financial transmission rights: design options

31
For discussion purposes only Financial Transmission Rights: Design options Presentation to Electricity Commission 2 September 2009

Upload: kevork

Post on 18-Jan-2016

25 views

Category:

Documents


1 download

DESCRIPTION

Financial Transmission Rights: Design options. Presentation to Electricity Commission 2 September 2009. Background. Transpower was asked for advice on how to: Simplify and make 2002 FTR more appealing to participants Deal with Dr Read’s 2002 concerns Implement an FTR market. Background. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Financial Transmission Rights: Design options

For discussion purposes only

Financial Transmission Rights: Design options

Presentation to Electricity Commission

2 September 2009

Page 2: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 2

Background

• Transpower was asked for advice on how to:

– Simplify and make 2002 FTR more appealing to participants

– Deal with Dr Read’s 2002 concerns

– Implement an FTR market

Page 3: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 3

Background

• Transpower’s advice is a suggested starting point for discussion

• Pricing should reflect underlying physics

• FTRs are internally consistent with locational marginal pricing

• Regulatory arrangements are different to 2002

• FTR trading platform can be significantly simplified without affecting dispatch

• Start simple and evolve with users

Page 4: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 4

What is the problem?

• Nodal prices are consistent with physical dispatch (i.e. they obey the laws of physics!)

• Locational price differences are caused by constraints in the transmission system NOT energy availability

• Commercial implications of transmission constraints:

– Bilateral contracts can only hedge energy costs

– Volatile and unpredictable locational price differences must be hedged separately

Page 5: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 5

What is the problem?

• There is little ability to hedge locational price difference

• Incentive is to vertically integrate and regionalise generation and retail

• Consequences:

– At best a partial locational price hedge

– Barrier to retail competition

– Significant cost to consumers

– Inefficient use of transmission assets

Page 6: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 6

What are the possible solutions?

• Remove locational price differences altogether

– Removes demand side response

• Use “rentals” to fund a hedge product

– The net amount that needs to be hedged is EXACTLY the rentals collected

– Preserves demand side “signals”

Page 7: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 7

Report Structure

• Part 1 – what is an FTR? How do they fit into integrated market design?

• Part 2 – design options

• Part 3 – implementation options

Page 8: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 8

Markets with locational marginal pricing

• A system for the efficient trading of electricity using supply and demand to set price

• Separate contestable and monopoly functions

• Characterised by “spot prices” that differ by location

• Wholesale market = competitive trading

• Retail market = customer choice

Page 9: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 9

Integrated market design

Co-ordinated spot market

Bid-based, security-constrained,

economic dispatch with nodal prices

ENERGY PRICINGBilateral contracts at nodal

price differencesT

RA

NS

MIS

SIO

N P

RIC

ING

Non

-dis

tort

iona

ry a

cces

s ch

arge

s

NE

W IN

VE

ST

ME

NT

Market-driven

RISK MANAGEMENTHedge against locational price

differences

NE

W G

EN

ER

AT

ION

Location and timing

NE

W T

RA

NS

MIS

SIO

NLocation and tim

ing

DE

MA

ND

SID

E P

AR

TIC

IPA

TIO

NN

EW

TR

AN

SM

ISS

ION

Cen

tral

ly p

lann

ed,

regu

lato

ry p

roce

ss,

TP

M

TRANSMISSION CONGESTIONFTR, LRA, vertical integration

RISK MANAGEMENTHedge against locational price

differences

Page 10: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 10

Physics – Kirchoff’s law

• This means that . . .– Every injection into and off-take from the grid effects electricity

flows on every circuit– Physical capacity rights cannot be meaningfully defined

• Which leads us to constraints and nodal prices . . .

Page 11: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 11

Commercial risk

• Kirchhoff's law and the occurrence of constraints create commercial risk:– Actions of other parties can impact on nodal price– Constraints impact on nodal prices

• Two primary risk management tools– Bilateral energy contracts referenced against price at a node

(often internalised by vertical integration) – Hedge to manage locational price risk arising from constraints

Page 12: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 12

Energy contract – example 1

GeneratorOffered at $2300 MW dispatched

Load300 MW

200 MW

100 MW

10

0 M

W

At limit

$2

$2

$2

Vertically integrated utility generates at A, commitment of 300 MW at $2 at B

Generation:

Cost to generate at A: -$600

Gets paid at A $600

Retail:

Buys 300MW from A -$600

Gets paid for 300MW at B: $600

Page 13: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 13

Energy contract – example 2

• Third party load increases at BGenerator 1Offered at $2240 MW dispatched

Load 1300 MW

200 MW

160 MW

40

MW

Constrained

Generator 2Offered at $3120 MW dispatched

$2

$4

$3

Load 260 MW

• Line A – B constrained

• Price at B increases to $4

• Retailer can’t meet obligation of 300MW at its generation cost of $2 to load at B ($600)

• To meet obligation of 300MW at B retailer must purchase all 300MW at B for $4 ($1200)

• Additional cost to gentailer is equivalent to the rentals of the system ($600)

Page 14: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 14

From an energy contract perspective

• The transmission price risk between A and B is the price difference B − A– Generation at A cannot offer an

energy contract referenced at B without taking the transmission price risk

– Load at B cannot accept an energy contract referenced at A without taking the transmission price risk

Generator 1Offered at $2240 MW dispatched

Load 1300 MW

200 MW

160 MW

40

MW

Constrained

Generator 2Offered at $3120 MW dispatched

$2

$4

$3

Load 260 MW

Page 15: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 15

How can A or B manage the transmission price risk?

• Either A or B needs a financial product that recompenses the value (PriceB - PriceA)/MW.– Generation at A can then offer a fixed energy price at B, or – Load at B can accept a fixed energy price hedge referenced at A

• The only cash stream correlated with nodal price differences is the rentals

• FTRs use this correlation to hedge price differences

Page 16: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 16

Energy price hedge values differ by location and over time

© Transpower 2002

Transmissionprice risk

Time

Price / MW h

$3

$1

$2

$4

$5

A

Nodal price at A

A

Nodal price at B

B

BEnergy price hedge value at A

Energy price hedge value at B

Page 17: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 17

Features of FTRs – trading risk

• Can be matched to an energy contract of a specified capacity and duration between two nodes – near perfect hedge

• Holder receives the rentals between two specified points for an agreed capacity and duration

• Protect the holder against extreme price risks (constraints, scarcity pricing)

• Can be allocated explicitly and/or through an auction• Traded in secondary auctions or markets• Only known product that exploits correlation of rentals with

locational price differences

Page 18: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 18

Features of FTRs – efficient investment

• Grid could operate with more constraints (more efficient)

• Signal the market value of constraints (FTR auction value)

• Provide an important economic signal to assist with the correct location and timing of new transmission investment

Page 19: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 19

Rental flows without FTRs

Electricity market

Rentals allocation

mechanism (TPM)

Rentals

Those who pay for transmission

Allocation minimises impact on nodal prices

– not paid to energy purchasers

Page 20: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 20

FTR market participants

Rentals

Residual revenue

Post allocation

mechanism

Electricity market participants

FTR Auction mechanism

FTR pre-allocation

mechanism (optional)

Auction revenue

Net revenue

Auctioned FTRs

FTR payments

Cas

h flo

ws

with

FT

Rs

FTR rentals + premiumFTR rentals

Rentals + premium

Page 21: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 21

Design emphasis?

• Merchant new investment?– Network investment governed by Part F of EGRs– Merchant investment in connection assets possible (probable?)– Allocation of FTRs to investors not high priority in short term

• Locational hedging– Reduce reliance on physical hedging– Reduce barriers to new retail entry (increased competition)– Provide means to fully hedge against transmission congestion

• High degree of user influence on design• Start simple and build with experience and need• WHAT DOES THIS MEAN FOR DESIGN?

Page 22: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 22

New Investment

• New investment – Merchant investment no longer the primary mechanism for

transmission upgrades– Allocation of FTRs to investors not high priority in short term

Pre-allocation of FTRs Pre-allocation to investors

No pre-allocation

2009 FTR recommendation

2002 FTR design

Page 23: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 23

Coverage

• Node to node, hubs and nodes, hubs only• Market power?• Start simple

FTR coverage

2002 FTR design

High coverage, Complexity

Low coverage, Simplicity

2009 FTR recommendation

HVDC only 2 hubs

Large hubs

Small hubs Interconnected grid

Whole grid

Page 24: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 24

Constraints only?

• Losses should be reasonably predictable• Constraints are not predictable• FTRs with losses are complicated and confusing

Losses and constraintsLosses and constraints

2002 FTR design

Constraints only

2009 FTR recommendation

Page 25: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 25

Revenue adequacy

• Dependent on FTR grid design• Incorrect grid outage assumptions, unplanned outages,

emergencies

FTR Revenue Risk

2002 FTR design

To FTR market participants

To FTR market operator/grid

owner

2009 FTR recommendation

Page 26: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 26

Revenue adequacy

• PJM, CAISO, MISO– FTR Credits are prorated proportionally

• Payments derated when revenue shortfall occurs• Excess rentals and auction revenue occurring over a month

are transferred to a balancing fund• At end of period balancing fund is used to clear unpaid FTRs

(pro rata)– NYISO

• Revenue shortfall is compensated for by imposing an uplift charge on transmission owners

• Attempts to link transmission maintenance standards with revenue adequacy

Page 27: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 27

Revenue adequacy in PJM

Page 28: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 28

FTR Duration

• Any duration required• Start low for accelerated learning• Change with market requirement

FTR duration2002 FTR design Long durationShort duration

2009 FTR recommendation

Hours Weeks Months Years Decades1 Month

Page 29: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 29

Obligations or options?

• Obligation FTRs can become a cost (obligation FTRs are directional)

• Obligation FTRs still hedge price difference even when –ve• Option FTRs always cash positive BUT lower capacity and

computationally different

OptionsObligations or optionsObligations 2002 FTR design

2009 FTR recommendation

Page 30: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 30

Post allocation of residual revenue

• Any allocation possible• Change results in value transfers• Simplest approach is to initially make no change

Pre-allocation of FTRs Pre-allocation to investors

No pre-allocation

2009 FTR recommendation

2002 FTR design

Page 31: Financial Transmission Rights: Design options

© Transpower 2009

For discussion purposes only slide 31

Implementation

• Transpower’s system is “up and running”• Can assist establishing an FTR market quickly if required• Transitional arrangements could see separation of systems from

Transpower