focus on dsa build: shielding build (steel & concrete) solenoid repair survey datum points
DESCRIPTION
Focus on DSA build: Shielding build (Steel & Concrete) Solenoid repair Survey datum points Solenoid plinth installation Rail system & alignment D2 installation in “out” position Alignment, logistics (wt, position) Cabling into synchrotron & DSA. Hall Work Schedule. - PowerPoint PPT PresentationTRANSCRIPT
• Focus on DSA build:– Shielding build (Steel & Concrete)– Solenoid repair– Survey datum points– Solenoid plinth installation
• Rail system & alignment
– D2 installation in “out” position• Alignment, logistics (wt, position)
– Cabling into synchrotron & DSA
Hall Work ScheduleWeekly coordination meetings (Tuesdays)
confirm responsibilities,plans & readiness
02 09 16 23 30Shielding
Bracing
Survey
Plinth Rails
D2
Synchrotron Installation cabling
Straw man schedule (not to be taken too literally – shows tasks & interactions)
Between now and December
• Buffer tank support– Manufacture (dwgs agreed, waiting for contract)– Installation (tied to wall)
• LCR– In progress (dwgs agreed, waiting for contract)
• Solenoid preparations– Repair & vac test– Controls & power supply to be completed
• Linde plant– Stand alone commissioning & with solenoid
• Q-triplet assemblies– Built up off line
• Q35 refurbishment• Water plant installation
December – Jan Shutdown
17 24 31 7 14Shielding removal Shielding reinstallation
X-frames
Trolley
Solenoid
Align
D2, Q4-6
Power & water
Lab closedNo facilities or cover
}
Not forgetting
• ToF & CKOV support (plans)• Platforms for LH system & Power supplies, RF (structure)• Magnetic shielding
– north and south
• Concrete platform to anchor MICE– Rolling platforms
– False floor
• Spectrometer solenoid installation• Power and cabling
comment
• There’s an incredible amount to do before 1st August
• …and up to December shutdown
• Must plan steps, identify resources, agree with STFC/ISIS management to make Dec-Jan shutdown successful