Project Status
![Page 3: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/3.jpg)
For Discussion Purposes Only 3
Rights-of-Way & Permits
ROW Remaining
All in place (Recent Washoe BIA Approval this week)
NTIA Route Changes for 5 Route Changes (2 NV, 3 CA)
Encroachment Permits
City of Reno Permits for M101( Approval 3/4/13)
Caltrans (Big Pine to China Lake)
Distribution
County Licenses for Kern County approval 3/3/13
County and City licenses include Anchor Access Agreements
NTIA Route Changes for 25 anchors and POIs
![Page 4: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/4.jpg)
Construction Status - Nevada
Installed Plant
Reno / Carson Nodes
28 miles fiber (Reno-Carson)
Conduit: 2 Segments
Present Operations
Curtis & Sons, Apex
Focused on 395 thru Carson
Issues
BIA Approval to Proceed in N111-N113
2 Route Changes (2,000 ft)
![Page 5: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/5.jpg)
Construction Status – Mono County
Installed Plant
Antelope, Bridgeport, Lee Vining, Mammoth Nodes
39 miles fiber (Coleville-VL)
Conduit: 8 Segments
Present Operations
Kleven, Westech, Apex, ASI
Focused State Line to June, and South of Mammoth to Crowley
Issues
Inyo National Forest
1 Route Changes (Mammoth)
![Page 6: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/6.jpg)
Construction Status – Inyo County
Installed Plant
Bishop, Independence, and Nodes (Olancha is in GS10)
2 miles fiber (Reno-Carson)
Conduit: 3 Segments
Present Operations
Westech – Heavily Plowing
Focused on southward from Bishop
Issues
BLM Trespass (Resolved)
Caltrans Permits
1 Route Change (Round Valley)
![Page 7: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/7.jpg)
Caltrans Permit Progress
![Page 8: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/8.jpg)
Construction Status – Kern & South End
Installed Plant
Reno / Carson Nodes
104 miles fiber (Barstow-Pearsonville)
Conduit: 15 Segments
Cable: 14 Segments
Present Operations
Westech, McCullin Pipeline
Ridgecrest Distribution
Focus
K121 (Inyokern Lateral)
County of Kern Distribution
![Page 9: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/9.jpg)
Environmental Issues / Responses
For Discussion Purposes Only 9
BLM
Claim: Trespassing into WSA: Outcome 200’ conduit re-installationt
$15K Study Cost; $20K for project monitoring
Section 106 Violations
N103 alleged disturbing of sacred artifacts - NTIA validated our practices
ESA Breach: Contractor drove over ESA; Invalidated by NTIA Study
INF archeological concerns: NTIA working with USFS
Long Bores (over 2,000 ft): negotiating for pit excavations, break up
Biological
Construction crews would be locked out of bird nesting areas: accelerated work in sensitive areas and obtained relief on timeframes
DFG 1602 Violations: Audit found unsatisfactory training with Sub-Contractors. Proactive Ride-Alongs, Training Sessions
![Page 10: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/10.jpg)
Node Construction
![Page 11: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/11.jpg)
Node Construction
For Discussion Purposes Only 11
Node Land Permit Site Bldg Powered
Reno Owned Yes Completed Placed Yes
Carson Owned Yes Completed Placed Yes
Antelope Fire Dist Yes Completed Placed Yes
Bridgeport County Yes Completed Placed No
Lee Vining School Yes Completed Placed No
Mammoth School Yes Completed Placed No
Bishop LADWP Yes 2/26/13 Ready N/A
Independence County Yes 3/1/13 Ready N/A
Olancha County Yes/PA 3/15/13 Ready N/A
Ridgecrest Owned Yes In Const Placed N/A
Barstow Owned Yes 3/7/13 Ready N/A
![Page 12: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/12.jpg)
Distribution Construction
For Discussion Purposes Only 12
Key Service Areas (Ridgecrest, Mammoth, Bishop) Contract Awarded to Kleven Construction underway in Ridgecrest Mammoth construction starts post April. To be
challenged in March Other Areas: Benton, Walker, Coleville, Bridgeport,
Lee Vining, Big Pine, Independence, and Lone Pine
Praxis Focus (Aerial and Smaller Areas) Boron InyoKern Round Valley (Aerial) Benton Tribe(Aerial) Bridgeport Indian Colony China Lake Distribution (Aerial) June Lake (Aerial) Randsburg / Johannesberg (Aerial) Cerro Community College (Aerial)
![Page 13: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/13.jpg)
Inyokern Distribution and Anchors
![Page 14: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/14.jpg)
Ridgecrest Distribution and Anchors
For Discussion Purposes Only 14
![Page 15: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/15.jpg)
Ridgecrest – China Lake Blvd.
![Page 16: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/16.jpg)
Bishop Distribution and Anchors
![Page 17: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/17.jpg)
Independence Distribution & Anchors
For Discussion Purposes Only 17
![Page 18: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/18.jpg)
Anchor Status
For Discussion Purposes Only 18
Attribute Number Comment
Anchors Visited 328
Completed Engineering Surveys 322
Access Agreements Signed 228
Access Agreements Pending 14 Kern Co Agreement
Access Agreements Rejected 0
Not Access Agreements in Place 37
Anchors Cancelled 39 By Choice of Customer / Site Moved
TOTAL ANCHORS 328
![Page 19: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/19.jpg)
Anchor Service Trench
For Discussion Purposes Only 19
Anchor Service Trench Integration With Backbone Conduit Placement. When the backbone work is being done in the street the backbone contractor will place the service trench and conduit to the customer location.
Cost savings over separate service trench. Using the same equipment and work setup as the backbone
Time savings. One crew completes backbone and service trench/conduit placement
Less disruption to anchor locations
Praxis fiber and NID installation follows
![Page 20: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/20.jpg)
Anchor Service Trench Ridgecrest Regional Hospital
For Discussion Purposes Only 20
This service trench will be completed by boring onto Hospital property using the same work setup and equipment as the backbone work on K104 that places conduit on N China Lake Blvd
![Page 21: For Discussion Purposes Only Digital 395 SE C RBC– Board Presentation Discussion Guide February 28, 2013](https://reader034.vdocuments.mx/reader034/viewer/2022051517/56649cb75503460f9497cce6/html5/thumbnails/21.jpg)
For Discussion Purposes Only 21
Thank You