  • FIVE POINTS ACTION PLAN UPDATENeighborhood Transportation Management ProgramDenver Public WorksSeptember 5, 2019

  • Past Studies Review NE Neighborhoods Next Steps Study (2015) Progress NTMP: Five Points Updateo What is the Neighborhood Transportation Management Program?o NTMP Action Plan Process Reviewo Five Points Timeline Updateo Action Plan Onlineo NTMP: Five Points Installation Status Looking Forward Questions

    TOPICS

    N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    PAST STUDIES:Curtis Park Neighborhood

    Assessment (2007)

    38th & BlakeStation Area Plan (2009)

    Next Steps (2011)

    NE Downtown Neighborhoods

    Study (2011)Next Steps (2015)

    NTMP: Five PointsAction Plan(2019)

  • NE DOWNTOWN STUDY (2011),NEXT STEPS (2015),

    OFVO O T

    ERE R

    VIEW Expands on the Curtis

    Park Neighborhood Assessment (2007) Process:o Identify & Prioritize a

    Project ListoPrioritized by four key

    elements

    N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    oCost Estimates Produced

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NE DOWNTOWN NEXT STEPS STUDY (2015)TIER 1 PROJECT STATUS

    1 Welton St: One to Two Way Conversion (Park Ave to Downing) Needs Additional Study2 Larimer St: Ped/Bike Crossing at Broadway Elevate Denver Bond Program3 21st St: Festival St/Bike Boulevard (Blake to 20th Avenue) Study/Design Starts 20204 31st St Bicycle/Pedestrian Bridge (over UPRR tracks) RiNo Railroad Connectivity Study5 21st St: Ped/Bike Crossing at Broadway Complete6 Broadway Study: Ped/Bike Crossings (Welton to Larimer) Study Starts 20207 Blake St: One to Two Way Conversion (38th St to Broadway) Complete8 Larimer St: One to Two Way Conversion (Broadway to 18th St) Needs Additional Study9 Broadway: Study to Evaluate Alternatives (Arapahoe to Welton) Study Starts 2020

    10 Welton St: Ped/Bike Crossing at Broadway Study Starts 2020

    Sheet1

    Project NameStatus

    1Welton St: One to Two Way Conversion (Park Ave to Downing)Needs Additional Study

    2Larimer St: Ped/Bike Crossing at BroadwayElevate Denver Bond Program

    321st St: Festival St/Bike Boulevard (Blake to 20th Avenue)Study/Design Starts 2020

    431st St Bicycle/Pedestrian Bridge (over UPRR tracks)RiNo Railroad Connectivity Study

    521st St: Ped/Bike Crossing at BroadwayComplete

    6Broadway Study: Ped/Bike Crossings (Welton to Larimer)Study Starts 2020

    7Blake St: One to Two Way Conversion (38th St to Broadway)Complete

    8Larimer St: One to Two Way Conversion (Broadway to 18th St)Needs Additional Study

    9Broadway: Study to Evaluate Alternatives (Arapahoe to Welton)Study Starts 2020

    10Welton St: Ped/Bike Crossing at BroadwayStudy Starts 2020

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NE DOWNTOWN NEXT STEPS STUDY (2015)TIER 2 PROJECT STATUS

    Project Name Status11 Blake St: One to Two Way Conversion (Broadway to 18th St) Needs Additional Study12 Curtis Park Traffic Calming Opportunities NTMP, Neighborhood Bikeways13 Lawrence St: Ped/Bike Crossing at Broadway Improved14 River North and Ballpark Complete Sidewalk Network Needs Additional Study15 Arapahoe St: Ped/Bike Crossing at Broadway Improved16 Champa St: Ped/Bike Crossing at Broadway Improved17 Curtis St: Ped/Bike Crossing at Broadway Not Started, Study Starts 202018 Stout St: Ped/Bike Crossing at Broadway Improved19 28th St: One to Two Way Conversion (Welton to Glenarm) NTMP Project20 24th St: Ped/Bike Crossing at Broadway Not Started, Study Starts 202021 27th St: One to Two Way Conversion (Welton to California) Needs Additional Study22 Study Connecting Parks to Destination Areas Needs Additional Study23 Curtis St Enhance Pedestrian Environment Needs Additional Study

    Sheet1

    Project NameStatus

    11Blake St: One to Two Way Conversion (Broadway to 18th St)Needs Additional Study

    12Curtis Park Traffic Calming OpportunitiesNTMP, Neighborhood Bikeways

    13Lawrence St: Ped/Bike Crossing at BroadwayImproved

    14River North and Ballpark Complete Sidewalk NetworkNeeds Additional Study

    15Arapahoe St: Ped/Bike Crossing at BroadwayImproved

    16Champa St: Ped/Bike Crossing at BroadwayImproved

    17Curtis St: Ped/Bike Crossing at BroadwayNot Started, Study Starts 2020

    18Stout St: Ped/Bike Crossing at BroadwayImproved

    1928th St: One to Two Way Conversion (Welton to Glenarm)NTMP Project

    2024th St: Ped/Bike Crossing at BroadwayNot Started, Study Starts 2020

    2127th St: One to Two Way Conversion (Welton to California)Needs Additional Study

    22Study Connecting Parks to Destination AreasNeeds Additional Study

    23Curtis St Enhance Pedestrian EnvironmentNeeds Additional Study

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NE DOWNTOWN NEXT STEPS STUDY (2015)TIER 3 PROJECT STATUS

    Project Name Status24 22nd St: One to Two Way Conversion (Champa to Stout) Needs Additional Study25 Glenarm Pl: One to Two Way Conversion (29th Street to Downing) Needs Additional Study26 Walnut St: One to Two Way Conversion (18th to Downing) Design 2020: Broadway to Downing27 Downtown Strategic Transportation Plan Travelshed Analysis DM: Downtown 2019-202028 Curtis St: One Way to Two Way Conversion (18th St to Broadway) Needs Additional Study29 California St: One Way to Two Way Conversion (Park Ave to Broadway) Needs Additional Study30 Champa St: One to Two Way Conversion (Downing to Broadway) Needs Additional Study31 Stout St: One to Two Way Conversion (Broadway to Downing) Needs Additional Study32 33rd St Multimodal Bridge (across UPRR tracks) RiNo Railroad Connectivity Study

    Sheet1

    Project NameStatus

    2422nd St: One to Two Way Conversion (Champa to Stout)Needs Additional Study

    25Glenarm Pl: One to Two Way Conversion (29th Street to Downing)Needs Additional Study

    26Walnut St: One to Two Way Conversion (18th to Downing)Design 2020: Broadway to Downing

    27Downtown Strategic Transportation Plan Travelshed AnalysisDM: Downtown 2019-2020

    28Curtis St: One Way to Two Way Conversion (18th St to Broadway)Needs Additional Study

    29California St: One Way to Two Way Conversion (Park Ave to Broadway)Needs Additional Study

    30Champa St: One to Two Way Conversion (Downing to Broadway)Needs Additional Study

    31Stout St: One to Two Way Conversion (Broadway to Downing)Needs Additional Study

    3233rd St Multimodal Bridge (across UPRR tracks)RiNo Railroad Connectivity Study

  • F O O T E R

    The NTMP is a new program from Public Works that identifies

    and delivers solutions to holistically address our neighborhood’s transportation priorities and challenges, through proactive outreach to residents. The program thoughtfully identifies operational improvements and longer-term projects.

    WHAT IS THE NEIGHBORHOOD TRANSPORTATION MANAGEMENT PROGRAM?

    N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

  • FIVE POINTS ACTION PLAN PROCESS

    N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    Spring/Summer 2018 Fall to Winter 2018 Summer 2019, Ongoing

  • FIVE POINTSACTION PLAN TIMELINE The timeline for the NTMP Five Points Action Plan has been

    updated to reflect up-to-date information:

  • Plan is completed and uploaded to the NTMP Website NTMP Operational

    Improvements are being installed/reviewed/designed NTMP Projects - Designs are in

    the process of or planned to get underway over next 2 months.

    FIVE POINTSACTION PLAN UPDATE

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    FINAL NTMP PROJECT MAP, PART 1

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    FINAL NTMP PROJECT MAP, PART 2

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NTMP PROJECT LIST & DESCRIPTIONSImprovement Type

    Improvement Type

    12 Larimer St and 31st St Intersection Daylighting, Crosswalks and Stop Bars18 Larimer St and 25th St Crosswalks and Stop Bars21 Arapahoe St and 32nd St New 4-Way Stop, Crosswalks and Stop Bars22 Arapahoe St and 31st St Crosswalks and Stop Bars24 Curtis St and 31st St New 4-Way Stop, Crosswalks and Stop Bars28 Curtis St and 25th St Intersection Daylighting37 Clarkson St and 26th Ave Intersection Daylighting38 Clarkson St and 25th Ave Intersection Daylighting39 Clarkson St and 23rd Ave Intersection Daylighting40 Emerson St and 26th Ave/28th St. New 4-Way Stop, Crosswalks and Stop Bars42 Emerson St and 23rd Ave Intersection Daylighting43 Washington St and 23rd Ave Crosswalks and Stop Bars44 Washington St and 22nd Ave Daylighting, Crosswalks

    NTMP Operational Project Number & Project Name

    2019 Installed

    2019 Coming Soon

    14 Larimer St and 29th St New 4-Way Stop, Crosswalks and Stop Bars, Intersect 16 Larimer St and 27th St Crosswalks and Stop Bars17 Larimer St and 26th St Crosswalks and Stop Bars

    NTMP Operational Project Number & Project Name

    Sheet1

    NTMP Operational Project Number & Project NameImprovement Type

    12Larimer St and 31st StIntersection Daylighting, Crosswalks and Stop Bars

    18Larimer St and 25th StCrosswalks and Stop Bars

    21Arapahoe St and 32nd StNew 4-Way Stop, Crosswalks and Stop Bars

    22Arapahoe St and 31st StCrosswalks and Stop Bars

    24Curtis St and 31st StNew 4-Way Stop, Crosswalks and Stop Bars

    28Curtis St and 25th StIntersection Daylighting

    37Clarkson St and 26th AveIntersection Daylighting

    38Clarkson St and 25th AveIntersection Daylighting

    39Clarkson St and 23rd AveIntersection Daylighting

    40Emerson St and 26th Ave/28th St.New 4-Way Stop, Crosswalks and Stop Bars

    42Emerson St and 23rd AveIntersection Daylighting

    43Washington St and 23rd AveCrosswalks and Stop Bars

    44Washington St and 22nd AveDaylighting, Crosswalks

    Sheet1

    NTMP Operational Project Number & Project NameImprovement Type

    14Larimer St and 29th StNew 4-Way Stop, Crosswalks and Stop Bars, Intersection Daylighting

    16Larimer St and 27th StCrosswalks and Stop Bars

    17Larimer St and 26th StCrosswalks and Stop Bars

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NTMP PROJECT LIST & DESCRIPTIONS

    NTMP Operational Project Number & Project Name Improvement Type

    11 Larimer St and 32nd St Intersection Daylighting, Crosswalks and Stop Bars26 Curtis St and 27th St New All-Way Stop31 California St and 26th St Crosswalks and Stop Bars8 Larimer St and 35th St Intersection Daylighting, Crosswalks and Stop Bars9 Larimer St and 34th St Crosswalks and Pedestrian Crossing Signs, Intersection Daylighting10 Larimer St and 33rd St Intersection Daylighting, Crosswalks and Stop Bars13 Larimer St and 30th St Crosswalks and Pedestrian Crossing Signs, Intersection Daylighting15 Larimer St and 28th St Crosswalks and Stop Bars19 Lawrence St and 30th St Crosswalks and Pedestrian Crossing Signs41 Emerson St and 25th Ave Intersection Daylighting, Study Reverse 2-Way Stop (Stop Sign Flip Study)

    2019 Coming Soon, continued

    Sheet1

    NTMP Operational Project Number & Project NameImprovement Type

    11Larimer St and 32nd StIntersection Daylighting, Crosswalks and Stop Bars

    26Curtis St and 27th StNew All-Way Stop

    31California St and 26th StCrosswalks and Stop Bars

    8Larimer St and 35th StIntersection Daylighting, Crosswalks and Stop Bars

    9Larimer St and 34th StCrosswalks and Pedestrian Crossing Signs, Intersection Daylighting

    10Larimer St and 33rd StIntersection Daylighting, Crosswalks and Stop Bars

    13Larimer St and 30th StCrosswalks and Pedestrian Crossing Signs, Intersection Daylighting

    15Larimer St and 28th StCrosswalks and Stop Bars

    19Lawrence St and 30th StCrosswalks and Pedestrian Crossing Signs

    41Emerson St and 25th AveIntersection Daylighting, Study Reverse 2-Way Stop (Stop Sign Flip Study)

  • LOOKING FORWARD

    N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    NTMP Five Points:oContinue to install Operational

    ImprovementsoComplete designs on Five Points Projects,

    advance constructionContinue study & design of NE

    Downtown Neighborhoods Projects w/ fundingoUse data-driven decision makingoFunding needed for many projectsoCoordinate transportation improvements

    with other City-led projects when feasible

  • N E I G H B O R H O O D T R A N S P O R T A T I O N M A N A G E M E N T P R O G R A M D E N V E R P U B L I C W O R K S

    Brittany Price, PEEngineering [email protected]

    Karen GoodCommunity Designer, Area [email protected]

    FIVE POINTS ACTION PLAN UPDATETOPICSPast Studies:Ne downtown study (2011),�Next Steps (2015), �OverviewSlide Number 5Slide Number 6Slide Number 7�what is the neighborhood transportation management program?FIVE POINTS action plan PROCESSFiVE POINTS�action plan TIMELINEFiVE POINTS�action plan UpdateSlide Number 12Slide Number 13Slide Number 14Slide Number 15Looking ForwardSlide Number 17