Flight Departures during Taxiway C Construction . San Diego International Airport . Phase 1. Start October 28,2009 = 78 Days of Construction. Phase 2. Start January 7,2010 = 66 Days of Construction. Phase 3. Start Feb 22, 2010 = 78 Days of Construction. Questions and Answers. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Flight Departures during Taxiway C Construction

FLIGHT DEPARTURES DURING TAXIWAY C CONSTRUCTION

San Diego International Airport

Page 2: Flight Departures during Taxiway C Construction

Phase 1

Start October 28,2009 = 78 Days of Construction

Page 3: Flight Departures during Taxiway C Construction

Phase 2

Start January 7,2010 = 66 Days of Construction

Page 4: Flight Departures during Taxiway C Construction

Phase 3

Start Feb 22, 2010 = 78 Days of Construction