• Focus on DSA build: – Shielding build (Steel & Concrete) – Solenoid repair – Survey datum points – Solenoid plinth installation • Rail system & alignment – D2 installation in “out” position • Alignment, logistics (wt, position) – Cabling into synchrotron & DSA

Upload: maxine

Post on 24-Jan-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points Solenoid plinth installation Rail system & alignment D2 installation in “out” position Alignment, logistics (wt, position) Cabling into synchrotron & DSA. Hall Work Schedule. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

• Focus on DSA build:– Shielding build (Steel & Concrete)– Solenoid repair– Survey datum points– Solenoid plinth installation

• Rail system & alignment

– D2 installation in “out” position• Alignment, logistics (wt, position)

– Cabling into synchrotron & DSA

Page 2: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

Hall Work ScheduleWeekly coordination meetings (Tuesdays)

confirm responsibilities,plans & readiness

Page 3: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points
Page 4: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

02 09 16 23 30Shielding

Bracing

Survey

Plinth Rails

D2

Synchrotron Installation cabling

Straw man schedule (not to be taken too literally – shows tasks & interactions)

Page 5: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

Between now and December

• Buffer tank support– Manufacture (dwgs agreed, waiting for contract)– Installation (tied to wall)

• LCR– In progress (dwgs agreed, waiting for contract)

• Solenoid preparations– Repair & vac test– Controls & power supply to be completed

• Linde plant– Stand alone commissioning & with solenoid

• Q-triplet assemblies– Built up off line

• Q35 refurbishment• Water plant installation

Page 6: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

December – Jan Shutdown

17 24 31 7 14Shielding removal Shielding reinstallation

X-frames

Trolley

Solenoid

Align

D2, Q4-6

Power & water

Lab closedNo facilities or cover

}

Page 7: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

Not forgetting

• ToF & CKOV support (plans)• Platforms for LH system & Power supplies, RF (structure)• Magnetic shielding

– north and south

• Concrete platform to anchor MICE– Rolling platforms

– False floor

• Spectrometer solenoid installation• Power and cabling

Page 8: Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points

comment

• There’s an incredible amount to do before 1st August

• …and up to December shutdown

• Must plan steps, identify resources, agree with STFC/ISIS management to make Dec-Jan shutdown successful