fidic conditions
TRANSCRIPT
-
8/13/2019 Fidic Conditions
1/85
By
V R K Murty
-
8/13/2019 Fidic Conditions
2/85
FIDIC(FEDERATION INTERNATIONALE DES
INGENIEURS- CONSEILS)
-
8/13/2019 Fidic Conditions
3/85
History:1909-1957 RIBA Form (Royal Institute of British Architects)1945 - ICE Form (Institution of Civil Engineers) Domestic
Contracts1956 - 1991 ACE Form (Association of Consulting Engineers)1957
Conditions of Contract (International) for works of CivilEngineering by FIDIC & FIEC Red Book 1stedition
1963 - JCT Form (Joint Contracts Tribunal)1969 FIDIC 2ndEdition published1977 FIDIC 3rdEdition published1987
FIDIC 4thEdition published
1999 FIDIC 5thEdition published
-
8/13/2019 Fidic Conditions
4/85
The Romano-Germanic group Law (PresentFrance, Belgium, Western Germany, north
Italy) :The Law is based on the idea that therelationship between those who govern andthose who are governed requires differentapproach from that required for the
relationship between individuals, and that theinterests of the individual cannot be given thesame weight as those of the society.Essentially the lawyer interprets legislative
provisionsPublic LawAdministrative Law deals withrelationship between the administration andpublic. This is used for Public works Contract
-
8/13/2019 Fidic Conditions
5/85
Private Law:A civil code for private contracts.It is based on the principle that a code should
not attempt to provide rules that areimmediately applicable to every conceivableconcrete case, but rather an organized systemof general rules from which a solution for anygiven problem may be deduced by as simple a
process as possible.The written constitution is held at the highestpoint of Authority. The French law was codifiedby legislation ensuring justice freedom and
dignity to the individual in 1789 after Frenchrevolution during rule of Napoleon.
-
8/13/2019 Fidic Conditions
6/85
Common Law Group: This law was mainlycreated by judges appointed by the crown in
the 12th
and 13th
centuries. It is therefore judgemade law, some times referred to as commonlaw. There is no separation between Publicand Private law. The Royal courts accessibleto common citizens. The sources are:
Judicial decisions when they are recognizedas precedents
Equity
Legislation
Regulations or subordinate legislation International treaties
Custom
-
8/13/2019 Fidic Conditions
7/85
-
8/13/2019 Fidic Conditions
8/85
-
8/13/2019 Fidic Conditions
9/85
Publications:
1. Conditions of contract for
construction
2. Plant design and build3. EPC turnkey
4. Short form of Contract
-
8/13/2019 Fidic Conditions
10/85
GENERAL PROVISIONS MAIN PLAYERS IN A CONTRACT PERFORMANCE OF CONTRACT DEFECT LIABILITY VALUATION AND PAYMENTS DELAYS, SUSPENSION AND TERMINATION RISKS AND RESPOSIBILITIES AND FORCE MAJEURE INSURANCE CLAIMS DISPUTES AND ARBITRATION CASE STUDIES
-
8/13/2019 Fidic Conditions
11/85
General provisions: 1.1.1.7 Schedules- Entitled schedules
compiled by the contractor and submitted
with the letter of tender as included in thecontract. They include bill of quantities,
data, lists and schedules of rates or prices.
-
8/13/2019 Fidic Conditions
12/85
General provisions
1.1.1 Contract- contract agreement, the
letter of acceptance, letter of tender, the
conditions, the specifications, the
drawings, the schedules or any other
documents mentioned in the contract
agreement or the acceptance letter
-
8/13/2019 Fidic Conditions
13/85
General provisions:
1.1.2.1 Party- Employer or contractor
1.1.2.2 Employer- Person named as employer in theappendix to tender and the legal successors in title to
this person 1.1.2.3 Contractor- Named as contractor in the letter of
tender and the legal successors in title to this person(s)
1.1.2.4 Engineer-Appointed by the employer to act asengineer for the purpose of the contract and named in
the appendix to the tender or other person appointedfrom time to time by the employer and notified to thecontractor
-
8/13/2019 Fidic Conditions
14/85
General provisions:
1.1.2.5 Contractors representative-Person named in the contract or
appointed by the contractor from time totime
1.1.2.6 Employers personnel- The
engineer, the assistants and all otherstaff, labour and other employees of theengineer and the employer
-
8/13/2019 Fidic Conditions
15/85
General provisions:
1.1.2.7 Contractors personnel-
Contractors representative, and all
personnel whom the contractor utilizes on
site who may include the staff, labour and
other employees of the contractor and of
each of the sub contractor
-
8/13/2019 Fidic Conditions
16/85
General provisions:
1.1.2.7 Contractors personnel-
Contractors representative, and all
personnel whom the contractor utilizes on
site who may include the staff, labour and
other employees of the contractor and of
each of the sub contractor
-
8/13/2019 Fidic Conditions
17/85
-
8/13/2019 Fidic Conditions
18/85
General provisions:
1.1.3.7 Defects notification period-
Period for notifying defects in the works
calculated from the date on which the
works or a section is completed
1.1.3.8 Performance certificate
-
8/13/2019 Fidic Conditions
19/85
General provisions:
1.1.4.1 accepted contract amount: The
amount accepted in the letter of
acceptance
1.1.4.2 Contract price:Accepted
contract amount adjusted in accordance
with contract agreement
-
8/13/2019 Fidic Conditions
20/85
General provisions:
1.1.4.7 Interim payment certificate:
Payment certificate other than final
payment certificate
1.1.4.10 Provisional sum:Sum which is
specified for execution of any part of the
work or for supply of plant, materials or
services
-
8/13/2019 Fidic Conditions
21/85
General provisions:
1.1.4.11 Retention money:The
accumulated retention money which the
employer retains in interim certificates
1.1.6.6 Performance security: The
performance security specified as per
contract for satisfactory completion of the
work
-
8/13/2019 Fidic Conditions
22/85
General provisions:
1.5 Priority of documents:
a) The contract agreement
b) The letter of acceptance
c) The letter of tenderd) The particular conditions
e) The general conditions
f) The specification
g)
The drawingsh) The schedules and any other documents forming partof contract
-
8/13/2019 Fidic Conditions
23/85
General provisions:
1.6 Contract agreement:
To enter into a contract agreement within 28
days after contractor receives letter ofacceptance
Based on the form annexed to the particularconditions
Stamp duties imposed by law to be borne bythe employer
-
8/13/2019 Fidic Conditions
24/85
General provisions:
1.7 Assignment:
Neither party shall assign whole or part ofwork
May assign whole or part of work with prioragreement of the other party at the solediscretion of the other party
May as security in favour of a bank orfinancial institution assign its right to anymoneys due
-
8/13/2019 Fidic Conditions
25/85
General provisions:
1.12 confidential details:Contractor
shall disclose such confidential and
other information as the engineer may
reasonably require in order to verify
contractors compliance with the
contract
-
8/13/2019 Fidic Conditions
26/85
General provisions:
1.13 Compliance with laws:
The employer to obtain planning, zoning or similarpermission for permanent works and shall indemnify
and hold contractor harmless The contractor shall give all notices, pay all taxes,
duties and fees and obtain all permits, licenses andapprovals as required by law and the contractor shallindemnify and hold the employer harmless against andfrom the consequences
-
8/13/2019 Fidic Conditions
27/85
General provisions:1.14 Joint and several liability:
The contractor constitutes a joint venture, consortiumor other unincorporated grouping of two or morepersons
These persons shall be deemed to be jointly andseverally liable to the employer for the performance ofthe contract
These parties shall notify the employer of their leaderwho shall have the authority to bind the contractor andeach of these persons
The contractor shall not alter its composition or legalstatus without prior consent of the employer
-
8/13/2019 Fidic Conditions
28/85
MAIN PLAYERS IN A CONTRACT:
The Employer
The Engineer
The Contractor
The Sub Contractors
Staff and labour
-
8/13/2019 Fidic Conditions
29/85
The Employer (Responsibilities and rights):
2.1 Handing over site:Right of access and
possession to all parts of site to the contractor
within the time specified Grants extension of time for any delay in
handing over site
Payment of any such cost plus reasonableprofit which shall be included in the contract
-
8/13/2019 Fidic Conditions
30/85
The Employer (Responsibilities and rights):
2.3 Employers personnel:
Employer responsible for ensuring that his
personnel co-operate with the contractorsefforts on safety procedures and protection of
environment
-
8/13/2019 Fidic Conditions
31/85
The Employer (Responsibilities and rights):
2.4 Employers financial arrangements:
Employer shall make financial arrangements
and maintain them to make payment ofcontract price to contractor according to the
terms of contract agreement
-
8/13/2019 Fidic Conditions
32/85
The Employer (Responsibilities and rights):
2.5 Employers claims:
Employer if he considers himself entitled for payment
from the contractor, the engineer shall give notice as
soon as practicable in respect of:
-- Determinations
-- Extension of time
-- Extension of defect liability period-- Notice not required in case of payment due for
issue of materials, electricity, water and gas
-
8/13/2019 Fidic Conditions
33/85
3 The Engineer (Duties and Authority)
The employer shall appoint Engineer who shallcarry out duties assigned to him in the contract
Whenever the Engineer exercises a specifiedauthority for which employers approval isrequired the employer is deemed to haveissued the approval
The engineer shall have no authority to amendthe contract
-
8/13/2019 Fidic Conditions
34/85
3 The Engineer (Duties and Authority):
The engineer shall have no authority to relieve
either party of their duties
Any approval, check, certificate, consent,examination, inspection, instruction, notice,
proposal, request, test or similar act by the
engineer shall nor relieve the contractor from
any of his responsibilities he has under the
contract
-
8/13/2019 Fidic Conditions
35/85
The Engineer (Duties and Authority):
3.3 Instructions of the engineer:
The instructions shall be given in writing
If the engineer gives oral instruction, receiveswritten confirmation from the contractor withintwo working days and does not reply by issuingwritten rejection within two working days after
receiving the confirmation the confirmationconstitutes written instruction of the engineer
-
8/13/2019 Fidic Conditions
36/85
The Engineer (Duties and Authority):
3.4 Replacement of the Engineer:
The employer shall give not less than 42 days
notice for replacing the engineer. The employershall not replace the engineer with a person
against whom the contractor raises reasonable
objections in writing
-
8/13/2019 Fidic Conditions
37/85
The Engineer (Duties and Authority):
3.5 Determinations:
The engineer shall consult with each party in
an endeavour to reach an agreement ordetermination in a particular issue after issuing
necessary notices. If agreement is not
achieved he shall make a fair determination in
accordance with contract.
-
8/13/2019 Fidic Conditions
38/85
4 The contractor (Obligations and rights):
4.1 The contractor shall design (to the extent
specified), execute and complete the works in
accordance to contract and with engineersinstructions and shall remedy any defects
The contractor shall provide the plant,
personnel, goods, consumables and services
-
8/13/2019 Fidic Conditions
39/85
4 The contractor (Obligations and rights):
4.1 contd.
Stability and safety of site operations
Submit details of arrangements and methodsof execution
Submit design (To the extent specified),
drawings, documents, as built documents,Operation and maintenance manuals
-
8/13/2019 Fidic Conditions
40/85
4 The contractor (Obligations and rights):
4.1The contractor shall design (to the extent
specified), execute and complete the works in
accordance to contract and with engineersinstructions and shall remedy any defects
The contractor shall provide the plant,
personnel, goods, consumables and services
-
8/13/2019 Fidic Conditions
41/85
4 The contractor (Obligations and rights):
4.1 contd.
Stability and safety of site operations
Submit details of arrangements and methodsof execution
Submit design (To the extent specified),
drawings, documents, as built documents,Operation and maintenance manuals
-
8/13/2019 Fidic Conditions
42/85
4 The contractor (Obligations and rights):
4.2 Performance security:
The contractor shall deliver performance
security within 28 days after receiving letter ofacceptance in the form, currency, amount
specified and valid and enforceable until the
contractor has executed and completed the
works and remedied all defects
-
8/13/2019 Fidic Conditions
43/85
4 The contractor (Obligations and rights):
4.11 Sufficiency of accepted contract amount
4.12 Unforeseeable physical conditions
4.13 Rights of way and facilities4.14 Avoidance of interference
4.15 Access route
4.16 Transport of goods- 21 days notice
4.17 Contractors equipment- Shall not removefrom site without consent of engineer
-
8/13/2019 Fidic Conditions
44/85
4 The contractor (Obligations and rights):
4.18 Protection of environment
4.19 Electricity, water and gas
4.20 Employers equipment and free- issuematerials
4.21 Progress reports
4.22 Security of site
4.23 Contractors operations on site
4.24 Fossils
-
8/13/2019 Fidic Conditions
45/85
5. Nominated sub contractors:5.1 Who is stated in the contract as being
nominated
5.2 Objection of contractor to nomination if
the contractor does not agree due to lack ofcompetence, resources and financial strength
5.3 Payments to nominated subcontractors
as certified by engineer
5.4 Evidence of payments to nominated sub
contractors before issuing payment
certificate
-
8/13/2019 Fidic Conditions
46/85
6. Staff and labour:6.1, 6.3 Contractor shall engage the labour as
required. He shall not employ staff and labourfrom employers personnel
6.2, 6.4, 6.5 Labour laws of the land shall befollowed. Working hours and days of restlocally recognized unless otherwise specified
-
8/13/2019 Fidic Conditions
47/85
6. Staff and labour:
6.6, 6.7Facilities like accommodation,
welfare and precautions first aid health,
safety to staff and labour6.8 Contractors superintendence
6.9, 6.11 Contractors personnel shall be
appropriately qualified, skilled. They will
be removed/ replaced if not suitable and
as directed by the engineer
-
8/13/2019 Fidic Conditions
48/85
Administration of Contract:
1. Handing over sitethe site shall be handed
over to the contractor by the employer withinthe period stated in the contract. Employergives extension of time and compensation forloss of profit and any other losses in case of
delay in handing over site. (2.1)2. Financial Arrangements Employer shall
make necessary financial arrangements andmaintain them for making payments against
contract price as per conditions of contractwithin 28 days of acceptance of contract(2.4)
-
8/13/2019 Fidic Conditions
49/85
Administration of Contract:
3. Performance securityThe contractor shall
deposit performance security within 28 days ofacceptance of contract valid and enforceabletill all works are satisfactorily completed and alldefects rectified . The amount of performance
security shall be in form and currency specifiedin the contract (4.2)
4. Commencement of work:The employer shallgive at least 7 days notice to commence work
after issue of letter of acceptance. Thecontractor shall commence work within 42 daysof acceptance of contract. (8.1)
-
8/13/2019 Fidic Conditions
50/85
Administration of Contract:
5. Programme for constructionThe contractor
within 28 days of acceptance of contract shallgive a detailed programme for sequence andstages of completion, methods of construction,procurement, materials and testing consistentwith period of completion. Revised programme
shall be furnished whenever it is found that theearlier programme submitted is not consistentwith the period of completion (8.2)
6. Details of temporary works - The contractor is
responsible for safety and stability of siteoperations. He shall submit methods ofexecution. He designs the works to the extentspecified in the contract. (4.1)
-
8/13/2019 Fidic Conditions
51/85
Administration of Contract:
7. Extension of time for completion: The
contractor shall be eligible for extension if Variations and substantial changes ordered by
the employer
Due to employers actions causing delays thatgive rise to entitlement of extension of time
Adverse climatic conditions affecting progressof work
Non availability of goods and personnel due tounforeseeable Government actions (8.4)
-
8/13/2019 Fidic Conditions
52/85
Administration of Contract:
7. Extension of time for completion: Extension of
time will be granted by the employer if thefollowing conditions exist:
a) Contractor diligently followed all proceduresstipulated by legally constituted authorities and
delay in progress of work was unavoidableb) These authorities delay or disrupt theprogress of the work which was unforeseeable
c) Any other conditions disrupting the workwhich were beyond the control of thecontractor (8.5)
-
8/13/2019 Fidic Conditions
53/85
Administration of Contract:
8. Rate of progress of work: The contractor shall
pay for any loss incurred by the employer if anytime:
a) Actual progress of work is too slow tocomplete the work within the contract period
b) Progress of work has fallen behind thecontract programme
c) The contractor is required to employadditional resources and employ new methodsfor construction as approved by the engineerinvolving additional cost to the employer tocomplete the work (8.6)
-
8/13/2019 Fidic Conditions
54/85
Administration of Contract:
8. Delay damages: The contractor shall pay delay
damages for every day of delay but notexceeding the sum specified in the contractusually not more than 10% of contract sum(8.7)
Suspension of work:Up to 28 days - Engineer may order suspensiongiving the reasons for suspension. Duringsuspension contractor shall protect the site and
materials. The contractor shall be entitled forextension of time and any such cost. (8.8)
-
8/13/2019 Fidic Conditions
55/85
Administration of Contract:
8. Suspension of work:
Beyond 28 days up to 84 days - The contractorshall be entitled for extension of time andpayment of any such cost thereof and cost ofwork of plant and machinery (8.10)
Prolonged suspension - If the suspensionexceeds 84 days, the contractor shall ask theengineer to allow him to proceed with the work.If the engineer fails to give permission to
proceed within 28 days after being requested,the contractor by giving notice may treatsuspension as omission of the affected portionof work. (8.11)
-
8/13/2019 Fidic Conditions
56/85
Administration of Contract:
9. Tests on completion: Contractor shall give 21
days notice to the engineer and carry out testson completion within 14 days. (9.1)
Delayed tests: If the engineer delays attendingtests extension of time shall be granted. If the
contractor in spite of 21 days notice fails to carryout tests, the engineer shall carry out the tests atthe risk and cost of the contractor. (9.2)
Retesting: The engineer may order retesting if
the tests do not pass, and the contractor shallcarry out the retesting at his cost. (9.3)
-
8/13/2019 Fidic Conditions
57/85
12. Measurement and evaluation:
12.1Works to be measured:
Whenever the engineer requires measurement
to certain part of work he will give notice to thecontractor and contractor shall promptly attend
or depute his representative
Supply any particulars required by the engineer
-
8/13/2019 Fidic Conditions
58/85
12. Measurement and evaluation:
12.2 Works to be measured:
Measurement shall be made of the net actual
quantity Method of measurement shall be in
accordance with BOQ and other applicable
schedules
-
8/13/2019 Fidic Conditions
59/85
12. Measurement and evaluation:
12.3 Evaluation:
Rate shall be appropriate rate for such item in
the contract and if no rate exists a new rateappropriate to the item of work if:
a) The measured quantity of an item is
changed by more than 10% of BOQb) The change in quantity multiplied by
such specified rate exceeds 0.01% of
the contract amount
-
8/13/2019 Fidic Conditions
60/85
12. Measurement and evaluation:
12.3 Evaluation:
c) The change in quantity directly changes the
cost per unit quantity by more than 1%d) The item is not specified in the contract as
fixed rate item
e) The item is ordered as variation, no rate isspecified in the contract and no rate is
appropriate because the item of work is not
similar in nature
-
8/13/2019 Fidic Conditions
61/85
12. Measurement and evaluation:
12.3 Evaluation:
f) New rate shall be derived from any relevant
item in the contract, otherwise it shall bederived from actual cost of work, together with
reasonable profit
-
8/13/2019 Fidic Conditions
62/85
13.Variations and adjustments:
13.2 Value engineering:
d) The proposal shall be prepared at the cost
of the contractor and design it if necessarye) The engineer will determine fee @ 50%
between reduction of contract value and
reduction in value in quality, life and
operational efficiency
-
8/13/2019 Fidic Conditions
63/85
13.Variations and adjustments:
13.3 variation procedure:
Engineer requests for a proposal for variation
The contractor responds in writing either by
giving reasons why he cannot comply or
submits
Description of proposed work and aprogramme, time for completion & valuation
-
8/13/2019 Fidic Conditions
64/85
13.Variations and adjustments:
13.3 Variation procedure:
The engineer as soon as practicable respond
with approval or disapproval or comments with
instructions to carry out the variation with any
requirements of costs
-
8/13/2019 Fidic Conditions
65/85
13.Variations and adjustments:
13.4 Payment in applicable currencies:
If the contract provides for payment in
different currencies;
The amount payable in each of the currencies
Expected currency proportions of the cost of
varied work with reference to the proportionsspecified in the contract
-
8/13/2019 Fidic Conditions
66/85
13.Variations and adjustments:
13.5 Provisional sums:
Provisional sum shall be used only for supplies
or services for which the provisional sum relates
Actual amount paid by the contractor
Percentage to cover overheads and profit as
stipulated in the contract
-
8/13/2019 Fidic Conditions
67/85
13.Variations and adjustments:
13.6 Day work: The engineer may order day work
basis for incidental or minor works or for which
no standard data is available. The contractorshall submit daily reports of quantities of plant
and materials used, contractors personnel, type
and time of contractors equipment and
temporary works employed and priced
statements of these resources.
-
8/13/2019 Fidic Conditions
68/85
13.Variations and adjustments:
13.7 Adjustments for changes in legislation:
The contract price shall be adjusted to take into
account any increase or decrease in cost
resulting from changes in the laws of the
country made after the base date.
The contractor is entitled to an extension oftime for any such delay
-
8/13/2019 Fidic Conditions
69/85
13.Variations and adjustments:
13.8 Adjustments for changes in cost:
Contract amounts payable shall be adjusted for
rises or falls in rates of labour, goods or otherinputs to the works by the following formula:
Pn= a + b Ln+ c En+ d Mn +
L0 E0 M0
-
8/13/2019 Fidic Conditions
70/85
13.Variations and adjustments:
13.8 Adjustments for changes in cost:
Pn Adjustment multiplier to be applied to
estimated contract value
a Fixed coefficient stated in the relevant table of
adjustment data representing non adjustable
portion in contractual payments
-
8/13/2019 Fidic Conditions
71/85
13.Variations and adjustments:
13.8 Adjustments for changes in cost:
b, c, d are coefficients representing the
estimated portion of each cost element relatedto the execution of work
Ln, En, Mn are the current cost indices
L0, E0, M0 Are the base cost indices onthe base date
-
8/13/2019 Fidic Conditions
72/85
13.Variations and adjustments:
13.8 Adjustments for changes in cost:
Notes:
If currency of index is not the relevant currency
of payment each index shall be converted into
relevant currency at selling rate of central bank
Engineer shall determine provisional index forinterim payments
-
8/13/2019 Fidic Conditions
73/85
13.Variations and adjustments:
13.8 Adjustments for changes in cost:
Notes:
If the contractor fails to complete workwithin
stipulated time the price index shall be
considered on the date 49 days prior toexpiry
of the time for completionor the current indexwhich ever is favourable to the employer
-
8/13/2019 Fidic Conditions
74/85
14.Contract price and payment:
14.1 The contract price:
Contract price shall be agreed or determined
and be subject to adjustments in accordancewith the contract
The contractor shall pay taxes, duties and fees
required to be paid by him under the contractand contract price shall not be adjusted except
for changes in legislation
-
8/13/2019 Fidic Conditions
75/85
14.Contract price and payment:
14.1 The contract price:
Quantities shown in bill of quantities are not to
be taken as actual quantities
The contractor shall submit proposed
breakdown of each lump sum within 28 days
after commencement of work
-
8/13/2019 Fidic Conditions
76/85
14.Contract price and payment:
14.2 Advance payment: (Mobilization advance)
Employer shall make an advance payment as
interest free loan for mobilization when thecontractor submits a guarantee by an entity
within a country approved by the employer
The advance payment shall be repaid by thecontractor through deductions from interim
payments due >10% of contract sum
-
8/13/2019 Fidic Conditions
77/85
14.Contract price and payment:
14.2 Advance payment: (Mobilization advance)
Deductions shall be made at the amortization
rate of 25% of the amount of each paymentcertificate
If the advance is not paid prior to issue of taking
over certificate/ termination the whole ofbalance shall become due
-
8/13/2019 Fidic Conditions
78/85
14.Contract price and payment:
14.3, 14.4 Application for interim payment
certificates & schedule of payments:
Contractor shall submit a statement in 6 copiesat the end of each month in the approved form
showing amount due, progress report and other
supporting documents.
-
8/13/2019 Fidic Conditions
79/85
14.Contract price and payment:
14.3, 14.4 Application for interim payment
certificates & schedule of payments (Details to
be attached) Estimated contract value of the works executed
Any amounts to be added or deducted due to
changes in legislation Retention money
-
8/13/2019 Fidic Conditions
80/85
14.Contract price and payment:
14.3, 14.4 Application for interim paymentcertificates & schedule of payments: (Details to
be attached) Any amounts to be added/ deducted for
advance payment/ repayment
Any amounts to be added/ deducted for plants
& materials intended for the work Any other additions/ deductions (claims)
-
8/13/2019 Fidic Conditions
81/85
14.Contract price and payment:
14.3, 14.4 Application for interim payment
certificates & schedule of payments: (Details to
be attached) Deduction of amounts certified in all previous
payments
The contractor shall submit within 42 days aftercommencement estimated installments of
payment in each quarter
-
8/13/2019 Fidic Conditions
82/85
14.Contract price and payment:
14.5 Plant and materials intended for works:
The contractor shall submit / maintain:
Satisfactory records of orders, receipts, costsand use of plant and materials
Shipped bill of lading, evidence of shipment,payment of freight &insurance charges, bank
guarantees Proper storage of plant & materials at site
-
8/13/2019 Fidic Conditions
83/85
14.Contract price and payment:
14.6 Issue of interim payment certificates:
The engineer shall within 28 daysafter
receiving statement issue a interim paymentcertificate. Cost of rectification/ non conformingwork/ material shall be withheld
14.7 The employer shall paythe contractor first
installment of advance payment within 42daysafter issue of letter of acceptance or within 21daysafter receipt of statement
-
8/13/2019 Fidic Conditions
84/85
14.Contract price and payment:
14.7 Issue of interim payment certificates:
Each interim paymentcertificate within 56days
after engineer receives the statement
Final paymentcertificate within 56 daysafter
receipt of payment certificate by the employer
-
8/13/2019 Fidic Conditions
85/85
14.Contract price and payment:
14.8 Delayed payment: If the contractor does notreceive the payment within specified time he will
be entitled for financing charges at 3% abovecentral bank rate
14.9 Retention money: After issue of taking overcertificate 50% of retention money shall be paid,
balance after expiry of defect notification periodand after withholding rectification cost ofdefects