7/25/2019 FL Smidth - Plant Overview - Water Consumption
1/16
Cement plant 1.2 Mio to/yearBrand NEW
Van Kennis / FL Smidth
Overview plant
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
2/16
World cement production
2010
Source: Wikipedia
Van Kennis / FL. Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
3/16
Scope of delivery:
- Feasibility including quantity ratio development, analysis of raw materials;
- Creating of basic engineering;
- Creating of construction layoutas built documentation,
- Delivery of the complete plant equipment;
- Delivery of automation systemprocess control unit;
- Delivery of elektrical kitsall wires and cables;
- Delivery of a cement lab including station for quality monitoring;
- Erection of the entire plant on civil work prepared groundings;
- Taking in funktionset and run up the completed plant;
- Training of the customers operating staff;
- Handing over of operation manuals and trouble shooting guidlines;
- One year full replacement warranty.
Van Kennis FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
4/16
Scope of erection:
- Erecting of the entire plant by an experienced team of the main supplier;
- Erecting under supervision of an experienced German engineering team;
- Erection will be done only in safe countries;
- The numbers of engineers and build-up staff will be paid by the seller,but have to be hosted by the purchaser;
- In case of build-up in a unsafe country have to be veriefied separate
instalment plans between the parties;
Delivery does not include:
- Delivery and transportation from the customers harbour to the erection place;
- Civil work;
- Any house-building work;
- Any steel frame work, except from the supplied steel construction;
- Lightning protection.
Van Kennis / FL. Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
5/16
1 Quarry
2 Crushers
3 Raw material homogenization
4 Aggregates
5 Raw material silos
6 Chimney
7 Electrical filter
8 Raw material vertical mill
9 Raw grist silo10 Evaporation cooler
11 Filter alkali bypass
12 Mixer for alkali bypass
13 Cyclon preheater
14 Coal
15 Coal grist mill
16 Filter for coal mill
17 Tube cooler
18 Filter clinker cooler
19 Clinker cooler
20 Rotary kiln
21 Clinker silo
22 Gypsum
23 Minerals
24 Classifier
25 Grinding mill (vertical or ball)
26 Packing station27 Palette control station
Scheme
Van Kennis / FL Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
6/16
Main supplier PENGFEIlicensed by FL-Smidth Danmark
Van Kennis - FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
7/16
Latest project done
in Aserbaidschan
Van Kennis/Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
8/16
Vertical mill
Ball mill
Rotary kiln
The customer determines the layout,
we just recommend
Van Kennis/FL. Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
9/16
Process analysing
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
10/16
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
11/16
Test lab by market leader WUXI
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
12/16
Energy facts:Gas consumption for rotary kiln: 6.673 m/h
Gas consumption for calcinator: 10.010 m/h
Electric power: 24.500 KW
Process water consumtion: 931 m/d
Area facts:Entire plant layout: 200.000 m
Ground loading total: 150.000 to
Transportation facts:20 & 40 container boxes: 11.000 to
Open sea flats: 8.000 to
Heaviest parts: 150 to
Gas rate: 35.82 MJ/Nm
28.000 KW recomm.
or 95 KW/to acc. ISO
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
13/16
TECHNICAL REPORT
FOR
4000T/D CEMENT PRODUCTION LINE
4000t/d
Final inspection together
with the customer on site
of supplier
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
14/16
Item/Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Gen.Layout
Geolo.Survey
Pre-design
Final design
Equipment
Training China
Shipping
Buildings
Erection
Com/Accept.
Site Training
Work schedule from valid contract onward to completion
Van Kennis/FL.Smidth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
15/16
Team work
Van Kennis/FL.Smidth
SuppliersSuper vision
Erection work
Van Kennis/FL.Smidth
V K i /FL S idth
-
7/25/2019 FL Smidth - Plant Overview - Water Consumption
16/16
Enjoying the new cement plant
Van Kennis/FL.Smidth
Congratulations with this plant