FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE MEETING

KENYA WILLIAMS

CAPITAL PROJECTS

Page 2: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

2

PLEASE HOLD ALL QUESTIONS

until the end of the presentation

that is when the Q&A session will begin

(Answers may be in the presentation)

Page 3: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

3

SERVICE LINES

Page 4: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

MARTHA CASTEX-TATUM

VICE MAYOR PRO-TEM

DISTRICT K

Page 5: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

JUAN CHAVIRA, PE

ASSISTANT DIRECTOR

CAPITAL PROJECTS

Page 6: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

6

THE PROJECT TEAM

MOHAMMAD SABZEVARI CITY OF HOUSTONSTEPHEN CAMPAGNA CITY OF HOUSTONMOHAMMAD WARRAD CITY OF HOUSTONIAN HLAVACEK CITY OF HOUSTON

ARAVIND NIMMA GUNDA CORPORATION LLCRAGHU VETURI GUNDA CORPORATION LLC

MARCEL STRACHAN CP&Y INC

Page 7: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

7

LET’S TALK ABOUT

what is this project

design updates

mobility features

next steps

Page 8: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

8

TYPE PAVING & DRAINAGE

STATUS DESIGN PHASE

BUDGET $32 MILLION

FONDREN ROAD

CONTACT STEPHEN CAMPAGNA

CITY OF HOUSTON PROJECT MANAGER832.395.2225

[email protected]

INSERT AERIAL MAP

Page 9: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

15,800LINEAR FT. OF STORM SEWER

PROJECT BY THE NUMBERS

24,000LINEAR FT. OF NEW SIDEWALK

2.2MILES OF NEW PAVEMENT

Figures are estimates and are subject to change

LINEAR FT. OF SANITARY SEWER

2,200

7

LINEAR FT. OF WATER LINES

14,600

TRAFFIC SIGNALS

Page 10: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

10

IMPROVEMENTS TO YOUR NEIGHBORHOOD

➢ Storm drainage system improvements for flooding relief

➢ New street paving

➢ New ADA compliance sidewalks

➢ New street lighting for vehicle and pedestrian safety

➢ New signal improvements with ADA compliance features

Page 11: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

MOHAMMAD SABZEVARI, PE

MANAGING ENGINEER

CAPITAL PROJECTS

Page 12: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

12

STORM DRAINAGE SYSTEM IMPROVEMENTS

➢ Improve capacity and Level of Service

➢ Increase drainage flow

➢ Better manhole placement and inlet improvements

➢ Enhanced safety for travel lanes during stormwater event

➢ In-line detention w/no adverse impact to Braes Bayou

Page 13: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

13

Page 14: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

14

Page 15: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

15

Page 16: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

16

Page 17: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

17

NEW DRAINAGE BOXES

Page 18: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

18

EXISTING ROADWAY CONDITIONS

Page 19: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

19

NEW INLET DESIGN

Page 20: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

20

NEW ROADWAY CROSS SECTION – TYPICAL

• 12-ft wide shared

bus lanes

• New 6-ft sidewalks

• Increased

pedestrian safety

Page 21: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

Fondren Road Schematics

21

Page 22: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

Fondren Road Schematics

22

Page 23: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

23

7 NEW SIGNAL ENHANCEMENTSINTERSECTIONS:

W. AIRPORT BLVD.

LUDINGTON DR.

W. BELLFORT AVE.

PORTAL DR.

CREEKBEND DR.

WILLOBEND DR.

S. BRAESWOOD BLVD.

Page 24: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

24

Page 25: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

25

Page 26: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

26

Page 27: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

IAN HLAVACEK, PE

MANAGING ENGINEER

TRANSPORTATION & DRAINAGE OPERATIONS

Page 28: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

28

EXISTING CRASH HEAT MAP

Page 29: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

29

SAFETY FEATURE: ACCESS MANAGEMENT

• Driveways and median openings create conflict points (x’s on the figure)

• Minimizing conflict points improves safety for people walking, bicycling, and driving

Page 30: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

30

ALTERNATIVES

We are currently looking at opportunities for left-turn designs.

Page 31: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

31

ECONOMIC IMPACTS – ACCESS MANAGEMENT

Federal Highway Administration:

“Installing raised medians often raises seriousconcerns by the business community that localbusinesses that depend upon pass-by traffic. . .willbe adversely affected by medians. Though thereare few studies of the actual impacts of medianson business sales, there are several surveys ofbusiness owner opinions. Surveys conducted inmultiple corridors in Texas, Iowa, and Floridademonstrate that the vast majority of businessowners believe there have been no declinesin sales, with some believing there are actuallyimprovements in business sales. . .One study inTexas indicated that corridors with access controlimprovements experienced an 18 percent increasein property values after construction.”

Source: https://safety.fhwa.dot.gov/geometric/pubs/accessmgmtbrochure/median.htm

Page 32: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

32

SAFETY FEATURE: LEFT-TURN LANES

• Left-turn lanes improve

traffic flow by removing

turning vehicles from through

lanes

• Left-turn lanes improve

safety by decreasing rear-

end collisions

• IDM requires left-turn

lanes at all median openings

However. . .

• New left-turn lanes do

impact trees and

landscaping

Page 33: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

33

MEDIAN OPENING REQUIRE LEFT-TURN LANES

Page 34: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

34

• Houston Public Works

is a leading Vision

Zero partner

• Houston Public Works

will be systematically

reviewing all projects

to find opportunities to

align with Vision Zero

• Some projects

(including Fondren)

have federal funding,

and any design

changes will need

approval of funding

partners

•Commitment to end

traffic deaths and

serious injuries by 2030.

•Traffic deaths and serious

injuries are an

unacceptable

and preventable public

health issue.

•Prioritizes street safety

and accessibility for all

modes and for people of

all ages and abilities.

Page 35: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

35

NEXT STEPS

Design Phase

2020

Construction Phase

2021

Construction Complete

2023

Timeline subject to change

Page 36: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

36

publicworks.houstontx.gov/engage

Page 37: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

37

WHO TO CONTACT

Send concerns or comments to

[email protected]

Questions? call 3.1.1 (713.837.0311)

visit houstontx.gov/311 (provide project #)

Page 38: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

38

THANK YOU!

Page 39: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …

39

QUESTIONS & ANSWERS