  • 8/13/2019 Fidic Conditions

    1/85

    By

    V R K Murty

  • 8/13/2019 Fidic Conditions

    2/85

    FIDIC(FEDERATION INTERNATIONALE DES

    INGENIEURS- CONSEILS)

  • 8/13/2019 Fidic Conditions

    3/85

    History:1909-1957 RIBA Form (Royal Institute of British Architects)1945 - ICE Form (Institution of Civil Engineers) Domestic

    Contracts1956 - 1991 ACE Form (Association of Consulting Engineers)1957

    Conditions of Contract (International) for works of CivilEngineering by FIDIC & FIEC Red Book 1stedition

    1963 - JCT Form (Joint Contracts Tribunal)1969 FIDIC 2ndEdition published1977 FIDIC 3rdEdition published1987

    FIDIC 4thEdition published

    1999 FIDIC 5thEdition published

  • 8/13/2019 Fidic Conditions

    4/85

    The Romano-Germanic group Law (PresentFrance, Belgium, Western Germany, north

    Italy) :The Law is based on the idea that therelationship between those who govern andthose who are governed requires differentapproach from that required for the

    relationship between individuals, and that theinterests of the individual cannot be given thesame weight as those of the society.Essentially the lawyer interprets legislative

    provisionsPublic LawAdministrative Law deals withrelationship between the administration andpublic. This is used for Public works Contract

  • 8/13/2019 Fidic Conditions

    5/85

    Private Law:A civil code for private contracts.It is based on the principle that a code should

    not attempt to provide rules that areimmediately applicable to every conceivableconcrete case, but rather an organized systemof general rules from which a solution for anygiven problem may be deduced by as simple a

    process as possible.The written constitution is held at the highestpoint of Authority. The French law was codifiedby legislation ensuring justice freedom and

    dignity to the individual in 1789 after Frenchrevolution during rule of Napoleon.

  • 8/13/2019 Fidic Conditions

    6/85

    Common Law Group: This law was mainlycreated by judges appointed by the crown in

    the 12th

    and 13th

    centuries. It is therefore judgemade law, some times referred to as commonlaw. There is no separation between Publicand Private law. The Royal courts accessibleto common citizens. The sources are:

    Judicial decisions when they are recognizedas precedents

    Equity

    Legislation

    Regulations or subordinate legislation International treaties

    Custom

  • 8/13/2019 Fidic Conditions

    7/85

  • 8/13/2019 Fidic Conditions

    8/85

  • 8/13/2019 Fidic Conditions

    9/85

    Publications:

    1. Conditions of contract for

    construction

    2. Plant design and build3. EPC turnkey

    4. Short form of Contract

  • 8/13/2019 Fidic Conditions

    10/85

    GENERAL PROVISIONS MAIN PLAYERS IN A CONTRACT PERFORMANCE OF CONTRACT DEFECT LIABILITY VALUATION AND PAYMENTS DELAYS, SUSPENSION AND TERMINATION RISKS AND RESPOSIBILITIES AND FORCE MAJEURE INSURANCE CLAIMS DISPUTES AND ARBITRATION CASE STUDIES

  • 8/13/2019 Fidic Conditions

    11/85

    General provisions: 1.1.1.7 Schedules- Entitled schedules

    compiled by the contractor and submitted

    with the letter of tender as included in thecontract. They include bill of quantities,

    data, lists and schedules of rates or prices.

  • 8/13/2019 Fidic Conditions

    12/85

    General provisions

    1.1.1 Contract- contract agreement, the

    letter of acceptance, letter of tender, the

    conditions, the specifications, the

    drawings, the schedules or any other

    documents mentioned in the contract

    agreement or the acceptance letter

  • 8/13/2019 Fidic Conditions

    13/85

    General provisions:

    1.1.2.1 Party- Employer or contractor

    1.1.2.2 Employer- Person named as employer in theappendix to tender and the legal successors in title to

    this person 1.1.2.3 Contractor- Named as contractor in the letter of

    tender and the legal successors in title to this person(s)

    1.1.2.4 Engineer-Appointed by the employer to act asengineer for the purpose of the contract and named in

    the appendix to the tender or other person appointedfrom time to time by the employer and notified to thecontractor

  • 8/13/2019 Fidic Conditions

    14/85

    General provisions:

    1.1.2.5 Contractors representative-Person named in the contract or

    appointed by the contractor from time totime

    1.1.2.6 Employers personnel- The

    engineer, the assistants and all otherstaff, labour and other employees of theengineer and the employer

  • 8/13/2019 Fidic Conditions

    15/85

    General provisions:

    1.1.2.7 Contractors personnel-

    Contractors representative, and all

    personnel whom the contractor utilizes on

    site who may include the staff, labour and

    other employees of the contractor and of

    each of the sub contractor

  • 8/13/2019 Fidic Conditions

    16/85

    General provisions:

    1.1.2.7 Contractors personnel-

    Contractors representative, and all

    personnel whom the contractor utilizes on

    site who may include the staff, labour and

    other employees of the contractor and of

    each of the sub contractor

  • 8/13/2019 Fidic Conditions

    17/85

  • 8/13/2019 Fidic Conditions

    18/85

    General provisions:

    1.1.3.7 Defects notification period-

    Period for notifying defects in the works

    calculated from the date on which the

    works or a section is completed

    1.1.3.8 Performance certificate

  • 8/13/2019 Fidic Conditions

    19/85

    General provisions:

    1.1.4.1 accepted contract amount: The

    amount accepted in the letter of

    acceptance

    1.1.4.2 Contract price:Accepted

    contract amount adjusted in accordance

    with contract agreement

  • 8/13/2019 Fidic Conditions

    20/85

    General provisions:

    1.1.4.7 Interim payment certificate:

    Payment certificate other than final

    payment certificate

    1.1.4.10 Provisional sum:Sum which is

    specified for execution of any part of the

    work or for supply of plant, materials or

    services

  • 8/13/2019 Fidic Conditions

    21/85

    General provisions:

    1.1.4.11 Retention money:The

    accumulated retention money which the

    employer retains in interim certificates

    1.1.6.6 Performance security: The

    performance security specified as per

    contract for satisfactory completion of the

    work

  • 8/13/2019 Fidic Conditions

    22/85

    General provisions:

    1.5 Priority of documents:

    a) The contract agreement

    b) The letter of acceptance

    c) The letter of tenderd) The particular conditions

    e) The general conditions

    f) The specification

    g)

    The drawingsh) The schedules and any other documents forming partof contract

  • 8/13/2019 Fidic Conditions

    23/85

    General provisions:

    1.6 Contract agreement:

    To enter into a contract agreement within 28

    days after contractor receives letter ofacceptance

    Based on the form annexed to the particularconditions

    Stamp duties imposed by law to be borne bythe employer

  • 8/13/2019 Fidic Conditions

    24/85

    General provisions:

    1.7 Assignment:

    Neither party shall assign whole or part ofwork

    May assign whole or part of work with prioragreement of the other party at the solediscretion of the other party

    May as security in favour of a bank orfinancial institution assign its right to anymoneys due

  • 8/13/2019 Fidic Conditions

    25/85

    General provisions:

    1.12 confidential details:Contractor

    shall disclose such confidential and

    other information as the engineer may

    reasonably require in order to verify

    contractors compliance with the

    contract

  • 8/13/2019 Fidic Conditions

    26/85

    General provisions:

    1.13 Compliance with laws:

    The employer to obtain planning, zoning or similarpermission for permanent works and shall indemnify

    and hold contractor harmless The contractor shall give all notices, pay all taxes,

    duties and fees and obtain all permits, licenses andapprovals as required by law and the contractor shallindemnify and hold the employer harmless against andfrom the consequences

  • 8/13/2019 Fidic Conditions

    27/85

    General provisions:1.14 Joint and several liability:

    The contractor constitutes a joint venture, consortiumor other unincorporated grouping of two or morepersons

    These persons shall be deemed to be jointly andseverally liable to the employer for the performance ofthe contract

    These parties shall notify the employer of their leaderwho shall have the authority to bind the contractor andeach of these persons

    The contractor shall not alter its composition or legalstatus without prior consent of the employer

  • 8/13/2019 Fidic Conditions

    28/85

    MAIN PLAYERS IN A CONTRACT:

    The Employer

    The Engineer

    The Contractor

    The Sub Contractors

    Staff and labour

  • 8/13/2019 Fidic Conditions

    29/85

    The Employer (Responsibilities and rights):

    2.1 Handing over site:Right of access and

    possession to all parts of site to the contractor

    within the time specified Grants extension of time for any delay in

    handing over site

    Payment of any such cost plus reasonableprofit which shall be included in the contract

  • 8/13/2019 Fidic Conditions

    30/85

    The Employer (Responsibilities and rights):

    2.3 Employers personnel:

    Employer responsible for ensuring that his

    personnel co-operate with the contractorsefforts on safety procedures and protection of

    environment

  • 8/13/2019 Fidic Conditions

    31/85

    The Employer (Responsibilities and rights):

    2.4 Employers financial arrangements:

    Employer shall make financial arrangements

    and maintain them to make payment ofcontract price to contractor according to the

    terms of contract agreement

  • 8/13/2019 Fidic Conditions

    32/85

    The Employer (Responsibilities and rights):

    2.5 Employers claims:

    Employer if he considers himself entitled for payment

    from the contractor, the engineer shall give notice as

    soon as practicable in respect of:

    -- Determinations

    -- Extension of time

    -- Extension of defect liability period-- Notice not required in case of payment due for

    issue of materials, electricity, water and gas

  • 8/13/2019 Fidic Conditions

    33/85

    3 The Engineer (Duties and Authority)

    The employer shall appoint Engineer who shallcarry out duties assigned to him in the contract

    Whenever the Engineer exercises a specifiedauthority for which employers approval isrequired the employer is deemed to haveissued the approval

    The engineer shall have no authority to amendthe contract

  • 8/13/2019 Fidic Conditions

    34/85

    3 The Engineer (Duties and Authority):

    The engineer shall have no authority to relieve

    either party of their duties

    Any approval, check, certificate, consent,examination, inspection, instruction, notice,

    proposal, request, test or similar act by the

    engineer shall nor relieve the contractor from

    any of his responsibilities he has under the

    contract

  • 8/13/2019 Fidic Conditions

    35/85

    The Engineer (Duties and Authority):

    3.3 Instructions of the engineer:

    The instructions shall be given in writing

    If the engineer gives oral instruction, receiveswritten confirmation from the contractor withintwo working days and does not reply by issuingwritten rejection within two working days after

    receiving the confirmation the confirmationconstitutes written instruction of the engineer

  • 8/13/2019 Fidic Conditions

    36/85

    The Engineer (Duties and Authority):

    3.4 Replacement of the Engineer:

    The employer shall give not less than 42 days

    notice for replacing the engineer. The employershall not replace the engineer with a person

    against whom the contractor raises reasonable

    objections in writing

  • 8/13/2019 Fidic Conditions

    37/85

    The Engineer (Duties and Authority):

    3.5 Determinations:

    The engineer shall consult with each party in

    an endeavour to reach an agreement ordetermination in a particular issue after issuing

    necessary notices. If agreement is not

    achieved he shall make a fair determination in

    accordance with contract.

  • 8/13/2019 Fidic Conditions

    38/85

    4 The contractor (Obligations and rights):

    4.1 The contractor shall design (to the extent

    specified), execute and complete the works in

    accordance to contract and with engineersinstructions and shall remedy any defects

    The contractor shall provide the plant,

    personnel, goods, consumables and services

  • 8/13/2019 Fidic Conditions

    39/85

    4 The contractor (Obligations and rights):

    4.1 contd.

    Stability and safety of site operations

    Submit details of arrangements and methodsof execution

    Submit design (To the extent specified),

    drawings, documents, as built documents,Operation and maintenance manuals

  • 8/13/2019 Fidic Conditions

    40/85

    4 The contractor (Obligations and rights):

    4.1The contractor shall design (to the extent

    specified), execute and complete the works in

    accordance to contract and with engineersinstructions and shall remedy any defects

    The contractor shall provide the plant,

    personnel, goods, consumables and services

  • 8/13/2019 Fidic Conditions

    41/85

    4 The contractor (Obligations and rights):

    4.1 contd.

    Stability and safety of site operations

    Submit details of arrangements and methodsof execution

    Submit design (To the extent specified),

    drawings, documents, as built documents,Operation and maintenance manuals

  • 8/13/2019 Fidic Conditions

    42/85

    4 The contractor (Obligations and rights):

    4.2 Performance security:

    The contractor shall deliver performance

    security within 28 days after receiving letter ofacceptance in the form, currency, amount

    specified and valid and enforceable until the

    contractor has executed and completed the

    works and remedied all defects

  • 8/13/2019 Fidic Conditions

    43/85

    4 The contractor (Obligations and rights):

    4.11 Sufficiency of accepted contract amount

    4.12 Unforeseeable physical conditions

    4.13 Rights of way and facilities4.14 Avoidance of interference

    4.15 Access route

    4.16 Transport of goods- 21 days notice

    4.17 Contractors equipment- Shall not removefrom site without consent of engineer

  • 8/13/2019 Fidic Conditions

    44/85

    4 The contractor (Obligations and rights):

    4.18 Protection of environment

    4.19 Electricity, water and gas

    4.20 Employers equipment and free- issuematerials

    4.21 Progress reports

    4.22 Security of site

    4.23 Contractors operations on site

    4.24 Fossils

  • 8/13/2019 Fidic Conditions

    45/85

    5. Nominated sub contractors:5.1 Who is stated in the contract as being

    nominated

    5.2 Objection of contractor to nomination if

    the contractor does not agree due to lack ofcompetence, resources and financial strength

    5.3 Payments to nominated subcontractors

    as certified by engineer

    5.4 Evidence of payments to nominated sub

    contractors before issuing payment

    certificate

  • 8/13/2019 Fidic Conditions

    46/85

    6. Staff and labour:6.1, 6.3 Contractor shall engage the labour as

    required. He shall not employ staff and labourfrom employers personnel

    6.2, 6.4, 6.5 Labour laws of the land shall befollowed. Working hours and days of restlocally recognized unless otherwise specified

  • 8/13/2019 Fidic Conditions

    47/85

    6. Staff and labour:

    6.6, 6.7Facilities like accommodation,

    welfare and precautions first aid health,

    safety to staff and labour6.8 Contractors superintendence

    6.9, 6.11 Contractors personnel shall be

    appropriately qualified, skilled. They will

    be removed/ replaced if not suitable and

    as directed by the engineer

  • 8/13/2019 Fidic Conditions

    48/85

    Administration of Contract:

    1. Handing over sitethe site shall be handed

    over to the contractor by the employer withinthe period stated in the contract. Employergives extension of time and compensation forloss of profit and any other losses in case of

    delay in handing over site. (2.1)2. Financial Arrangements Employer shall

    make necessary financial arrangements andmaintain them for making payments against

    contract price as per conditions of contractwithin 28 days of acceptance of contract(2.4)

  • 8/13/2019 Fidic Conditions

    49/85

    Administration of Contract:

    3. Performance securityThe contractor shall

    deposit performance security within 28 days ofacceptance of contract valid and enforceabletill all works are satisfactorily completed and alldefects rectified . The amount of performance

    security shall be in form and currency specifiedin the contract (4.2)

    4. Commencement of work:The employer shallgive at least 7 days notice to commence work

    after issue of letter of acceptance. Thecontractor shall commence work within 42 daysof acceptance of contract. (8.1)

  • 8/13/2019 Fidic Conditions

    50/85

    Administration of Contract:

    5. Programme for constructionThe contractor

    within 28 days of acceptance of contract shallgive a detailed programme for sequence andstages of completion, methods of construction,procurement, materials and testing consistentwith period of completion. Revised programme

    shall be furnished whenever it is found that theearlier programme submitted is not consistentwith the period of completion (8.2)

    6. Details of temporary works - The contractor is

    responsible for safety and stability of siteoperations. He shall submit methods ofexecution. He designs the works to the extentspecified in the contract. (4.1)

  • 8/13/2019 Fidic Conditions

    51/85

    Administration of Contract:

    7. Extension of time for completion: The

    contractor shall be eligible for extension if Variations and substantial changes ordered by

    the employer

    Due to employers actions causing delays thatgive rise to entitlement of extension of time

    Adverse climatic conditions affecting progressof work

    Non availability of goods and personnel due tounforeseeable Government actions (8.4)

  • 8/13/2019 Fidic Conditions

    52/85

    Administration of Contract:

    7. Extension of time for completion: Extension of

    time will be granted by the employer if thefollowing conditions exist:

    a) Contractor diligently followed all proceduresstipulated by legally constituted authorities and

    delay in progress of work was unavoidableb) These authorities delay or disrupt theprogress of the work which was unforeseeable

    c) Any other conditions disrupting the workwhich were beyond the control of thecontractor (8.5)

  • 8/13/2019 Fidic Conditions

    53/85

    Administration of Contract:

    8. Rate of progress of work: The contractor shall

    pay for any loss incurred by the employer if anytime:

    a) Actual progress of work is too slow tocomplete the work within the contract period

    b) Progress of work has fallen behind thecontract programme

    c) The contractor is required to employadditional resources and employ new methodsfor construction as approved by the engineerinvolving additional cost to the employer tocomplete the work (8.6)

  • 8/13/2019 Fidic Conditions

    54/85

    Administration of Contract:

    8. Delay damages: The contractor shall pay delay

    damages for every day of delay but notexceeding the sum specified in the contractusually not more than 10% of contract sum(8.7)

    Suspension of work:Up to 28 days - Engineer may order suspensiongiving the reasons for suspension. Duringsuspension contractor shall protect the site and

    materials. The contractor shall be entitled forextension of time and any such cost. (8.8)

  • 8/13/2019 Fidic Conditions

    55/85

    Administration of Contract:

    8. Suspension of work:

    Beyond 28 days up to 84 days - The contractorshall be entitled for extension of time andpayment of any such cost thereof and cost ofwork of plant and machinery (8.10)

    Prolonged suspension - If the suspensionexceeds 84 days, the contractor shall ask theengineer to allow him to proceed with the work.If the engineer fails to give permission to

    proceed within 28 days after being requested,the contractor by giving notice may treatsuspension as omission of the affected portionof work. (8.11)

  • 8/13/2019 Fidic Conditions

    56/85

    Administration of Contract:

    9. Tests on completion: Contractor shall give 21

    days notice to the engineer and carry out testson completion within 14 days. (9.1)

    Delayed tests: If the engineer delays attendingtests extension of time shall be granted. If the

    contractor in spite of 21 days notice fails to carryout tests, the engineer shall carry out the tests atthe risk and cost of the contractor. (9.2)

    Retesting: The engineer may order retesting if

    the tests do not pass, and the contractor shallcarry out the retesting at his cost. (9.3)

  • 8/13/2019 Fidic Conditions

    57/85

    12. Measurement and evaluation:

    12.1Works to be measured:

    Whenever the engineer requires measurement

    to certain part of work he will give notice to thecontractor and contractor shall promptly attend

    or depute his representative

    Supply any particulars required by the engineer

  • 8/13/2019 Fidic Conditions

    58/85

    12. Measurement and evaluation:

    12.2 Works to be measured:

    Measurement shall be made of the net actual

    quantity Method of measurement shall be in

    accordance with BOQ and other applicable

    schedules

  • 8/13/2019 Fidic Conditions

    59/85

    12. Measurement and evaluation:

    12.3 Evaluation:

    Rate shall be appropriate rate for such item in

    the contract and if no rate exists a new rateappropriate to the item of work if:

    a) The measured quantity of an item is

    changed by more than 10% of BOQb) The change in quantity multiplied by

    such specified rate exceeds 0.01% of

    the contract amount

  • 8/13/2019 Fidic Conditions

    60/85

    12. Measurement and evaluation:

    12.3 Evaluation:

    c) The change in quantity directly changes the

    cost per unit quantity by more than 1%d) The item is not specified in the contract as

    fixed rate item

    e) The item is ordered as variation, no rate isspecified in the contract and no rate is

    appropriate because the item of work is not

    similar in nature

  • 8/13/2019 Fidic Conditions

    61/85

    12. Measurement and evaluation:

    12.3 Evaluation:

    f) New rate shall be derived from any relevant

    item in the contract, otherwise it shall bederived from actual cost of work, together with

    reasonable profit

  • 8/13/2019 Fidic Conditions

    62/85

    13.Variations and adjustments:

    13.2 Value engineering:

    d) The proposal shall be prepared at the cost

    of the contractor and design it if necessarye) The engineer will determine fee @ 50%

    between reduction of contract value and

    reduction in value in quality, life and

    operational efficiency

  • 8/13/2019 Fidic Conditions

    63/85

    13.Variations and adjustments:

    13.3 variation procedure:

    Engineer requests for a proposal for variation

    The contractor responds in writing either by

    giving reasons why he cannot comply or

    submits

    Description of proposed work and aprogramme, time for completion & valuation

  • 8/13/2019 Fidic Conditions

    64/85

    13.Variations and adjustments:

    13.3 Variation procedure:

    The engineer as soon as practicable respond

    with approval or disapproval or comments with

    instructions to carry out the variation with any

    requirements of costs

  • 8/13/2019 Fidic Conditions

    65/85

    13.Variations and adjustments:

    13.4 Payment in applicable currencies:

    If the contract provides for payment in

    different currencies;

    The amount payable in each of the currencies

    Expected currency proportions of the cost of

    varied work with reference to the proportionsspecified in the contract

  • 8/13/2019 Fidic Conditions

    66/85

    13.Variations and adjustments:

    13.5 Provisional sums:

    Provisional sum shall be used only for supplies

    or services for which the provisional sum relates

    Actual amount paid by the contractor

    Percentage to cover overheads and profit as

    stipulated in the contract

  • 8/13/2019 Fidic Conditions

    67/85

    13.Variations and adjustments:

    13.6 Day work: The engineer may order day work

    basis for incidental or minor works or for which

    no standard data is available. The contractorshall submit daily reports of quantities of plant

    and materials used, contractors personnel, type

    and time of contractors equipment and

    temporary works employed and priced

    statements of these resources.

  • 8/13/2019 Fidic Conditions

    68/85

    13.Variations and adjustments:

    13.7 Adjustments for changes in legislation:

    The contract price shall be adjusted to take into

    account any increase or decrease in cost

    resulting from changes in the laws of the

    country made after the base date.

    The contractor is entitled to an extension oftime for any such delay

  • 8/13/2019 Fidic Conditions

    69/85

    13.Variations and adjustments:

    13.8 Adjustments for changes in cost:

    Contract amounts payable shall be adjusted for

    rises or falls in rates of labour, goods or otherinputs to the works by the following formula:

    Pn= a + b Ln+ c En+ d Mn +

    L0 E0 M0

  • 8/13/2019 Fidic Conditions

    70/85

    13.Variations and adjustments:

    13.8 Adjustments for changes in cost:

    Pn Adjustment multiplier to be applied to

    estimated contract value

    a Fixed coefficient stated in the relevant table of

    adjustment data representing non adjustable

    portion in contractual payments

  • 8/13/2019 Fidic Conditions

    71/85

    13.Variations and adjustments:

    13.8 Adjustments for changes in cost:

    b, c, d are coefficients representing the

    estimated portion of each cost element relatedto the execution of work

    Ln, En, Mn are the current cost indices

    L0, E0, M0 Are the base cost indices onthe base date

  • 8/13/2019 Fidic Conditions

    72/85

    13.Variations and adjustments:

    13.8 Adjustments for changes in cost:

    Notes:

    If currency of index is not the relevant currency

    of payment each index shall be converted into

    relevant currency at selling rate of central bank

    Engineer shall determine provisional index forinterim payments

  • 8/13/2019 Fidic Conditions

    73/85

    13.Variations and adjustments:

    13.8 Adjustments for changes in cost:

    Notes:

    If the contractor fails to complete workwithin

    stipulated time the price index shall be

    considered on the date 49 days prior toexpiry

    of the time for completionor the current indexwhich ever is favourable to the employer

  • 8/13/2019 Fidic Conditions

    74/85

    14.Contract price and payment:

    14.1 The contract price:

    Contract price shall be agreed or determined

    and be subject to adjustments in accordancewith the contract

    The contractor shall pay taxes, duties and fees

    required to be paid by him under the contractand contract price shall not be adjusted except

    for changes in legislation

  • 8/13/2019 Fidic Conditions

    75/85

    14.Contract price and payment:

    14.1 The contract price:

    Quantities shown in bill of quantities are not to

    be taken as actual quantities

    The contractor shall submit proposed

    breakdown of each lump sum within 28 days

    after commencement of work

  • 8/13/2019 Fidic Conditions

    76/85

    14.Contract price and payment:

    14.2 Advance payment: (Mobilization advance)

    Employer shall make an advance payment as

    interest free loan for mobilization when thecontractor submits a guarantee by an entity

    within a country approved by the employer

    The advance payment shall be repaid by thecontractor through deductions from interim

    payments due >10% of contract sum

  • 8/13/2019 Fidic Conditions

    77/85

    14.Contract price and payment:

    14.2 Advance payment: (Mobilization advance)

    Deductions shall be made at the amortization

    rate of 25% of the amount of each paymentcertificate

    If the advance is not paid prior to issue of taking

    over certificate/ termination the whole ofbalance shall become due

  • 8/13/2019 Fidic Conditions

    78/85

    14.Contract price and payment:

    14.3, 14.4 Application for interim payment

    certificates & schedule of payments:

    Contractor shall submit a statement in 6 copiesat the end of each month in the approved form

    showing amount due, progress report and other

    supporting documents.

  • 8/13/2019 Fidic Conditions

    79/85

    14.Contract price and payment:

    14.3, 14.4 Application for interim payment

    certificates & schedule of payments (Details to

    be attached) Estimated contract value of the works executed

    Any amounts to be added or deducted due to

    changes in legislation Retention money

  • 8/13/2019 Fidic Conditions

    80/85

    14.Contract price and payment:

    14.3, 14.4 Application for interim paymentcertificates & schedule of payments: (Details to

    be attached) Any amounts to be added/ deducted for

    advance payment/ repayment

    Any amounts to be added/ deducted for plants

    & materials intended for the work Any other additions/ deductions (claims)

  • 8/13/2019 Fidic Conditions

    81/85

    14.Contract price and payment:

    14.3, 14.4 Application for interim payment

    certificates & schedule of payments: (Details to

    be attached) Deduction of amounts certified in all previous

    payments

    The contractor shall submit within 42 days aftercommencement estimated installments of

    payment in each quarter

  • 8/13/2019 Fidic Conditions

    82/85

    14.Contract price and payment:

    14.5 Plant and materials intended for works:

    The contractor shall submit / maintain:

    Satisfactory records of orders, receipts, costsand use of plant and materials

    Shipped bill of lading, evidence of shipment,payment of freight &insurance charges, bank

    guarantees Proper storage of plant & materials at site

  • 8/13/2019 Fidic Conditions

    83/85

    14.Contract price and payment:

    14.6 Issue of interim payment certificates:

    The engineer shall within 28 daysafter

    receiving statement issue a interim paymentcertificate. Cost of rectification/ non conformingwork/ material shall be withheld

    14.7 The employer shall paythe contractor first

    installment of advance payment within 42daysafter issue of letter of acceptance or within 21daysafter receipt of statement

  • 8/13/2019 Fidic Conditions

    84/85

    14.Contract price and payment:

    14.7 Issue of interim payment certificates:

    Each interim paymentcertificate within 56days

    after engineer receives the statement

    Final paymentcertificate within 56 daysafter

    receipt of payment certificate by the employer

  • 8/13/2019 Fidic Conditions

    85/85

    14.Contract price and payment:

    14.8 Delayed payment: If the contractor does notreceive the payment within specified time he will

    be entitled for financing charges at 3% abovecentral bank rate

    14.9 Retention money: After issue of taking overcertificate 50% of retention money shall be paid,

    balance after expiry of defect notification periodand after withholding rectification cost ofdefects