flow time 2-critical path method based on the book: managing business process flows
DESCRIPTION
Flow Time 2-Critical Path Method Based on the book: Managing Business Process Flows. 6. 4. A3. A1. 4. 3. S. E. A4. A6. 3. 2. A2. A5. Flow Time Example: Activity Times. What is the Theoretical Flow Time. Critical Path method. Ardavan Asef-Vaziri, Sep. 2013. 2. A3. A1. S. E. - PowerPoint PPT PresentationTRANSCRIPT
4. Flow-Time Analysis
Flow Time
2-Critical Path Method
Based on the book: Managing Business Process Flows
4. Flow-Time Analysis
Flow Time Example: Activity Times
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
What is the Theoretical Flow Time Critical Path method 2Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Critical Path Method: Paths
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
Critical Path is the longest Path
How many paths?
Critical Path method 3Ardavan Asef-Vaziri, June, 2015
10 11 8
4. Flow-Time Analysis
Critical Path Example of Flow Time
a) The Critical Path is A1-A4-
A6. The theoretical flow time
of the process is 4+4+3= 11.
b) What will happen if
activity A5 is increased from
2 to 4?
A5 is not on critical path. Increasing its time by 2
increases the length of the path A2-A5-A6 from 8 to 10.
It does not become a critical path. The flow time is still
11.
c) What will happen if activity A5 is increased from 2 to
5?
Critical Path method 4Ardavan Asef-Vaziri, June, 2015
10 1
1 8
4. Flow-Time Analysis
Critical Path Example of Flow Time
The length of the path A2-A5-A6
becomes 11.
Both A1-A4-A6 and A2-A5-A6
are critical path. The flow time
is still 11.
d) What will happen if activity A1 is increased from 4 to
5?
Path A1-A4-A6 is still critical and the flow time increases
to 12.
e) What will happen if activity A3 is increased from 6 to
8?
Now path A1-A3 becomes critical and the flow time
increases to 4+8 =12.
Critical Path method 5Ardavan Asef-Vaziri, June, 2015
10 1
1 8
4. Flow-Time Analysis
Theoretical Critical Path vs. Critical Path
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
W1
W2
W4
W3
W6
W7
W5
W9
W8
The time of the critical path differs from the time of the theoretical critical path. Why?
The critical path itself also may differ from the theoretical critical path. Why?
Critical Path method 6Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Critical Path Methos: Forward Path; Earliest Starts
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S0
0
0
0
0
0
4
3
3
4
4
3
4
4
3
4
4 10
8
5
5
5
8 8
10
10
8 11
11
11
11
Critical Path method 7Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Forward Path; Earliest Starts
10
3020
Max = 30
5
35
35
35
Critical Path method 8Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Backward Path; Latest Starts
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S0
0
0
0
0
0
4
3
3
4
4
3
4
4
3
4
4 10
8
5
5
5
8 8
10
10
8 11
11
11
111
111
11
11
11
555
88
8
8
8
8
8
4
6
4
4
66
633
3
40
0
0 11
11
Critical Path method 9Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
30
3030
Min = 35
5
35
45
30
Backward Path; Latest Starts
Critical Path method 10Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Activity Slack
Slack, or float: The amount of time a noncritical
task can be delayed without delaying the project
Slack—LFT – EFT or LST – EST
EST—Earliest Start Time; Largest EFT of all predecessors
EFT—Earliest Finish Time; EST + duration for this
task
LFT—Latest Finish Time; Smallest LST of following tasks
LST—Latest Start Time; LFT – duration for this task
Critical Path method 11Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Critical Path, Slacks
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
0 4
3
4
4 10
8 8 11
11
11
11
5
88
8
4
663
40
11
Critical Path method 12Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
A Key Problem: The Impact Converging Activities
15Activity
215Activity
1
15Activity
15Activity
2
15Activity
1
Which process has a longer flow time?.
In a deterministic world they both have a flow time of 30 mins. The situation differs in real world where nothing is deterministic.Suppose instead of an exact number of 15, the activity time is uniformly distributed in the range of 10 to 20. The average is still 15.
Critical Path method 13Ardavan Asef-Vaziri, June, 2015
4. Flow-Time Analysis
Activity time = 10+10rand()rand() is a random number between 0 and 1. If it is ranch = 0, the duration of the activity is 10, if rand() = 1, 1, the duration of the activity is 20. For all possible rand() 10 ≤ Activity Time ≤ 20For the fist project, the project duration is computed as the duration of Activity 1 + duration of Activity 2. That is10+10rand()+10+10rand()We can generate 1000 instance of each activity in excel and compute project duration.
A Key Problem: The Impact Converging Activities
Critical Path method 15Ardavan Asef-Vaziri, June, 2015
Activity 1 Activity 2 Project 111.49 17.18 28.6718.24 10.55 28.7810.11 12.32 22.4312.87 14.05 26.9115.52 15.58 31.1119.19 16.92 36.1111.18 13.78 24.9712.55 12.12 24.6616.97 19.19 36.1618.11 11.54 29.6511.82 11.87 23.6814.11 16.55 30.6617.40 16.71 34.1111.35 17.84 29.1913.80 14.27 28.0610.17 17.33 27.5015.51 11.22 26.73
Average 30.02
4. Flow-Time Analysis
For project 2, still duration of all the activities are computed as 10 ≤ 10+10rand() ≤ 20However, the the project duration is computed as the MAX duration of (Activity 1, Activity 2) + duration of Activity 3. Max duration of (Activity 1, Activity 2) > 10+10rand(). That is the significance of convergence points.
A Key Problem: The Impact Converging Activities
Critical Path method 15Ardavan Asef-Vaziri, June, 2015
Not even in a single instance the duration of Project 1 was greater that that of Prject 2.
Act1 Act2 Act 1&2 Act 3 Project 2 d(p2)>=d(P1)11.49 15.63 15.63 17.18 32.81 118.24 15.98 18.24 10.55 28.78 110.11 15.66 15.66 12.32 27.98 112.87 15.68 15.68 14.05 29.73 115.52 19.11 19.11 15.58 34.69 119.19 12.84 19.19 16.92 36.11 111.18 15.49 15.49 13.78 29.27 112.55 16.59 16.59 12.12 28.70 116.97 16.41 16.97 19.19 36.16 118.11 18.55 18.55 11.54 30.09 111.82 19.03 19.03 11.87 30.90 114.11 16.35 16.35 16.55 32.90 117.40 10.33 17.40 16.71 34.11 111.35 15.00 15.00 17.84 32.84 113.80 15.08 15.08 14.27 29.34 110.17 15.03 15.03 17.33 32.35 115.51 17.66 17.66 11.22 28.88 1
Average= 31.71 1000
4. Flow-Time Analysis
Key Problem Flow time: 10,000 Instances
Critical Path method 17Ardavan Asef-Vaziri, June, 2015
Activity 1 Activity 2 Project 111.49 17.18 28.6718.24 10.55 28.7810.11 12.32 22.4312.87 14.05 26.9115.52 15.58 31.1119.19 16.92 36.1111.18 13.78 24.9712.55 12.12 24.6616.97 19.19 36.1618.11 11.54 29.6511.82 11.87 23.6814.11 16.55 30.6617.40 16.71 34.1111.35 17.84 29.1913.80 14.27 28.0610.17 17.33 27.5015.51 11.22 26.73
Average 30.02
Act1 Act2 Act 1&2 Act 3 Project 2 d(p2)>=d(P1)11.49 15.63 15.63 17.18 32.81 118.24 15.98 18.24 10.55 28.78 110.11 15.66 15.66 12.32 27.98 112.87 15.68 15.68 14.05 29.73 115.52 19.11 19.11 15.58 34.69 119.19 12.84 19.19 16.92 36.11 111.18 15.49 15.49 13.78 29.27 112.55 16.59 16.59 12.12 28.70 116.97 16.41 16.97 19.19 36.16 118.11 18.55 18.55 11.54 30.09 111.82 19.03 19.03 11.87 30.90 114.11 16.35 16.35 16.55 32.90 117.40 10.33 17.40 16.71 34.11 111.35 15.00 15.00 17.84 32.84 113.80 15.08 15.08 14.27 29.34 110.17 15.03 15.03 17.33 32.35 115.51 17.66 17.66 11.22 28.88 1
Average= 31.71 1000
4. Flow-Time Analysis
Converging Activities + Common Resources
Activity R2
Activity B2
Activity B1
Activity R1
Activity G
All activities are [10,20] minutes. 10+10RAND(). Average 15. One Recourse Red, One Resource Blue, One Resource Green.Project Duration >> 45
Critical Path method 18Ardavan Asef-Vaziri, June, 2015
Microsoft Excel Worksheet
4. Flow-Time Analysis
Activity B1 Activity R1 Max B1, R1 Activity R2 Activity B2 Upper Path Lower Pth Both Paths Activity G Project13.54 11.37 13.54 15.92 11.20 29.46 24.74 29.46 13.47 42.93 32.036514.11 18.92 18.92 17.78 16.42 36.70 35.34 36.70 12.43 49.13 34.1599217.06 18.57 18.57 10.49 19.18 29.06 37.75 37.75 11.58 49.33 36.179913.28 18.62 18.62 13.49 19.53 32.11 38.15 38.15 12.16 50.31 36.5076910.56 18.23 18.23 19.88 18.24 38.10 36.47 38.10 17.12 55.23 37.0730710.93 18.17 18.17 16.59 17.90 34.75 36.07 36.07 19.82 55.89 57.337716.27 12.90 16.27 14.08 15.20 30.35 31.48 31.48 11.48 42.96 57.3493716.61 14.26 16.61 19.68 16.76 36.29 33.37 36.29 10.42 46.71 57.3967312.75 19.72 19.72 11.70 19.96 31.42 39.68 39.68 14.55 54.23 57.4039811.41 17.03 17.03 19.08 12.91 36.11 29.94 36.11 13.37 49.48 57.4271613.82 10.23 13.82 18.60 10.44 32.42 24.26 32.42 14.39 46.81 57.6928512.45 18.87 18.87 15.98 16.83 34.85 35.70 35.70 10.39 46.09 57.7263811.54 10.69 11.54 16.92 11.90 28.46 23.45 28.46 15.78 44.24 57.8893616.32 19.50 19.50 16.63 17.89 36.13 37.38 37.38 18.75 56.13 57.9690517.21 15.19 17.21 15.61 13.87 32.83 31.08 32.83 13.91 46.74 58.167210.40 10.16 10.40 10.96 11.14 21.36 21.54 21.54 17.04 38.58 58.2273518.00 16.74 18.00 13.57 15.93 31.57 33.93 33.93 16.51 50.44 58.4555215.08 15.10 16.74 14.86 15.15 31.59 31.88 33.38 15.16 48.54
4. Flow-Time Analysis
1 23 45 67 89 11113315517719922124326528730933135337539741944146348550752955157359561763966168370572774977179381583785988190392594796999130
35
40
45
50
55
60