foresite group, addendum - gwinnett county

9
Page 1 of 5 FORESITE GROUP, INC. ADDENDUM #2 3740 Davinci Court, Suite 100 Peachtree Corners, Georgia 30092 P| 770.368.1399 F| 770.368.1944 [email protected] TO: All Plan Holders & Interested Parties FROM: Foresite Group, Inc., Anthony Pappas– Project Manager PAGES: Nine (includes attachments) DATE: December 18, 2017 SUBJECT: Gwinnett County Department of Community Services Renovation of the Rhodes Jordan Aquatic Center BL13017, Addendum #2 ATTACHMENTS: PreBid Meeting Signin Sheet Product Data Sheet PreBid Meeting Items: 1. See attached signin sheet from the prebid meeting on 12/14/17. Questions/Answers: 1. Question: Is the pool painted currently? Answer: No. 2. Question: The plans say to remove the frog and log raft. Does anything new go in their place? Answer: The plans call for removal of the anchoring hardware for the floating raft and frog. There will not be anything new being installed in these two locations. Clean and patch anchor attachment areas before applying plaster. 3. Question: The plans call for items to be reworked in the mechanical room. Per our understanding, we are to replace the piping from the pump discharge on. So essentially 95% of the piping is being replaced. In the process, we are replacing the filters, the piping as described, the valves and gauges. We understand that we will be reusing the chemical feed systems, the pumps, pump strainers, pump suction piping valves, pump motor starters and flow meters. Please confirm. Answer: Please review plans and specs. Chemical Feed systems are to be reconnected per drawing details. Pump, pump suction valve and connection, strainer and motor starter to remain. New flowmeters are required.

Upload: others

Post on 18-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FORESITE GROUP, ADDENDUM - Gwinnett County

Page 1 of 5 

 FORESITE GROUP, INC.                    ADDENDUM #2 

3740 Davinci Court, Suite 100 Peachtree Corners, Georgia 30092 

P| 770.368.1399 F| 770.368.1944 

[email protected]  

 

TO:     All Plan Holders & Interested Parties FROM:   Foresite Group, Inc., Anthony Pappas– Project Manager PAGES:   Nine (includes attachments) DATE:     December 18, 2017 SUBJECT:   Gwinnett County Department of Community Services 

   Renovation of the Rhodes Jordan Aquatic Center    BL130‐17, Addendum #2 

 

ATTACHMENTS:  Pre‐Bid Meeting Sign‐in Sheet Product Data Sheet    

Pre‐ Bid Meeting Items:  

1. See attached sign‐in sheet from the pre‐bid meeting on 12/14/17.  

Questions/Answers:  

1. Question: Is the pool painted currently? Answer: No.  

2. Question: The plans say to remove the frog and log raft. Does anything new go in their place? Answer: The plans call  for  removal of  the anchoring hardware  for the floating raft and frog. There will not be anything new being installed in these two locations. Clean and patch anchor attachment areas before applying plaster. 

 3. Question: The plans call for  items to be reworked  in the mechanical room. Per 

our understanding, we are to replace the piping from the pump discharge on. So essentially 95% of the piping  is being replaced. In the process, we are replacing the  filters, the piping as described, the valves and gauges. We understand that we will be re‐using the chemical feed systems, the pumps, pump strainers, pump suction  piping  valves,  pump motor  starters  and  flow meters.  Please  confirm. Answer:  Please  review  plans  and  specs.  Chemical  Feed  systems  are  to  be  re‐connected  per  drawing  details.  Pump,  pump  suction  valve  and  connection, strainer and motor starter to remain. New flowmeters are required. 

Page 2: FORESITE GROUP, ADDENDUM - Gwinnett County

Page 2 of 5 

 4. Question: The specifications  indicate the “main drains are to be constructed to 

meet VGB  requirements”. Are we  replacing  the grating and  frames only or are we tearing out the existing drains and reconstructing? Please confirm. If we are modifying  the  concrete  boxes,  please  provide  details.  Answer:  The  existing drains are  to be  removed and  reconstructed with all new pieces. The  concrete boxes are to remain unmodified.   

5. Question: The plans show safety pads at the termination of two play slides and the large pad under the rope swing. Do we remove all three pads and reinstall or remove  the  pads  and  replace with  new  pads?  If  new  pads,  please  specify  a manufacturer.  Answer:  The Owner will  provide  three  (3)  new  safety  pads  for these  locations. The Contractor  is to remove all three (3) safety pads, clean and re‐install Owner provided pads.   

6. Question: Can we get a manufacturer of  the  lily pads  that are  to be  replaced? Answer: The Owner will provide the replacement lily pad, all new anchoring and associated fastening hardware. The BoMar floatable Lily Pad FL50 (Large) to be installed is shown in the attachments for reference.  

 7. Question: We understand that we are to remove and clean the pads at the base 

of  the  poles  at  the  Lily Walk. Do we  replace  or  simply  reinstall?  If we  are  to replace the pads, please specify a manufacturer. Answer: Contractor to remove, clean pool deck and install new Owner provided pads.  

 8. Question: It is our understanding that the original construction including padding 

around the  four cargo net poles.  Is any work to be done to this padding at the poles? Answer: The pads currently wrapping the poles are new and are to remain in place. Contractor to clean existing pads.  

 9. Question:  Note  13  on  Sheet  C‐0,  says,  “Remove  padded  seat  wall”.  Do  we 

assume  that  this means  removed padding not  the  seat wall? Answer: Remove padding currently  installed on seat wall. Concrete wall to remain. Contractor to purchase and install new padding in this location.  

 10. Question:  Can  you  provide  a  manufacturer  for  the  replacement  seat  wall 

padding? Answer: Renosys softside safety pads or equivalent to match existing ‐ (800) 783‐7005. 

 11. Question: A note on C‐0 says to remove 6 Lily pad panels and protect cylinders in 

place. Are the cylinders considered to be the floor anchors? Answer: Yes.  

12. Question:There is a detail on Sheet C‐2 that shows floatable anchors with cover. Is  this detail  included so  that Contractor has an  idea of what  the anchors  look 

Page 3: FORESITE GROUP, ADDENDUM - Gwinnett County

Page 3 of 5 

like under the frog and log raft? Or does this mean that we are supposed to put in new anchors somewhere?Answer: This detail  is  included so that Contractors understand what the anchors look like. The frog and log raft and anchors are not being replaced. These anchor locations are to be plastered over. 

 13. Question: Spec  section  2.04B  specifies  the  installation  of  new  collector  tubes 

under the main drains. Are we replacing collector tubes, please confirm. Answer: No. 

 14. Question:Spec section 2.05, A1 says “Provide piping between the pool and filter 

room”. Are we  tearing out existing piping all  the way  to  the equipment room? Answer: No. 

 15. Question: Spec 2.05B5 Specifies pipe below the deck and below the equipment 

room  floor.  Are  we  installing  any  new  pipe  under  the  deck  or  under  the equipment room floor? Answer: No. 

 16. Question: Other than piping above grade in the mechanical room, why are there 

references in the specifications to below grade piping? Answer: There will be no below grade piping work. 

 17. Question:2.05B10, This paragraph specifies the installation of a site sump pump 

and  piping.  Confirm  if  a  new  site  sump  is  required. Answer:  Site  sump  is  not required. 

 18. Question:2.05B13 specifies all stainless steel fasteners and hardware. Is this just 

for the new valves and flanges in the replacement piping or are we replacing the bolts  and  fasteners  on  the  suction  piping  that  remains.  Answer:  All  new connections that require hardware shall be stainless steel. 

 19. Question:2.05B18, This paragraph specifies the use of waterstop collars on new 

pipe penetrations at walls, we do not see any pipe penetrations specified, please confirm. Answer: Waterstop collars are not required. 

 20. Question:Can we get a specification for painting the water features as shown on 

the drawings? Answer: There is to be no painting on any of the play structures in the pool.  

 21. Question:The drawings  indicate that the play structure, mushroom and tipping 

bucket  get  cleaned  and  repainted.  Can  we  assume  that  the poly/plastic/fiberglass waterslides on  the play  structure do not get painted?  If they do get painted, please specify a paint for the poly/plastic slides. Answer: Do not paint play structure elements. 

 

Page 4: FORESITE GROUP, ADDENDUM - Gwinnett County

Page 4 of 5 

22. Question: There  is  a  large  commercial  water  slide  and  slide  tower.  Please confirm  that  no  painting work  is  to  be  done  on  the  slide  tower. Answer: No painting work is to be done on the slide tower. 

 23. Question:Regarding the specifications,  it seems  like this project would be best 

served if we got a new, job specific set of specifications. Unless we are mistaken, there are dozens of references in the specifications on work that is not shown on the  drawings.  Please  confirm.  Answer: Work  not  shown  in  the  drawings was included in the specifications in the event additional work is required to complete work shown in the drawings.   

24. Question: There  is one relief fan to be replaced  in the pump room and exhaust fans in the acid and chlorine rooms. Are the exterior louvres to remain? Answer: Yes, the exterior louvres are to remain.   

25. Question: Will HVAC or electrician wire exhaust fans? Answer: The work shown on  the  plans  is  to  be  installed  and working  correctly  per  the  project  contract. Trades  required  to  install  and  connect  the  work  shown  in  the  plans  will  be determined by the General Contractor. 

 26. Question: The specifications call out three  (3)  layers of tile to be removed and 

replaced. How many  layers of tile are there to be replaced? Answer: All tiles  in pool and around pool and coping are to be removed and replaced with new tile. Currently there are two (2) layers of tile in place scheduled for removal and demo in the project plans.   

27. Question:  There  are  two  (2)  cup  anchors  with  no  callouts  directing  the Contractor  to  remove  and  or  replace. What  is  to  be  done with  the  anchors? Answer:  These  anchors  are  to  be  removed  and  the  area  underneath  is  to  be cleaned, patched and plastered over.   

28. Question:  Is  the  caulk  joint  between  the  tile  and  the  coping  to  be  replaced? Answer:  All  joints  on  the  pool  deck,  adjacent  the  coping  and  tile  are  to  be replaced to match existing per manufacturers recommendation.  

 29. Question: The plans have a callout to paint the walls, ceiling, doors and floors in 

the pump room and acid/chlorine rooms. Is the floor to be painted the same as the other surfaces? Answer: The floor in the pump room and acid/chlorine rooms is  to be sealed with Tnemec or equivalent epoxy sealant  to match existing and appropriate for a pool chemical environment. Contractor to submit product data to Owner’s Representative for submittal review prior to construction.  

Page 5: FORESITE GROUP, ADDENDUM - Gwinnett County

Page 5 of 5 

30. Question: We understand  that  the  scope of work  for  this project  includes  the caulk  joint around  the pool at  the back  side of  the coping. However, does our proposal need to  include new caulk for the rest of the deck joints? These joints tie  together  in  some places. Answer: Deck  caulking  is  included  in  the  scope of work, pre sheet C‐0 Legend; and Project Manual, Scope of Work , section 01010‐1, Part 1 GENERAL, C., item #3, “Removal and replacement of all caulking on pool deck joints and pool tiling”. 

  

END OF ADDENDUM 2 

Page 6: FORESITE GROUP, ADDENDUM - Gwinnett County
Page 7: FORESITE GROUP, ADDENDUM - Gwinnett County

P.O. Box 495

Mount Dora, FL 32757

Phone: 352.742.9193

Fax: 352.343.3872

www.bomarsoftplaygrounds.com

email: [email protected] or [email protected]

Floatable Submittal: Lily Pad

© 2016 BoMar Soft Playgrounds International, Inc. All Rights Reserved. Designs are the property of BoMar Soft Playgrounds International, Inc. and are not to be sold or distributed to any other party without expressed written consent. Prices, colors and designs are subject to change at the discretion of BoMar Soft Playgrounds International, Inc.

TYP. Urethane Color Coating

1/8” Flexible Urethane Coating

Fiberglass Reinforcement

Sculpted Closed Cell Foam

Urethane Color Coating

Flexible Urethane Coating

S.S. Anchor

Features• High density soft EVA closed cell foam (sculpted)• Flexible rubberized urethane coatings for foam

protection• Fiberglass reinforced base coatings for added

strength• High gloss, durable urethane coloration for UV

resistance• Stainless steel base plate with a 3” cup and 3/8”

bar for attaching the chain clip

Optional S.S. Chain• Stainless steel 3/8” chain for anchoring• Stainless steel 3” pool cup anchor with 3/8” ss bar,

threaded for removable plug• Stainless steel 3/8” jaw to eye swivel to attach

chain to floatable and cup anchor• Reinforced PVC sleeve for each chain• Easy set up, stainless steel hardware

WarrantyFull time waterpark:1 year on all defects in workmanship and materialsunder normal use.

All seasonal parks:2 years (2 seasons) on defects in workmanship andmaterials under normal use.

Should defects occur, contact BoMar SoftPlaygrounds within 5 days of the occurrence.

FL48 Lily Pad (Small) 3’ 3’ 6”FL49 Lily Pad (Medium) 42” 42” 6”FL50 Lily Pad (Large) 4’ 4’ 9”

Length Width Height

Side View

Top View

Page 8: FORESITE GROUP, ADDENDUM - Gwinnett County

! Submittal

!

Page 9: FORESITE GROUP, ADDENDUM - Gwinnett County

P.O. Box 495Mount Dora, FL 32757Phone: 352.742.9193

Fax: 352.343-3872www.bomarsoftplaygrounds.com

email: [email protected] or [email protected]

Submittal: Cup and Anchor for Floatables

Chain comes in various sizesLength Width Height

© 2010 BoMar Soft Playgrounds International, Inc. All Rights Reserved. Designs are the property of BoMar Soft PlaygroundsInternational, Inc. and are not to be sold or distributed to any other party without expressed written consent. Prices, colors anddesigns are subject to change at the discretion of BoMar Soft Playgrounds International, Inc.

Specs316 stainless steel chain316 cup anchor

Fiber reinforced chain cover for safety

WarrantyFull time waterpark:1 year on all defects in workmanship and materialsunder normal use.

All seasonal parks:2 years (2 seasons) on defects in workmanship andmaterials under normal use.

Should defects occur, contact BoMar Soft Playgroundswithin 5 days of the occurrence.