Federal Aviation Administration JFK Bay Runway Construction December 2009

Upload: others

Post on 17-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

JFK Bay Runway

Construction

December 2009

Page 2: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

2JFK Construction

December 2009

Included

• Major initiative timeline

• Dual ground control

• Summary of KAAMCO-presented planned

runway configurations and traffic flows

– 4s Ground Operations – August 20, 2009

– 4s Airspace Flows - September 17, 2009

– 22s Ground Operations & Airspace Flows – October

15, 2009

– 31L/4L Intersection Closure – November 19, 2009

Page 3: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

3JFK Construction

December 2009

Runway Taxiway Closures/Approach Impacts

Page 4: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

4JFK Construction

December 2009

Dual Ground Control/SMS Process

• SRMD

signature in

process

• Training

starts during

January

Page 5: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

5JFK Construction

December 2009

Departure Favorable Configurations• Arrivals to 22L; departures from 22R & 31R (1)

• Arrivals to 31R; departures from 22R & 22L (2)

• Arrivals to 4R; departures from 4L and 31R (3)

#1 #2 #3

Page 6: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

6JFK Construction

December 2009

Departure ConfigurationArrive 22L; Depart 22R & 31R

• Arrive 22L

– Cross active departure runway (22R) at multiple locations

– No airspace changes needed

• Depart 22R and 31R

– Jetblast from 31R departures affect 22L arrivals – Eastern

Service Center and Flight Standards investigating

– 31R use DIXIE, WHITE, RBV

– Considering 22R departures at ‘YA’ (newly constructed) to

avoid intersection (22R/31R)

• 31R Jetblast implications

– 22R use other departure fixes – depart runway heading

Page 7: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

7JFK Construction

December 2009

22L Arrivals - Red

22R & 31R Departures - Blue

YA

Page 8: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

8JFK Construction

December 2009

Arrive 22L, Depart 22R & 31R

Green – 22L Arrivals

Blue – 31R Departures

Red – 22R Departures

Page 9: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

9JFK Construction

December 2009

22L Arrivals

Page 10: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

10JFK Construction

December 2009

22R & 31 Departures

Page 11: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

11JFK Construction

December 2009

Departure ConfigurationArrive 31R; Depart 22R & 22L

• Arrive 31R

– Displaced threshold – 9000’ available

– Airspace reallocation

• Depart 22R and 22L

– Taxi route crosses 31R

– 22R and 31R intersection – Eastern Service Center and Flight

Standards reviewing jetblast implications

• Considering 22R departures at ‘YA’ (newly constructed) to avoid

intersection (22R/31R)

– 22L depart on 205 heading, 22R rwy heading

– 22L departures mostly to north and east

Page 12: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

12JFK Construction

December 2009

31R Arrivals - Red

22R & 22L Departures - Blue

YA

Page 13: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

13JFK Construction

December 2009

Arrive 31R, Depart 22R & 22L

Green – 31R Arrivals

Red – 22R & 22L Departures

Page 14: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

14JFK Construction

December 2009

31R Arrivals

Page 15: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

15JFK Construction

December 2009

22 Departures

Page 16: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

16JFK Construction

December 2009

Departure ConfigurationArrive 4R; Depart 4L & 31R

• Arrive 4R

– No airspace changes needed

• Depart 4L and 31R

– 31R Jetblast affects 4R arrivals taxi to ramp

– Approval to depart 4L runway heading in progress (right

to 100º required)

• De-conflicts arrivals and departures (+ 3-5 departures per

hour)

– 31R used for RBV, WHITE & DIXIE departures

Page 17: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

17JFK Construction

December 2009

Red = 4R Arrivals

Blue = 31R Departures

Yellow = 4L Departures

Page 18: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

18JFK Construction

December 2009

Arrive 4R, Depart 4L & 31R

Green – 4R Arrivals

Blue – 31R Departures

Red - 4L Departures

Page 19: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

19JFK Construction

December 2009

Runway 4 Arrival Tracks

Page 20: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

20JFK Construction

December 2009

Runway 4 & 31 Departure Tracks

Page 21: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

21JFK Construction

December 2009

Arrival Favorable Configurations• Arrivals to 13L & 22L; departures from 22R (4)

• Arrivals to 22L & 22R; departures from 31R (5)

• Arrivals to 4R and 4L; departures from 31R (6)

#4 #5 #6

Page 22: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

22JFK Construction

December 2009

Arrival ConfigurationArrive 13L & 22L; Depart 22R

• Arrive 13L and 22L

– 13L displaced threshold, 9000’ available

– If 13L landings go to end, cross active departure runway (22R) at

multiple locations

– 13L primarily use CAMRN and LENDY

– No airspace changes needed

– 22L arrivals cross active departure runway (22R) at multiple locations

– 22L primarily use ROBER

• Depart 22R

– Considering departing at ‘YA’ to avoid intersection (22R/13L) • Reduce runway crossings

– Runway heading departures

Page 23: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

23JFK Construction

December 2009

13L & 22L Arrivals - Red

22R Departures - Blue

Page 24: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

24JFK Construction

December 2009

Arrive 13L & 22L, Depart 22R

Green – 13L Arrivals

Blue – 22L Arrivals

Red – 22R Departures

Page 25: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

25JFK Construction

December 2009

13R & 22L Arrivals

Page 26: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

26JFK Construction

December 2009

22R Departures

Page 27: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

27JFK Construction

December 2009

Arrival ConfigurationArrive 22R & 22L; Depart 31R

• Arrive 22R and 22L

– 22L arrivals cross active arrival runway (22R) at multiple

locations

– 22R displaced threshold – 8000’ available

– No airspace changes needed

• Depart 31R

– Dependent on LGA configuration (not departing Rwy 13)

• Mitigated by LGA RNAV SIDs (4-8-2010)

– Jetblast from 31R departures affect 22L arrivals – Eastern

Service Center and Flight Standards investigating

Page 28: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

28JFK Construction

December 2009

22L & 22R Arrivals - Red

31R Departures - Blue

Page 29: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

29JFK Construction

December 2009

Arrive 22R & 22L, Depart 31R

Page 30: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

30JFK Construction

December 2009

22 Arrivals

Page 31: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

31JFK Construction

December 2009

31R Departures

Page 32: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

32JFK Construction

December 2009

Arrival ConfigurationArrive 4R & 4L; Depart 31R

• Arrive 4R & 4L– No airspace changes needed

• Depart 31R – Jetblast affecting 4R arrivals taxi to ramp

– 4L Arrival & 31R departure intersecting runway separation

– May require additional spacing between successive 31R

departures

– All must top Rwy 4 arrivals except RBV, WHITE and DIXIE

departures

– Departure airspace modification

– Reroute V16 prop traffic

Page 33: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

33JFK Construction

December 2009

4R & 4L Arrivals- Red

31R Departures - Blue

Page 34: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

34JFK Construction

December 2009

Arrive 4R & 4L; Depart 31R

Green – 4R & 4L Arrivals

Blue – 31R Departures

V16

Page 35: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

35JFK Construction

December 2009

Runway 4 Arrival Tracks

Page 36: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

36JFK Construction

December 2009

Runway 31L Departure Tracks

Page 37: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

37JFK Construction

December 2009

Planned Configurations During 4L ClosureSeptember 16 thru September 29, 2010

• Land 13L & 22L Depart 13R

– 2000 foot ceiling and 3 mile visibility required

– 13R - Departure runway available = 10,700’

• Land 31R & 31L Depart 31L

– 31L Landing runway available = 11,248’

– 31L Departure runway available = 10, 700

• Land 13L Depart 13R

– ILS 13L possible during poor weather

– 13R Departure runway available = 10,700’

• Land 4R & 13R Depart 13L

– 2000 foot ceiling and 3 mile visibility required

– 13R - Landing runway available = 8,657’

Page 38: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

38JFK Construction

December 2009

Page 39: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

39JFK Construction

December 2009

Arrive 4R & 13R, Depart 13L

Green – 4R & 13R Arrivals

Red – 13L Departures

Page 40: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

40JFK Construction

December 2009

4R & 13R Arrivals

Page 41: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

41JFK Construction

December 2009

13L Departures

Page 42: Federal Aviation JFK Bay Runway Construction · JFK Construction December 2009 Included • Major initiative timeline • Dual ground control • Summary of KAAMCO-presented planned

Federal AviationAdministration

42JFK Construction

December 2009

IOUs