february 19, 2009 ercot follow up on questions from 2/11 discussion on proposed expedited switch...
DESCRIPTION
3 Two or Three Types? If with proposed rulemaking the Expedited Switch replaces the On- Cycle Switch: –ERCOT believes we may have to make minor system changes. –No TX SET version change foreseen. –Cancels inside the window(s) to be managed with the MarkeTrak process. If proposed rulemaking has 3 types of switches – Off-cycle, On-cycle and Expedited: –ERCOT would work with the market to add the expedited switch processes into the stacking logic. –TX SET change would be required to accommodate the expedited switch transaction. –ERCOT believes we may have to make major system changes and facilitate a flight test with the market prior to implementation.TRANSCRIPT
![Page 1: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/1.jpg)
February 19, 2009
ERCOT
Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…
![Page 2: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/2.jpg)
2
ERCOT’s understanding of the proposed rulemaking:
– Currently there are 2 types of Switch transactions:• On-Cycle – ERCOT sends the First Available Switch Date (FASD)
to the TDU• Out-of-Cycle – ERCOT sends the FASD and the Special Read Date
Requested by the Rep to the TDU
– After the rule making ERCOT believes the Expedited Switch will replace the On-Cycle Switch:
• Expedited – ERCOT sends the FASD to the TDU. TDU returns a Scheduled Meter Read Date (SMRD) for the Switch within the 6 calendar day window.
• Out-of-Cycle – ERCOT sends the FASD and the Special Read Date Requested by the Rep to the TDU
![Page 3: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/3.jpg)
3
Two or Three Types?
• If with proposed rulemaking the Expedited Switch replaces the On-Cycle Switch:– ERCOT believes we may have to make minor system changes.– No TX SET version change foreseen.– Cancels inside the window(s) to be managed with the MarkeTrak
process.
• If proposed rulemaking has 3 types of switches – Off-cycle, On-cycle and Expedited:– ERCOT would work with the market to add the expedited switch
processes into the stacking logic.– TX SET change would be required to accommodate the expedited
switch transaction.– ERCOT believes we may have to make major system changes and
facilitate a flight test with the market prior to implementation.
![Page 4: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/4.jpg)
4
Parking Lot / Questions for follow up?
• What other questions would MPs like ERCOT to research to bring back to future meetings?1. Show trans flow of priority MVI with switch2. Show trans flow of permit pending MVI with switch3. Review impact to ERCOT system/stacking logic if change
evaluation / cancellation window for switches from 5 day to 2 day
4. Review impact to ERCOT system/stacking logic if change FASD date from EPD+3BD to EPD+1BD, EPD+2BD
5. Review impact to ERCOT system/stacking logic if change FASD to equal the 6 calendar days out (TDSP bounce back the FASD as the SMRD)
![Page 5: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/5.jpg)
5
• Scenario 1 - • Priority Move In received day before a scheduled Switch
– ERCOT will accept the Move In and cancel the Switch, same as standard MVI scenario
Follow up #1 – Trans Flow of Priority MVI with Switch
REP C is Rep of Record
REP A submits
Expedited Switch
Saturday 02/07
Monday
02/09
Thursday 02/12
Sunday 02/15
Wednesday
02/18
Saturday02/21
Switch FASD is calculated at 3 Business
daysTDSP schedules Switch within the 6 day window
Switch for REP A is Scheduled
for 02/17
Rep B submits
priority MVI for 02/17 Switch for
2/17 will be Cancelled
![Page 6: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/6.jpg)
6
• Scenario 2 - • Priority Move In received same day as scheduled Switch
– ERCOT will accept the Move In. The Switch will not be cancelled on receipt of the Move In.
– Switch will be cancelled upon receipt of the 814_04 on the Move In
Follow up #1 – Trans Flow of Priority MVI with Switch
REP C is Rep of Record
REP A submits
Expedited Switch
Saturday 02/07
Monday
02/09
Thursday 02/12
Sunday 02/15
Wednesday
02/18
Saturday02/21
Switch FASD is calculated at 3 Business
daysTDSP schedules Switch within the 6 day window
Switch for REP A is Scheduled
for 02/17 Rep B submits
priority MVI for 02/17
Switch for 2/17 will be Cancelled
upon receipt of the 814_04 on the
Move In
![Page 7: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/7.jpg)
7
• Scenario 1• Permit Pending Move In received prior to Switch.
– ERCOT will accept the Switch. Switch is not cancelled.
Follow up #2 – Trans Flow of Permit Pending MVI w/Switch
REP C is Rep of Record
Rep B submits MVI
requesting 2/16. TDSP
responds with 814_28 PT
Saturday 02/07
Monday
02/09
Thursday 02/12
Sunday 02/15
Wednesday
02/18
Saturday02/21
Switch FASD is calculated at 3 Business
daysTDSP schedules Switch within the 6 day window
Switch for REP A is Scheduled
for 02/17
REP A submits
Expedited Switch
![Page 8: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/8.jpg)
8
• Scenario 1• Cancel & Notification changed to 2 business days
– ERCOT would accept the 814_08 from the CR until 2 business days prior to the Scheduled Meter Read Date of the Switch.
– ERCOT would have to make system changes. Similar to MVI logic.
– No TX SET version change foreseen.
– Cancels inside the 2 day window to be managed with the current MarkeTrak process.
Follow up #3 – Trans Flow / Impact of 5 day to 2 day for evaluation / cancellation window
![Page 9: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/9.jpg)
9
• Scenario 1 - continued• Cancel & Notification changed to 2 business days
– ERCOT will accept the 814_08 from the CR until 2 business days prior to the Scheduled Meter Read Date of the Switch.
Follow up #3 – Trans Flow / Impact of 5 day to 2 day for evaluation / cancellation window
REP C is Rep of Record
Rep A submits
Expedited Switch
Saturday 02/07
Monday
02/09
Thursday 02/12
Sunday 02/15
Wednesday
02/18
Saturday02/21
Switch FASD is calculated at 3 Business
daysTDSP schedules Switch within the 6 day window
Switch for REP A is Scheduled
for 02/16
REP Cancel will be accepted through 2/11
2 business day cancel window
814_06 Notification will be sent 2/12
![Page 10: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/10.jpg)
10
• Scenario 2• Cancel & Notification changed to 2 business days
– TDSP determines the Switch can be worked prior to Scheduled Meter Read Date. ERCOT send 814_06 after the Switch completes in ERCOTs system
Follow up #3 – Trans Flow / Impact of 5 day to 2 day for evaluation / cancellation window
REP C is Rep of Record
Rep A submits
Expedited Switch
Saturday 02/07
Monday
02/09
Thursday 02/12
Sunday 02/15
Wednesday
02/18
Saturday02/21
Switch FASD is calculated at 3 Business
daysTDSP schedules Switch within the 6 day window
Switch for REP A is Scheduled
for 02/16
TDSP determines they can work the switch early and
completes for 02/11
814_06 is not sent till after the Switch Completes in ERCOTs system or at 2 Business Prior to the SMRD of 2/16
![Page 11: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/11.jpg)
11
Follow up #4 and #5
4. Review impact to ERCOT system/stacking logic if change FASD date from EPD+3BD to EPD+1BD, EPD+2BD
5. Review impact to ERCOT system/stacking logic if change FASD to equal the 6 calendar days out (TDSP bounce back the FASD as the SMRD)
If proposed rulemaking changes the FASD timeline – ERCOT would work with the market to adjust the new FASD timeline
along with other expedited switch changes into the MIMO stacking logic business rules
– TX SET change would be required to accommodate the expedited switch transaction.
– ERCOT believes we may have to make major system changes and facilitate a flight test with the market prior to implementation.
![Page 12: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/12.jpg)
12
REP / TDSP Questions for follow up?
• What other questions were brought up for MPs to review and bring back for next time?– All MPs – review slide deck and determine impacts, gaps,
questions – TDSPs asked
• Are REPs open to the use of estimates?• How will the expected switch date of an expedited switch be
communicated to the customer?– REPs asked
• What additional changes have to occur at the TDSP level if FASD remains at 3BD but the evaluation window shrinks from 5BD to 2BD
• What if the 6th calendar day is on a non-business day? Will the TDSP go back to the last BD to determine the scheduled date?
![Page 13: February 19, 2009 ERCOT Follow up on questions from 2/11 discussion on proposed Expedited Switch rulemaking changes…](https://reader036.vdocuments.mx/reader036/viewer/2022082723/5a4d1b3e7f8b9ab05999f8b4/html5/thumbnails/13.jpg)
13
Parking Lot / Questions for follow up?
• What other questions were brought up for MPs to review and bring back for next time?– Obviously any rulemaking changes then result in corresponding
PRR, RMGRR that the market and ERCOT would need to review.
• Do we need another workshop?