factors effecting performance

47
10-06-2014 1 1 FACTORS AFFECTING PERFORMANCE By Bert van Gent Dredging and Marine Contractors 2 Dredging and Marine Contractors Dredging…? 3 Double production…! Dredging and Marine Contractors

Upload: bembie83

Post on 21-Dec-2015

31 views

Category:

Documents


1 download

DESCRIPTION

Performance

TRANSCRIPT

10-06-2014

1

1

Chapter title

FACTORS AFFECTING PERFORMANCE

By Bert van Gent

Dredging and Marine Contractors

2

Dredging and Marine Contractors

Dredging…?

3

Double production…!

Dredging and Marine Contractors

10-06-2014

2

4

Breakdown of the dredging process

Overview of dredgers

• Cutter suction dredger

• Trailing suction hopper dredger

• Backhoe dredger

• Grab dredger

• Other equipment

• Environmental dredgers

Equipment

Dredging and Marine Contractors

5

1. Loosening the material (and/or dislodging)

2. Picking up the loosened material

3. Transport

• through the primary dredger

• further transport

4. Disposal of the material

• under water

• on shore

Breakdown of the Dredging Process

Dredging and Marine Contractors

6

• Hydraulic (erosion, discharge pipe, etc.)

• Mechanical (cutter, conveyor belt, etc.)

Remark

The different sub-processes may require different types of

dredging equipment

Means to realise the partial processes

Dredging and Marine Contractors

10-06-2014

3

7

1. Hydraulic/mechanical dredgers (CSD)

2. Hydraulic dredgers (TSHD)

3. Mechanical dredgers (Backhoe, Grab)

4. Environmental dredgers

Overview of dredgers

Dredging and Marine Contractors

8

Cutter Suction Dredger (CSD)

Hydraulic/Mechanical Dredgers

Dredging and Marine Contractors

9

Cutter Suction Dredgers

Mid-size, 600-1500 kW

Small < 600 kW

Large, 1500-3000 kW

Dredging and Marine Contractors

Cutter power

10-06-2014

4

10

Mega, 5500-7500 kW Heavy Duty, 3000-5500 kW

Cutter power

Cutter Suction Dredgers

Dredging and Marine Contractors

11

• Main characteristics

• Most important parts of the dredger

• Working principle

• Production limiting factors

• Some characteristic figures

Cutter Suction Dredgers

Dredging and Marine Contractors

12

Main characteristics

• Nearly all kinds of soils (sand, clay, rock)

• Stationary dredger:

− vulnerable to shipping

− sensitive to wave conditions

• Some are self-propelled for mobilisation

Cutter Suction Dredgers

Dredging and Marine Contractors

10-06-2014

5

13

Cutter Suction Dredgers - Parts

Dredging and Marine Contractors

14

Most important parts, machinery

• Cutter head and cutter drive

• Dredge pump(s)

• (Side-) Winches and sheaves for the side

wires for swinging

Cutter Suction Dredgers

Dredging and Marine Contractors

15

Working principle

• Cutter disintegrates or dislodges the material

mechanically by rotating cutter head

• Material sucked up and transported through pipeline

by use of centrifugal dredge pumps

• Pontoon movement by:

- swinging around working spud

- progress by successive steps (stepping)

and spuds (spudding)

Cutter Suction Dredgers

Dredging and Marine Contractors

10-06-2014

6

16

CSD WORK METHOD (1)

Swing

to SB

Dredging and Marine Contractors

17

Stop at SB,

Push dredger

forward

CSD WORK METHOD (2)

Dredging and Marine Contractors Dredging and Marine Contractors

18

Start swing

to PS

CSD WORK METHOD (3)

Dredging and Marine Contractors

10-06-2014

7

19

Continue

swing

to PS

CSD WORK METHOD (4)

Dredging and Marine Contractors

20

Stop at PS,

Push dredger

forward

CSD WORK METHOD (5)

Dredging and Marine Contractors

21

Start swing to SB

CSD WORK METHOD (6)

Dredging and Marine Contractors

10-06-2014

8

22

Stop in

Centre Line

CSD WORK METHOD (7)

Dredging and Marine Contractors

23

Aux. spud

down

CSD WORK METHOD (8)

Dredging and Marine Contractors

24

Main spud

up

CSD WORK METHOD (9)

Dredging and Marine Contractors

10-06-2014

9

25

Main spud

forward

CSD WORK METHOD (10)

Dredging and Marine Contractors

26

Main spud

down

CSD WORK METHOD (11)

Dredging and Marine Contractors

27

Aux. spud

up

CSD WORK METHOD (12)

Dredging and Marine Contractors

10-06-2014

10

28

CSD WORK METHOD (13)

Start

swing

to SB

Dredging and Marine Contractors

29

CSD WORK METHOD (14)

Continue

swing

to SB

Dredging and Marine Contractors

30

Process topics

• Over-cutting versus under-cutting

• Spill

• Cutter heads

• Anchors

Cutter Suction Dredger

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

11

31

spillage

(cutting deeper than design level)

undercutting overcutting

Cutter Suction Dredger

Dredging and Marine Contractors Dredging and Marine Contractors

32

Cutter head

• Back ring - arms - hub

• Blades - teeth: chisels / pick points

• Various shapes

Cutter with chisels

Cutter Suction Dredger

Dredging and Marine Contractors Dredging and Marine Contractors

33

Sand/clay cutter head

Cutter Suction Dredger

Rock cutter head

Dredging and Marine Contractors

10-06-2014

12

34

• Anchors

Depending on soil type

Flipper Delta

Stevshark

Cutter Suction Dredger

Dredging and Marine Contractors

35

• Anchors

Anchor islands

Cutter Suction Dredger

Dredging and Marine Contractors

36

Production limiting factors

• Soil characteristics

• Available power on cutter

• Side winches (max. power and velocity)

• Thickness and width of the layer to be dredged

• Dredging depth (ladder angle, spuds, cavitation)

• Pumping distance (pump- and pump drive characteristics)

• Shipping

• Waves and currents

• Dirt and debris

Cutter Suction Dredger

Dredging and Marine Contractors

10-06-2014

13

37

cutter suction dredger small mid-size large

dimensions 65 * 10 * 2 m 70 * 16 * 4 m 120 * 20 * 5 m

(L*W*Dr)

total power < 3,000 kW < 9,000 kW < 13,000 kW

cutter power < 600 kW < 1,500 kW < 3,000 kW

max. swing speed 19 m / min 32 m / min 32 m / min

max. dredging depth 15-20 m 25 m 25 - 30 m

discharge diameter 0.35 - 0.70 m 0.65 - 0.85 m 0.75 - 0.85 m

Characteristic Figures

Cutter Suction Dredger

Dredging and Marine Contractors

38

cutter suction dredger heavy duty mega

dimensions 125 * 22 * 5 m 140 * 24 * 6.5 m

(L*W*Dr)

total power < 23,000 kW < 28,000 kW

cutter power < 5,500 kW < 7,000 kW

max. swing speed 32 m / min 32 m / min

max. dredging depth 25 - 35 m 30 - 35 m

discharge diameter 0.80 - 0.90 m 0.90 - 1.00 m

Characteristic Figures

Cutter Suction Dredger

Dredging and Marine Contractors

39

Cutter Suction Dredger

10-06-2014

14

40

Suction dredgers

• Trailing Suction Hopper Dredger (TSHD)

• Plain suction dredger

• Barge unloading dredger

• Water Injection Dredger (WID)

Hydraulic Dredgers

Dredging and Marine Contractors

ing and Marine Contractors

41

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

42

Mid-Size 8,800 m3

Large 13,500 m3

Small, 4000 m3

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

10-06-2014

15

43

Jumbo 18,000 – 22,000m3

Mega 37,000 m3

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

44

• Main characteristics

• Most important parts of the dredger

• Process description

• Production limiting factors

• Some characteristic figures

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

45

Main characteristics

• Free sailing

• Self-propelled

• Self-loading when trailing

• Self-unloading or -discharging

• Seagoing or inland waterway vessel

• All soils (also weak rock!)

• Relatively insensitive for waves

• Not vulnerable for shipping

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

10-06-2014

16

46

bow-coupling for pumping ashore or rainbowing

suction pipe hopper

service crane

pump room

propulsion

engine room

swell compensator

wheel house

draghead

- 70m

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

47

Most important parts

• Dragheads

• Dredge pump(s)

• Hopper, loading and unloading system

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

48

Dredging cycle

• Loading at the dredging- or sand borrow area

• Sailing (loaded) to the unloading area

• Unloading (dumping or pumping)

• Sailing (empty) to the dredging area

TSHD Process Description

Dredging and Marine Contractors

10-06-2014

17

49

TSHD Process Description

Excavation (Erosion & Cutting)

Dredging and Marine Contractors

50

Suction

TSHD Process Description

Dredging and Marine Contractors

51

Loading Loading (overflow)

TSHD Process Description

Dredging and Marine Contractors

10-06-2014

18

52

Longitudinal section

Top view hopper

Loading: Basic Principle

TSHD Process Description

Dredging and Marine Contractors

53

Top view hopper

Full Load: Basic Principle

Longitudinal section

TSHD Process Description

Dredging and Marine Contractors

54

Text (full)

Hopper loading (mud)

Dredging and Marine Contractors

Total Volume [m3]

Draught [m] (=tons)

Max.

draught

Max. volume

Mud [m3]

10-06-2014

19

55

Text (full)

Hopper loading (sand)

Dredging and Marine Contractors

Draught [m] (=tons) Max.

draught

Overflow losses

Sand [m3]

Total Volume [m3]

Max.`volume

56

Sailing loaded

TSHD Process Description

Dredging and Marine Contractors

57

Discharge

TSHD Process Description

Dredging and Marine Contractors

10-06-2014

20

58

Rainbowing

Hopper Self-discharge: rainbow

TSHD Process Description

DDredging and Marine Contractors

ng and Marine Contractors

59

Hopper Self-discharge: Pump ashore

TSHD Process Description

Dredging and Marine Contractors

60

Text (full)

TSHD Process Description

Dredging and Marine Contractors

Hopper Self-discharge: system

Dredge pump

Jets Jets

Water

Sand

Jets

Water inlet Discharge

10-06-2014

21

61

Text (full)

TSHD Process Description

Dredging and Marine Contractors

Jets Jets

Dredge pump

Jets

Water inlet

Hopper Self-discharge: system

Discharge

62

Text (full)

TSHD Process Description

Dredging and Marine Contractors

Jets

Water inlet Discharge

Dredge pump

Jets Jets

Hopper Self-discharge: system

Dredging and Marine Contractors

63

Text (full)

TSHD Process Description

Dredging and Marine Contractors

Jets Jets

Water inlet Discharge

Dredge pump

Jets

Hopper Self-discharge: system

Dredging and Marine Contractors

10-06-2014

22

64

Sailing empty

TSHD Process Description

Dredging and Marine Contractors

start overflow

DRAUGHT (m)

start

dredging

stop

loading

sailing

loaded

emptying hopper

sailing

empty

TIME IN MINUTES

Cycle-time per trip

next

trip

TSHD Load Graph (emptying by bottom door disposal)

VOLUME SAND (m3)

TOTAL LOAD (ton)

Dredging and Marine Contractors

start overflow

DRAUGHT (m)

start

dredging

stop

loading

sailing

loaded

unloading

hopper

sailing

empty

TIME IN MINUTES

Cycle-time per trip

next trip

VOLUME SAND (m3)

TSHD Load Graph (discharging to shore)

Dredging and Marine Contractors

10-06-2014

23

67

Process related topics

• The hull

• The hopper

• Dragheads, suction pipes and belongings

• Centrifugal pumps

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

68

The hull

• Sailing characteristics

• Resistance

• Small keel clearance

• Maximum carrying capacity versus draft, length and width

• Strength

• Stability

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

69

The hopper

• Carrying capacity

• Volume

• Weight

• Filling system

• Overflow system

• Bottom door disposal system

• Self-discharge system

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

10-06-2014

24

Hopper: carrying capacity

Restriction by volume (full hopper)

Restriction by weight (max. draught)

Low density soils

e.g.: Mud - 1.2 ton/m3

5,000 x 1.2 = 6,000 ton

High density soils

e.g.: Sand - 2.0 ton/m3

3,500 x 2.0 = 7,000 ton

HOPPER

HULL

MUD

5,000 m3

6,000 ton

HOPPER

HULL

SAND

3,500 m3

7,000 ton

Dredging and Marine Contractors

Overflow System

Conical bottom-valves

Bottom-doors

Hopper: loading & dumping facilities

Dredging and Marine Contractors

72

Dragheads

DDredging and Marine Contractors

ing and Marine Contractors

10-06-2014

25

73

Sand Draghead

Dredging and Marine Contractors

74

Different dragheads

Dredging and Marine Contractors

75

Suction Pipe

Dredging and Marine Contractors

10-06-2014

26

76

Workability – Weather Delay

DrDredging and Marine Contractors

edging and Marine Contractors

Swell

Compensator

Draghead Winch

Pressure

Jar

Seabottom

Swell Compensator

Oil

Draghead

Dredging and Marine Contractors

78

Centrifugal Pumps

Hardware

• Types & sizes

• Basic parts

inboard pump under water pump

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

27

79

Working principle

• Energy Distribution

• Propulsion

• Pumps

• Boardnet

• Centrifugal pump

Centrifugal Pumps

Dredging and Marine Contractors

80

Density & velocity meter

Engine-room with 2 pumps in line

Centrifugal Pumps

Dredging and Marine Contractors

81

Production limiting factors

• Soil characteristics

• Available propulsion power

• Drag head size and weight

• Keel clearance when loaded

• Dredging depth

• Pumping distance (pump- and pump drive characteristics)

• Waves and currents

• Dirt and debris

Production may vary a lot due to these factors

Trailing Suction Hopper Dredger

Dredging and Marine Contractors

10-06-2014

28

82

Limiting factors

A drag head grid damaged by boulders

Dredging and Marine Contractors Dredging and Marine Contractors

83

Limiting factors

Dirt and debris

Dredging and Marine Contractors

84

trailing suction small mid-size large

hopper dredger

dimensions 55*10*4 m 90*18*7 m 130*23*9 m

(L*W*Dr)

max. dredging 10-35 m 25-55 m 25-75 mdepth

hopper capacity <4,000 m3 <8,000 m3 <15,000 m3

sailing speed 8 knots 12 knots 14 knots

propulsion power 400 kW 3,500 kW 8,000 kW

diam. suction-pipe 0.35-0.9 m 0.80 m 0.90-1.00 m

Trailing Suction Hopper Dredger Characteristic Figures

Dredging and Marine Contractors

10-06-2014

29

85

trailing suction jumbo mega

hopper dredger

dimensions 180*32*13 m 225 x 38 x 12 – 15.5 m

(L*W*Dr)

max. dredging 50-120 m 55 - 155 mdepth

hopper capacity <30,000 m3 30,000 - 46,000 m3

sailing speed 17 knots 16 - 18 knots

propulsion power

(while dredging) 18,000 kW 26,000 kW

diam. suction-pipe 1.20 m 1.2 - 1.4 m

Trailing Suction Hopper Dredger Characteristic Figures

Dredging and Marine Contractors

86

Trailing Suction Hopper Dredger

87

Suction Dredgers

• Plain Suction Dredger

• Barge unloading dredger

• Water Injection Dredger (WID)

Other Hydraulic Dredgers

Dredging and Marine Contractors

10-06-2014

30

88

• Suction of free running material (sand)

• Jet water for dislodging and fluidising material

• Deep suction pit necessary

• Stationary dredger, not swinging, only intermittently moving forward

Plain suction dredger

Dredging and Marine Contractors

89

Barge Unloading Dredger

• Unloading of barges by suction

• Jets for dislodging and fluidising

• Barge to be shifted alongside the dredger during suction

Dredging and Marine Contractors

90

Water Injection Dredger

• Injection of water into bottom

• Low pressure and high capacity

• Fine sand and silt

• Movement of material due to gravity forces (density current)

Dredging and Marine Contractors

10-06-2014

31

91

92

Backhoe Dredger

Dredging and Marine Contractors

93

Backhoe Dredger

Mega backhoe Simson, 3460 kW

Dredging and Marine Contractors

10-06-2014

32

94

• Main characteristics

• Typical parts

• Dredging cycle

• Production limiting factors

• Some characteristic figures

Backhoe or Hydraulic Excavator

Dredging and Marine Contractors

95

Main characteristics

• Normal backhoe/front-shovel on pontoon or

• Specially built pontoon (with spuds) with backhoe on rotating table

• Dredged material is loaded into barges

• Reasonable cutting force can be generated

• Suitable for:

• “Non-rock” type soils with stones

• Blasted rock

• Precision dredging

Backhoe

Dredging and Marine Contractors

96

Dredging blasted rock

Backhoe

Dredging and Marine Contractors

10-06-2014

33

97

Bucket

Stick Boom

Backhoe - parts

Spud

Dredging and Marine Contractors

98

• Different types and sizes to be fitted:

• Sticks

• Buckets

• Booms

• Positioning with spuds

Backhoe

Dredging and Marine Contractors

99

Dredging cycle

• Lowering bucket

• Filling bucket by cutting and tilting

• Hoisting bucket

• Turning crane towards barge

• Emptying bucket into barge

• Turning back

Backhoe

Dredging and Marine Contractors

10-06-2014

34

100

overlap Nett dredging width

Centre line

Reach

Barge

Working Method Backhoe

Preferred working direction:

backwards

=> Higher production

=> Less spill

But…

Forward dredging is also possible

Dredging and Marine Contractors

101

• Work method

• Excavation force at large depth

• Slope dredging (bucket positioning)

• Precision dredging along quay-walls

• Soil and obstructions

• Hard material (no rock)

• Big boulders

• Removal of debris or vegetation

• Workability

• Waves

• Shipping

Production Limiting Factors

Dredging and Marine Contractors

102

Backhoe Small Medium Large Mega

Length m1

30 45 50 65

Draught m1

1.5 2.0 2.5 3.5

Dredging Depth m1

10-15 15 - 20 20 - 30 20 - 30

Bucket size m3

1 - 3 2 - 8 5 - 20 15-40

Power Installed kW 500 < 1,000 < 2,000 < 4200

Backhoe Characteristic Figures

Dredging and Marine Contractors

10-06-2014

35

103

Backhoe

104

Grab Dredger

Dredging and Marine Contractors

105

• Main characteristics

• Dredging characteristics

• Typical parts

• Dredging cycle

• Production limiting factors

• Some characteristic figures

Grab Dredger

Dredging and Marine Contractors

10-06-2014

36

106

Main characteristics

• Can also be used for construction works (shore & bank protection)

• Normal grab-crane on pontoon

OR

• Specially built pontoon (with spuds) with fixed grab-crane on rotating table

• Small grab dredgers for difficult accessible areas

Grab Dredger

Dredging and Marine Contractors

107

Dredging characteristics

• Dredging up to large depth’s

• Cannot create an even bottom

• Dredged material is loaded into barges

• Non-rock types of soil

• Suitable for debris and vegetation

Grab Dredger

Dredging and Marine Contractors

108

Areas with difficult access

Grab Dredger

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

37

109

Groyne Construction

Grab Dredger

Dredging and Marine Contractors

110

Typical parts

• Different types and sizes to be fitted:

• Grabs

• Booms

• Positioning with spuds or anchors

Grab Dredger

Dredging and Marine Contractors

111

Standard grab (sand, clay, mud)

Cactus/Polyp grab (stones)

Grab Dredger

Dredging and Marine Contractors

10-06-2014

38

112

Dredging cycle

• Lowering grab

• Closing grab

• Hoisting grab

• Turning crane towards barge

• Emptying grab into barge

• Turning back

Grab Dredger

Dredging and Marine Contractors

113

Production limiting factors

• Hard material

• Big boulders, blasted rock

• Removal of debris or vegetation

• Dredging depth

• Waves and currents

• Shipping

Grab Dredger

Dredging and Marine Contractors

114

Grab Dredger Small Mid-size Large

Dimensions L x Dr. 30 x 1.5 45 x 1.7 50 x 2

Dredging Depth m1 25 40 50

Grab size m3 2.5 - 5 5 - 15 15 - 50

Characteristic Figures

Grab Dredger

Dredging and Marine Contractors

10-06-2014

39

115

• Bucket ladder dredger (BLD)

• Dipper dredger

• Rock breaker

• Plough or bottom leveller

Other Mechanical Dredgers

Dredging and Marine Contractors

116

Bucket Ladder Dredger

• Revolving chain of buckets

• Swinging like a cutter suction dredger

• No spuds, position fixed by wires

• Buckets turning upside down to empty

• Discharge into barges

Dredging and Marine Contractors

117

Buckets are turning upside down to

discharge into barges

Bucket Ladder Dredger

Dredging and Marine Contractors

10-06-2014

40

118

Bucket Ladder Dredger in Action

Dredging and Marine Contractors

119

Rock Breaker

• Hydraulic power to break rock

• Assists dredger on small spots

• Broken rock to be removed by excavator

Dredging and Marine Contractors

120

Plough or Bottom Leveller

• Towed by tug

• Assisting TSHD with removal of ridges and high spots

• Removal of soft material from small harbours

• Low production

• Cheap

Dredging and Marine Contractors

10-06-2014

41

121

Water based

• Barges

• Work boats and launches

• Anchor pontoons, floating line pontoons

• Booster station

Other Equipment

Dredging and Marine Contractors

122

Survey launch

Multicat for handling and transport

A-frame for anchor handling

Dredging and Marine Contractors Dredging and Marine Contractors

123

Floating pipeline pontoons

Rubber floating pipeline

Use of floating pipeline

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

42

124

Floating cover

Female Ball Joints Male

Rubber Floating Line

Dredging and Marine Contractors Dredging and Marine Contractors

125

Booster station

Dredging and Marine Contractors

126

Land based • Pipelines and valves

• Bulldozers, shovels, etc.

Other Equipment

Dredging and Marine Contractors

10-06-2014

43

127

• Objective

• Types

• Typical Aspects

Environmental Dredgers

Dredging and Marine Contractors

128

Objective:

Environmental Dredgers

• Optimise precision

• Accurately dredging of thin layer

• Minimise disposal capacity by high concentration (minimisation of

dilution)

• Minimise turbulence and turbidity

• Safety: bring dredged bottom material via closed system to barge or

disposal area

Dredging and Marine Contractors

129

H H D Clean

Contaminated

Contaminated material is left behind, and falls in overdepth

Accuracy Aspects

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

44

130

D increased, H not removed H (contaminated) removed

Accuracy Aspects

Dredging and Marine Contractors Dredging and Marine Contractors

131

Typical aspects

Environmental Dredgers

• Automation necessary

• Maximising concentration

• Controlling excavation level

• Controlling layer thickness

• Output level low due to:

• High accuracy

• Avoiding turbulence

Dredging and Marine Contractors

132

Types

• Environmental disc cutter dredger

Disc cutter head with closed bottom plate and shields

• Environmental auger dredger

Dual active rotating auger in enclosed area

• Horizontally closing grab

Grab sealed off when closed

• Hydraulic excavator fitted with closed visor bucket

• Encapsulated Bucket Ladder Dredger

Environmental Dredgers

Dredging and Marine Contractors

10-06-2014

45

133

Disk bottom (cutter) dredger

disk cutterhead with closed bottom plate and shields

Environmental Dredgers

Dredging and Marine Contractors Dredging and Marine Contractors

134

Environmental Auger Dredger

Environmental Dredgers

Dredging and Marine Contractors Dredging and Marine Contractors

135

• Grab is horizontally closing

• Sealde off after closing

Environmental Dredgers

Dredging and Marine Contractors Dredging and Marine Contractors

10-06-2014

46

136

Standard Grab

Dredging and Marine Contractors

137

Horizontally Profiling Grab

Dredging and Marine Contractors

138

Environmental Dredgers

Hydraulic excavator fitted with closed visor bucket

Dredging and Marine Contractors

10-06-2014

47

139

Environmental Dredgers

Bucket Ladder Dredger with encapsulated bucket line

Dredging and Marine Contractors

140

THE END

Dredging and Marine Contractors