftheglassyouplantouse?Providespecificationsofitscharacteristicsrelatedtobothshortwaveandlongwaveradiation?
SingleclearglassforResidentialbuildingSingleGlazedUnitUValue:1.0Btu./hr.ft2⁰FSC:0.62VLT:51%
9.4 Whatpassivesolararchitecturalfeaturesarebeingusedinthebuilding?Illustratetheapplicationsmadeintheproposedproject.
The building structure will be designed in such awaythatsolarlightcanbeutilisedmaximumfordaytime. In addition to that, natural ventilation &shading are twootherpassive strategieswhich areeffectively incorporated in the project designed torespondtothelocalclimate.
9.5 Doesthelayoutofstreets&buildingsmaximisethepotentialforsolarenergydevices?Haveyouconsideredtheuseofstreetlighting,emergencylightingandsolarhotwatersystemsforuseinthebuildingcomplex?Substantiatewithdetails.
Looking at the long term cost effectiveness,efficiency & requirement of electricity rather thanthe solar hotwater system,we are providing solarlighting (two lights and one fan) in each flatthrough solar PV panels by connecting solargenerationtothegrid.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 23
9.6 Isshadingeffectivelyusedtoreducecooling/heatingloads?WhatprincipleshavebeenusedtomaximizetheshadingofWallsontheEastandtheWestandtheRoof?Howmuchenergysavinghasbeeneffected?
Yes.Shadinghasbeeneffectivelyusedtoreducethecoolingloads.
9.7 Dothestructuresuseenergy‐efficientspaceconditioning,lightingandmechanicalsystems?Providetechnicaldetails.Providedetailsofthetransformersandmotorefficiencies,lightingintensityandair‐conditioningloadassumptions?AreyouusingCFCandHCFCfreechillers?Providespecifications.
Yes.Theroomswillbesodimensionedthateffectiveairconditioningcanbecarriedout.Publicareaswillbe cooled by natural ventilation. The design of thebuildingwill be such thatmaximumuse of naturalventilation can be achieved. The walls, roofs andopenings will be so designed that influx of heat isminimum.
9.8. Whatarethelikelyeffectsofthebuildingactivityinalteringthemicro‐climates?Provideaselfassessmentonthelikelyimpactsoftheproposedconstructiononcreationofheatisland&inversioneffects?
Heat emission from the proposed construction canbefromthefollowingsources:Heat absorbed from the concrete structures, heatgeneratedfromequipments/appliances,andduetoincreasedpopulation in theproposeddevelopment.However the heat generatedwill not be significantandwill be dissipated in the lush greens and openareas provided within. Hence it can be concludedthattheheatislandeffectshallnotbeaconcernfortheproposedproject.
9.9. Whatarethethermalcharacteristicsofthebuildingenvelope?(a)roof;(b)externalwalls;and(c)fenestration?GivedetailsofthematerialusedandtheU‐valuesortheRvaluesoftheindividualcomponents.
UvalueinW/m20K
Wallassembly 0.567W/m20K
Roofassembly 0.404W/m20K
9.10 Whatprecautions&safetymeasuresareproposedagainstfirehazards?Furnishdetailsofemergencyplans.
The fire fighting system shall compromise ofhydrant system, sprinkler system and portableextinguishers. Smoke detectors will be providedalong with manual call points. External yardhydrants shall be installed around all buildings inthe complex in galvanized steel fire hose cabinet(weatherproof).Allexternalyardhydrantsshallbeat one meter height from finished ground level asper National Building Code. External fire hydrantsshallbelocatedsuchthatnoportionofanybuildingismorethan45mfromahydrant,andtheexternalhydrants are not vulnerable to mechanical orvehiculardamage.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 24
9.11 Ifyouareusingglassaswallmaterialprovidesdetailsandspecificationsincludingemissivityandthermalcharacteristics.
U=5.7Watts/m2/K,SHGC=0.54
9.12 Whatistherateofairinfiltrationintothebuilding?Providedetailsofhowyouaremitigatingtheeffectsofinfiltration.
Thefollowingmeasureswillbeadoptedtomitigatetheeffectsofinfiltration: Aluminiumwindowswithrubbergasket,sothat
thewindowsaresealed,willbeprovided. Summer cross section ventilation will be
maximum.
9.13 Towhatextentthenon‐conventionalenergytechnologiesareutilisedintheoverallenergyconsumption?Providedetailsoftherenewableenergytechnologiesused.
Looking at the long term cost effectiveness,efficiency & requirement of electricity rather thanthe solar hotwater system,we are providing solarlighting (two lights and one fan) in each flatthrough solar PV panels by connecting solargenerationtothegrid.
10. EnvironmentManagementPlan
TheEnvironmentManagementPlanwouldconsistofallmitigationmeasuresforeachitemwiseactivitytobeundertakenduringtheconstruction,operationandtheentirelifecycletominimizeadverseenvironmentalimpactsasaresultoftheactivitiesoftheproject.Itwouldalsodelineatetheenvironmentalmonitoringplanforcomplianceofvariousenvironmentalregulations.Itwillstatethestepstobetakenincaseofemergencysuchasaccidentsatthesiteincludingfire.
EnclosedasAnnexureVII
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 25
ANNEXUREI
AREASTATEMENT
DEDUCTIONS : -
BALANCE AREA OF PLOT ( 1 --- 2 c )
NET AREA OF PLOT
ADDITION FOR : -
TOTAL PLOT AREA FOR F.S.I. PURPOSE ( 5 + 6 c )
MAXIMUM F.S.I. PERMISSIBLE ON PLOT
MAXIMUM BUILT UP PERMISSIBLE ON PLOT ( 7 X 8 )
a
4.00
1,49,480.00
1918 NOS X 30.00 = 57,540.00 REHAB BUILT UP AREA ( TOTAL TENANT = 2074 NOS )
TOTAL PROPOSED AREA REHABILITATION COMPONENT ( 10g + 11 )
10
11
12 78,590.18
13
TOTAL BUILT UP FOR THE SCHEME ( 10a + 13 )14 1,38,442.54
15 TOTAL F.S.I. FOR THE SCHEME 14 / 7
SALE BUILT UP AREA PERMISSIBLE IN SITU ( 9 --- 10a )16 89,627.64
TOTAL BUILT UP PROPOSED TO BE CONSUMED IN SITU ( 10a + 16 )17
AREA IN
09
08
07
06
05
04
03
02
01
SR.No. SQ.MT.
3.70464
TOTAL PERMISSIBLE AREA SALE COMPONENT
BLDG. R1 TO R6 PASSAGE AREA
A ) AREA STATEMENT
TOTAL HUTMENTS AREA APPROX
DEDUCTION FOR 10% R. G. ( NOT APPLICABLE ) PHYSICAL R.G. PROVIDED 10% OF AREA = 31,470.91 X 10% = 3147.09
100 TENANTS : 1 BALWADI OF 30.00 SQ.MT. (2072 / 100 = 21 NOS )100 TENANTS : 1 WELFARE CEN. OF 30.00 SQ.MT. (2072 / 100 = 21 NOS )
AMENITY AREA100 TENANTS : 1 SOCIETY OFF. OF 16.00 SQ.MT.
21 NOS x 20.00 x 1.20 = 504.00 SQ.MT.
37,370.00
AREA UNDER 40.00 M. W. D. P. ROAD
AREA UNDER 20.00 M. W. D. P. ROADb
21 NOS x 20.90 x 1.20 = 526.68 SQ.MT. ( BALWADI ) 21 NOS x 20.90 x 1.20 = 526.68 SQ.MT. ( WELFARE CENTER )
1,559.43
31,470.91
37,370.00
3,637.09
2,262.00
TOTAL ( 2 a + 2 b ) 5,899.09c
a AREA UNDER 40.00 M. W. D. P. ROAD
AREA UNDER 20.00 M. W. D. P. ROADb
c
3,637.09
2,262.00
31,470.91 + 5,899.09
TOTAL ( 2 a + 2 b )
148 COMMERCIAL EXISTING CARPET AREA = 2250.00
SCHOOL ( 5 )
a
b
c
57,595.64
15,469.90
532.86
f
1,557.36
TOTAL ( 10a + 10b + 10c + 10d + 10e + 10f )g 77,030.75
78,590.18
1,49,480.00
84.36+53.79+27.87+31.03+31.03 = 228.08
MANDIR ( 1 ) + CHURCH ( 1 ) +BUDDHAVIHAR ( 1 ) = 395.88 + AREA NOT LIST + 16.16 =
EXTRA SCHOOL dAREA NOT LIST
1,012.63
163.00e
2,256.72
31,470.91
5,899.09
3,147.09
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 26
BUILDINGANDTENEMENTSTATEMENT
Sr.No.
BuildingNo. BuildingConfigurationNo.ofShops
No.ofFlats
REHABTOWER 1 Bldg.R1 2B+G+27thUpperfloors 17 3872 Bldg.R2 2B+G+27thUpperfloors 21 4113 Bldg.R3 2B+G+28thUpperfloors 25 2684 Bldg.R4 2B+G+28thUpperfloors 29 3205 Bldg.R5 2B+G+28thUpperfloors 29 2686 Bldg.R6 2B+G+28thUpperfloors 27 2647 SchoolNo.1 2B+G+2ndUpperfloors 8 SchoolNo.2 2B+G+3rdUpperfloors 9 SchoolNo.3 2B+G+2ndUpperfloors
SALETOWER 10 Bldg.T1 2B+G+2P+S+26thupperfloors 20311 Bldg.T2 2B+G+2P+S+26thupperfloors 20312 Bldg.T3 2B+G+2P+S+26thupperfloors 19813 Bldg.T4 2B+G+2P+S+26thupperfloors 20314 Bldg.T5 2B+G+2P+S+26thupperfloors 20315 Bldg.T6 2B+G+2P+S+84thupperfloors 168
16 Retail/Commercial
G+4thupperfloors 50 ‐
TOTAL 198 2,893
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 27
ANNEXUREIITOPOSHEET
PROJECT SITE
E43A16
E43A15&A11E43B3
E43B4
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 28
ANNEXUREIIILOCATIONPLAN
ProjectSite
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 29
ANNEXUREIV
SUPERIMPOSEDOFPROPOSEDLAYOUTONEXISTINGGOOGLEIMAGE
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 30
ANNEXUREV
PROPOSEDCONCEPTUALPLAN
RETAIL /COMMERCIALG + 4
S. No. 510
S. No. 510
NET REHAB PLOT AREA =10948.95 SQ.MT. NET SALE PLOT AREA =20521.96 SQ.MT.S. No. 509
TWO WAYRAMP1:10
CLUB HOUSE
POOL
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 31
ANNEXUREVI
WATERBUDGETCALCULATION
ParticularsNoofFlats/rooms
OccupancyTotal
Population
TotalWaterRequirement/
person
WaterDemandKLD
DomesticwaterfromMunicipal
Flushing
RehabFlats 1918 6 11,508 90 45 135 1,554Shops(Rehab) 148 3 444 15 30 45 20SchoolBuilding 1545.49m2 1person/4m2 386 15 30 45 17SaleFlats 975 6 5,850 90 45 135 790Retail/Commercial 6007.27m2 1person/10m2 601 15 30 45 27
Total 18,789 2,408
SwimmingPoolWaterMake‐Up
6
TotalWaterRequired 2,414
SewageGeneration 2,249
Sludge 22RecyclingforFlushing
RehabFlats 1918 6 11,508 45 45 518Shops(Rehab) 148 3 444 30 30 13SchoolBuilding 1545.49m2 1person/4m2 386 30 30 12SaleFlats 975 6 5,850 45 45 263Retail/Commercial 6007.27m2 1person/10m2 601 30 30 18Total 18,789 824
3,192.47 m2 5l/m2 16ExcessTreatedWatertoMunicipalSewer
1,387
90%ofDomestic&100%ofFlushingRequirement
RecyclingforGardening
WaterRequirementBasis(inlpcd)*
1%ofSewageGeneration
BasisforWatersupplyistakenfromBIS:NationalBuildingCodeofIndia2005:Part9pg19
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 32
ANNEXUREVII
ENVIRONMENTALMANAGEMENTPLANDURINGCONSTRUCTIONPHASE
Sr.No.
EnvironmentalComponents
PredictedImpacts
ProbablesourceofImpact
MitigationMeasures
Remarks
CONSTRUCTIONPHASE1. AmbientAir
QualityNegativeimpactinsideconstructionsitepremises.Nonegativeimpactoutsidesite.
Dustemissionsfromexcavation,airemissionsfrommachineryandotherconstructionactivitiesatsite.
Dustreductionmeasuressuchasroadwatering.Periodicmaintenanceofconstructionequipment.Useofgoodqualityfuels.UseofPersonalProtectiveEquipments
Impactsaretemporaryduringconstructionphase.Impactswillbeconfinedtoshortdistances,ascoarseparticleswillsettlewithintheshortdistancefromactivities.
2. Noise Negativeimpactnearnoise
Useofwellmaintainedequipment.
generationsourcesinside
Noisegeneratedfrom
Heavyconstructionactivitylimitedtoday‐
Temporaryimpactsduring
premises.Nosignificantimpacton
constructionactivitiesandoperationofconstruction
timehoursonly.Useofnoisemufflersinandconstruction
constructionphase.Noblastingorotherhighnoiseactivities
ambientnoiselevelsinthe
equipmentandDGsets
vehicle. envisaged.
surroundingarea.
Useofearplugs/muffsbyconstructionstaff.
3. Water Nosignificantnegativeimpact.
Surfacerunofffromprojectsite.Oil/fuelandwastespills.Improperdebrisdisposal.Dischargeofsewagefromlabourcamp.
Siltfencestoreducerun‐offSecondarycontainmentanddykesinmaterialstorageareas.Sewagetreatmentinseptictanks.
Labourwillbeemployedtoreducesizeoflabourcamps.Noperennialsurfacewaterresourceadjacenttosite.Noexcavationworkwillbe
4. Land Minornegativeimpact
Excavation,Constructiondebris,waste
Reutilizationandrecyclingofconstructiondebris
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 33
fromlabourcamp.
Wastefromlabourcampswillbecollectedandcompostedonsite.Noncompostablewastewillbetransportedtolandfillsite.Topsoilwillbeconservedandusedforlandscapinginfunctionalphase.
‐
5. Aesthetics Minornegativeimpacts
ConstructionactivitiesandExcavation
Theimpactswillbecompensatedbyextensivetreeplantationandgardeningintheusephase.
Shorttermimpactrestrictedonlyintheinitialstagesofconstruction.
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 34
ENVIRONMENTALMANAGEMENTPLANDURINGFUNCTIONALPHASE
Sr.No.
EnvironmentalComponents
PredictedImpacts
ProbableSourceOfImpact
MitigationMeasures
Remarks
FunctionaLPHASE
1. AmbientAirQuality
MinorNegativeimpact
ParticulateandgaseousemissionsfromDGsetsandvehiclemovement
Useoflowsulphurgoodfuel
PeriodicmaintenanceofDGsets
UseofCNG/LPGasafuelshouldbeencouraged.
DGsetswillbeused.
2. Noise Minornegativeimpactinsidepremises.
Noisefromvehiclemovementandoperationofdieselgeneratorsetsduringpowerfailure.
HousingofDGsetsinbuildingswithappropriateacoustics.
Trafficmanagementmeasurestoreducenoise
Appropriatetreeswhichwillactasnoisesbarrierswillbeplantedinthepremisesandalongroadside.
‐‐
3. Water Nosignificantadverseimpact
Oil/fuelandwastespillsinvehicleparkingarea.
Dischargeofsewage.
Dischargeofcontaminatedstormwater
Sewagewaterwillbetreatedandrecycled.
Rainwaterharvestingandrechargeofgroundwateraquiferisproposed.
Goodhousekeepingandstormwatermanagementwillbefollowed.
Recycledwaterwillbeusedforgardeningandflushingpurpose.
4. Land Nonegative Storageanddisposalofsolid
Treatmentandreuse Segregationofdryandwet
Application form for Environmental Clearance Project Name: Redevelopment Project at Subhash Nagar, Thane (W).
Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 35
Sr.No.
EnvironmentalComponents
PredictedImpacts
ProbableSourceOfImpact
MitigationMeasures
Remarks
impact wastes.
Dischargeofsewage.
Fuelandmaterialspills.
ofsewagewater.
Integratedwastemanagementandspillcontrolplan
Drygarbagewillbesentforrecyclingandwetgarbagewillbecomposted.
garbagebeforewillbedonebeforedisposal.
5. Biological OverallPositiveimpact
Habitatdisturbance
Greenspacesinsidethepremiseswillhelptocompensatetheearliereffectfromvegetation.
Landscapingandextensiveplantationinthepremises.
Landscapingwillhelpinreducinganyadverseimpactsonairandnoisequality.
6. Socio‐economic
Overallpositiveimpact
Increasedjobopportunityinhouseholdmaintenanceandancillaryservices.
‐‐ Positiveandlongtermimpact‐
FunctionaLPHASE
7. TrafficPattern
NosignificantImpact
Thecomplexislikelytoaddmoderatelytothetrafficflowconsideredduringpeakhour.
TrafficManagementpractiseswillbeemployed.
Adequateparkingspacewillbeprovidedinthepremises.